On the 2d day of June, 1926, the claimant entered into a contract with the State of New York for the construction of the two main piers of the Mid-Hudson bridge at Poughkeepsie. This claim arises out of an alleged breach of this contract by the defendant. The total contract price was $1,889,925. The contract called for the sinking of two caissons, one on either side of the Hudson river, known as the east and west caissons. They were to be sunk until they reached a suitable foundation in the bed of the river and upon these caissons, after they were in place, were to be erected the piers for this highway bridge. While the work was in progress on each of these caissons the east caisson tipped toward the east to an angle of about forty-five degrees and was thereafter righted and sunk. The principal item claimed by the claimant against the defendant is for the righting of this caisson.
These caissons were designed by Daniel E. Moran, one of the
“ Mid-Hudson Bridge — Conference at Poughkeepsie
“ July 15th, 1927.
“ Conclusion; — East Caisson.
“ (1) Continue removing bottoms.
“ (2) When the bottoms removed on west side correspond to the open pockets on the east side, begin dredging in pockets and continue dredging until it is safe to remove more or all pockets.
“ Conclusion; — West Caisson.
“ (1) Level up with concrete.
“ (2) Lighten caisson by pumping.
“ (3) Place stone along west side, 1,000 tons (about).
“ (4) Catch on anchor of East Caisson and pull toward east, putting strain on all east anchors.
“ (5) Dredge on east side as necessary.”
At that time the claimant was engaged in removing bottoms from certain pockets of the east caisson. It had removed those from pockets 3, 5 and 7 on the east side, 20, 22 and 24, which were center pockets, and 16, which was a pocket on the west side. It was also endeavoring to remove the bottoms from two other pockets on the west side, viz., 14 and 12. It will be noted that the contractor was to do two things with relation to the east caisson, one, to continue removing bottoms, two, when the bottoms removed on the west side corresponded to the open pockets on the east side it was to begin dredging in the pockets and continue until it was safe to remove more or all pockets. There is testimony on the part of the defendant that Mr. Moran at this conference advised the contractor that there was to be no dredging beneath the cutting edge. This is contradicted by the claimant’s witnesses.
On July 15, 1927, no dredging had been done at the site of the east caisson save a small trench along the northeasterly edge thereof when the cutting edge first landed on the river bottom. After the conference of July 15, 1927, the contractor proceeded to remove bottoms until on the 26th day of July, 1927, he had removed bottoms from three pockets on the east side, five in the center and two on the west side. At that time the bottom of the east caisson had penetrated the river bed approximately eleven feet with a list of four-tenths of a foot to the west. Also, after the conference of July fifteenth the contractor began dredging in the pockets where the bottoms had been removed, and from that date until July 27,
It is contended by the claimant that the memorandum of July 15, 1927, constituted an order from the State to the contractor, that such order was carried out and that this was one of the reasons why the caisson listed. It may be conceded that such was the effect of the memorandum because under the contract the State reserved to itself the right to supervise the method of doing the work. The difficulty with the claimant’s contention with regard
In addition to contending that the defendant had issued an order which the claimant was bound to obey and that in so doing the damage had been caused, the claimant contended that the caisson was not properly designed in that it lacked stability and that this was the real reason for the fisting of the caisson. The State defends on the ground that the design was proper and claims that the quality of stability was not lacking. In support of its contention, the claimant offered testimony on the part of certain experts to the effect that the center of buoyancy, which is the center of volume of the underwater body, at one stage was lower than the center of gravity and that this caused the caisson to tip. These experts claimed that the caisson was not properly designed to enable it to be lowered to the bottom of the river. Of course, the complete answer to this argument lies in the fact that both caissons were successfully lowered to the river bed. It is true that at one point during the operations, about three feet of sand ballast was added in the bottom of each pocket and that the center walls of the caisson were never constructed as high as the perimeter wall. Be that as it may, each caisson was sunk and the east caisson did not tip until after the claimant had excavated soil from underneath the center and easterly third, leaving the westerly third resting upon solid earth. The Court of Claims has found that the east caisson was stable when floated and was stable when it landed on the bottom of the river.
There is no difference of opinion between the members of our court upon the law of the case. The majority readily concede both that the memorandum of July 15, 1927, constituted an order and that the contractors might rightfully presume that the body of the caisson was proper in design and possessed the quality of stability. The entire question with relation to this claim is one of fact. The facts have been resolved by the court below in favor of the defendant. These findings are borne out by the record. There was no breach of the contract by the State. The judgment of the Court of Claims dismissing this item was proper and is affirmed.
McNamee and Crapser, JJ., concur; Hill, P. J., dissents, with an opinion, in which Heffernan, J., concurs.