Appeal from a judgment of the County Court of Warren County (Moynihan, Jr., J.), entered April 10, 1995, upon a decision of the court in favor of defendant.
In March 1990 defendant, a home construction contractor, entered into a written contract with plaintiff whereby defendant would construct a log home for plaintiff on property plaintiff owned in Washington County. The contract price for the construction of the log home was $80,700. During construction of the home in 1990 plaintiff made daily visits to the building site. Upon completion of the home, a certificate of occupancy was issued. Plaintiff immediately took up residence in
Plaintiff subsequently commenced the instant action for breach of contract, alleging that defendant failed to use proper procedures and skills in constructing the log home which caused plaintiff to sustain damages in the sum of $10,000.
Defendant in his answer set forth a counterclaim alleging that despite full performance of the work contracted for, plaintiff failed and refused to pay the balance due on the contract in the sum of $5,000. Defendant then specifically alleged in his bill of particulars several extras that he performed for plaintiff at plaintiffs specific requests totaling $10,713.67. In his bill of particulars, defendant also claimed $5,000 in damages due to plaintiffs refusal to allow defendant to show the home as a model after construction.
Following a nonjury trial, County Court permitted the parties to submit proposed findings of fact and conclusions of law. Thereafter, the court dismissed plaintiffs complaint ruling, inter alia, that plaintiffs claims were based on special requests made by plaintiff during the construction of the log house. Concerning defendant’s counterclaim County Court found in defendant’s favor as to seven of the first eight extra items alleged and awarded damages for each of the seven extra items, amounting to a total award of $9,733.67. The court denied defendant’s request for $1,000 as an extra cost for the tub, toilet and tile due to insufficient proof, and also denied defendant’s request for $5,000 in damages for plaintiffs refusal to allow defendant to show the home as a model. Additionally, County Court awarded defendant costs and expenses in the sum of $1,159.55. Plaintiff appeals.
Subsequent to the perfection of this appeal, defendant moved for permission to serve an amended answer and counterclaim on plaintiff. This request was granted by County Court. Consequently, defendant argues that this appeal is now moot because the central issue raised by plaintiff was that the court granted relief to defendant in excess of the amount requested in the ad damnum clause. As a result, this Court allowed each party to submit supplemental briefs as to the propriety of County Court’s grant of defendant’s motion to amend the ad damnum clause.
The judgment of County Court should be affirmed. County Court properly awarded defendant reimbursement for orally
Plaintiff argues that County Court improperly awarded defendant reimbursement for changes and extras plaintiff allegedly verbally requested because the changes were not in writing and, therefore, were not binding on plaintiff. This argument lacks merit. Plaintiff bases his argument on a clause in the written agreement providing that any alteration or deviation involving specific extra costs will be executed only upon written orders (see, General Obligations Law § 15-301 [1]). However, this prohibition is not applicable where, as here, the conduct of the parties demonstrates an indisputable mutual departure from the written agreement and the changes were clearly requested by plaintiff and executed by defendant (see, Pau v Bellavia, 145 AD2d 609, 610; Rose v Spa Realty Assocs., 42 NY2d 338, 341, 343).
Plaintiff’s assertion that County Court improperly permitted defendant to testify as to the cost of providing the alleged modifications to the agreement, without furnishing documentary evidence supporting his testimony, is rejected. The record reveals that defendant was involved in every phase of the construction and clearly had personal knowledge of the cost of the modifications at issue (see, Reed Paving v Glen Ave. Bldrs., 148 AD2d 934, 935; Najjar Indus. v City of New York, 87 AD2d 329, 332, affd 68 NY2d 943).
We reject plaintiff’s contention that County Court’s verdict is against the weight of the evidence in respect to the denial of his claim for damages because of defendant’s failure to (1) utilize splints to keep the logs together, (2) construct a drain in the garage floor, (3) install Anderson brand glass doors, and (4) to construct retaining walls at the north end of the house to combat soil erosion. The testimony of defendant concerning the above items was based on his personal knowledge and was sufficient to sustain County Court’s denial of plaintiff’s entire claim. We note that although our authority to review a verdict in a nonjury trial "is not limited to determining whether the findings of the trial court are supported by the weight of the credible evidence, deference will still be given to the trial court’s assessment of credibility issues” (J & J Structures v Callanan Indus., 215 AD2d 890, 891, lv denied 86 NY2d 708; see also, Hoover v Durkee, 212 AD2d 839, 841; Carter v State of New York, 194 AD2d 967).
Also without merit is plaintiff’s argument that County Court erred in allowing defendant to amend the ad damnum clause
Mercure, Crew III, Yesawich Jr. and Spain, JJ., concur. Ordered that the judgment is affirmed, with costs.