Plaintiff brings this action to recover damages for breach of a contract whereby plaintiff performed certain electrical work in the construction of Charles Evans Hughes High School. Defendant board of education moved to dismiss the action as barred by a limitation included in the contract. The contract provided that no claim arising under it could be brought unless started ‘ ‘ within one year after the date of acceptance of the work under this contract by the Board,” On June 4, 1969, plaintiff applied for final payment. On July 11 the board found that plaintiff had substantially completed its contract on June 25, and the work was accepted on August 7, 1969. A check for the balance of the contract price was delivered to plaintiff on September 10. This action was begun October 21, 1971. Plaintiff had previously served a notice of claim on March 2,1970.
The order entered March 14,1973, New York County, denying defendant’s motion to dismiss the complaint should be reversed on the law and the motion granted, with costs.
Markewich, J. P., Murphy, Lupiano, Steuer and Lane, JJ., concur.
Order, Supreme Court, New York County, entered on or about March 14, 1973, unanimously reversed, on the law, the motion granted, and the complaint dismissed. The appellant shall recover of respondent $40 costs and disbursements of this appeal.