Iroquois Gas Transmission System, L.P. v. Federal Energy Regulatory Commission

                        United States Court of Appeals


                     FOR THE DISTRICT OF COLUMBIA CIRCUIT


               Argued May 14, 1998       Decided July 21, 1998 


                                 No. 97-1276


                   Iroquois Gas Transmission System, L.P., 

                                  Petitioner


                                      v.


                    Federal Energy Regulatory Commission, 

                                 Respondent 


                              Consolidated with

                                 No. 97-1533


---------


                  On Petitions for Review of Orders of the 

                     Federal Energy Regulatory Commission


     Joseph S. Koury argued the cause for petitioner.  With him 
on the briefs were James T. McManus, Jeffrey A. Bruner 
and Paul W. Diehl.

     Samuel Soopper, Attorney, Federal Energy Regulatory 
Commission, argued the cause for respondent.  With him on 
the brief were Jay L. Witkin, Solicitor, and Susan J. Court, 



Special Counsel.  John H. Conway, Deputy Solicitor, entered 
an appearance.

     Dennis Lane argued the cause for intervenors Public Ser-
vice Commission of the State of New York, et al.  With him 
on the brief were David W. D'Alessandro, Mary Ann Walker, 
Neil L. Levy, Richard A. Rapp, Jr., Lillian S. Harris and 
Kevin J. McKeon.

     Before:  Wald, Williams and Henderson, Circuit Judges.

     Opinion for the Court filed by Circuit Judge Williams.

     Concurring opinion filed by Circuit Judge Wald.

     Williams, Circuit Judge:  Iroquois Gas Transmission Sys-
tem, L.P., ran up substantial legal defense costs as a result of 
federal investigations into environmental violations committed 
in its construction of a natural gas pipeline.  The Federal 
Energy Regulatory Commission issued orders excluding 
these legal costs from the rate base used to calculate Iro-
quois's permissible charges, explaining that Iroquois had 
failed to carry the burden of proving that the costs were 
prudently incurred.  Iroquois says the orders were grounded 
in an impermissible presumption of non-recoverability and 
asks us to set them aside, relying primarily on our decisions 
in Mountain States Telephone and Telegraph Co. v. FCC, 939 
F.2d 1021 (D.C. Cir. 1991) ("Mountain States I") and Moun-
tain States Telephone and Telegraph Co. v. FCC, 939 F.2d 
1035 (D.C. Cir. 1991) ("Mountain States II").  Because the 
Commission has failed to come to grips with the questions 
that Mountain States II said must be answered when ad-
dressing a utility's recovery of legal expenses, we remand the 
case for a more reasoned decision.

                                    * * *


     In November 1990 the Commission granted Iroquois a 
certificate of public convenience and necessity under Section 7 
of the Natural Gas Act (the "Act"), authorizing the company 
to build and operate a new pipeline stretching from the 
Canadian border to Long Island.  The pipeline went into full 
service in January 1992.  Before long, however, Iroquois 
found itself in trouble for environmental violations.  Around 
November 1991 the U.S. Attorney's Office for the Northern 



District of New York, in conjunction with the FBI and the 
Environmental Protection Agency, began an investigation 
into whether Iroquois's construction activities violated the 
Clean Water Act.  The record suggests that the investigation 
focused on points where the pipeline crossed creeks and 
streams in upstate New York, allegedly discharging silt and 
sediment in violation of Iroquois's Clean Water Act permit, 
and on Iroquois's alleged failure to build so-called trench 
breakers, which control soil erosion and pipeline corrosion.  
An Army Corps of Engineers inspection report from 
early 1992 cited a potential overall penalty of more than 
$115,000,000.  Civil investigations, presumably closely relat-
ed, were also undertaken by the U.S. Attorney's offices for 
the Northern, Eastern, and Southern Districts of New York. 
In addition, FERC's own enforcement staff launched a sepa-
rate investigation to determine whether Iroquois had violated 
the environment-related conditions of its Section 7 certificate.  
Ultimately an Iroquois affiliate and four of its employees 
entered into guilty pleas and a civil settlement costing $22 
million in fines and penalties, and Iroquois consented to a 
settlement with the Commission admitting violations of envi-
ronmental conditions in its certificate and agreeing not to 
pass the fines and penalties on to its ratepayers.  Iroquois 
Gas Transmission System, L.P., 75 FERC p 61,205 (1996).  

     In the course of resolving these disputes Iroquois ran up a 
legal bill of more than $15,000,000.  While the various inves-
tigations were still under way, Iroquois filed with the Com-
mission for a general rate increase to recover its pipeline 
construction costs.  The rate proceeding culminated in a set-
tlement between Iroquois and its customers resolving all 
issues except the rate and accounting treatment of the legal 
defense costs.  Hearings on these reserved issues were held 
before an administrative law judge, who determined that the 
legal costs were not unrecoverable per se, and observed that 
"[t]he participants have presented nothing to rebut Iroquois's 
position that the legal costs were incurred as an appropriate 
and normal response to investigatory activities arising from 
the construction undertaken to provide service to the rate-
payers."  Iroquois Gas Transmission System, L.P., 72 
FERC p 63,004, at 65,027 (1995).



     The Commission reversed the ALJ's initial decision and 
held that Iroquois's legal defense costs could not be included 
in its rate base.  Iroquois Gas Transmission System, L.P., 77 
FERC p 61,288 (1996).  "Allowing recovery of Iroquois' litiga-
tion expenses," the Commission concluded,

     would fail to recognize the interests of Iroquois' ratepay-
     ers, shared by the Commission, that emanate from Sec-
     tion 7 of the NGA.  These interests are to ensure that 
     the pipeline is built in compliance with all applicable 
     federal environmental and safety laws so as to prevent 
     any future personal injuries or environmental damage.

Id. at 62,280.  The Commission based its disallowance of 
recovery on Iroquois's failure to demonstrate any countervail-
ing economic or non-economic benefit to ratepayers from the 
activities that gave rise to the investigations.  The Commis-
sion denied Iroquois's request for rehearing, Iroquois Gas 
Transmission System, L.P., 78 FERC p 61,216 (1997), and 
later rejected similar claims in a second rate case filed by 
Iroquois.  Iroquois Gas Transmission System, L.P., 77 
FERC p 61,352, at 62,538 (1996), rehearing denied, 80 FERC 
p 61,199, at 61,797-98 (1997).  Iroquois petitioned for review 
in this court.

     At the outset the Commission concedes two propositions, 
one general and one specific to this case.  First, the Commis-
sion admits that although the Act gives the natural gas 
company the burden of showing that a proposed rate increase 
is just and reasonable, 15 U.S.C. s 717c(e), as a matter of 
FERC practice "a natural gas company is ordinarily not 
required to show that all of its expenditures were prudent 
unless serious doubts are raised regarding the prudence of 
those costs."  FERC Br. at 24.  See, e.g., Trans World 
Airlines, Inc. v. CAB, 385 F.2d 648, 657 (D.C. Cir. 1967);  
Minnesota Power & Light Co., 11 FERC p 61,312, at 61,645 
(1980).  Second, the Commission does not seriously contest 
that it effectively raised a presumption against recovery in 
this case, putting the burden on Iroquois to demonstrate that 
its expenditures were prudently incurred.  See 78 FERC at 
61,927 ("[S]ince [Iroquois] was seeking to recover the legal 
defense costs in its rates, it had the burden of proving that 



the costs were just and reasonable.").  Indeed, at times the 
Commission seemed to erect something close to an irrebutta-
ble presumption against recovery.  See id.  ("Iroquois placed 
itself in the untenable position of arguing that its illegal 
activities, supposedly taken to save time and money during 
construction, were in the interests of its ratepayers, and, 
therefore, just and reasonable.") (emphasis added).

     The Commission contends, however, that it adequately 
justified its decision to invert the normal presumption in this 
case, because Iroquois's legal costs by their very nature 
raised a serious doubt as to prudence (i.e., because they grew 
out of civil and criminal violations).1  See FERC Br. at 24.  
One immediate problem with this approach is that as of the 
time the hearing was held before the ALJ no violations had 
been proven or admitted;  the investigations were still ongo-
ing and the precise contours of any eventual charges were 
still uncertain.  But even if that problem is put aside, the 
Commission runs into another barrier:  our decisions in the 
Mountain States cases.

     In Mountain States I we held that the Federal Communi-
cations Commission had failed to provide a reasoned justifica-
tion for its presumption that antitrust litigation expenses 
incurred by AT&T could not be recovered from ratepayers.  
939 F.2d at 1029-35.  "Illegality of carrier conduct from 
which an antitrust litigation expense stems," we concluded, 
"does not inexorably compel or warrant either rejection or 
stigmatization of the expense as a factor in rate calculations."  
Id. at 1031.  We noted that in two tax decisions the Supreme 
Court had described litigation expenses--even those incurred 
in a losing cause--as ordinary and legitimate costs of doing 
business.  Id. at 1031-32 (citing Commissioner v. Heininger, 

__________
     1 When asked by the ALJ to come forward with evidence raising 
doubts about the prudence of the costs, FERC's staff counsel 
answered, "[I]t is our belief that the recoverability issue is simply a 
matter of fairness, and there wasn't a whole lot to say about it."  
Similarly, counsel for the Public Service Commission of the State of 
New York responded, "It's our view that these are not the typical 
costs that are incurred to provide service by a utility and we cannot 
conceive of a scenario under which they would be recoverable."



320 U.S. 467 (1943), and Commissioner v. Tellier, 383 U.S. 
687 (1966)).

     In Mountain States II, issued the same day as Mountain 
States I, we reviewed a new FCC regulation governing the 
accounting treatment of litigation expenses generally.  The 
new rule attached a presumption of non-recoverability to all 
litigation expenses that resulted in an adverse final judgment 
or post-judgment settlement in any federal statutory case, 
unless the regulated company could show that ratepayers 
benefited from the underlying activity.  939 F.2d at 1039.  
Holding that "the FCC may disallow any expense incurred as 
a result of carrier conduct that cannot reasonably be expected 
to benefit ratepayers," id. at 1043, we found the new rule 
quite sensible in the context of antitrust violations, since the 
effect of such violations is typically to injure consumers.  But 
we went on to say that the FCC had inadequately justified its 
application of the new rule to statutory violations beyond 
antitrust, where an absence of ratepayer benefit "is neither 
self-evident, as it is in the antitrust context, nor bolstered by 
either analytical or empirical support."  Id. at 1044.  By the 
same token we rejected the FCC's "terse assertion" that 
violations of federal statutory law "raise public policy implica-
tions" sufficient to justify presumptive disallowance of associ-
ated litigation costs.  Id. at 1045.2

     We emphasized in Mountain States II that the FCC had 
not taken sufficient account of the perverse incentive effects 
set in motion by a presumption against recovery of litigation 
expenses.  Such a presumption, we observed, was likely to 
induce excessive caution in carriers, causing them to shun 
activities that might conceivably be found to violate federal 
law, even when those activities promise benefits to ratepay-
ers.  Id. at 1046.  We illustrated the point in a passage whose 
uncanny relevance to the instant case calls for full quotation:

__________
     2 On remand the FCC decided to retain its special accounting 
rules with respect to antitrust judgments and settlements, but 
abandoned them with respect to antitrust litigation expenses and all 
costs arising from other types of litigation.  In the Matter of 
Accounting for Judgments and Other Costs Associated With Litiga-
tion, 12 FCC Rcd. 5112 (1997).



     Consider the following example:  A carrier has to choose 
     between instituting a strict pollution monitoring policy or 
     a lax policy that is arguably sufficient under the law and 
     would cost $50,000 less than the strict policy.  The 
     carrier will surely be sued under a federal statute if it 
     adopts the lax policy, and there is a 10% chance that it 
     will lose;  if it does, the plaintiff would recover $100,000, 
     making the expected or ex ante cost of the lawsuit 
     ($100,000 x .10 =) $10,000.  Thus the carrier reasonably 
     determines that adopting the lax policy will produce a net 
     benefit of $40,000 to the ratepayers, who would otherwise 
     have to pay the cost of the strict monitoring policy.  It 
     would be misleading to say that requiring ratepayers to 
     bear the cost of the resulting judgment, if any, causes 
     them to subsidize the carrier's illegal activity.  The carri-
     er made the "right" decision, i.e., what the ratepayers 
     would have decided in their own economic self-interest;  
     it just turned out to be the "wrong" decision as a matter 
     of how the law was finally interpreted.  Perhaps the 
     agency has a more capacious notion of ratepayer benefit 
     than merely paying lower rates.  If it does, however, it 
     has neither said as much nor indicated why ratepayers 
     are generally harmed in some non-economic way by the 
     violation of federal statutes.

Id. at 1044-45.

     The Commission quoted this passage in its initial order, see 
77 FERC at 62,279-80, acknowledging its relevance but 
claiming to find refuge in its final two sentences.  While the 
FCC in Mountain States II had failed to articulate any non-
economic harm flowing from violations of federal statute law, 
the Commission said, here Iroquois's ratepayers have a gen-
eral interest in compliance with federal environmental and 
safety laws, and thus are harmed whenever those laws are 
violated.  77 FERC at 62,280.  The inclusion of environmen-
tal compliance requirements in Iroquois's Section 7 certifi-
cate, according to the Commission, represented an "implicit 
recognition that it would be appropriate for ratepayers to pay 
costs that may be incurred to build a pipeline in an environ-
mentally responsible manner.  It is not reasonable then to 



elevate the ratepayer interest in saving time and money to 
such a preeminent position in the interests to be considered 
when deciding whether costs are recoverable in the rates."  
Id.

     We pause here to note that the Commission correctly 
placed its initial focus on the prospect of ratepayer benefits 
from the underlying activity rather than from the litigation.  
Even though it is commonly prudent (in the conventional 
sense of the term) to incur legal expenses in defending 
conduct that turns out to have been illegal, there appears no 
reason why ratepayers should bear the expense of defending 
conduct that had no ex ante prospect of benefiting them.  See 
Mountain States II, 939 F.2d at 1043.

     Nonetheless, we find the Commission's treatment of Moun-
tain States II unconvincing.  The asserted ratepayer interest 
in compliance with environmental and safety laws is virtually 
as generic as the amorphous "public policy implications" we 
found inadequate to justify the presumption of non-
recoverability in Mountain States II.  939 F.2d at 1045.  
Because all citizens share an interest in widespread compli-
ance, not just with environmental or safety laws but with laws 
of any kind, the Commission's approach would result in the 
presumptive disallowance of all litigation expenses leading to 
anything short of outright triumph for the regulated entity.

     More important, the Commission's approach utterly fails to 
respond to the problem of incentives posed in Mountain 
States II.  Iroquois's ratepayers, in common with the general 
population of upstate New York, undoubtedly share an inter-
est in maintaining the purity of the region's creeks and 
streams.  But the same ratepayers have a unique and concen-
trated interest in timely and efficient pipeline construction.3  

__________
     3 In fact, Iroquois's customers evidently had a special interest in 
speedy construction.  In Iroquois's certificate proceeding the Com-
mission found as a general matter that the pipeline's proposed 
customers "have an urgent and significant need for additional 
natural gas supplies during the 1991-1992 winter season."  Iroquois 
Gas Transmission System, L.P., 52 FERC p 61,091, at 61,343 
(1990).  In a later order denying a stay of Iroquois's construction 
certificate, the Commission noted the dangers of "delay[ing] further 
the badly needed entry of the Iroquois-supplied gas into the North-



Although our concurring colleague asserts that some ratepay-
ers would willingly pay higher rates in exchange for assur-
ances of environmental compliance, see Concurring Op. at 1-
2, laws obligating firms to satisfy environmental standards 
are necessary precisely because most consumers, if given a 
choice, appear unwilling to pay the full cost of satisfying 
higher standards.  If consumer demand were actually enough 
to cause ordinary firms in competitive industries to incur the 
costs of protecting the environment, there would be little 
need for environmental regulation.

     Indeed, because of the limitation of the utility's rates to 
recovery of cost under the statute's "just and reasonable" 
formula, the ratepayers have the same interest in optimizing 
environmental compliance costs as they would if they built the 
pipeline themselves through a cooperative or a partnership.  
As our opinion in Mountain States II made clear, a firm 
incurring optimal environmental compliance costs will on 
occasion take measures that are ultimately found illegal.  In 
Mountain States II 's example, where a saving of $50,000 
runs a 10% risk of triggering $100,000 in additional costs, the 
ex ante expected benefit for the ratepayers is $40,000.  Con-
trary to our concurring colleague's suggestion, see Concur-
ring Op. at 2, Mountain States II does not establish a 
ratemaking principle that affirmatively encourages regulated 
companies to violate environment-related certificate condi-
tions.  It does, however, recognize that ratepayers often 
benefit from activities that tack reasonably close to the wind, 
and that policies inducing management to pursue absolutely 
risk-free environmental compliance measures are therefore 
not, on their face, in the ratepayers' interest.

     Yet the Commission's approach seems sure to chill some 
lawful activity beneficial to ratepayers;  indeed, it would seem 
calculated to encourage regulated firms to avoid any and all 
litigation risks.  "[L]awsuits are a recurring fact of life in 
operating a business," Mountain States I, 939 F.2d at 1034, 
and in the area of federal environmental regulation the line 
between permissible and impermissible conduct is often 
drawn in (muddy) water.  Compare United States v. Mango, 

__________
east market."  Iroquois Gas Transmission System, L.P., 54 FERC 
p 61,103, at 61,342 (1991).



997 F. Supp. 264, 285 (N.D.N.Y. 1998) (holding that CWA 
authorized Army Corps of Engineers to regulate Iroquois's 
"backfilling of trenches excavated in waterways and wetland 
areas") with id. at 283-87, 295-98 (holding that CWA does not 
authorize Corps to impose permit conditions not related to 
discharge of dredged or fill material, such as those designed 
to prevent wetland drainage).  Thus the Commission must do 
a better job of explaining why all activities that turn out to 
violate environmental laws should be presumed unlikely "to 
benefit ratepayers," as required for presumptive disallowance 
under Mountain States II.  939 F.2d at 1043.4

     The Commission's attempted distinction of Appalachian 
Electric Power Co. v. FPC, 218 F.2d 773 (4th Cir.1955), is also 
insubstantial.  There the Fourth Circuit held that legal costs 
incurred by a regulated utility in an unsuccessful challenge to 
the Commission's jurisdiction over a proposed power plant 
were recoverable from ratepayers as expenses necessary to 
the development of the project.  According to the Commis-
sion, the costs of the jurisdictional challenge in Appalachian 
were an example of "normal civil litigation" costs;  other 
examples given by the Commission were the "cost of attor-
neys hired to secure any state or federal permits, or litigation 
to perfect eminent domain rights or to establish property 
values."  77 FERC at 62,281.  Iroquois's case is different, the 
Commission said, because it "is not the type of case where a 
regulated company, interpreting the law in a manner most 
favorable to the company, loses a court case."  Id.  In fact 
that description seems, at least at first glance, to fit Iroquois's 
case quite snugly.  Beyond offering a few conclusory state-
ments ("there is no punitive aspect associated with the loss of 
a challenge [to] the agency's regulatory jurisdiction," id.), the 

__________
     4 The Commission mystifyingly asserted that Iroquois's agree-
ment not to recover any of the $22 million in fines and penalties 
from its ratepayers "impl[ied] that the pipeline itself recognized 
that the ratepayers did not benefit from the illegal activities."  77 
FERC at 62,281.  Given that the same agreement explicitly re-
served the issue of recoverability of legal expenses, see id. at 62,277 
n.11, we can see no basis for the supposed inference.



Commission never explains why action based on a legal 
interpretation "most favorable to the company" should have 
been presumptively beneficial to ratepayers in Appalachian 
but presumptively harmful here.5

     In short, the Commission has not made clear which types of 
legal defense costs are presumed recoverable for ratemaking 
purposes and which not, or why the costs here belong on the 
nonrecoverable side of the line.  Particularly in light of the 
explicit discussion of pollution laws in Mountain States II, the 
Commission's burden here requires more than the making of 
general allusions to the public interest in compliance with 
environmental statutes or with Section 7 certificate require-
ments.  Of course, we do not reach the ultimate question 
whether Iroquois's legal defense costs were in fact prudently 
or imprudently incurred, and thus whether they may or may 
not be borne by the ratepayers.  We hold only that the 
Commission has not adequately justified its apparent decision 
to impose upon Iroquois the burden of proving that its 
activities benefited ratepayers.

     The case is remanded to the Commission for further pro-
ceedings consistent with this opinion.

     So ordered.


__________
     5 The Commission suggests in passing that the present case 
differs from Appalachian in that "Iroquois admitted to knowingly 
violating federal laws."  77 FERC at 62,281.  Litigation costs 
incurred in defense of knowing or willful violations might indeed call 
for more stringent treatment under the Mountain States II frame-
work, though "willful" and "knowing" are of course "word[s] of 
many meanings" depending upon context, see Bryan v. United 
States, 1998 WL 309067, *4 (U.S. June 15, 1998), and the settlement 
context suggests the presence of tradeoffs whose implications are 
unclear.  In any event, the Commission nowhere else relies on or 
develops the argument that Iroquois committed knowing violations, 
and we can find no support in the record before us to support such 
an assertion.




     Wald, Circuit Judge, concurring in the judgment:  Al-
though I agree that this case must be remanded for further 
consideration, I write separately to emphasize the breadth of 
the analysis FERC should undertake on remand.  Although 
the ultimate issue in this case is who is to bear Iroquois's 
litigation costs, not whether Iroquois's conduct was legal or 
illegal, the latter consideration is certainly relevant, in my 
view.  It is worth noting, therefore, that Iroquois admitted 
violating several environmental-related conditions of its sec-
tion 7 certificate, and our discussion of whether it is "just and 
reasonable" for the company to then shift the litigation costs 
related to those violations to its ratepayers should in no way 
be read as directing FERC to ignore the harm to the 
environment that has been suffered as a result of those 
violations.  Rather, I think it important that the calculus of 
whether a rate is reasonable take into consideration noneco-
nomic benefit as well as economic benefit.  It may well be 
true that a thoroughly informed ratepayer will prefer a 
cheaper product obtained by way of environmental violations 
over a more expensive product produced legally.  But I'm not 
sure that this can be presumed to be the case, as the majority 
opinion appears to assume.  In an antitrust case, as Moun-
tain States II recognized, the analysis is easier:  A presump-
tion that litigation expenses associated with a violation of the 
antitrust laws are disallowed is reasonable because we can 
assume that consumers would prefer to buy products in a 
competitive market, since competition is presumed to make 
products both cheaper and better.  Thus, it would be difficult 
to show that anticompetitive conduct would be beneficial to 
ratepayers in any way.  Here, however, the equation is not so 
simple:  We cannot presume that noncompliance with environ-
mental regulations would be a benefit to ratepayers if the 
economic costs of compliance outweigh the economic costs of 
noncompliance, since the noneconomic benefit of compliance 
must also enter the calculus.  It may well be the case, for 
example, that a ratepayer would prefer to pay higher rates in 
exchange for the assurance that the pipeline from which it 



obtains its gas is in compliance with environmental laws.  (I 
can imagine several reasons for this preference:  for the 
goodwill benefits compliance confers, to aid in thwarting 
litigation, or even because the ratepayer lives in the geo-
graphic area for which noncompliance is proposed and will 
suffer as a citizen.)  I agree that under our precedent 
FERC's simple assertion that ratepayers have an interest in 
compliance with the law is insufficient to disallow recovery of 
Iroquois's litigation costs.  As Mountain States II holds, 
FERC must also take into consideration the economic bene-
fits noncompliance may confer, though I must admit I have a 
good deal of trouble with the proposition that FERC can 
validly attach an environmental condition on a section 7 
permit, but the company is simultaneously encouraged by 
ratemaking principles to violate it if it can build the pipeline 
cheaper or faster by doing so.  That kind of law makes no 
sense to me.  But I also believe that even the Mountain 
States II calculus is far more expansive than the majority 
opinion suggests.  By seeming to give priority to economic 
over noneconomic considerations, I fear that the majority will 
dissuade FERC from adequately considering the environmen-
tal costs of Iroquois's conduct, costs that may well affect the 
decision about whether forcing ratepayers to bear its litiga-
tion costs is indeed "just and reasonable."