The complaint in this action, alleged that a firm, Abells & Strong, in June, 1893, entered into a contract with the defendant (the city
The complaint alleged, also, that there was due the plaintiff, by reason of the premises, the sum of $1,604.99, with interest from July 6, 1894. The cause of action was assigned before the commencement of this action by the contractors to this plaintiff.
The defendant’s answer put in issue the matter in controversy m the action.
The firm of Abells & Strong, pursuant to a notice duly advertised, issued by the common council of the defendant, dated June 26, 1893, for proposals to grade Boyden street, from Pattison street to Teall avenue, on the 3d of July, 1893, filed with the city a bid to construct the work for the price stated in the complaint, and further provided “ for all extra work done by written order of the Commissioner of Public Works — its actual reasonable cost to the contractor, as determined by the Commissioner, plus fifteen per cent of said cost.” This bid was accepted by the city,' and the contract was entered into between the parties in writing for the work in July,
These officers under the city charter were the proper officers to represent the city in this work. In the progress of the work a fill became necessary along the side of the street, 'varying from three to twelve and fifteen feet in height; so that, in attempting to perform" the contract) it was discovered that if the top of the embankment was of the width of the street, the toe of the embankment riiust necessarily extend over the premises of abutting owners sufficiently to support the embankment with the earth slope required by the contract. If the fill was fifteen feet deep, the toe of the bank would be thirty feet upon the adjoining owners’ property. The adjoining owners refused to permit any portion of the embankment upon their premises and forbade it. An emergency, therefore, suddenly arose which neither of the parties seemed to have contemplated when the contract was made, and to persist in the performance-of the contract would render all concerned liable as trespassers and the work would probably be stopped. . The only way out of the difficulty was, therefore, to construct a vertical wall.
The city engineer was the only witness sworn. ' He testified that the work was necessary, in order to carry out the contract, to build this vertical wall, and that it was extra work. The trial court found that it was extra work, and that the city, with full knowledge of the situation, had ratified the act of the city engineer acting for the commissioner of public works in ordering the extra work, by paying for a part thereof, recognizing it as valid and accepting the work as performed; that the extra work was worth the amount claimed therefor by the plaintiff; that, during the progress of the work, it became necessary to build the wall as a retaining wall to properly support the earth drawn upon the street for the purpose of making the fill and in order to protect the property of adjoining owners; and that the defendant, through the city engineer arid the commissioner of public works, authorized and directed the contract 'ors to build the said wall. These findings are sustained by the evidence The work was not only necessary and proper, but it was performed
The learned counsel for the defendant insists that this stone work was not legally authorized by the defendant, and cites the provisions' of the city charter (Laws of 1885, chap. 26, § 155),.which provides: “ Whenever the common council shall order any work to be done or materials or supplies to be. furnished under, the provisions of the foregoing sections of this title, the same shall be done by contract if it shall involve an expenditure exceeding seventy-five dol-. lars, and such contract shall be let to the lowest bidder,” etc. This is a part of title 9 of chapter 26, which is entitled “local assessments and improvements.” The 138th section provides that the city shall have jurisdiction to construct and repair sewers, pavements, gutters, sidewalks, and make other local improvements subject to the provisions of that act. The defendant’s counsel also contends that, as the extra work was not ordered by the commissioner in writing, there can be no recovery for this work.
The last objection will be answered first. This provision of the contract could be and was waived by the commissioner and the defendant; and whether waived or not, the oral direction was ratified and adopted by the commissioner in wilting, which was equivalent to an original authority in writing.
There is more difficulty with the first objection, and it is earnestly contended by the defendant that it had no power either to order this extra work without advertising for bids for it under the charter or to ratify it after the work had been done; and it appeals to the well-known principle- -that a municipal corporation finds the measure of its power in the statute creating it or imposing the power. This principle has been invoked in many cases -of local improvements in cases'where fraud was apparent and collusion manifest between.the corporation officers and the contractors, and when, under the guise of extra work, they have sought to avoid th¿ publicity of advertising for bids for work and material the courts have been careful to protect the people from such fraudulent contracts and contrivances, and
In Brady v. Mayor, etc., of New York (20 N. Y. 312), where, under the charter of New York city that required all work performed for the city which should cost more than $250 should be subjected to public competition, a contract for setting curbs and gutter stones and flagging a portion of a street omitted all reference to rock excavation in the street which would be about seven-eighths of the work, the court held that such a contract was void and the common council could not ratify it, but the court says at page 319 : “ It is not necessary to deny that one who has bona fide performed labor under a contract which is void from a failure to comply with the statutes may maintain an action against the city to recover a qua/ntum meruit where the work has been accepted by the city and has gone into use for public purposes.” That is the case at bar exactly, and that portion of the complaint covering this extra work is based upon a quantum meruit.
The matter of The Petition of Merriam (84 N. Y. 596) was also a New York case where in the advertisement for proposals for constructing a sewer a price was fixed -for rock excavations, which constituted a large portion of the work. Held, that this was a violation of the charter requiring competitive bids, clearly so where the city assumes to fix the price in advance.
In The Matter of Rosenbaum (119 N. Y. 24), where a contract was let after advertisement and upon competition for paving a street with a patent pavement, the work of laying bridges, stones or crosswalks was not included, but the work of laying those crosswalks was awarded without advertisement or competition in violation of the provisions of the charter of New York city upon the order of Wil
Smith v. The City of Newburgh (77 N. Y. 130) was a case where a lease was executed to the city that was void under its charter.
In Moynahan v. Birkett (81 Hun, 395) was where the public authorities assumed to fix in advance the prices for extra work without knowing what such extra work would be in detail, and thus shutting off competition therefor. This case is subject to the same criticism as The Matter of Merriam (supra).
The eases above cited are thóse relied upon by the defendant’s counsel to sustain its contention here. In view of the importance of the questions we have reviewed them at some length, and it is not perceived that they aid the defendant.
The learned judge at Special Term, in directing this judgment, cites as an authority Weston v. City of Syracuse (82 Hun, 67). An examination of that-case and the authorities it cites will be uSefiil in sustaining the respondent’s contention here.
Reference may also be profitably made to Smith v. The City of Utica (6 N. Y. Supp. 792); Nelson v. The Mayor, etc., of New York (63 N. Y. 535); Peterson v. The Mayor of New York (17 id. 449); Mulholland v. The Mayor, etc., of New York (113 id. 631); Fleming v. The Village of Suspension Bridge (92 id. 368); Moore v. The Mayor, etc., of New York (73 id. 238, 248). At the last page the court says: “When there has been a bona fide performance of a contract of which the city has had the benefit there is a strong- equity in favor of the contractor seeking his pay, entitling him to the benefit of a ratification, even of a- void contract, upon slight evidence, if the ratifying body has general power over the subject of the contract, and of an estoppel when an estoppel fairly results from the conduct of the general agents of the city.” (Citing with approval the remark quoted from Brady v. The Mayor, supra.)
And Judge Martin, in Smith v. The City of Utica (supra) makes the same quotation from Moore v. The Mayor, and cites upon the question of estoppel several cases at page 194, to which reference may be. made.
We concur with the trial court in its conclusions.
The judgment should be affirmed, with costs.
All concurred, except Follett and Green, JJ., dissenting.