IN THE SUPREME COURT
STATE OF NORTH DAKOTA
2024 ND 22
Friends of the Rail Bridge (FORB),
Downtown Business Association of
Bismarck, and CD Holdings, LLC, Appellants
v.
North Dakota Department of Water Resources
and BNSF Railway Company, Appellees
No. 20230240
Appeal from the District Court of Burleigh County, South Central Judicial
District, the Honorable Jackson J. Lofgren, Judge.
AFFIRMED.
Opinion of the Court by McEvers, Justice.
William J. Delmore (argued), Bismarck, ND, and Lyle G. Witham (appeared),
Erie, CO, for appellants.
Erik J. Wallevand (argued) and Matthew A. Sagsveen (appeared), Assistant
Attorneys General, Bismarck, ND, for appellee North Dakota Department of
Water Resources.
Evan Nelson (argued) and Jason A. Lien (appeared), Minneapolis, MN, and
Wade C. Mann (on brief) and Zachary R. Eiken (on brief), Bismarck, ND, for
appellee BNSF Railway Company.
Tory L. Jackson, Bismarck, ND, for amicus curiae National Trust for Historic
Preservation in the United States.
Friends of the Rail Bridge, et al. v. N.D. Dep’t of Water Resources,
et al.
No. 20230240
McEvers, Justice.
[¶1] Friends of the Rail Bridge (“FORB”), Downtown Business Association of
Bismarck (“DBAB”), and CD Holdings, LLC appeal from a judgment
dismissing their administrative appeal for lack of subject matter jurisdiction.
We affirm.
I
[¶2] In September 2017, BNSF Railway Company (“BNSF”) applied to the
Department of Water Resources (“DWR”)1 for Sovereign Land Permit S-2095
to construct a new rail bridge across the Missouri River between Bismarck and
Mandan, North Dakota. On December 13, 2022, FORB requested DWR conduct
a “public hearing” or “public meeting” under N.D. Admin. Code § 89-10-01-07
on BNSF’s permit application. On December 21, 2022, DWR responded, stating
it would hold an “information-gathering public meeting” under N.D. Admin.
Code § 89-10-01-07 on January 20, 2023. The meeting was duly noticed to the
public.
[¶3] On January 12, 2023, BNSF applied to DWR for Sovereign Land Permit
S-2398 to remove the existing rail bridge upon the completion of the new
bridge. DWR notified the public that an “information-gathering public
meeting” under N.D. Admin. Code § 89-10-01-07 would be held on March 3,
2023, concerning permit application S-2398. The two public meetings were
held and members of FORB, DBAB, BNSF, and the public provided written
and oral comments. On April 24, 2023, DWR issued Sovereign Land Permits
S-2095 and S-2398 to BNSF. Neither FORB nor DBAB requested an
administrative hearing after issuance of the permits.
1 At the time, DWR was known as the Office of the State Engineer.
1
[¶4] On May 4, 2023, FORB and DBAB appealed to the district court. CD
Holdings was added as an additional appellant. DWR and BNSF moved to
dismiss for lack of subject matter jurisdiction due to improper service and
Appellants’ failure to exhaust their administrative remedies. The court
dismissed the appeal, concluding Appellants failed to perfect their appeal
because they did not request a hearing under N.D.C.C. § 61-03-22, and
therefore the court lacked subject matter jurisdiction to hear the appeal.
II
[¶5] Appellants argue the district court erred in concluding that they failed
to perfect their appeal and that the court lacked subject matter jurisdiction.
When jurisdictional facts are undisputed, a dismissal for lack of subject matter
jurisdiction is reviewed de novo. Olympic Fin. Grp., Inc. v. N.D. Dep’t of Fin.
Insts., 2023 ND 38, ¶ 10, 987 N.W.2d 329.
[¶6] The district court has appellate jurisdiction as provided by law or by rule
of this Court. N.D. Const. art. VI, § 8. “Appeals from administrative agency
decisions to a district court involve the exercise of appellate jurisdiction
conferred by statute.” Opp v. Dir., N.D. Dep’t of Transp., 2017 ND 101, ¶ 8, 892
N.W.2d 891. “For a district court to acquire subject matter jurisdiction over an
appeal from an administrative agency decision, the appellant must satisfy the
statutory requirements for perfecting an appeal.” Id. Interpretation of a
statute is a question of law. Meier v. N.D. Dep’t of Hum. Servs., 2012 ND 134,
¶ 6, 818 N.W.2d 774. When interpreting a statute, we look at the statute’s plain
language and give each word its plain and ordinary meaning unless a contrary
intention plainly appears. Id.; N.D.C.C. § 1-02-02.
[¶7] Section 61-03-22, N.D.C.C., requires a person aggrieved by DWR’s action
or decision to request a hearing within 30 days and prior to appealing:
Any person aggrieved by an action or decision of the
department under this title has the right to a hearing. The
department must receive a request for a hearing within thirty days
after the aggrieved person knew or reasonably should have known
of the action or decision. Once a hearing has been held or if the
2
hearing request is denied, the person aggrieved has the right to
petition for reconsideration or appeal under chapter 28-32.
[¶8] The “action or decision” that Appellants alleged they have been
aggrieved by is DWR’s issuance of the permits to BNSF on April 24, 2023.
Appellants state in their notice of appeal to the district court that they are
appealing from the permits issued on April 24, 2023. It is undisputed that
Appellants did not request a hearing within 30 days (or at any time) after
DWR’s April 24, 2023 issuance of the permits. Accordingly, no hearing was
held, nor was a hearing request denied by DWR.
[¶9] Appellants argue FORB’s December 13, 2022 letter to DWR was a
request for a hearing under N.D.C.C. § 61-03-22 and the January 20, 2023 and
March 3, 2023 meetings were hearings under N.D.C.C. § 61-03-22. In its letter,
FORB requested DWR conduct a “public hearing” or “public meeting” under
N.D. Admin. Code § 89-10-01-07 on BNSF’s Sovereign Land Permit S-2095
application to construct a new rail bridge. Under N.D. Admin. Code § 89-10-
01-07, DWR may hold an “information-gathering public meeting . . . before
final action on a project.” This administrative code section requested by FORB
specifically provides, “The meeting is not an adjudicative proceeding hearing
under North Dakota Century Code chapter 28-32.” N.D. Admin. Code § 89-10-
01-07(4). “Upon completion of the review and any public meeting held under
section 89-10-01-07, [DWR] may grant, deny, or condition the application.”
N.D. Admin. Code § 89-10-01-06(3). Hearings under N.D.C.C. § 61-03-22 “must
be conducted by the office of administrative hearings.” N.D.C.C. § 54-57-03(1).
In contrast, a public meeting “must be conducted by the department.” N.D.
Admin. Code § 89-10-01-07(3).
[¶10] An adjudicative proceeding under ch. 28-32 “means an administrative
matter resulting in an agency issuing an order after an opportunity for hearing
is provided or required” and “includes administrative matters involving . . . a
hearing on an application seeking a right, privilege, or an authorization from
an agency.” N.D.C.C. § 28-32-01(1). At an adjudicative proceeding hearing, the
parties are allowed to present evidence and to examine and cross-examine
witnesses. N.D.C.C. § 28-32-21(2). Adjudicative proceedings require the agency
3
to make findings of fact, conclusions of law, and an order based upon its
findings and conclusions. N.D.C.C. § 28-32-39(1). “Any party to any proceeding
heard by an administrative agency, except when the order of the
administrative agency is declared final by any other statute, may appeal from
the order within thirty days after notice of the order has been given as required
by section 28-32-39.” N.D.C.C. § 28-32-42(1).
[¶11] DWR responded to FORB’s letter, stating it would hold an “information-
gathering public meeting” under N.D. Admin. Code § 89-10-01-07 on January
20, 2023. Both that meeting and the March 3, 2023 meeting were noticed to
the public as an “information-gathering public meeting” under N.D. Admin.
Code § 89-10-01-07. The office of administrative hearings did not conduct the
proceedings on January 20, 2023, and March 3, 2023. Therefore, we conclude
FORB’s request citing the authority under N.D. Admin. Code § 89-10-01-07
was for a “public meeting” and the proceedings held were “public meetings,”
not hearings under N.D.C.C. § 61-03-22. Further, N.D.C.C. § 61-03-22 requires
the hearing request be made within 30 days after knowing of the action or
decision. FORB’s request and the public meetings came before DWR issued the
permits, which was the decision or action appealed to the district court. FORB’s
December 2022 request was made before BNSF even applied for Permit S-2398
in January 2023. Prior to issuing the permits, Appellants were not “aggrieved”
because DWR could have denied BNSF’s applications for permits. Therefore,
to the extent Appellants argue the applications (which are not actions or
decisions of DWR) or the public notices constitute an “action or decision,” we
reject that argument.
[¶12] Appellants cite Aggie Investments GP v. Public Service Commission of
North Dakota, 451 N.W.2d 141 (N.D. 1990), in support of their argument that
they perfected the appeal. In Aggie, the Public Service Commission (“PSC”)
held “public input hearings . . . to give the public opportunity to present
comments or statements on [Northern States Power Company’s] proposed rate
increase.” 451 N.W.2d at 141. On appeal to the district court, the court
dismissed the appeal for lack of subject matter jurisdiction. Id. at 142. This
Court reversed the district court, concluding the Fargo public input hearing
4
was a “hearing or a part thereof” under N.D.C.C. § 28-32-15 (1989)2 and the
court had subject matter jurisdiction. Id. at 143. We reasoned the publicly
noticed hearing, although lacking sworn testimony and formally introduced
evidence, constituted a “hearing or a part thereof”:
The Fargo public input hearing was publicly noticed as a
“hearing” by the PSC and was intended to give the public an
opportunity to present statements on [Northern States Power
Company’s] proposed rate increase. A hearing examiner presided
over the proceedings. Local citizens attended the hearing and
voiced their concerns over the proposed rate increase. The
proceedings were transcribed by a court reporter.
Although persons attending the hearing were informed
through a PSC handout entitled “Procedure in Major Rate Cases”
that they could be sworn as witnesses if they wanted their
statements to be part of the “official record,” we do not believe that
the absence of sworn testimony and formally introduced evidence
renders the public input hearing any less a “hearing” for appellate
jurisdiction purposes. “The word ‘hearing’ contemplates an
opportunity to be heard.” State v. Milhollan, 50 N.D. 184, 195 N.W.
292, 295 (1923). Unlike the ultimate decision-making meetings at
issue in Happy Day [Day Care Center v. Social Service Board of
North Dakota, 313 N.W.2d 768 (N.D. 1981)], the Fargo public input
hearing clearly contemplated the public’s opportunity to have their
statements included as part of the “official record.”
Id.
[¶13] Here, FORB requested a “public hearing” or “public meeting” under N.D.
Admin. Code § 89-10-01-07, and DWR notified the public that “information-
gathering public meeting[s]” under N.D. Admin. Code § 89-10-01-07 would be
held. There is no ambiguity as to the nature of the proceedings. Section 89-10-
01-07(4), N.D. Admin. Code, is clear that these meetings are not “adjudicative
proceeding hearing[s].” As discussed above, even if these meetings could be
considered hearings, N.D.C.C. § 61-03-22 requires the hearing be held after
2 Section 28-32-15, N.D.C.C., is now codified at N.D.C.C. § 28-32-42.
5
DWR’s action or decision, not before the action or decision. At issue in Aggie
was the jurisdictional statute in ch. 28-32, not N.D.C.C. § 61-03-22. Moreover,
in Aggie, a hearing examiner presided over the proceedings; whereas, here,
DWR, not the office of administrative hearings as required by N.D.C.C. § 54-
57-03(1), conducted the meetings. Aggie is legally and factually different from
this case.
[¶14] Appellants contend that “a permit is an ‘adjudicative proceeding [that]
does not involve a hearing on a complaint against a specific-named
respondent’” under N.D.C.C. § 28-32-21(3)(a). Section 28-32-21, N.D.C.C.,
provides the procedures that agencies “shall comply with . . . in all adjudicative
proceedings.” Section 28-32-21 does not state that all permit applications
require adjudicative proceedings. Absent a timely request for a hearing
regarding a DWR action or decision, and the hearing being held or denied, an
aggrieved person has no right to appeal under chapter 28-32. N.D.C.C. § 61-
03-22.
[¶15] Appellants argue DWR’s failure to create and certify a record or
transcript of the meetings “block[s]” their right to appeal in the district court.
As noted above, an appeal must be perfected before the court has the ability to
hear the appeal. After an appeal is perfected, the agency is required to prepare
and file the record of the proceedings before the agency. See N.D.C.C. § 28-32-
44(2). Because Appellants did not perfect an appeal, the court lacks subject
matter jurisdiction. Lacking jurisdiction, the court did not err in dismissing
the appeal without requiring DWR to file the record.
[¶16] Because Appellants did not satisfy the statutory requirements for
perfecting an appeal, the appeal was not properly perfected and the district
court lacked subject matter jurisdiction. We conclude the court did not err in
dismissing the appeal.
6
III
[¶17] The parties’ remaining arguments are either without merit or
unnecessary to our decision. We affirm the judgment of dismissal.
[¶18] Jon J. Jensen, C.J.
Daniel J. Crothers
Lisa Fair McEvers
Jerod E. Tufte
Douglas A. Bahr