— This action is for a sum alleged to be due upon a contract between Lee & Pans, copartners, and Fiorito Brothers, also copartners, who had taken a contract to construct a part of a highway in Idaho between Coeur D’Alene and the Washington state line and had employed Lee & Paus to haul the sand and gravel required for this work at an agreed price of sixty cents per cubic yard for deliveries from what was known as Kennedy’s pit, and if sand and gravel was obtained from a different place appellants agreed to pay a flat price of thirty-five cents per cubic yard based upon a two-mile haul. The contract required Lee & Paus to give a surety bond in the sum of $10,000 for the performance of their part of the agreement, and they assigned to respondent all sums due or to become due them under the contract, and their assignee brings this action to recover $3,094.80 alleged to be due for the delivery of 5,158 yards of sand and gravel on the basis of sixty cents per yard. Appellants answered and denied that there was anything due respondent and alleged that Lee & Paus, his assignors, had defaulted in the performance of their contract and abandoned the same; that by reason thereof appellants were compelled to procure other persons to complete the contract, and in so doing were required to pay a greater amount than they would have been required to pay Lee &
We think a proper construction of the contract required Lee & Paus to haul the entire amount of sand and gravel required to complete the work undertaken by appellants.
The undisputed evidence shows that for the completion of the work undertaken by appellants in constructing this highway there was hauled 34,741 cubic yards of sand and gravel. Of this Lee & Paus delivered or caused to be delivered the first 5,157 yards before they abandoned the work, and thereafter appellants contracted with the Cascade Investment Company to haul the remaining amount of sand and gravel required, which was 29,584 yards, and were required to pay, or did pay, this latter company on a basis of ninety cents per cubic yard. Eespondent contends that this price was in excess of the reasonable value of the work, but this question was submitted to the jury under proper instructions.
The court in effect instructed the jury that defendants were entitled to offset against any amount that might be due Lee & Paus for their work in hauling sand and gravel any amount paid by defendants for labor or material bills incurred by Lee & Paus and any sum paid for hauling sand and gravel in the construction of said highway in excess of the amount they were to receive for said hauling, provided the sum paid for finishing the hauling was under the circumstances reasonable, which is a correct statement of the law applicable to the facts of this ease, and although the verdict is a general verdict for the exact amount that would have been due Lee & Paus for the actual yardage they caused to be delivered upon their contract had there been no offsets, there is no reason to suppose the jury did not find the additional amount which appellants were required to pay the Cascade Investment Company to complete the Lee & Paus contract a reasonable price for doing this work in accordance with the instructions of the court.
In its seventh instruction the court instructed the jury that there was no evidence to support the claim of appellants that they had paid Materne Brothers $4,000 on account of work performed for Lee & Paus in said hauling and that they should disallow this item to appellants. In this we think the court was in error. There is very substantial evidence to support appellants’ claim of this payment; one of the Materne Brothers testified positively to this fact, in which testimony he is corroborated by Lee, one of the contractors for whom the work was performed, and also by one of the Fiorito brothers who testified that this amount was paid, and there being no evidence contrary to the testimony of these three witnesses, the instruction that the jury should disallow this claim was error.
With regard to the items aggregating $3,708.10, claimed by appellants to have been paid on account of yardage
It is apparent from the foregoing consideration of these various items of account that the jury in arriving at their verdict omitted to take into account the $2,320.70 paid by appellants in excess of what they would have been required to pay Lee & Paus had the original contract for hauling this material been carried out according to its terms.
For the reasons herein stated the cause is reversed, with directions to set aside the judgment and award a new trial, appellants to recover costs of this appeal.