ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Granite Construction Company ) ASBCA No. 62281
)
Under Contract No. W9126G-15-C-0037 )
APPEARANCES FOR THE APPELLANT: Michael A. Branca, Esq.
Joseph N. Frost, Esq.
Peckar & Abramson, P.C.
Washington, DC
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Clark Bartee, Esq.
Engineer Trial Attorney
U.S. Army Engineer District, Galveston
OPINION BY ADMINISTRATIVE JUDGE EYESTER
PURSUANT TO BOARD RULE 11
Granite Construction Company (Granite) appeals a decision by the U.S. Army
Corps of Engineers (Corps or government) denying Granite compensation for 19 days
of a 49-day suspension of work. The Corps concluded that those 19 days were adverse
weather delays, which Granite should have anticipated pursuant to the terms of the
contract. The Board previously granted Granite partial summary judgment on a
contract interpretation issue concerning the interplay of the contract’s unusually severe
weather, default, and suspension of work clauses. According to the decision, the only
remaining issue for the Board to decide is whether the Corps suspended the work for a
reasonable period of time pursuant to the suspension of work clause.
The Board has jurisdiction over the appeal pursuant to the Contract Disputes
Act, 41 U.S.C. § 7101. The parties elected to waive a hearing and submit the
remaining issue in this appeal on the record pursuant to Board Rule 11. Based on the
following, we conclude that the Corps’ suspension of work for 49 days was reasonable
and deny Granite’s appeal.
FINDINGS OF FACT
1. On August 31, 2015, the Corps awarded Granite fixed-priced contract
No. W9126G-15-C-0037 to perform the construction of new outlet structures and
cutoff walls at the Addicks and Barker dams to support the Buffalo Bayou and
Tributaries federal flood control project in Houston, Texas (Joint Stipulations of Fact
(JSF) ¶ 1; R4, tab 1 at 2574, 2628). 1 The contract incorporated by reference Federal
Acquisition Regulation (FAR) 52.242-14, SUSPENSION OF WORK (APR 1984) and
FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (R4,
tab 1 at 2575).
2. In addition, the contract included SECTION 01 10 00.00 45, Part 1.4, TIME
EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989)
(ER 415-1-15), which explained how to determine time extensions for unusually
severe weather (more severe than the adverse weather anticipated for the project
location during any given month) in accordance with the default clause. Part 1.4
included a table showing monthly anticipated adverse weather delays and Granite was
required to reflect those delays in its project schedule. For example, the table showed
anticipated adverse weather delays (based on a seven-day work week) for the months
of August (10), September (13) and October (10), for a combined total of 33 days for
those months. The contract also required Granite to record any adverse weather and
resulting impact to normally scheduled work on its daily contractor quality control
reports. If the actual adverse weather delay days exceeded the number of days
anticipated in the schedule, the contracting officer was to convert qualifying delays to
calendar days and issue a modification in accordance with the default clause. (R4,
tab 1 at 2633)
3. In addition, the contract addressed the release of water from the dams.
Specifically, Section 01 00 10, Part 1.4 explained that “under normal conditions” the
operational, combined release of water from the Addicks and Barker dams was limited
to 2,000 cubic feet per second (CFS) as measured downstream at the Piney Point
gauging station (JSF ¶ 4; R4, tab 1 at 2628-29). Section 00 31 33, Paragraph 2.3 of the
contract similarly provided that the combined releases could not exceed 2,000 CFS
“under normal operating conditions” and that the maximum discharge from one reservoir
of 2,000 CFS required the other to be closed (JSF ¶ 5; R4, tab 1 at 2536, 2545).
Part 1.4.1 addressed emergency operations at the dams (R4, tab 1 at 2629). The contract
explained that when emergency scheduled releases were in effect, releases could reach
8,000 CFS for each dam (id. at 2544).
4. On September 29, 2015, the Corps issued, and Granite acknowledged, a
Notice to Proceed. The notice established a required completion date of the contract
of May 31, 2019. (JSF ¶ 2; see also R4, tab 2)
1
In their briefs, both parties utilized the Joint Stipulations of Fact filed with the Board
on June 12, 2020. The JSF serves as the basis for our Findings of Fact except
as noted.
2
5. Almost two years later, on August 25, 2017, Hurricane Harvey made landfall
on the coast of Texas bringing rain and flooding to Houston, which included the contract
project site at the Addicks and Barker dams (JSF ¶ 6). On or before August 28, 2017,
but after the hurricane made landfall, the Corps began releasing water from the Addicks
and Barker dams (JSF ¶ 7). At all times relevant to this action, the Corps exercised
exclusive control over the operation of the Addicks and Barker dams (JSF ¶ 3).
6. The combined flow rate of the released water increased to over 4,000 CFS
(JSF ¶ 7). The Corps continued to increase the combined flows of water from the
Addicks and Barker dams through August 29, 2017 (JSF ¶ 8). By August 29, 2017,
the combined discharges from the Addicks and Barker dams into the Buffalo Bayou, in
conjunction with flows entering the Buffalo Bayou downstream of the dams, caused
the measured flow at the Piney Point gauging station to exceed 10,000 CFS (JSF ¶ 9).
7. On September 5, 2017, the Corps issued Serial Letter No. C-0039, directing
Granite to “SUSPEND WORK,” retroactively to August 28, 2017 and prospectively
through October 15, 2017, on construction of the new outlet structure at the Addicks
dam site; construction of cutoff walls and new outlet structure at the Barker dam site;
and construction of cutoff walls at the Noble Road site of the Barker dam (JSF ¶ 10;
R4, tab 3). The suspension of work, issued pursuant to FAR 52.242-14, did not apply
to emergency repairs of damage to the dams (pursuant to contract parts 1.4.1 relating
to emergency operations and 1.5 relating to damage to work), repairs to damaged work
caused by the Hurricane Harvey floods (pursuant to contract part 1.5 relating to
damage to work), construction activities related to recovery and restoration that could
be performed safely, and activities not affected by the flooding around the dams
(JSF ¶ 11; R4, tab 3 at 3583-84). The total period of suspension ordered by the
contracting officer was 49 calendar days (JSF ¶ 12).
8. The alternate administrative contracting officer (AACO) who issued the
suspension letter explained in a declaration that he considered the following when
calculating the number of days to suspend work: the Tax Day Flood in April 2016; the
forecast magnitude for Hurricane Harvey; the projections of conditions for the dams
from the Corps’ Water Management System (CWMS) models; and discussions with
others including Granite’s project manager (R4, tab G-57 at 3893). The CWMS
models provided information on current and projected inflows, outflows, stage levels,
and projected dates when the flood waters would be fully discharged from each dam.
The AACO also considered the time Granite would need to restore the project site
before it could resume work. The AACO explained that the project sites were initially
under water due to the record flood and most of the partially constructed work was
completely submerged. (Id. at 3894)
9. On November 3, 2017, both Granite and the Corps executed Modification
No. A00030, which extended the contract time by 49 calendar days (JSF ¶ 13; R4,
3
tab 4 at 3753-54). The Corps issued the modification to “extend the time for
performance allowed under Specification Section 01 10 00.00 45 for delays from the
Suspension of Work due to Hurricane Harvey during the period August 28, 2017
thru October 15, 2017” (R4, tab 4 at 3754). The modification was “not a release of
claims by the Contractor and [did] not preclude the Contractor from pursuing any
claim for monetary compensation from events occurring during the timeframe of the
days covered in this modification” (JSF ¶ 14; R4, tab 4 at 3754).
10. During the suspension period, Granite produced the required daily quality
control reports. The quality control report dated August 28, 2017, the first day of the
suspension and after the hurricane made landfall, stated that there was no work at the
sites due to flooding, except the crews were moving equipment out of the flooded
area. The report explained that Granite was directed to suspend construction at the
Addicks and Barker dams through October 15, 2017 due to flooding and it “[c]ould
not continue working on critical activities due to flooding in and around the Addick[s]
and Barker Dam.” The report stated that Granite’s own corporate office was closed
due to the hurricane and flooding. (R4, tab G-4 at 3555) Reports issued through the
suspension period showed Granite performed some work, including recovery work as
a result of the hurricane (see, e.g., R4, tabs G-12 at 3579, G-21 at 3617). All but one
of the quality control reports issued during the suspension period stated that Granite
could not work on critical activities due to flooding in and around the dams (R4,
tabs G-4-G-10, G-12-G-46, G-48-G-52). The quality control reports from August 25
through September 15 explained that there was a weather delay caused by the
hurricane (R4, tabs G-5-G-7, G-10, G-12-G-22). The two reports for September 1-2,
right after the hurricane began, noted the delay was due to impounded water or
inundation from reservoir releases (R4, tabs G-8-9). The October 10, 2017 quality
control report explained that Granite could not continue working on critical activities
due to reservoir impounded levels and the release of water volume downstream (R4,
tab G-47 at 3715).
11. Based on the time when the hurricane made landfall and Granite’s own
quality control reports, we find that the root cause of the flooding in and around the
dams was Hurricane Harvey. In addition, the AACO explained that the Corps needed
to release the water behind the dams and did so in accordance with Corps’ procedures
(app. supp. R4, tab A-1 at 9-10). We also find, therefore, that at the time the Corps’
released water, around August 28-29, 2017, which was either during or right after
Hurricane Harvey made landfall in the area, the release was due to the hurricane and
therefore not under normal conditions.
12. On October 16, 2017, the day after the suspension of work ended, Granite
notified the government that it made the necessary repairs to resume work on the
construction of the new outlet at the Addicks dam, but that it also needed to continue
damage repairs due to flooding from the hurricane. The letter also explained that it
4
could not resume construction of the cutoff wall and new outlet at the Barker dam due
to damage of specialty equipment from the flooding. As a result, Granite requested an
extension of the suspension for this work through November 27, 2017. R4, tab G-54
at 3741 By Granite’s own admission, the 49-day suspension was required and in fact,
Granite needed additional days added to the suspension period.
13. The AACO stated that during the suspension period, the Corps conducted
informal assessments as to whether the suspension should be lifted or extended. These
assessments considered information from the hydrology and hydraulics section
regarding the water retained behind the dams and when the dams would be emptied.
(App. supp. R4, tab A-1 at 16-17). The AACO explained that “[t]he water behind the
dams basically would have precluded [Granite] from working in the borrow pits until
the water receded” (id. at 17). The AACO also stated that he did not believe work
could be performed prior to October 15, 2017 on the suspended items because a
sufficient amount of restoration work needed to be completed first (id. at 21-22). We
find the AACO’s statement that Granite could not perform work on suspended items
prior to October 15, 2017 is consistent with Granite’s contemporaneous documents
including the quality control reports and October 16, 2017 letter.
14. On June 14, 2018, Granite submitted a request for equitable adjustment
seeking $1,250,474 and five calendar days beyond the suspension of work time period
as compensation for the additional costs that it had incurred as a result of the
suspension (JSF ¶ 15; R4, tab 6 at 3768-69). On November 30, 2018, the Corps and
Granite executed bilateral Modification No. P00008 increasing the contract value by
$961,008 and adding four calendar days towards contract completion (JSF ¶ 16; R4,
tab 5 at 3756-57). The modification noted Granite submitted an REA in accordance
with FAR 52.242-14 and Section 01 10 00.00 45, paragraph 1.5, DAMAGE TO
WORK, “for cost[s] associated with the direction to partially suspend work on
September 5, 2017 due to unprecedented rain and flooding caused by Hurricane
Harvey as well as site reclamation activities required to repair the site to pre-flood
conditions” (R4, tab 5 at 3757). As Modification No. P00008 compensated Granite for
only 30 days, it included an express reservation of rights for Granite to pursue
compensation for the remaining 19 days of time-related costs in the amount of
$233,779 (JSF ¶ 17; R4, tab 5 at 3757). The AACO explained during his deposition that
the partial compensation consisted of prorated days where Granite was responsible for
the days set forth in the adverse weather clause and the government was responsible for
the rest (app. supp. R4, tab A-1 at 18; see also JSF ¶ 21).
15. Granite submitted a certified claim on May 23, 2019, requesting a
contracting officer’s final decision. Granite’s claim sought $233,779, plus interest,
which represented the time-related costs that Granite alleged it had incurred as a result
of an express suspension of the work by the Corps. (JSF ¶ 22; R4, tab 6 at 3759, 3762-
63) According to the claim, the total REA negotiated amount for the suspension delay
5
(as opposed to site reclamation costs, for example) was $602,904.86 and the
government paid Granite for 30 days, or $369,125.42; Granite was seeking the
remaining 19 days of delay costs (see R4, tab 6 at 3767).
16. On August 30, 2019, the contracting officer issued a final decision denying
Granite’s claim (JSF ¶ 23; R4, tab 8). The contracting officer stated that it was
reasonable to suspend work for 49 days due to the extreme weather conditions caused
by Hurricane Harvey (R4, tab 8 at 3849). The contracting officer also stated, however,
that compensation for all 49 days was not permitted as 19 of those days were
anticipated adverse weather delay days identified in Part 1.4 of the contract, for which
Granite accepted the risk (id. at 3849-50). On November 26, 2019, Granite filed its
notice of appeal with the Board.
17. The quantum amount claimed by Granite is not in dispute. By letter dated
September 3, 2020, the Corps stipulated that the quantum amount of $233,779 is
accurate.
DECISION
In Granite Constr. Co., the Board granted partial summary judgment in favor of
Granite by concluding that the monthly anticipated adverse weather delays set forth in
Section 1.4, TIME EXTENSIONS FOR UNUSUSUALLY SEVERE WEATHER,
may not be subtracted from a suspension period issued pursuant to FAR 52.242-14,
SUSPENSION OF WORK as the unusually severe weather clause applies to the
default clause only. Granite Constr. Co., ASBCA No. 62281, 21-1 BCA ¶ 37,756
at 183,281. Specifically, we stated that Section 1.4 only defines what constitutes
“unusually severe weather” for determining if the default is excused under the default
clause and there is nothing linking that section and the default clause to the suspension
of work clause. Id. 2
As relevant here, the Board explained to the parties that the remaining issue was
“whether the 49 day suspension period was ‘reasonable,’ as that word is used in the
Suspension Clause, or not.” Granite Constr. Co., 21-1 BCA ¶ 37,756 at 183,280,
183,282. In this regard, the applicable suspension of work clause states the contracting
officer may order the contractor “to suspend, delay, or interrupt all or any part of the
work . . . for the period of time” the contracting officer finds “appropriate for the
convenience of the Government.” FAR 52.242-14(a). That FAR clause also explains
the following regarding an unreasonable suspension period:
(b) If the performance of all or any part of the work is, for
an unreasonable period of time, suspended, delayed, or
interrupted (1) by an act of the Contracting Officer in the
2
Familiarity with that decision is presumed.
6
administration of this contract, or (2) by the Contracting
Officer’s failure to act within the time specified in this
contract (or within a reasonable time if not specified), an
adjustment shall be made for any increase in the cost of
performance of this contract (excluding profit) necessarily
caused by the unreasonable suspension, delay, or
interruption, and the contract modified in writing
accordingly. However, no adjustment shall be made under
this clause for any suspension, delay, or interruption to the
extent that performance would have been so suspended,
delayed, or interrupted by any other cause, including the
fault or negligence of the Contractor, or for which an
equitable adjustment is provided for or excluded under any
other term or condition of this contract.
FAR 52.242-14. The clause implements FAR 42.1302, which states that “[a]
suspension of work under a construction . . . contract may be ordered by the
contracting officer for a reasonable period of time. If the suspension is unreasonable,
the contractor may submit a written claim for increases in the cost of performance,
excluding profit.”
Therefore, pursuant to FAR 52.242-14, a contractor is only entitled to an
equitable adjustment when the government suspends work for an unreasonable period
of time, thereby delaying work. See George Sollitt Const. Co. v. United States,
64 Fed. Cl. 229, 237 (2005) (for government to be found liable for an action or
inaction that delays contract work, the delay in question must be unreasonable);
Nassar Grp. Int’l N.G.I. S.A.L. (Offshore) R.C., ASBCA No. 58451, 22-1 BCA
¶ 38,206 at 185,548. A contractor may be compensated only for unreasonable
government delays because there are “some situations in which the government has a
reasonable time to make changes before it becomes liable for delay.” George Sollitt
Const. Co., 64 Fed. Cl. at 237 (quoting Essex Electro Engr’s, Inc. v. Danzig, 224 F.3d
1283, 1289 (Fed. Cir. 2000)).
Accordingly, Granite bears the burden of first showing that there was a delay of
unreasonable length extending the contract completion time; next, Granite would need
to show the unreasonable delay was proximately caused by the government’s action or
inaction, the delay resulted in some injury, and there was no delay concurrent with the
suspension that was Granite’s fault. CEMS, Inc. v. United States, 59 Fed. Cl. 168, 230
(2003) (citing P.J. Dick, Inc. v. Principi, 324 F.3d 1364, 1375 (Fed.Cir.2003)).
Granite first contends the government tacitly admitted the suspension period
was unreasonable “by virtue of Modification No. P00008, which provided Granite
with compensation for 30 of the 49 days” (app. br. at 6-7; app. reply at 4-5). In
7
response, the government states that it “elected to equitably adjust the contract price
for 30 days’ worth of costs” but this was not an admission by the government that the
suspension was for an unreasonable amount of time (gov’t reply at 3). Further, even if
it was an admission, the government states it only committed to paying 30 of the
49 days thereby signifying the remaining 19 days of suspension was reasonable (id.).
We agree with the government in that even if the modification was a tacit admission,
which we conclude it was not, it could be an admission that only 30 of the 49 days
were unreasonable and the government already compensated Granite for those days.
Granite next contends the suspension of time was unreasonable because the
government is relying on the adverse weather clause and the Board’s previous decision
stated the government could not subtract the adverse weather delays from the
suspension period (app. br. at 7-8; app. reply at 5-6). The government argues that
the 19 days excluded by the modification for payment were due to actual delays from
adverse weather for which no adjustment should be made (gov’t reply at 4). The
government asserts that Granite documented in its quality control reports and
correspondence that the weather delay caused by Hurricane Harvey prevented it from
performing critical activities under the contract for the 49 days at issue (id.; gov’t br.
at 20-21). The government further contends that Granite’s program manager agreed
that 49 days was a reasonable suspension period (gov’t reply at 5).
Granite has failed to prove the government suspended the contract for an
unreasonable amount of time. The suspension period started about when Hurricane
Harvey made landfall and lasted 49 days (findings 5, 7). As noted, during that time,
the suspension was limited in nature; it prohibited Granite from performing
construction of the new outlets at the dams but permitted Granite to perform other
work such as emergency repairs, repairs to damaged work and recovery and
restoration activities not affected by the flooding (finding 7). Granite did in fact
perform some of this work at the project sites, including recovery work (finding 10).
The AACO established the 49-day suspension period by considering several
relevant factors including how the Corps handled a prior flood on another project,
forecasts of the magnitude for Hurricane Harvey, CWMS models, discussions with
Granite’s project manager, the time needed to restore the project site to resume work,
and the condition of the project site (finding 8). As discussed, Granite’s own quality
control reports support the AACO’s 49-day suspension period as reasonable. The
reports explained that Granite could not perform work on critical activities due to
flooding, which we found was due to Hurricane Harvey (finding 11). Further, the day
after the suspension ended, Granite notified the government that it could resume work
on the construction of the new outlet at the Addicks dam but needed to continue
damage repairs at that site due to flooding from the hurricane, and that it could not
resume construction of the cutoff wall and new outlet at the Barker dam due to damage
of specialty equipment from the flooding (finding12). In fact, Granite requested an
8
extension of the suspension period for this work through November 27, 2017, which
was partially granted (findings 12, 14).
Accordingly, we found that not only did Granite’s contemporaneous documents
show the suspension period was reasonable and that Granite could not perform work
on suspended items prior to October 15, 2017, the documents actually showed Granite
requested additional time for suspending certain work (findings 10, 16). We conclude
that the government suspended the contract for a reasonable amount of time. See
CEMS, Inc., 59 Fed. Cl. at 231-32 (concluding a contracting officer’s decision to
suspend paving work on a bicycle path for almost five months due to weather
conditions was reasonable).
In addition, Granite argues that the government caused the project site to flood
for 49 days when it unilaterally decided to open the flood gates upstream of the project
and beyond the contract’s limits and therefore it was not Hurricane Harvey that caused
the delay but the government (app. reply at 2-4, 6). The government contends that
Granite has failed to prove the government is the sole cause of flooding at the site,
especially as contract modifications signed by Granite identified Hurricane Harvey as
the basis for the suspension of work (gov’t br. at 19).
Even assuming there was any unreasonable suspension time period, Granite has
failed to show the government was the sole cause of such delay, either by its actions or
inaction. See CEMS, Inc., 59 Fed. Cl. at 232 (contractor entitled to recovery of costs
associated with the delay only if the government was the sole cause of the delay);
see also FAR 52.242-14(b). Contrary to Granite’s assertions that the Corps’ release of
water at the dams caused the flooding and therefore the delay, we found the underlying
cause of the suspension of work was Hurricane Harvey (finding 11). Further, we note
that the contract explained that “under normal conditions” the combined release of
water from the dams was limited to a total of 2,000 CFS, but under emergency
operations releases could reach 8,000 CFS for each dam (finding 3). Neither party
addresses this language or explains whether and how a hurricane could be considered
“normal conditions.” Regardless, we found a hurricane caused the delay, and is not
“normal conditions” (finding 11), and therefore the government could not be the sole
cause of the delay.
In addition, there was no inaction on the part of the Corps that caused the delay.
In this regard, the Corps conducted informal assessments during the suspension period
to determine whether the suspension should be lifted or extended and considered
information from the hydrology and hydraulics section regarding the water retained
behind the dams and when the dams would be emptied (finding 13).
9
CONCLUSION
For the foregoing reasons, the appeal is denied.
Dated: November 1, 2023
LAURA EYESTER
Administrative Judge
Armed Services Board
of Contract Appeals
I concur I concur
RICHARD SHACKLEFORD MICHAEL N. O’CONNELL
Administrative Judge Administrative Judge
Acting Chairman Acting Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 62281, Appeal of Granite
Construction Company, rendered in conformance with the Board’s Charter.
Dated: November 1, 2023
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals