Cleary v. Sohier

Court: Massachusetts Supreme Judicial Court
Date filed: 1876-04-05
Citations: 120 Mass. 210, 1876 Mass. LEXIS 153
Copy Citations
3 Citing Cases
Lead Opinion
By the Court.

The building having been destroyed by fire without fault of the plaintiff, so that he could not complete his contract, he may recover under a count for work done and materials furnished. Lord v. Wheeler, 1 Gray, 282. Wells v. Calnan, 107 Mass. 514, 517. Judgment for the plaintiff.