Combustion Engineering, Inc. v. Miller Hydro Group

January 3, 1994   UNITED STATES COURT OF APPEALS
                    FOR THE FIRST CIRCUIT
                                        

No. 93-1266

                 COMBUSTION ENGINEERING, INC.

                    Plaintiff, Appellant,

                              v.

                 MILLER HYDRO GROUP, ET AL.,

                    Defendants, Appellees.

                                         

No. 93-1267

                COMBUSTION ENGINEERING, INC.,

                     Plaintiff, Appellee,

                              v.

                  MILLER HYDRO GROUP, ET AL,

                   Defendants, Appellants.

                                         

                         ERRATA SHEET

   The opinion  of this Court  issued on December 30,  1993, is
amended as follows:

   On page  25, 1st  full paragraph, line  5, "When  a directed
verdict  was served,"  should  be "after  a directed  verdict was
ordered,".

                UNITED STATES COURT OF APPEALS
                    FOR THE FIRST CIRCUIT
                                         

No. 93-1266

                COMBUSTION ENGINEERING, INC.,

                    Plaintiff, Appellant,

                              v.

                 MILLER HYDRO GROUP, ET AL.,

                    Defendants, Appellees.
                                         

No. 93-1267

                COMBUSTION ENGINEERING, INC.,

                     Plaintiff, Appellee,

                              v.

                 MILLER HYDRO GROUP, ET AL.,

                   Defendants, Appellants.
                                         

        APPEALS FROM THE UNITED STATES DISTRICT COURT

                  FOR THE DISTRICT OF MAINE

           [Hon. Gene Carter, U.S. District Judge]
                                                 
                                         

                            Before

               Boudin and Stahl, Circuit Judges,
                                               

                 and Fuste,* District Judge.
                                           

                                         

                

*Of the District of Puerto Rico, sitting by designation.

John H.  Montgomery with whom  Gordon F. Grimes,  David A.  Soley,
                                                                 
Diane S. Lukac, Faith  K. Bruins and Bernstein, Shur,  Sawyer & Nelson
                                                                  
were on briefs for plaintiff.
George  S.  Isaacson  with whom  David  W.  Bertoni  and  Brann  &
                                                                  
Isaacson were on briefs for defendant Miller Hydro Group.
    
Roy  S. McCandless with whom  Robert S. Frank, Mark K. Googins and
                                                              
Verrill & Dana were on brief for party-in-interest appellee Kansallis-
          
Osake-Pankki.

                                         
                      December 30, 1993
                                       

     BOUDIN,  Circuit Judge.   This  appeal  arises out  of a
                           

complex commercial  dispute,  with  overtones  of  deception,

relating to the  construction of a hydroelectric  facility in

Maine.    In  the ensuing  litigation,  neither  the builder,

Combustion Engineering,  Inc., nor  the  owner, Miller  Hydro

Group,  succeeded  in  recovering against  the  other.   Both

appeal.  We affirm the district court.

                        I. BACKGROUND

     In the early 1980's,  Miller Hydro set about  creating a

hydroelectric facility on the Androscoggin River  near Lisbon

Falls, Maine, to generate electricity.  It first negotiated a

contract with Central Maine Power Company by which the latter

agreed to  purchase a  set amount of  power from  the planned

facility.   Miller  Hydro  also  obtained  financing  from  a

Finnish bank, Kansallis-Osake-Pankki, and  a license to build

the  project  from the  Federal Energy  Regulatory Commission

("FERC").

     In May 1986,  Miller Hydro entered into  a contract--the

central document  at  issue  in  this  case--with  Combustion

Engineering  for  the  latter  to build  the  facility  on  a

"turnkey" basis.   The turnkey contract,  by cross-reference,

provided for a facility including turbines with a capacity of

7800 cubic  feet of  water per second.1   Under  its contract

                    

     1The  7800 cfs figure, which  is important to this case,
appears  in technical specifications  annexed to  the turnkey
contract.   A shorter and more general "project description,"

                             -3-

with  Maine Central  Power,  Miller  Hydro  was  expected  to

provide power capacity of 14  megawatts, and the Miller Hydro

contract  with Combustion Engineering  also referred  to this

requirement by cross-reference.  

     Subject  to  these  and  other  specifications,  it  was

entirely up to Combustion Engineering to design and build the

new facility.   The turnkey contract contained  incentive and

penalty provisions,  one of which  lies at the heart  of this

case.  The price set for construction was fixed at just under

$24  million,  but  the  contract  provided  that  Combustion

Engineering would  earn a sliding-scale  bonus for efficiency

to the extent  that the facility produced power  in excess of

77,500  megawatt hours  per  year;  a  corresponding  penalty

provision reduced Combustion Engineering's fixed price to the

extent that the  facility was less efficient than a specified

minimum output of 73,500 megawatt hours per year.

     The  turnkey contract provided that the bonus or penalty

would be determined by certain tests  that would be performed

by an independent  tester at the completion  of construction.

A  protocol  specified  how  the  test  would  be  conducted,

including a  requirement that  the  facility be  tested at  a

"total flow of 7800 cfs."  It  also permitted Miller Hydro to

require  a   retest  by  a   different  tester  if   it  were

                    

also  annexed,  refers  to  turbine  discharge   capacity  of
"approximately 8,000" cfs.

                             -4-

dissatisfied with  the  initial test.    It appears  that  if

Combustion  Engineering had built a highly efficient plant of

the size specified, Miller Hydro might have been liable for a

bonus payment as large as $850,000.

     What  happened instead  is  that Combustion  Engineering

built a far larger plant  with turbines having a maximum flow

capacity of over 9000 cfs or more and a power capacity  of 18

to 19 megawatts.   Miller Hydro claims that  this increase in

size  was  done  deliberately  and   secretly  by  Combustion

Engineering  in order to  manipulate the bonus  provisions of

the construction contract.  Miller Hydro and Kansallis-Osake-

Pankki both say that they did not learn of the increase until

it was too late to modify the facility.

     When the facility was tested at a total  flow of 9000 or

more cfs, the tester reported results that equated to a bonus

of over  $8  million.   In  Miller Hydro's  view,  Combustion

Engineering had invested $1 million or so of its own money in

increasing the facility's  size in order  to reap a  ten-fold

increase  in the incentive bonus.  Miller Hydro also objected

to the  test itself and  invoked its right  to a retest.   It

also refused to state its "final acceptance" of the facility,

or to make final construction  payments.  Instead of agreeing

to  a  retest, Combustion  Engineering promptly  brought suit

against Miller Hydro in district court.  

                             -5-

     In its complaint Combustion Engineering set forth claims

based  on   contract,  unjust   enrichment,  and   promissory

estoppel, and it sought to enforce a mechanic's lien  against

the facility.  As damages,  it demanded an incentive bonus of

$8.16 million,  a final  construction payment  of $45,364,  a

further  payment of $1,236,427 in amounts withheld from prior

payments, and a  claimed early completion bonus  of $893,894.

Kansallis-Osake-Pankki  intervened,  arguing  that Combustion

Engineering had by contract subordinated its rights under the

mechanic's  lien  statute  to  the  bank's  mortgage  on  the

facility.

     Miller   Hydro    counterclaimed   against    Combustion

Engineering  asserting  contract,   fraud,  and  racketeering

claims.  Miller  Hydro tells us that Central  Maine Power has

not  agreed to  buy the  extra  power that  the facility  can

generate and that Miller Hydro  will or may incur  additional

costs  as a  result  of  the facility's  enlarged  size.   In

particular, it says that it  may face penalties from FERC for

building a facility larger than the license permits, and that

it may  have to  reconstruct fish-protection facilities  that

were keyed to the originally planned smaller turbines.

     Because  the case  presented  both  legal and  equitable

claims,  the district  court  bifurcated the  trial.   In the

first phase, Combustion Engineering tried its contract claims

to the  jury and  Miller Hydro tried  its contract  and fraud

                             -6-

counterclaims to the same jury.  (Miller Hydro's racketeering

counterclaim  was  dismissed by  the  court  in circumstances

recounted  below.)   In  the  second  phase the  trial  judge

proposed   to  rule   himself  on   Combustion  Engineering's

equitable claims (unjust enrichment and promissory  estoppel)

and  to  resolve  any   outstanding  issues  concerning   the

mechanic's   lien  claim,   including  priority   as  between

Combustion Engineering and Kansallis-Osake-Pankki.

     After Combustion Engineering presented its case in chief

to the jury, the district  court entered judgment as a matter

of law against Combustion Engineering on its contract claims.

The court  held that  Combustion  Engineering had  materially

breached its contract in testing the facility at a total flow

in excess of 7800 cfs  and in other departures from the  test

protocol.   The court  found it  unnecessary to reach  Miller

Hydro's argument that  the refusal of Combustion  Engineering

to  agree to  a  retest was  also a  breach of  contract that

barred recovery.

     Miller  Hydro's  own  contract and  fraud  counterclaims

against  Combustion Engineering  were submitted  to  the jury

together with a  special verdict form.  On  January 23, 1992,

the  jury  returned  its  verdict,  finding  that  Combustion

Engineering  had  breached  the  contract  by  designing  the

facility for a maximum flow in excess of 7800 cfs, and not in

accordance  with  the  FERC  license.   It  found  the actual

                             -7-

maximum  flow to be  at least 9000  cfs and the  power output

capacity to be  18 megawatts.  It also  found that Combustion

Engineering  had  provided  materially  false information  to

Miller Hydro.   Nevertheless, the jury awarded  no damages to

Miller Hydro either for breach of contract or  fraud, finding

(in  response to special verdict questions) that Miller Hydro

had not  proved damages  from the breach  of contract  or the

misrepresentations. 

     On October 6,  1992, the  trial judge  filed a  decision

denying  Combustion  Engineering  recovery on  its  equitable

claims.    The  court  held that  under  Maine  law  material

breaches  of  contract  did  not  automatically  preclude  an

equitable recovery but that the plaintiff's good faith effort

to  perform was  a  prerequisite; and  the  court ruled  that

Combustion Engineering "did  not seek in  good faith to  meet

its  obligations  under  the  turnkey  contract,"  given  the

deliberate breaches and misrepresentations found by the jury.

The jury findings, the court  said, were binding on the court

in deciding the equitable claims.  

     On  the same  day, the  trial judge  denied a  motion by

Combustion  Engineering  requesting  the  court  to  order  a

retesting of the  facility, to appoint a  special master, and

to allow the  filing of a supplemental complaint.   The court

ruled that this motion, filed on June 3, 1992, well after the

jury  verdict,  came  too  late.    Not  only  had  extensive

                             -8-

discovery  been conducted but the jury trial had already been

held and  the case  was nearing  completion.   Further delay,

said the court, would be unfair to both of the other parties.

     Finally, by decision  entered on December 22,  1992, the

trial judge ruled on Combustion Engineering's mechanic's lien

claim.  It rejected the  claim on the ground that enforcement

of such  a lien  required a valid  underlying claim  and that

Combustion Engineering  had been found  to lack such  a valid

claim.  The court granted Kansallis-Osake-Pankki's request to

discharge  the mechanic's  lien.    It  also  granted  Miller

Hydro's requests, made in its counterclaims, for declarations

of breach  of contract  and  misrepresentation by  Combustion

Engineering.  

     On January 11, 1993, the court entered final judgment in

the case.   Combustion Engineering has appealed  the directed

verdict against it on its  contract claims, and the denial of

its  equitable  claims,  its mechanics  lien  claim,  and its

motion  to  retest.   Miller Hydro  has appealed  the earlier

dismissal of its racketeering counterclaim.  Neither side has

explicitly sought to  disturb the judgment on  Miller Hydro's

contract  and  fraud  counterclaims  entered  upon  the  jury

verdict.

                        II. DISCUSSION

     Combustion Engineering  advances a  series of  different

arguments on appeal, variously involving the directed verdict

                             -9-

against it  on  its contract  claims,  the dismissal  of  its

equitable claims,  the district  court's refusal  to order  a

retest, and  the ruling discharging the mechanic's  lien.  We

begin with these  issues, reserving for the  end a discussion

of Miller Hydro's cross-appeal.

     Combustion  Engineering's  first, and  most  extensively

briefed,  point  on  appeal  is its  attack  on  the district

court's  grant of a directed verdict--now renamed judgment as

a matter of law, Fed. R. Civ. P. 50(a)--dismissing Combustion

Engineering's  contract  claims  against  Miller  Hydro.   We

review  such  a dismissal  de  novo,  asking whether  on  the
                                   

evidence  presented  a  reasonable jury  could  find  for the

plaintiff.   Murray v.  Ross-Dove Co., 5  F.3d 573,  576 (1st
                                    

Cir. 1993).  In considering this question, it is assumed that

issues  of  credibility  are resolved,  and  inferences  from

evidence drawn, in favor of the non-moving party.  Id.
                                                      

     At the threshold one might  think that the attack on the

directed verdict is barred by the jury's subsequent findings.

These  findings, on  Miller Hydro's  counterclaims, establish

that Combustion  Engineering breached the turnkey contract by

building  a  plant  well  in  excess  of  the  contracted for

capacity.   Miller Hydro  claims that  Combustion Engineering

has  forfeited its  right  to  challenge  those  findings  by

failing  to  "appeal"  from  the  jury   verdict;  Combustion

Engineering  replies that  appeals  are from  judgments,  not

                             -10-

findings, and that it has appealed the judgment rejecting its

contract claims.

     We  think that  in this  case the  jury findings  do not

settle  the propriety  of  the directed  verdict.   The  jury

verdict might  insulate the directed  verdict if the  jury in

deciding the counterclaims had independently reached the same
                                            

conclusion on the same issue.   But here the trial  judge, in

submitting the counterclaims to the jury, instructed the jury

that as  a matter of  law "the turnkey contract  required the

construction of a hydroelectric facility  . . . . designed to

accommodate a maximum  hydraulic flow of 7800  cubic feet per

second."2 

     A central  theme of Combustion Engineering's argument on

appeal is that the contract  did not make 7800 cfs a  maximum

figure.   We  think it  would be odd  to uphold  the directed

verdict on the  ground that the jury found the  same thing as

the district  judge (namely, that  the 7800 cfs figure  was a

ceiling) when  in fact the district  judge told it  to do so.

This  is not  to  say that  the district  court  erred in  so

instructing  the jury--on  the contrary,  we  agree with  its

reading of  the contract--but rather to explain  why we think

                    

     2The court also told the  jury that the court itself had
rejected Combustion Engineering's contract claims because the
court had found (in directing a verdict) a material breach of
contract by Combustion  Engineering, namely,  its failure  to
show compliance "with the testing requirement of testing at a
total flow of  7800 cfs" as required by  the protocol annexed
to the turnkey contract.

                             -11-

that the directed  verdict decision by the district  court is

not insulated by  the jury verdict and should  be reviewed on

the merits.

     Turning  to the  merits, the  first issue  before us  in

relation  to  the  directed verdict  is  whether  the testing

protocol required that the final acceptance test be conducted

at a  maximum of  7800  cfs.   Although  formally this  is  a

separate  issue from whether  the turnkey contract  made 7800

cfs  the maximum  size for  the facility,  we think  that the

reality here  is that the  two issues are interrelated.   One

might be able to read the 7800  cfs figure differently in the

test protocol  and the  contract  design specifications,  but

would  be  unlikely  to  do  so in  this  case.    Combustion

Engineering treats the two issues together, and so do we.

     The district  court construed  the turnkey  contract and

ruled as  a matter  of law  that the  7800 cfs  figure was  a

target and ceiling  figure for both construction  and testing

of the  facility.  As noted  above, the 7800  cfs figure does

appear   in   annexed   technical   specifications   although

apparently  not in  the body  of the  contract itself.   This

cross-reference  might not be  conclusive if it  stood alone,

but it does  not stand alone.   Two other pieces of  evidence

intrinsic  to the  contract--the FERC  license  and the  test
         

protocol--support the view  that the 7800 cfs figure was both

target and ceiling for the project.

                             -12-

     First,  the FERC license was incorporated in the turnkey

contract  by  cross reference,  the  contractor  promising to

construct the  facility in accordance with the  license.  The

FERC license refers to the  project as having turbines with a

total capacity  of 14 megawatts,  a figure  that the  turnkey

contract treats as a counterpart to the 7800 cfs  figure.  As

already  noted, the turnkey  contract refers to  14 megawatts

and the annexed technical specifications to 7800 cfs.3

     Second, the test protocol annexed to the turnkey project

clearly provided for  testing at "a total flow  of 7800 cfs."

One can imagine a  contract providing for a facility   with a

large capacity  while limiting the test to  some lower figure

(perhaps  the  expected  normal flow).    Here,  however, the

reference  to the same figure in the technical specifications

and in  the test  protocol strongly suggests  as a  matter of

common sense that the facility was  to be built and tested at

that figure.

     Combustion Engineering's brief argues that the 7800  cfs

figure  was actually intended  as a minimum,  urging that the
                                           

figure be read as akin to other figures in the  contract that

are  allegedly  performance minima.    Combustion Engineering

                    

     3There was  also evidence  that the  license application
initially reflected a  flow of 6800 cfs and  that approval of
FERC to increase this to 7800 was obtained in 1985.  However,
there is some doubt that  this evidence could be described as
intrinsic, at least in the form submitted, and we do not rely
upon it to sustain the directed verdict.

                             -13-

also suggests that in  any event the  7800 figure was only  a

rough  approximation.    It  also  argues  that  the  parties

contemplated  modifications  in whatever  figure  was chosen.

Finally, it claims that Miller  Hydro learned of the increase

and waived  its objection.   Some of  these arguments  are in

tension with others, and none is persuasive.

     There  may be figures  in the turnkey  contract that are

performance minima.   But certainly  the normal reading  of a

performance or capacity figure in a license is that, like the
                                           

speed limit sign on a highway,  it is intended as a  maximum.

Here, the contract said that the facility  was to be built in

accordance with  the license, and the license  provided for a

14  megawatt facility, a figure that the contract's technical

specifications equated  to a  facility having  a capacity  of

7800 cfs.   Thus, we  think that  7800 cfs was  a target  and

ceiling and not a minimum.

     We agree with Combustion Engineering's claim  that, even

treating 7800 cfs as a  ceiling, there may be room  for minor

deviations;  but an increase to over 9000 cfs--there was some

testimony that  9600 cfs  or more  was the  real capacity--is

hardly  a  minor  change.     Correspondingly,  the  megawatt

capacity increased from 14 megawatts to 18 megawatts or more,

hardly  a  minor  adjustment.    The  engineer  who  assisted

Combustion  Engineering testified that a change from 7800 cfs

to 9000 cfs or more would be material.

                             -14-

     There were  provisions for  modification of  the turnkey

contract  by  agreement, but  Combustion Engineering  has not

proved   any  agreement  by   Miller  Hydro   permitting  the

contractor to exceed the  7800 cfs figure.  As  for the claim

of waiver or estoppel, that  issue was submitted to the jury.

The jury's verdict that  Combustion Engineering breached  the

contract  by constructing a  facility in  excess of  7800 cfs

appears  implicitly to reject the waiver or estoppel defense.

This is quite understandable since there is no clear evidence

that Miller Hydro knew of the change in capacity until it was

too  late to alter course, and substantial evidence indicates

that Combustion Engineering sought to conceal its deviation. 

     Combustion Engineering argues that at the very least the

contract  was ambiguous,  so that  extrinsic evidence  should

have been admitted and  the issue submitted to a  jury.  Some

jurisdictions  follow  the traditional  binary  rule  that an

integrated contract  is either clear or ambiguous and, in the

former  case, extrinsic  evidence  is excluded;  other states

follow  the  so-called  modern approach,  allowing  extrinsic

evidence  to   "interpret"  even   a  seemingly   unambiguous

document.   See  A. Farnsworth, Contracts    7.12,  at 521-23
                                         

(1990).  But  we need not decide  in this case precisely  how

Maine resolves  the problem,  because Combustion  Engineering

has not properly pointed to any extrinsic evidence that could

alter the result.

                             -15-

     We   say    "properly"   pointed    because   Combustion

Engineering's  brief  does  have an  entire  page  of capsule

summaries of  documents,  events or  testimony purporting  to

comprise  relevant extrinsic  evidence.    In  this  page  of

summaries, not  a single  reference appears  to a  transcript

page or an exhibit number or to an appendix or addendum page.

There is some  similar material in the fact  statement of the

brief, with record or appendix references, and we have sought

to match up the summaries  with relevant portions of the fact

statement.  Having  done so as best we can, our conclusion is

that this  "evidence," even  if considered,  does not  create

ambiguities warranting jury resolution.

     To take  Combustion Engineering's first  capsule summary

as an  example, the brief  says that an engineer  working for

both  Combustion Engineering and Miller Hydro told the latter

that "the Turbine  Specifications were minimums that  did not

limit Combustion  Engineering's right  to select  appropriate

equipment."   The engineer's actual  letter, however,  merely

affirms  the contractor's right  to design the  generator and

electrical equipment and says  that "the overall  performance

expected  of  the  equipment  was  outlined  in  the  minimum

criteria . .  . ."  Nothing  in the quotation associates  the

general  reference  to  minimum criteria  with  the  7800 cfs

figure.  The balance of the evidence summarized by Combustion

Engineering is even less persuasive.

                             -16-

     Later in its brief, Combustion Engineering makes a quite

different  argument.   It  says  that  even assuming  that  a

violation  of the  test protocol  occurred,  this should  not

debar  Combustion Engineering  from  all recovery  under  the

contract.  It argues that  testing was directed to fixing the

efficiency bonus or  penalty, and that proper  testing should

not be  found to  be a "condition  precedent" to  recovery of

other  amounts,  such  as the  final  payment  due  under the

contract or sums  retained temporarily  from prior  payments.

The  company  also  invokes  the  notion   that  "substantial

performance" is sufficient to allowit to sue on the contract.

     It may be  a close question  whether standing alone  the

breach   of  a   testing   protocol--among  other   breaches,

Combustion  Engineering tested  the facility  at  a flow  far

greater  than  7800  cfs--should  preclude  recovery  of  the

balance of the contract price  as well as the possible bonus.

If this were  the posture of the case, we would be obliged to

engage  in a  close  reading  of the  test  protocol and  its

relation  to the  rest of  the contract.   One  can certainly

conceive of a case in which the contractor failed to fulfil a

requirement needed to earn a  bonus payment but would not, in

ordinary  circumstances, be  deemed  to  lose  the  right  to

collect the basic price for work done.

     Here, however, Combustion Engineering  violated not only

the test protocol but the contract specifications by building

                             -17-

an oversized  facility, and  the breach  was substantial  and

deliberate.   The jury verdict alone confirms the substantial

breach,   and  its  deliberate   character  is   patent  from

Combustion  Engineering's misrepresentations  and efforts  at

concealment.   Even if the violation  of the testing protocol

did not  preclude all  further recovery  under the  contract,

assuredly  the substantial and  deliberate breach did  so and

precludes  a   contractual   claim   based   on   substantial

performance.  

     This premise of a substantial and deliberate breach also

disposes  of Combustion  Engineering's  equitable claims  for

unjust enrichment and promissory estoppel.  We agree with the

district court  that, even  if such  claims may  be permitted

under  Maine law  where contractual  claims  have been  lost,

Maine  law appears  to make  good faith  a condition  of such

equitably based  recoveries.4  Here  Combustion Engineering's

good faith is  disproved by the jury verdicts.   The verdicts

                    

     4The  most recent Maine decision  to which we are cited,
says  that an  equitable  recovery may  be  allowed when  the
builder  provided  materials  or   services  "in  an   honest
endeavor"  to  perform  the  contract.    Loyal  Erectors  v.
                                                         
Hamilton  &  Son,  Inc., 312  A.2d  748,  755-56  (Me. 1973);
                      
Accord,  Levine v.  Reynolds, 54  A.2d 514,  517 (Me.  1947).
                            
Even  if Maine  law is  more fluid,  allowing the  judge some
flexibility  in weighing  the  equities, see  A. Horton  & P.
McGehee,  Maine Civil Remedies,  11-17 (2d ed.  1992), we are
                              
certain  from its  statements here  that  the district  court
would exercise that  discretion to disallow recovery,  and we
would have no difficulty sustaining that decision.

                             -18-

were binding on the court, see Dairy Queen, Inc. v. Wood, 369
                                                        

U.S. 469 (1962), and are amply supported by the evidence.

     This  outcome  becomes  even  more  compelling when  one

appreciates that the deliberate and substantial breach placed

Miller Hydro at risk of significant harm.  There may be cases

where building "more"  than one promised is a  benefit to the

owner; but  that is hardly assured in the case of a federally

licensed dam.   Indeed,  it may be  that Miller  Hydro itself

will  ultimately suffer because  of violation of  its federal

license  terms or because the fish protection facilities will

have to be  rebuilt.  Nor is  it clear that it  has gained by

obtaining extra  power that  it says it  can neither  sell to

CentralMaine Power nor economically wheel to other customers.

     Miller Hydro  alludes  to  these  possibilities  without

providing much supporting detail.   We have no way of knowing

how much substance  there is to them, nor  whether short term

disadvantages may be offset  in part, or even outweighed,  by

the long-term benefits  of a larger  facility with a  greater

capacity  to  produce  power.    What  we  do  know  is  that

Combustion  Engineering was not entitled to create such risks

for  Miller  Hydro by  secretly  deviating--substantially and

deliberately--from  the  terms  of the  contract.    That one

behaving  in this fashion now forfeits  the balance due under

the contract does not seem in the least unfair.

                             -19-

     Combustion Engineering has  two remaining arguments that

require little  discussion.  It  first argues that  the court

should have granted  its motion for a retest  of the facility

in accordance  with the protocol.   This demand was  made not

only  after  Combustion Engineering  had  turned down  Miller

Hydro's  own request  for  retest,  but  after  the  directed

verdict  and the  jury verdict  in this  case.   The district

court's   refusal  to  grant  this  highly  belated,  if  not

impudent,  request for equitable  relief was well  within its

discretion.  

     The other argument is Combustion Engineering's attack on

the  district court's  refusal to grant  it relief  under the

Maine    mechanic's   lien   statute.      It   may   be   an

oversimplification  to say that  the statute creates  only an

additional remedy and not  a new right; but it  is clear that

under Maine  law, as  in many  jurisdictions, the  mechanic's

lien depends  on the claimant having a valid underlying claim

for monetary  recovery based on  the construction  performed.

Bangor Roofing & Sheet Metal Co. v. Robbins Plumbing Co., 116
                                                        

A.2d 664, 666 (Me. 1955).  Combustion Engineering has no such

valid underlying claim  in this case,  so the district  court

properly discharged the mechanic's lien.

     There remains  Miller Hydro's  own appeal.   As  already

noted,  the   jury   found  (in   deciding   Miller   Hydro's

counterclaims) that  Combustion Engineering had  breached its

                             -20-

contract  and engaged in misrepresentation but that the proof

did  not support  a finding  of  damages from  the breach  or

falsehoods.   Miller Hydro does not challenge these verdicts,

which limited  its judgment  on these  claims to  declaratory

relief.  Rather,  it argues that the district  court erred by

dismissing  its   remaining  racketeering   counterclaim  and

declining to submit that claim to the jury.

     The  remaining  counterclaim   comprised  three  related

counts   under   the   Racketeer   Influenced   and   Corrupt

Organizations Act,  18 U.S.C.    1961, et seq. ("RICO").   In
                                              

substance,  these  RICO  counts,  asserted  in  a   pleadings

amendment,  charged Combustion Engineering and various of its

employees with a fraudulent scheme to obtain inflated bonuses

from  one or more power-plant construction projects.  Various

uses  of  the  mails  or  telephone  system  in  aid  of  the

fraudulent scheme  were alleged.   For  the RICO  violations,

Miller   Hydro  sought   damages,   injunctive  relief,   and

attorney's fees.

     After the RICO counts were added, Combustion Engineering

on April 16, 1991, moved to dismiss the counts under  Fed. R.

Civ. P. 12(b)(6) for failure to state a claim; it asserted as

grounds for  dismissal various somewhat technical  defects in

the RICO counterclaims  (e.g., that  a separate  "enterprise"
                             

had not been sufficiently alleged).   On October 4, 1991, the

district court granted the motion  to dismiss but on a ground

                             -21-

only  barely suggested by  a footnote in  the motion, namely,

that an  earlier, October  19, 1990,  discovery order  by the

magistrate judge had found a  failure of Miller Hydro to make

out a prima facie case of fraud by Combustion Engineering.  
                 

     The   magistrate  judge's  order  had  been  entered  in

resolving discovery disputes  including Miller Hydro's  claim

that  Combustion Engineering had  lost the protection  of the

attorney client privilege as to certain materials because its

attorney   was   participating   in   a  fraudulent   scheme.

Interpreting  Maine law governing  the privilege, see  Me. R.
                                                     

Evid.  502(d)(1),  the  magistrate  judge  found  that Miller

Hydro's evidence thus far made out the necessary prima  facie
                                                             

case  on  "the first  three  elements  of fraud  [knowing  or

reckless  misrepresentation of a  material fact] but  not the

final two [purpose and effect of inducing reliance]."  Absent

sufficient proof of each element  needed to prove fraud,  the

magistrate judge found no  loss of the privilege and  refused

to order protection of the documents in issue.

     On  appeal,  Miller  Hydro  complains  sharply  that  in

resolving the Rule 12(b)(6) motion  the district judge had no

right  to  rely  on materials  beyond  the  pleadings without

giving Miller Hydro notice and  an opportunity to counter the

extra-pleading material.  Although Rule 12(b)(6) does require

"a  reasonable opportunity" to  counter material  outside the

pleadings, the magistrate  judge's finding of no  prima facie
                                                             

                             -22-

case  was cited in Combustion Engineering's motion to dismiss

and  arguably Miller Hydro  had the necessary  opportunity to

counter it.  This court  has looked through form to substance

in applying  the rule's  requirement.  See  Moody v.  Town of
                                                             

Weymouth, 805 F.2d 30, 31 (1st Cir. 1986).
        

     What  is  more  troublesome is  Miller  Hydro's further,

substantive  argument  that  the magistrate  judge's  finding

cannot support the district court's order dismissing the RICO

claims.  All  that the finding showed, says  Miller Hydro, is

that  in October 1990, while discovery was still underway, it

lacked enough evidence to show that all elements of fraud had

been made  out to the  extent needed to vitiate  the attorney

client privilege.5  Even assuming  that the standards are the

same for  proving fraud  in relation  to the  attorney-client

privilege  issue and in relation to a RICO claim, it does not

follow  that evidence  was equally  lacking  in October  1991

after further discovery had been conducted.

     The district court did  not discuss any of  the evidence

in its  brief order of  dismissal in October 1991.   Further,

the court  actually allowed  the Maine  fraud claims  made by

Miller  Hydro to  go the  jury.   Yet common alleged  acts of

fraud  underlay  both the  Maine  fraud  and the  RICO  fraud

                    

     5The standard of  proof is rather elusive since  a prima
                                                             
facie  case does not require  definitive proof; yet the fraud
     
claim itself has  to be proved under  Maine law by  clear and
convincing evidence.  

                             -23-

counts.   Indeed,  Miller Hydro  argues  that RICO  fraud  is

easier to prove than fraud under Maine law because the latter

requires that each element be proved by clear and  convincing

evidence.  The district court's seeming concession that there

was enough evidence  of fraud under Maine law  adds to doubts

whether we could  sustain the court's  dismissal of the  RICO

counts based on the magistrate judge's finding.

     We need  not resolve  the matter,  however, because  the

jury's  verdict  taken  together   with  other  circumstances

persuades  us that  Miller Hydro  was  not prejudiced  by the

dismissal of the RICO claims.  The jury found that no damages

had been proved by Miller Hydro on the two counterclaims that

did reach the jury  even though the jury found both breach of

contract  by Combustion  Engineering  and  acts amounting  to

fraud.   The  central damage  claims  argued to  the jury  by

Miller  Hydro--e.g., delay  costs, prospective  rebuilding of
                   

the fishways--are  common to the  Maine fraud and  RICO fraud

claims,  and the  jury finding  of no  damages on  the former

suggests the same outcome would have resulted on the latter.

     Miller Hydro  argues, although without much detail, that

its damage  claims based on breach of  contract were somewhat

narrower than  those covered  by fraud.   Its theory  is that

contract  damages must  be within  the  contemplation of  the

parties but  fraud damages  need not be,  and we  will assume

that  this  is  so.    But  Miller  Hydro  does  not  suggest

                             -24-

(attorney's fees  aside) that  its actual  damages for  fraud

were narrower under Maine law  than under RICO and, given the

common acts  of  alleged fraud,  it is  hard to  see why  the

damage claims under  RICO would be broader.   Instead, Miller

Hydro simply asserts that the fraud damage claims under Maine

law  required clear and convincing evidence while those under

RICO required merely a preponderance of the evidence.  

     It is by  no means clear that the jury was told that the

fraud damages  under Maine law had to  be proved by clear and

convincing  evidence.6    But  even  if  the  jury  had  been

explicitly told clear and convincing evidence was required in

computing   damages,  we  would  still  find  no  showing  of

prejudice in this  case.  Perhaps where the  issue of damages

is shown to be very  close--turning, for instance, on a clash

of  expert opinions--the  asserted  difference  in burden  of

proof between a common law fraud and a civil RICO claim could

be decisive.  See Wilcox  v. First Interstate Bank of Oregon,
                                                            

815 F.2d 522, 531 (9th Cir. 1987).  But the burden of showing

                    

     6The district  court's generally lucid  instructions did
tell the jury that the elements of fraud under Maine law  had
to be established by clear and convincing evidence.  But when
the court came to instructing  on the computation of damages,
where  it discussed contract  and fraud damages  together, it
did not say that any  of these determinations had to be  made
                              
by clear  and convincing  evidence.  Indeed,  the jury  could
easily  have inferred the contrary  because the court went on
to  say that  an award  of  exemplary damages  did require  a
finding of malice by clear and convincing evidence.

                             -25-

prejudice is upon the party claiming error, and we think that

here that burden has not been met.

     Miller Hydro's main efforts at trial appear to have been

devoted  to establishing  Combustion Engineering's  breach of

contract and  fraud, findings  very important  in shoring  up

Miller Hydro's own defense to Combustion Engineering's claims

against  it.   When a  directed verdict  was served,  after a

directed verdict was  ordered, Miller Hydro chose  to present

no  case  in  chief  of  its  own  in  support  of   its  own

counterclaims.    Instead,  Miller  Hydro  relied   upon  the

evidence that Combustion  Engineering had offered in  its own

case in chief before the directed verdict was granted.  It is

not  surprising  that,   absent  an  affirmative  independent

showing as to  how Miller Hydro would suffer  from the larger

facility,  the jury  awarded  no  damages.    Miller  Hydro's

decision to stop while ahead  was probably good tactics,  but

it does not suggest that an adjustment in the burden of proof

would have altered the result.

     More important, there is nothing in Miller Hydro's reply

brief--which  offers the burden  of proof distinction  as the

basis for presuming prejudice--that discusses the evidence of

damages in  any detail  or provides  any basis  for believing

that a different standard of  proof could alter the result in

this  case.    In the  present  circumstances,  including the

nature of  the jury  instructions and  the seemingly  limited

                             -26-

weight  placed  on  damages  at  trial,  we  think  that  the

theoretical  possibility of a different result is not enough.

And absent a showing that would suggest a real possibility of

a  different result,  it  is time  for  this already  lengthy

litigation to come to an end.

     Having considered consequential  damages, it remains  to

address two other possible differences in remedy.  First, the

RICO statute allows attorney's  fees to a person "injured  in

his business  or property" by a RICO  violation.  18 U.S.C.  

1964(c).  It is far from clear, however, that such attorney's

fees would be  available where, as here, the  jury finds that

no actual injury  has been proved.  Again,  given the absence

of  some showing  by Miller  Hydro  that a  jury could  award

damages  limited solely to attorney's fees,  we think that no

showing of prejudice has been made.

     Second, Miller  Hydro argues  that under  RICO it  would

have  been  entitled  to injunctive  relief  that  remains of

continuing importance to  it.  Specifically, it  asserts that

Combustion Engineering, having  had its belated motion  for a

retest denied  by the district  court, is now trying  (how is

not explained) to pursue its demand for a retest though other

means.     This  conduct,  says  Miller   Hydro,  constitutes

continuing RICO fraud that the district court would have been

asked to  enjoin if the  RICO claims had not  been dismissed.

                             -27-

See  18 U.S.C.    1964(a) (injunctive remedy  available under
   

RICO).

     We think this  is too  thin a  reed on which  to hang  a

remand  and further litigation  under RICO.   Taken together,

the district  court's dismissal  of Combustion  Engineering's

contract  and equitable claims and  the court's denial of the

belated  motion  for  a retest  establish  definitively  that

Combustion Engineering has no  further claim for a retest  or

any other remedy under  the turnkey contract.   If Combustion

Engineering   were  to  pursue  any  such  claim  through  an

independent  law suit, we  think that sanctions  for baseless

litigation might well be available.

                       III. CONCLUSION

     This  case  could  plausibly have  been  settled  at the

outset by, for  example, payment of any remaining amounts due

under the contract but without any bonus payment.  Now, after

wearisome and no doubt expensive litigation over an imperfect

contract  and imperfect conduct, neither side has gained what

it  sought at  the outset.    This may  itself be  a  form of

justice, but it could have been achieved at a lower price.

     Affirmed.  No costs.
             

                             -28-