Legal Research AI

Baker v. McCabe

Court: Court of Appeals for the First Circuit
Date filed: 2000-10-31
Citations: 230 F.3d 470
Copy Citations
17 Citing Cases
Combined Opinion
          United States Court of Appeals
                    For the First Circuit


No. 99-1843

                JOHN W. BAKER AND SUSAN BAKER,

                   Plaintiffs, Appellants,

                              v.

         TRUDY COXE, THOMAS W. FRENCH, JAY COPELAND,
          PATRICIA A. HUCKERY, BRADFORD G. BLODGET,
     JANE W. MEAD, SUSAN F. TIERNEY AND JANET G. McCABE,

                    Defendants, Appellees.


         APPEAL FROM THE UNITED STATES DISTRICT COURT

              FOR THE DISTRICT OF MASSACHUSETTS

          [Hon. Patti B. Saris, U.S. District Judge]


                            Before

                     Lynch, Circuit Judge,
                Coffin, Senior Circuit Judge,
                  and Lipez, Circuit Judge.



     Robert H. D’Auria for appellants.
     James A. Sweeney, Assistant Attorney General, with whom
Thomas F. Reilly, Attorney General, was on brief for appellees.




                       October 31, 2000
            COFFIN, Senior Circuit Judge.           This controversy, now

approaching its tenth anniversary, arises out of the frustration

experienced by plaintiffs-appellants, John and Susan Baker, in

applying for a permit to build a pier on Clark's Island in

Plymouth Harbor, Massachusetts.           The purpose of the pier was to

enable equipment to be unloaded onto the island to support

plaintiffs' agricultural pursuits, which included a tree farm.

The presence of a nesting site for sea birds on plaintiffs'

property,    and   the   possible   impact     of    future   agricultural

activity on it, aroused the concern of defendants-appellees,

eight Massachusetts officials and employees of environmental

regulatory bodies.1




     1    Seven of the defendants served at various levels in the
Massachusetts Executive Office of Environmental Affairs (EOEA).
Their names and relative positions are as follows:
     (1) Trudy Coxe, Secretary of EOEA, and Susan Tierney, former
Secretary;
     (2) Janet McCabe, former Assistant Secretary of EOEA for
Environmental Impact Review;
     (3) Bradford Blodget, state ornithologist and employee of
EOEA’s Division of Fisheries and Wildlife;
     (4) Thomas French, Director of the Natural Heritage and
Endangered Species Program, a division of Fisheries and
Wildlife;
     (5) Jay Copeland, environmental reviewer for Natural
Heritage; and
     (6) Patricia Huckery, intern and assistant to Copeland and
subsequently a Wetlands Environmental Reviewer for Natural
Heritage.
     The eighth defendant is Jane Mead, Director of the
Massachusetts Office of Coastal Zone Management.

                                    -3-
         By delaying the pier permit, defendants are alleged,

pursuant to 42 U.S.C. § 1983, to have infringed plaintiffs' due

process and equal protection rights (Count I) and their First

Amendment rights by retaliating against them for their exercise

of free speech (Count VII).2   The district court dismissed Count

I for failure to state a claim, see Baker v. Coxe, 940 F. Supp.

409 (D. Mass. 1996), and granted summary judgment to defendants

on Count VII, see id., 52 F. Supp 2d. 244 (D. Mass. 1999).

After perusing a tower of volumes of depositions and exhibits,

we conclude, as did the district court, that appellants have not

demonstrated interference with constitutional rights, but have

merely asserted righteous indignation at the zealous actions of

well-intentioned government officials.

                       Factual Background

         We report in suitably labeled groupings the essential

relevant facts.

         The Land Involved.      The Bakers have owned land on

Clark's Island since 1979. Since 1987, they have administered a

forestry trust in order to operate a tree farm.   On this site is

a major nesting area, or heronry, for several varieties of sea

birds, including herons and egrets.    At one time, the northern



    2     Seven other counts of the complaint asserted pendent
state law claims.

                               -4-
end of Clark's Island was reported to be among the largest

breeding grounds for waterfowl in the state of Massachusetts.

The Bakers had given the Manomet Bird Observatory access to the

island to conduct studies of the birds.

              The ACEC Issue.         In April 1989, a bill was considered

for presentation to the Massachusetts Legislature that would

have classified certain tracts of land, including the Bakers'

property, as an Area of Critical Environmental Concern (ACEC).

If so classified, that land would have been subject to use

restrictions and presumably a diminution in value.                         Realizing

that    his   land     would    be    subject   to   such    a    law,    Mr.   Baker

telephoned a state senator and "mentioned" that he opposed it.

When    the   Bakers    learned       that   the   Manomet       Bird    Observatory

supported the ACEC bill, they revoked the permission that had

been granted to enter their land.                    The ACEC bill did not

progress beyond the drafting stage and was never presented to

the legislature.

              The Pier Application. Two years later in May 1991, the

Bakers applied to the Army Corps of Engineers for a permit to

build a pier in order to receive farming equipment for use in

connection with their tree farm.                   The Corps was prepared to

issue    a    permit    when,    in    September     1991,   Jay        Copeland,   an




                                         -5-
environmental reviewer for Natural Heritage, received notice

from the Corps of the pending application.

               Natural   Heritage's       Interest.          Copeland    and   his

assistant, Huckery, felt that the nesting area was close enough

to the tree farm operations, which would have been aided by the

pier, to disrupt the heronry and cause the birds to abandon

their nests. Copeland requested that the permit not be issued

until he investigated the pier's possible impact.                       The Corps

obliged        and    initiated    notice-and-comment          proceedings     on

September 26, 1991.

               Contact with Dr. Parsons.              Copeland consulted his

superior, the Director of Natural Heritage, Thomas French, who

had visited the heronry five years earlier with Dr. Katharine

Parsons,       an    ornithologist      who   had    conducted    her    doctoral

research on Clark's Island.             French advised Copeland to gather

more information from Dr. Parsons.                  Dr. Parsons told Copeland

that in 1989 she had learned that someone had used a "bush hog"

mower     to    clear    brush    and    shrubbery      on    heronry    grounds,

destroying many unfledged birds and nests.                   She also mentioned

Baker’s opposition to the 1989 ACEC legislation and speculated

that the tree farm was not a serious effort but rather a "tax

dodge."    Copeland included these remarks in his notes.                 Not only




                                        -6-
had Copeland taken no position on the ACEC issue, but there was

no evidence that any other defendant had.

            Visit to the island.               On October 21, 1991, Copeland

visited     the   heronry        with     representatives         from    the     U.S.

Environmental Protection Agency, the U.S. Fish and Wildlife

Service and the Army Corps of Engineers, along with the Bakers'

project manager, and Blodget, the state ornithologist.                            They

found the heronry essentially destroyed, observing large piles

of     recently   cut        brush,     abandoned     nests,      and     protective

vegetation coarsely mowed or "bush hogged."                     But ornithologist

Blodget was of the opinion that, granted an opportunity to re-

vegetate, the heronry would revive.                    So Copeland felt that

further    review      was    needed     and    he   sought     support    from    Dr.

Parsons.

            Dr. Parsons' Letter.               Two days later, on October 23,

1991, she wrote a letter at Copeland's behest to underscore the

importance of the heronry.               Noting her credentials and prior

research at the heronry site, Dr. Parsons asserted in the letter

that the present owners had "clearly [] diminished and perhaps

decimated" the usefulness of the heronry.                     Copeland circulated

this    letter    to   other     agencies       to   try   to   get     support   for

obtaining an environmental review of the pier permit.




                                         -7-
             Contacts with Agencies.               At about this time, several

contacts were made with other agencies.                      Copeland inquired of

the Massachusetts Department of Revenue about the tax status of

the tree farm and sought to discover other ways in which the

Bakers      could    still     qualify      for    tax     concessions.          In    his

subsequent letter to the Corps of Engineers opposing the pier

permit,      Copeland        indicated      two    possibilities:         granting       a

conservation easement and seeking tax relief for allowing the

land   to    revert     to    its   natural       state.      French      and   Huckery

contacted the Department of Environmental Management to see if

the tree farm was being operated in compliance with the forestry

permit;      an     inspection      later    proclaimed       the    farm       in    full

compliance.         Blodget asked Christopher Dowd, an investigator

with the U.S. Fish and Wildlife Service, to determine whether

the destruction of the heronry in 1989 violated the Migratory

Bird Treaty Act, 16 U.S.C. §§ 703-712 (MBTA), and if so, to

ascertain who was responsible.                After some investigation, Dowd

concluded that the information was too stale to justify further

action.

             Natural Heritage Files Opposition.                     On November 8,

1991, Natural Heritage sent a letter to the Corps opposing the

pier   permit       application      on   the     ground    that    the    pier      would

facilitate tree-farming activity, which was likely to contribute


                                          -8-
significantly to the destruction of a major natural resource.

Both the U.S. Environmental Protection Agency and the U.S. Fish

and Wildlife Service sent similar letters.

            Plaintiffs Sue Dr. Parsons.      Shortly after this, Mr.

Baker sued Dr. Parsons, claiming that her October 23 letter was

defamatory.    Eventually, this suit was dismissed as contravening

a   law     proscribing    "strategic    litigation    against    public

participation" (SLAPP).        See Baker v. Parsons, No. 93-3212

(Mass. Super. Ct. Jan. 11, 1996) (dismissing suit pursuant to

Mass. Gen. Laws ch. 231, § 59(h), the anti-SLAPP statute).

            Issuance of the EIR.    The Massachusetts Environmental

Policy Act, Mass. Gen. Laws ch. 30, §§ 61-62 (MEPA), requires

review of all projects larger than a certain size.         Although the

size of the pier project did not mandate it, environmental

review could still be had under a "fail safe" provision of MEPA,

if requested by the Secretary of EOEA, by two state agencies, or

by ten citizens.       See 301 C.M.R. § 11.03(6).        In this case,

after failing to persuade the Secretary or another agency,

Natural Heritage did succeed, in October 1992, in garnering ten

citizens to request review.        The Bakers accordingly filed an

Environmental Notification Form on June 25, 1993.          On August 9,

EOEA issued a decision requiring the Bakers to take the next

step   by    filing   an   Environmental   Impact     Report   (EIR),   a


                                   -9-
comprehensive planning document that required an evaluation of

the environmental impact on the heronry not only of the proposed

pier, but also the associated forestry practices.

              Lawsuit Challenging the EIR.      The Bakers brought suit

against EOEA in Massachusetts Superior Court, challenging the

breadth of the EIR.     That court, through Judge Cratsley, limited

the EIR to "how the pier will affect the public interest in the

tidelands across which the pier will be built, and the public

interest in wetlands and water-related resources."                 Baker v.

Coxe, No. 935795C, 1994 WL 878942, at *3 (Mass. Super. Ct. Dec.

22, 1994).      Following this decision, the parties agreed on the

restricted scope of the EIR.

              Coastal Zone Management’s Consistency Review.               The

remaining hurdle for the Bakers was a federal consistency review

from    the   Massachusetts    Office   of    Coastal   Zone     Management.

Defendant Jane Mead was in charge of the review, which was

considerably delayed, apparently because of missing paperwork.

Eventually, in the spring of 1997, the pier permit was granted

and the pier was built.

              The district court wrote two opinions.        In the first,

it dismissed Count I, holding that the complaint did not allege

conduct egregious enough to invoke either a due process or an

equal   protection    claim.     In   the    second   opinion,    the   court


                                  -10-
granted summary judgment to defendants on Count VII, which

alleged     the   pier   permit    was      delayed    in    retaliation   for

plaintiffs' opposition to the ACEC legislation and their lawsuit

against Dr. Parsons.       We review these rulings de novo.                See,

e.g., Nestor Colon Medina & Sucesores, Inc. v. Custodio, 964

F.2d 32, 39 (1st Cir. 1992) (summary judgment); Coyne v. City of

Somerville, 972 F.2d 440, 442-43 (1st Cir. 1992) (Rule 12(b)(6)

dismissal).

                                  Discussion

A.          Substantive Due Process and Equal Protection

            In the field of local permits, the nature of the

government conduct (or misconduct) required to establish either

a substantive due process or an equal protection claim is so

similar as to compress the inquiries into one.                See PFZ Props.,

Inc. v. Rodriguez, 928 F.2d 28, 32 (1st Cir. 1991) (equating the

standards where the "equal protection claim represent[ed], in

effect, a recharacterization of [the] substantive due process

claim.").     In equal protection cases, we have articulated the

need   to    establish    a   "gross        abuse     of    power,   invidious

discrimination or fundamentally unfair procedures."                   Creative

Env'ts, Inc. v.      Estabrook, 680 F.2d 822, 832 n.9 (1st Cir.

1982); accord PFZ, 928 F.2d at 32.             In substantive due process

cases, we have required proof of an "abuse of power that shocks


                                     -11-
the conscience, or action that is legally irrational."               PFZ, 928

F.2d at 31-32 (internal quotation marks omitted).

             We have held that even an arbitrary denial of a permit

in violation of state law -- even in bad faith -- does not rise

above the constitutional threshold for equal protection and

substantive due process claims.         See Nestor Colon, 964 F.2d at

45 (“We have left the door slightly ajar for federal relief

[only] in truly horrendous situations.”).               We have thus observed

a   marked    difference   between      the    inevitable       misjudgments,

wrongheadedness, and mistakes of local government bureaucracies

and the utterly unjustified, malignant, and extreme actions of

those who would be parochial potentates.

             Plaintiffs alleged that three instances of official

misconduct reveal defendants' shocking abuse of power.                    The

first    occurred   when   defendants       requested     the   Massachusetts

Department of Revenue and the Plymouth Assessor's Office to

investigate whether plaintiffs' tree farm operation was a tax

dodge.    There was never an investigation.               The second alleged

abuse occurred when defendants sought to revoke the forestry

permit.      Although   this   did    lead    to   an    investigation,   the

operations were found to be in full compliance.                 The third and

most serious allegation was that defendants had reported, albeit

belatedly, possible violations of a federal statute, the MBTA,


                                     -12-
to   the    U.S.    Fish   and   Wildlife     service,       which       could    have

subjected plaintiffs to criminal prosecution.                     See 16 U.S.C. §

707.       However, the accusation was too old to merit further

investigation and the matter was put to rest without further

ado.   In fact, none of defendants' three alleged abuses resulted

in adverse action against plaintiffs.

             Plaintiffs invoke Rubinovitz v. Rogato, 60 F.3d 906

(1st Cir. 1995), in support of their claims.                  But the scenario

in Rubinovitz was much more stark.                 In that case, a city

official was alleged to have engaged in a vendetta against a

landlord      who   had    evicted     her    friend    by    enlisting          other

government officials from various departments to cut off the

landlord's     gas,    water,    and   sewage    services,         to    charge    the

landlord     with     building   code    violations,         and    to    frustrate

relations with a contractor.            See id. at 908-09.              Not only did

the spurned tenant's avenger wreak havoc on the landlord in

multiple ways, but there was not the slightest vestige of any

legitimate government purpose served.              Rubinovitz, in which we

acknowledged that plaintiff had adduced "only barely enough

evidence" to survive summary judgment, illustrates the extreme

"malicious      orchestrated      campaign"      needed      to     surmount       the

constitutional threshold.            Id. at 912.       Accordingly, that case




                                       -13-
does not support plaintiffs' more benign treatment as being

actionable.

            Although ultimately ruled by the Superior Court to be

beyond the subject matter of the Corps of Engineers permit, the

broad scale MEPA review of plaintiffs' pier application pursued

by defendants was not an irrational undertaking at the time.

The regulation, which governs MEPA review of private projects,

i.e., those that require no agency funding, limits the scope of

an EIR to "include no more than all direct and indirect impacts

from activity necessary to carry out" the project.           301 C.M.R.

§   11.02   (emphasis   added).    The   reach   of   such   a   word   as

"indirect" is rubbery enough to invite, initially at least,

varying views.

            The authority relied on by the Superior Court was

Villages Dev. Co., Inc. v. Secretary of the Executive Office of

Envtl. Affairs, 410 Mass. 100, 571 N.E.2d 361 (1991), which

involved a large multi-use community development project of some

1066 residential units on 379 acres, including various athletic

and recreational facilities.      In that case, a developer sought

a permit to create a new access road to a highway to protect a

bicycle path that crossed the existing access road.              The EIR

approved by MEPA gave the Secretary power to review not only the

access road project, but all potential impacts of the entire


                                  -14-
development, including traffic, wetlands, drainage, and waste

disposal.     The Supreme Judicial Court ruled that the scope of

the EIR exceeded the indirect impacts that might arise from

granting the permit to build an access road, holding that the

Secretary had authority to review only the access road project,

and its direct and indirect impacts, not the environmental

impact of the developer's entire project.                See id. at 113-14,

571 N.E.2d at 369-70.           This was a case where a very small tail

was sought to wag a very big dog.            In Judge Cratsley's case, the

tail was considerably bigger and the dog considerably smaller.

Although the Superior Court ruling, like the decision on which

it relied, found the EIR too broad, EOEA's review effort in this

case   was     not   irrational       so     as    to   violate     plaintiffs'

constitutional rights to due process and equal protection.                   We

therefore hold that the dismissal of Count I was proper.

B.           First Amendment Retaliation

             The   delay   of    a   land    use   permit   in    unjustifiable

retaliation for the applicant's expressions of his political

views may violate the First Amendment if plaintiff proves three

elements: that he engaged in protected speech, that he was

qualified for the permit, and that the delay was in retaliation

for the disfavored speech.           See Nestor Colon, 964 F.2d at 40-41.

In analyzing this claim, the district court acknowledged that


                                      -15-
only John Baker, not his wife Susan, had engaged in protected

speech and that, but for defendants' opposition, he would have

obtained a permit without delay.           Its analysis of plaintiff's

prima facie case therefore concentrated on the third element,

evidence of defendants' motivation.

             Of the eight defendants, the court found that the

evidence     pointed   to   only   four    who   had     actual    or   imputed

knowledge of Baker's opposition to the ACEC legislation --

Copeland, Huckery and French of Natural Heritage, and Janet

McCabe, the assistant EOEA secretary who directed the MEPA

review.     Defendants Coxe, Tierney, Blodget and Mead could not

have retaliated as a matter of law, the court reasoned, because

none had access to the file in which Copeland noted Baker's

opposition to the ACEC legislation and therefore could not have

known of the alleged catalyst for the retaliatory action.

             As to the remaining four defendants, the district court

held   the     circumstantial      evidence      of    retaliatory       motive

insufficient to hurdle summary judgment.               The court considered

eleven similar construction projects, none of which had been

subjected     to   environmental    review       under    MEPA's    fail-safe

provision.     Plaintiff urged the court to infer illegal motive

from the fact that these comparable permit applications had not

been targeted for review.       Of the eleven, however, only four had


                                    -16-
been located near heron colonies, and these were distinguished:

two involved less vulnerable roosteries, not heronries; one had

occurred   too    long   ago    to   be   relevant;   and   the   fourth   was

resolved amicably.

           The court also commented on the temporal remoteness

between the protected speech and defendants' alleged retaliatory

actions.   Two years had elapsed between Baker's 1989 opposition

to ACEC and the process of seeking MEPA review, which did not

commence until 1991.           Although the Bakers' suit against Dr.

Parsons may have ratcheted up the acrimony, defendants' review

of the pier was well under way prior to the suit against Dr.

Parsons and therefore could not have been in retaliation for it.

           Most    significantly,         the   court   not       only   found

insufficient evidence of illegal motive to satisfy plaintiff's

summary judgment burden, but also ruled in the alternative that

           Even   if   Mr.   Baker   had   sufficiently
           established the necessary elements of a
           prima facie case, defendants have asserted a
           compelling    nonretaliatory    reason    in
           rebuttal, one that plaintiff has done little
           to counter -- the concern that the project
           would facilitate the Bakers’ tree farming
           activities . . . . [D]efendants' primary
           reason for opposing the Bakers' project was
           not the environmental impact of the pier
           itself, but [the impact] of the secondary
           activities (tree and brush clearing) it
           would support.

Baker v. Coxe, 52 F. Supp 2d. at 253.


                                     -17-
               We comment briefly on the rulings regarding plaintiff's

failure to make out a prima facie case, although we prefer not

to    rest     our    own    decision    on     them.      Regarding   defendants'

knowledge of Baker's ACEC opposition, it seems to us a stretch

that    all    eight       defendants    shared      the   knowledge    of   Baker's

opposition from Copeland's handwritten notes in the file and

cared deeply enough about the issue to retaliate.                     No defendant,

not     even    Copeland,       had     taken    a   position    on    the    issue.

Postulating such a widespread, concerted effort among officials

from varying levels of different agencies assumes that any

environmental issue, no matter how ancient, would serve as a

lightning rod, galvanizing everyone who worked in the EOEA to

exact his vengeance on remote antagonists.

               As for the eleven projects cited by plaintiffs, wholly

apart    from        the    district    court's      conclusions,      we    see   one

overshadowing difference between them and the Clark's Island

project: only in the latter was there evidence of preexisting

damage to a bird nesting area.                The proximity of the heronry to

the tree farm operations and the site of the proposed pier

stimulated Copeland's concern before he had any information

about Baker's views on the ACEC bill.                       Although the Bakers

disavowed responsibility, the evidence of devastation observed

during the October 21, 1991, visit was unrebutted.                      To attempt


                                          -18-
to liken this pier project to others presenting no such evidence

of prior damage is to strain at gnats and swallow a camel.

              We agree with the court's ruling on motivation.                      To

draw     an    inference     of    differential       treatment         caused     by

retaliation would be unreasonable, particularly in light of

Baker's minimal opposition to the ACEC legislation and the lack

of interest on the part of Copeland and the other defendants.

There is no basis for suspecting any motive other than their

legitimate concern for the Clark's Island heronry for what

involved a lengthy period of substantial effort on the part of

defendants.          To   reason   that    spite    or     revenge   could       have

motivated everyone from an intern to the Secretary of the EOEA

would indeed be an exercise in attenuation.

              But we prefer not to labor on the somewhat technical

elements of the prima facie case.            In our view, the dispositive

ruling    of   the    district     court   was     that,    even   if    plaintiff

established the elements of retaliation, defendants proffered a

satisfactory and unrebutted nonretaliatory reason for their

actions: the concern that the project would facilitate the

Bakers' tree farming.             Appellant nonetheless takes exception

with the district court's finding that defendants' asserted

nonretaliatory reason was not pretextual.                    None of the four

claimed errors, however, holds up on examination.


                                      -19-
           The     first    contests     that   a    disputed       issue    of   fact

remains as to whether the Bakers were responsible for the damage

to the heronry.          This issue is immaterial because the point is

not who caused the destruction, but that it was damage to the

heronry,     not    Baker's     political       views,       that    first     evoked

defendants' concern.

           Second,        plaintiff    makes     much    of     the     fact      that

defendants' opposition focused mainly on the secondary effects

flowing from the construction of the pier -- clearing vegetation

to accommodate the tree farm -- and not on the pier itself.                         He

urges us to view the EIR as a thinly disguised attempt to

retaliate.         This    argument    misfires       because,       although      the

defendants' concerns directed at the secondary effects were

determined by Judge Cratsley to be misguided, those concerns

were legitimate and the record is bereft of evidence to support

a conclusion that they were animated by an unconstitutional

motive.    After Judge Cratsley's ruling, defendants refrained

from any further effort.

           Third,        plaintiff    asserts    that    defendants'         feigned

concern    for     the     environment    was       belied     by    their     "smear

campaign," which derided the tree farm as a tax dodge, accused

the Bakers of violating the MBTA, and resulted in a compliance

review of the forestry plan.             As we have noted, the "smears"


                                       -20-
were expressions of concern over the debilitated condition of a

salvageable nesting area.        Again, the record lacks evidence from

which   to    conclude    that   these   expressions   had    an   invidious

objective.

              Finally, plaintiff contends that the Clark's Island

site was not a unique or a particularly valuable nesting area.

Whether or not the diversity of the bird population made Clark's

Island unique seems beside the point.          Defendants' understanding

from    Dr.    Parsons    that   a   heronry   had   been    decimated   was

undisputed.

              We therefore conclude that on this record no reasonable

fact finder could find defendants' opposition to the pier permit

application to be in retaliation for Baker's protected speech.

              Affirmed.




                                     -21-