Corridor H Alternatives, Inc. v. Slater

Court: Court of Appeals for the D.C. Circuit
Date filed: 1999-02-09
Citations: 166 F.3d 368, 334 U.S. App. D.C. 240, 166 F.3d 368, 334 U.S. App. D.C. 240, 166 F.3d 368, 334 U.S. App. D.C. 240
Copy Citations
22 Citing Cases

                        United States Court of Appeals


                     FOR THE DISTRICT OF COLUMBIA CIRCUIT


            Argued September 23, 1998   Decided February 9, 1999 


                                 No. 97-5301


               Corridor H Alternatives, Incorporated, et al., 

                                  Appellants


                                      v.


                          Rodney Slater, Secretary, 

                  U.S. Department of Transportation, et al.,

                                  Appellees


                Appeal from the United States District Court 

                        for the District of Columbia 

                               (No. 96cv02622)


     Andrea C. Ferster, with whom Thomas R. Michael was on 
the briefs, for appellants.

     Elizabeth S. Merritt, with whom Paul W. Edmondson, 
Laura S. Nelson, Thomas S. Martin, and Thomas B. Wilner 



were on the brief, for amici curiae National Trust for Historic 
Preservation, et al.

     Sheila D. Jones, with whom Lois J. Schiffer, Assistant 
Attorney General, U.S. Department of Justice, John A. Bry-
son, and Marta Hoilman, Attorneys, U.S. Department of 
Justice, Brett J. Gainer, Attorney-Advisor, Federal Highway 
Administration, and William G. Malley were on the brief, for 
appellees.  Greer S. Goldman, Attorney, U.S. Department of 
Justice, and Eliot R. Cutler entered appearances.

     Before Wald and Tatel, Circuit Judges, and Buckley, 
Senior Circuit Judge.

     Opinion for the court filed by Senior Circuit Judge 
Buckley.

     Buckley, Senior Judge:  Corridor H Alternatives, Inc., and 
several other environmental and public interest groups (col-
lectively, "CHA") challenge a highway project in West Virgi-
nia that had been developed and approved by various federal 
and state agencies.  Specifically, they assert (1) that the 
Federal Highway Administration violated the Department of 
Transportation Act by failing to identify all the historic sites 
it was charged with protecting prior to its decision approving 
the route of the proposed highway and by erroneously con-
cluding that the highway would not "use" two of the sites it 
did identify;  and (2) that the agency violated the National 
Environmental Policy Act by failing to give adequate consid-
eration to the improvement of existing roads as an alternative 
to the construction of the new highway.

     The district court held that the agencies had complied with 
both statutes.  Because we conclude that the Federal High-
way Administration was required to identify the historic sites 
that might be at risk before it issued its decision approving 
the highway's proposed route, we affirm in part and reverse 
in part with instructions to the district court to remand the 
matter to the Administration.

                                I. Background

     Congress enacted the Appalachian Regional Development 
Act of 1965, 40 U.S.C. app. ss 1 et seq. (1994), in order to 

stimulate economic development in Appalachia by providing 
the "basic facilities" that were believed essential for the 
region's growth.  These facilities were to include an "Appala-
chian development highway system" and a supporting net-
work of local access roads.  See id. ss 2(a), 201(a).

     Congress assigned responsibility for planning the new sys-
tem to the Appalachian Regional Commission, which is com-
posed of representatives of the Federal Government and the 
participating States.  Id. s 101(a).  The Commission was 
directed to designate "general corridor locations and termini 
of the development highways."  Id. s 201(b).  Pursuant to 
this authority, the Commission approved a plan for a 13-state 
regional highway system that called for the establishment of 
23 corridors, each of which would contain a highway that 
would permit anticipated traffic to proceed in safety between 
major termini at an average speed of 50 miles per hour, 
commensurate with the terrain.  See Joint Appendix ("J.A.") 
at 289, 486.

     The Commission did not map the corridors;  it merely 
identified their terminal points.  The task of determining 
their exact routes was left to the Federal Highway Adminis-
tration ("FHWA" or "Administration") and the affected 
states.  In the case of Corridor H, which is the subject of this 
litigation, the Commission merely established that it was to 
extend from Interstate 79 ("I-79") near Weston, West Virgi-
nia, eastward to Interstate 81 ("I-81") near Strasburg, Virgi-
nia.  J.A. at 455.

     Between 1982 and 1994, a 40-mile section of the new 
Corridor H highway was built from its I-79 terminus to a 
point just west of Elkins, West Virginia.  In 1996 the State of 
Virginia decided to withdraw from the project, with the result 
that the eastern terminus is now located in West Virginia just 
west of its border with Virginia.  The present plan calls for 
the building of approximately 100 more miles.

     Federally funded highway projects must comply with a 
number of statutory requirements.  Those relevant here are 
section 106 of the National Historic Preservation Act, codified 
at 16 U.S.C. s 470f (1994) ("section 106");  section 4(f) of the 



Department of Transportation Act, codified at 49 U.S.C. 
s 303 (1994) ("section 4(f)");  and the environmental impact 
analysis mandated by the National Environmental Policy Act, 
42 U.S.C. ss 4321 et seq. (1994) ("NEPA").

     Section 106 of the National Historic Preservation Act pro-
vides that before a federal agency may authorize the expendi-
ture of funds for a federal or federally assisted undertaking, 
it must first consider the effects of such an undertaking on 
"any district, site, building, structure, or object that is includ-
ed in or eligible for inclusion in the National Register."  16 
U.S.C. s 470f.

     The U.S. Department of Transportation regulations imple-
menting section 106 establish three steps that an agency must 
take in order to comply with section 106.  First, the agency 
must identify the properties that are listed or eligible for 
listing in the National Register.  36 C.F.R. s 800.4 (1998).  
Next, it must evaluate the effects of the proposed undertak-
ing on those properties.  Id. s 800.5.  Finally, if the agency 
determines that the project would have an adverse effect on a 
historic property, it must consider measures to mitigate the 
potential damage.  Id.

     Section 4(f) of the Department of Transportation Act states 
that the Secretary of Transportation

     may approve a transportation program or project ... 
     requiring the use of ... land of an historic site of 
     national, State, or local significance ... only if--

               (1) there is no prudent and feasible alternative to 
          using that land;  and

               (2) the program or project includes all possible plan-
          ning to minimize harm to the ... historic site resulting 
          from the use.

49 U.S.C. s 303(c).  The Secretary has delegated this respon-
sibility to the FHWA.  49 C.F.R. s 1.45(4) (1997).  The 
FHWA's regulations implementing section 4(f) identify the 
historic sites that are subject to the section as "all properties 
on or eligible for the National Register of Historic Places."  
23 C.F.R. s 771.135(e) (1998).  Because the historic proper-

ties protected by section 106 are similarly defined, it follows 
that the agency must complete its section 106 determinations 
before it can comply with section 4(f).

     The National Environmental Policy Act requires that an 
environmental impact statement ("EIS") be prepared for any 
"major Federal action[ ] significantly affecting the quality of 
the human environment."  42 U.S.C. s 4332(C).  The EIS 
must include, among other things,

     a detailed statement ... on--

               (i) the environmental impact of the proposed action,

               (ii) any adverse environmental effects which cannot 
          be avoided should the proposal be implemented, [and]

               (iii) alternatives to the proposed action....

Id.  In a case requiring an EIS, the agency must prepare a 
"concise public record of decision" that identifies all the 
alternatives it has considered and describes all the factors it 
has taken into account in reaching its decision.  40 C.F.R. 
s 1505.2 (1998).

     The U.S. Department of Transportation, the FHWA, and 
the West Virginia Department of Transportation ("WVDOT") 
(collectively, "the agencies") began planning for the Corridor 
H project in the late 1970's.  They produced a draft environ-
mental impact statement in 1981 but suspended work on the 
project until 1990.  They then decided to proceed with the 
environmental review in two stages, each of which resulted in 
the issuance of a draft EIS.

     The first of these, the Corridor Selection Draft EIS 
("CSDEIS"), was issued by WVDOT in 1992.  It was con-
cerned with the demarcation of the actual 2,000-foot-wide 
route that Corridor H would take from Elkins, West Virginia, 
to its eastern terminus, which was then located on I-81 in 
Virginia.  In conducting this review, WVDOT considered five 
alternatives, including:  the construction of a new four-lane 
highway (the "Build Alternative"), improvements of existing 
two-lane roads (the "Improved Roadway Alternative"), and 
the self-described "No Build Alternative."  It concluded that 
only the Build Alternative and the No Build Alternative 

merited more detailed evaluation because the Improved 
Roadway Alternative would not be able to achieve the pro-
ject's speed and safety objectives.  J.A. 292.

     The second study, the Alignment Selection Draft EIS 
("ASDEIS"), was completed two years later, in 1994.  Its 
purpose was twofold:  to evaluate the environmental impact of 
numerous 200- to 250-foot-wide "alignments" of the highway 
itself, i.e., the actual ground within Corridor H that the 
proposed four-lane highway would occupy, and to reexamine 
the Improved Roadway Alternative.  WVDOT issued its Fi-
nal EIS ("FEIS") on April 8, 1996, establishing the bound-
aries of Corridor H and reaffirming its decision to proceed 
with the four-lane Build Alternative.

     The FEIS adopted a "Programmatic Agreement," earlier 
entered into by the FHWA and the relevant historic preser-
vation officials, which established the procedures that would 
be followed by the FHWA in complying with the require-
ments of section 106.  The Programmatic Agreement divided 
Corridor H into 14 segments or sections and required the 
FHWA to identify the historic properties in each of them in 
the sequence set forth in the agreement, to assess the pro-
ject's impact on the properties, and to "utilize all feasible, 
prudent and practicable measures to avoid adverse effects" to 
them.  It also stipulated that "[n]o work shall proceed in any 
section which precludes consideration of alternate alignments 
in [s]ections where treatment of historic properties has not 
yet been finalized."  Programmatic Agreement, reprinted in 
J.A. at 185-98.

     Four months later, in August 1996, the FHWA issued its 
Record of Decision for the Corridor H project ("ROD").  The 
ROD approved the FEIS's selection of the four-lane Build 
Alternative as the preferred basis for the project as well as 
its adoption of the corridor route and highway alignments 
favored in the CSDEIS and ASDEIS, as modified to avoid 
the constructive use of the Corricks Ford and Moorefield 
Civil War battlefields.  The FHWA concluded that by virtue 
of these modifications, the highway would not "substantially 
impair" the battlefields.



     The ROD also incorporated the Programmatic Agreement's 
segment-by-segment approach to compliance with section 106.  
In recognition of the fact that the section 4(f) process could 
not be completed prior to the identification of the protected 
historic sites pursuant to section 106, the ROD specified that 
its approval of the project was conditional only and would not 
become final, as to any section of the corridor, "until the 
Section 106 process has been completed for that section and 
for any immediately adjacent section(s)."  Record of Decision 
at 16, reprinted in the J.A. at 302.

     CHA challenged the approval of the Corridor H project in 
district court.  In considering the parties' cross motions for 
summary judgment, the court observed that both parties had 
advanced reasonable arguments in support of their respective 
positions;  but because of the deference due to agency deci-
sions that are not arbitrary or capricious, the court felt 
obliged to grant summary judgment in favor of the agencies 
on all counts of the complaint.  See Corridor H Alternatives, 
Inc. v. Slater, 982 F. Supp. 24, 35 (D.D.C. 1997).

                                II. Discussion


     On appeal, CHA argues that the FHWA (1) violated section 
4(f) both by deferring the investigations of the historic sites 
until after the issuance of the ROD and by adopting the 
Programmatic Agreement's incremental, segment-by-segment 
approach to implementing the section;  (2) acted arbitrarily 
and capriciously and contrary to section 4(f) when it deter-
mined that the project would not substantially impair the two 
Civil War battlefields;  and (3) violated NEPA by rejecting 
the improvement of existing two-lane roads as a reasonable 
alternative to achieving the objectives of Corridor H.  We 
address these claims in turn.

     A.Section 4(f)

     FHWA regulations establish the procedures that must be 
followed in complying with section 4(f).  We defer to the 
FHWA's interpretation of its regulations unless "it is plainly 



erroneous or inconsistent with the regulation itself."  Canadi-
an Am. Oil Co. v. NLRB, 82 F.3d 469, 473 (D.C. Cir. 1996).

     CHA and the agencies base their cases on different sec-
tions of the regulations.  In support of their claim that the 
FHWA is required to complete the section 4(f) process for the 
entire Corridor H project before issuing the ROD, CHA cites 
sections 771.135(b) and (l) of the agency's regulations.  Sec-
tion 771.135(b) directs that

     [a]ny use of lands from a section 4(f) property shall be 
     evaluated early in the development of the action when 
     alternatives to the proposed action are under study.

23 C.F.R. s 771.135(b) (1998) (emphasis added).  Section 
771.135(l) (1998) provides that in cases requiring the prepara-
tion of an EIS, the agency "will make the section 4(f) approv-
al either in its approval of the final EIS or in the ROD."  Id. 
s 771.135(l) (emphasis added).

     The agencies, on the other hand, contend that sections 
771.135(m) and (n) permit the FHWA to prepare separate 4(f) 
evaluations after it has issued the ROD.  Section (m) states in 
relevant part:

     Circulation of a separate section 4(f) evaluation will be 
     required when:

          (1) A proposed modification of the alignment or design 
     would require the use of section 4(f) property after the 
     ... draft EIS, or final EIS has been processed;

          (2) The Administration determines, after processing 
     the ... draft EIS, or final EIS that section 4(f) applies to 
     a property;

          (3) A proposed modification of the alignment, design, 
     or measures to minimize harm (after the original section 
     4(f) approval) would result in a substantial increase in the 
     amount of section 4(f) land used, a substantial increase in 
     the adverse impacts to section 4(f) land, or a substantial 
     reduction in mitigation measures;  or



          (4) Another agency is the lead agency for the NEPA 
     process, unless another [Department of Transportation] 
     element is preparing the section 4(f) evaluation.

23 C.F.R. s 771.135(m) (1998).  Section (n) continues:

          If the Administration determines under s 771.135(m) 
     or otherwise, that section 4(f) is applicable after the ... 
     final EIS has been processed, the decision to prepare and 
     circulate a section 4(f) evaluation will not necessarily 
     require the preparation of a new or supplemental envi-
     ronmental document.

23 C.F.R. s 771.135(n) (1998) (emphasis added).  The agen-
cies argue that while subsection (n) requires the FHWA to 
issue a separate section 4(f) evaluation in any of the four 
circumstances listed in section (m), it does not state that 
these are the only circumstances in which a separate 4(f) 
evaluation is permitted.  They then point to the phrase "or 
otherwise" in subsection (n) which, they claim, would be 
meaningless if it did not permit separate analyses under 
circumstances other than those described in the prior subsec-
tion. Thus, they maintain, the regulations permit the FHWA 
to use a "separate evaluation" in this case.

     This argument is more resourceful than persuasive.  Be-
cause they do not claim that any of the four situations 
described in subsection (m) apply here, the agencies are 
asking us to give greater weight to their creative interpreta-
tion of "or otherwise" than to the crystalline command, in 
subsections (b) and (l), that the 4(f) evaluations be made while 
"alternatives to the proposed action are under study" and 
that the FHWA complete the 4(f) process no later than in the 
ROD.  Id. s 771.135(b), (l).  While deference is normally due 
an agency's interpretation of its own rules, that is not the 
case where "an alternative reading is compelled by the regu-
lation's plain language."  Thomas Jefferson Univ. v. Shalala, 
512 U.S. 504, 512 (1994) (internal quotation marks omitted).  
It is hard to imagine less ambiguous directives than those on 
which CHA relies.



     Nor are we impressed by the agencies' remaining argu-
ments. They assert that their sequential, segment-by-segment 
approach is authorized by subsection (o) of the regulations, 
which provides in relevant part:

          (o) An analysis required by section 4(f) may involve 
     different levels of detail where the section 4(f) involve-
     ment is addressed in a tiered EIS.

          (1) When the first-tier, broad-scale EIS is prepared, 
     the detailed information necessary to complete the sec-
     tion 4(f) evaluation may not be available at that stage in 
     the development of the action.  In such cases, an evalua-
     tion should be made on the potential impacts that a 
     proposed action will have on section 4(f) land and wheth-
     er those impacts could have a bearing on the decision to 
     be made....

          (2) A section 4(f) approval made when additional de-
     sign details are available will include a determination 
     that:

          (i) The preliminary section 4(f) determination made 
     pursuant to paragraph (o)(1) of this section is still val-
     id....  

23 C.F.R. s 771.135(o) (1998).

     This section permits a preliminary, first tier 4(f) determina-
tion in circumstances where the unavailability of critical infor-
mation precludes the completion of the kind of evaluation 
section 4(f) requires.  Even then, the validity of the final, 
second tier 4(f) approval is dependent on the ability of the 
agency to affirm that the preliminary determination remains 
valid.  Here, however, the agencies have failed to make even 
the preliminary section 4(f) determination subsection (o)(1) 
requires.

     Finally, we also reject the agencies' contention that section 
771.105 of the regulations authorizes post-ROD compliance 
with section 4(f).  Section 771.105 sets forth the FHWA 
policy that "[t]o the fullest extent possible, all environmental 
investigations ... be coordinated as a single process...."  23 
C.F.R. s 771.105(a) (1998).  While there is obvious merit to 


coordinating environmental reviews of the kind required by 
NEPA and section 4(f), we do not read section 771.105 as 
authority for the agencies to disregard the explicit require-
ment, in sections 771.135(b) and (l), that they complete the 
section 4(f) process before the FHWA issues the ROD.

     Because we conclude that the agencies have failed to 
comply with section 4(f), we need not address their finding 
that Corridor H will not "use" the Corricks Ford and Moore-
field Civil War Battlefields.

     B.NEPA

     CHA also claims that the ROD failed to comply with 
NEPA's requirement that adequate consideration be given to 
the Improved Roadway Alternative ("IRA").  The agencies 
respond that they sufficiently evaluated the IRA and decided 
that it could not meet the needs of the project.

     At "the heart of the environmental impact statement," 40 
C.F.R. s 1502.14 (1998), is the requirement that it identify 
the reasonable alternatives to the contemplated action and

     present the environmental impacts of the proposal and 
     the alternatives in comparative form, thus sharply defin-
     ing the issues and providing a clear basis for choice 
     among options by the decisionmaker and the public.

Id.  The statute, however,

     directs agencies only to look hard at the environmental 
     effects of their decisions, and not to take one type of 
     action or another, [and we] correspondingly enforce the 
     statute by ensuring that agencies comply with NEPA's 
     procedures....

Citizens Against Burlington, Inc. v. Busey IV, 938 F.2d 190, 
194 (D.C. Cir. 1991).  We have recognized that a "rule of 
reason" applies both to an agency's identification of the 
available alternatives and to its examination of their relative 
merits, and we have declared that we will defer to its conclu-
sions "so long as the alternatives are reasonable and the 
agency discusses them in reasonable detail."  Id. at 196.


     We are satisfied that the agencies have met NEPA's "hard 
look" requirement and that they have adequately supported 
their determination that the IRA would not advance Con-
gress's goal of providing West Virginia with the "basic facili-
ties" essential for its economic growth.  See Appalachian 
Regional Development Act of 1965, 40 U.S.C. app. s 2(a).  In 
section II of the CSDEIS, entitled "Alternatives Considered," 
the WVDOT reviewed the merits and deficiencies of five 
alternatives, including the No Build Alternative, the four-lane 
Build Alternative, and the IRA in light of Congress's objec-
tive of developing a regional highway system and the design 
standards established for the system by the Appalachian 
Regional Commission.  In its review of the IRA, the WVDOT 
discussed in detail the reasons why that alternative could not 
adequately address issues such as roadway deficiencies, safe-
ty considerations, and regional system linkage.  We therefore 
defer to the agencies' decision to proceed with the four-lane 
Build Alternative.

                               III. Conclusion


     We hold that the plain language of section 4(f) regulations 
771.135(b) and (l) requires the agencies to complete the 
section 4(f) process prior to the issuance of an ROD fixing the 
route of the proposed four-lane highway.  We also find that 
the agencies took the "hard look" at the IRA that is required 
by NEPA.  For these reasons we affirm in part and reverse 
in part the district court's grant of summary judgment for the 
agencies, and we direct the court to return the matter to the 
agencies with instructions to complete the section 4(f) process 
before proceeding further with the Corridor H project.

     So ordered.


                              

Boost your productivity today

Delegate legal research to Cetient AI. Ask AI to search, read, and cite cases and statutes.