Legal Research AI

LA Pub Svc Cmsn v. FERC

Court: Court of Appeals for the D.C. Circuit
Date filed: 1999-04-13
Citations: 174 F.3d 218
Copy Citations
14 Citing Cases
Combined Opinion
                        United States Court of Appeals


                     FOR THE DISTRICT OF COLUMBIA CIRCUIT


              Argued March 8, 1999       Decided April 13, 1999 


                                 No. 98-1088


                Louisiana Public Service Commission, et al., 

                                 Petitioners


                                      v.


                    Federal Energy Regulatory Commission, 

                                  Respondent


                 Arkansas Public Service Commission, et al., 

                                 Intervenors


     On Petition for Review of Orders of the Federal 
     Energy Regulatory Commission

     Michael R. Fontham argued the cause for petitioners.  
With him on the briefs were Noel J. Darce and George M. 
Fleming.



     David H. Coffman, Attorney, Federal Energy Regulatory 
Commission, argued the cause for respondent.  With him on 
the brief were Jay L. Witkin, Solicitor, and John H. Conway, 
Deputy Solicitor.

     Douglas G. Green argued the cause for intervenor Entergy 
Services, Inc.  With him on the brief was J. Wayne 
Anderson.

     Earle H. O'Donnell and Roger L. St. Vincent were on the 
briefs for intervenor Occidental Chemical Corporation.

     Mary W. Cochran, Paul R. Hightower, Clinton A. Vince, 
and Glen L. Ortman were on the brief for intervenors City of 
New Orleans and Arkansas Public Service Commission.

     Before:  Wald, Silberman, and Ginsburg, Circuit Judges.

     Opinion for the Court filed by Circuit Judge Silberman.

     Silberman, Circuit Judge:  FERC determined that Enter-
gy Corporation had violated the inter-company formula tariff 
that it administers to equalize costs among its five parallel 
subsidiaries;  the Commission declined, however, to order a 
refund from the subsidiaries that were undercharged by 
virtue of the tariff violation to the customers of the over-
charged subsidiaries.  The state regulatory bodies of Louisi-
ana and Mississippi (the service areas of the overcharged 
subsidiaries), supported by an energy consumer as interve-
nor, petition for review of the Commission's order, contending 
that the Commission abused its discretion in declining to 
order a refund.  We deny the petition.

                                      I.


     Entergy Corporation owns five public utilities--Entergy 
Gulf States, Entergy Arkansas, Entergy Louisiana, Entergy 
New Orleans, and Entergy Mississippi--that provide electri-
cal power to retail customers in Arkansas, Louisiana, Missis-
sippi, and Texas.  (Entergy Arkansas, alone among the sub-
sidiaries, sells wholesale as well as retail power.)  Entergy's 
subsidiaries are linked by more than common parentage:  
each subsidiary makes its capacity available to its sister 


companies as a backstop for when demand exceeds self-
generated supply.  Maintaining the availability of such capac-
ity, of course, carries costs, even when it is not tapped for 
power generation.  Since the subsidiaries' retail rates are set 
by state regulators based on principles of cost-of-service 
ratemaking, it would be inequitable--vis-a-vis a subsidiary's 
retail customers--for that subsidiary not to earn compensa-
tion from its sister companies when it keeps capacity on hand 
for them.

     The Entergy subsidiaries' response to this problem of cost 
equalization inter se is the System Agreement, a tariff that 
has been filed with and approved by the Commission pursu-
ant to s 205 of the Federal Power Act (FPA), 16 U.S.C. 
s 824d (1994).  One provision of the Agreement, known as 
the MSS-1 schedule, requires monthly payments from subsid-
iaries contributing less than their fair share of the System's 
total capacity to subsidiaries contributing more.1  A company 
first determines its capability:  the power that its "available" 
generating units--whether owned, leased or operated for its 
benefit--can generate in the month at issue.  Next the 
company ascertains its responsibility ratio by dividing its use 
of power (self-generated and otherwise)--known as load re-
sponsibility--by the sum of all the individual companies' load 
responsibilities.2  Then the company determines its propor-
tionate share of total System capability--known as capability 
responsibility--by multiplying its responsibility ratio by the 
total System capability, and compares this figure to its actual 
capability for the month.  If the company's actual capability 
is less than its capability responsibility, then the company is 
"short" and must make a monthly payment;  if the company's 
actual capability exceeds its capability responsibility, then the 
company is "long" and will receive a monthly payment.  The 
size of the payment is determined by multiplying the long 

__________
     1  These transactions are sales of electric energy at wholesale in 
interstate commerce, and hence are subject to the Commission's 
regulatory authority.  See 16 U.S.C. s 824 (1994).

     2  The company load responsibility, measured monthly, is a 
rolling 12-month average of the company's hourly loads, i.e., sales 
of power, coincident with the System's monthly peak hour load.


company's MSS-1 rate--its average cost of oil and gas gener-
ating units based on the previous year's operating results--by 
the number of megawatts by which the company is long.3

     As a formula rate tariff, the MSS-1 tariff's components 
may vary and hence the formula may dictate different equali-
zation payments from month to month.  Such changes do not, 
however, subject the Entergy system to the Federal Power 
Act's pre-filing and pre-approval requirements for changes in 
a tariff;  they are instead countenanced by FPA s 205(f), 16 
U.S.C. s 824d(f), which governs automatic adjustment claus-
es.  The retail rates charged by the subsidiaries to their 
customers are subject to state regulatory authority and oper-
ate quite differently.  Apart from a fuel adjustment clause 
that allows for automatic changes in retail rates when fuel 
costs change, the retail rates are fixed by state regulators and 
remain in place until the regulators initiate a new rate case.

     In 1985, when the current version of the System Agree-
ment was approved by the Commission, there were four 
Entergy subsidiaries.  Entergy Louisiana and Entergy New 
Orleans were consistently short;  Entergy Arkansas and En-
tergy Mississippi consistently long.  (A fifth subsidiary, En-
tergy Gulf States, joined the System in a merger approved in 
1993.)  Despite this imbalance among the subsidiaries in 
terms of relative contribution to System capability, circum-
stances were such that each subsidiary, in terms of absolute 
need for power given consumer demand, was maintaining a 
sizable number of operating units that were rarely (if ever) 
tapped for power generation.  In 1986, Entergy's operating 
committee initiated the Extended Reserve Shutdown (ERS) 
program in the hope of reducing the costs of maintaining this 
unnecessary capacity.  Under the program, some of the 
generating units would be identified as unnecessary for ca-
pacity needs, removed from active service, and preserved in a 
reserve status.  It was hoped that the ERS program would 
allow the companies to reduce staffing and other operating 

__________
     3  If there is more than one short company, the payment 
obligation is allocated based on the ratio of each short company's 
deficiency to the total deficiency of the short companies.



and maintenance expenses that otherwise would have been 
required to maintain the units in a constant state of readi-
ness, enable the companies to defer the cost of repairing 
broken units until it was necessary to bring the reserve units 
back on line, and obviate the need to construct costly new 
generating capacity to meet long-term requirements.  Al-
though Entergy contemplated retiring some of the ERS units 
rather than bringing them back on line, it intended to return 
many of the units to active service notwithstanding the 8-12 
month period necessary to restore the ERS units.  Forty 
percent of the units placed in ERS since the inception of the 
program in 1986 had been restored to active service by 1993.

     The dispute before us stems not from Entergy's implemen-
tation of the ERS program itself, but rather from Entergy's 
decision to allow the individual companies to include ERS 
units within the category of "available" capability for pur-
poses of cost equalization under the MSS-1 tariff.  Recall 
that the higher a company's capability relative to the capabili-
ties of its sister companies, the better off that company will 
be in terms of cost equalization under MSS-1.  Under the 
version of the System Agreement then in place,

     A unit is considered available to the extent the capability 
     can be demonstrated and (1) is under the control of the 
     System Operator, or (2) is down for maintenance or 
     nuclear refueling.  A unit is considered unavailable if in 
     the judgement of the Operating Committee it is of insuf-
     ficient value in supplying system loads because of (1) 
     obsolescence, (2) physical condition, (3) reliability, (4) 
     operating cost, (5) start-up time required, or (6) lack of 
     due-diligence in effecting repairs or nuclear refueling in 
     the event of a scheduled or unscheduled outage.

Entergy Servs., 80 F.E.R.C. p 61,197, at 61,787 (1997) (foot-
note omitted) (emphasis in original).  Entergy's Operating 
Committee interpreted "available" to include ERS units, 
which had the effect of improving the lot of those companies 
that had relatively more ERS-eligible units.  That benefitted 
Entergy Arkansas and Entergy New Orleans:  in the period 
1987-1993, Entergy Arkansas, which was long to begin with, 



became more long, and Entergy New Orleans, which was 
short to begin with, grew less short.  Conversely, Entergy 
Mississippi and Entergy Louisiana were, at least in this 
respect, disadvantaged by virtue of the inclusion of ERS units 
in MSS-1:  Entergy Mississippi, which was long to begin 
with, became less long, and Entergy Louisiana, which was 
short to begin with, became more short.  (The inclusion of 
ERS units as "available" for MSS-1 purposes also bears on 
the MSS-1 rates of the long companies.  As noted, that rate 
is the average cost per megawatt of the long company's oil 
and gas-fired generating units.  A long company, by placing 
units into ERS, reduces the cost associated with those units 
and consequently reduces the average cost of all of its oil-and 
gas-fired generating units, and hence its MSS-1 rate.)  Hold-
ing constant the number of units that each company actually 
put in ERS from 1987-1993, an Entergy officer determined 
that Entergy Mississippi received $8.8 million less, and En-
tergy Louisiana paid $10.6 million more, than would have 
been the case had ERS units been excluded from MSS-1.

     Though inclusion of ERS units in the MSS-1 calculation 
began in 1986, neither the Commission nor any other party 
challenged the practice until 1993.  One issue presented in 
FERC's review of the merger of Gulf States into the Entergy 
system as a fifth subsidiary was whether to allow Gulf States 
to include its then-existing ERS units as available capability 
for MSS-1 purposes before those units were returned to 
active service;  the Commission decided that Gulf States 
should not receive credit for those ERS units because "there 
has been no historic practice of maintaining rough production 
cost equalization between Gulf States and the Operating 
Companies."  Entergy Servs., Inc., 65 F.E.R.C. p 61,332, at 
62,497 (1993).  The Commission, sua sponte, raised the 
broader question of whether Entergy's System Agreement 
permits the four incumbent subsidiaries to count their ERS 
units as "available" for MSS-1 purposes, and initiated a 
proceeding under FPA s 206, 16 U.S.C. s 824e (1994), to 
determine whether the Entergy companies were violating the 
Agreement.  See Entergy Servs., 65 F.E.R.C. at 62,548.


     The Louisiana Public Service Commission and the Missis-
sippi Public Service Commission, petitioners here, argued 
that the Entergy system had violated the MSS-1 tariff's clear 
definition of "available" units by including ERS units in 
MSS-1.  They requested that Entergy Arkansas and Enter-
gy New Orleans, the operating companies that benefitted 
from the inclusion of ERS units in the MSS-1 calculation, 
refund to the customers of Entergy Louisiana and Entergy 
Mississippi the amount by which their rates had been escalat-
ed by virtue of the alleged tariff violation.  The Commission 
agreed that Entergy had violated its tariff, relying on the 
ALJ's finding that ERS units are neither under the control of 
the System Operator nor down for maintenance or nuclear 
refueling, but rather are effectively in storage.  See Entergy 
Servs., Inc., 80 F.E.R.C. at 61,786-87.  But FERC decided 
that the equities of the case did not support a refund because 
the end result of the tariff violation was not unjust, unreason-
able, or unduly discriminatory.  See id. at 61,787-88.  (The 
Commission expressly disclaimed any reliance on Entergy's 
submission that it acted in good faith in interpreting the tariff 
to address the novel problem of unnecessary capacity.  See 
id. at 61,788 & n.45.)4

     The Commission then turned to the appropriate treatment 
of ERS units going forward.  An amendment to the System 
Agreement was proposed that would include an ERS unit as 
an available unit under MSS-1 if Entergy intends to return 
the unit to service at a future date, with Entergy's "intent" to 
be ascertained by an examination of several enumerated 
factors and recorded in the minutes of the Operating Commit-
tee.  See id. at 61,788-89.  Over the objections of the Louisi-
ana and Mississippi regulators that it would be unjust to 
impose MSS-1 costs for units that provide no present benefit 
to the system and that the amendment's ambiguity made it 

__________
     4  The Commission also noted that because it was declining to 
order refunds based on its discretion, it had no need to address 
whether or to what extent FPA s 206(c), 16 U.S.C. s 824e(c) (1994), 
might preclude ordering refunds in any event.  See Entergy Servs., 
80 F.E.R.C. at 61,788 n.46.



susceptible to discriminatory application, the Commission ap-
proved the proposed amendment.  See id. at 61,789.

     Upon FERC's denial of the Louisiana and Mississippi 
regulators' request for rehearing on the refund and amend-
ment issues, see Entergy Services, Inc., 82 F.E.R.C. p 61,098 
(1998), the regulators, joined by an energy consumer (Occi-
dental Chemical Corporation) as intervenor, brought the in-
stant petition for review.  They contend that the Commission 
abused its discretion by relying on superficial, even irrational, 
equitable factors to deny the requested refund, especially 
when the Commission's self-described general policy is to 
provide refunds to remedy overcharges.5  And, while aban-
doning their complaint to the Commission that the concept of 
the amendment is unlawful insofar as it countenances the 
inclusion of some ERS units in the MSS-1 schedule, petition-
ers argue that the wording of the amendment is so ambiguous 
and prone to discriminatory implementation that the Commis-
sion has effectively abdicated its statutory responsibilities in 
approving it.

                                     II.


     We take up the refund issue first.  Before addressing 
petitioners' various attacks on the Commission's reasoning, 
we think we should clarify a point on which the briefs were 
somewhat obscure:  just what sort of injury has been caused 
by Entergy's violation of its tariff.  No one disputes that 
holding everything else constant, the decision to include ERS 
units in MSS-1 worked to the detriment of the two compa-

__________
     5  Intervenor Occidental makes a similar argument for a full 
refund but, unlike petitioners, alternatively seeks a refund under 
Western Resources, Inc., 65 F.E.R.C. p 61,271, at 62,252 (1993), in 
which the Commission held that in certain circumstances involving a 
tariff violation that benefits ratepayers, it would deny a full refund 
but award a refund of the time value of the overcharged amount.  
But since only intervenor Occidental raises the Western Resources 
refund issue before us, we decline to address it.  See Illinois Bell 
Tel. Co. v. FCC, 911 F.2d 776, 786 (D.C. Cir. 1990) ("An intervening 
party may join issue only on a matter that has been brought before 
the court by another party.").


nies, Entergy Louisiana and Entergy Mississippi, that had 
fewer ERS-eligible units than the other companies in the 
system.  Entergy Louisiana, a short company, became more 
short, i.e., faced higher MSS-1 payment obligations;  Entergy 
Mississippi, consistently a long company, became less long, 
i.e., received less in MSS-1 payments.  But since the retail 
rates of both companies were fixed before Entergy began to 
include ERS units in MSS-1 and did not change until peti-
tioners initiated rate cases in 1994, the harm cannot be found 
in an increase in retail rates charged to customers--as retail 
rates were fixed, no such increase occurred.  Nor can it be 
asserted that the injured parties are Entergy Louisiana and 
Entergy Mississippi--after all, these companies, along with 
the other Entergy subsidiaries and the holding company, 
support the Commission's order.  We gather the harm arises 
from petitioners' expectation that but for the distortions in 
MSS-1 payments flowing from the tariff violation, they would 
have brought rate cases earlier that would have lowered retail 
rates.

     This injury might well warrant a refund to the retail 
customers of Entergy Louisiana and Entergy Mississippi.  
But the Commission claimed it took a broader perspective 
and concluded that the equities cut against ordering a refund.  
Petitioners, while emphasizing the Commission's self-
described "general policy ... to order refunds to remedy 
overcharges," Entergy Servs., 82 F.E.R.C. at 61,369 (footnote 
omitted), do not--and, indeed, could not--contend that the 
policy is without exception.  See Koch Gateway Pipeline Co. 
v. FERC, 136 F.3d 810, 816 (D.C. Cir. 1998) (vacating refund 
order as an abuse of discretion);  Towns of Concord v. FERC, 
955 F.2d 67, 72 (D.C. Cir. 1992) ("[O]ur examination of the 
Federal Power Act reveals no statutory command mandating 
refunds when the rate charged exceeds that filed.").6  In-
stead, petitioners submit that the Commission's four grounds 

__________
     6  The Commission's authority to order refunds of amounts 
improperly collected in violation of the filed rate derives from FPA 
s 309, 16 U.S.C. s 825h (1994).  See Towns of Concord, 955 F.2d at 
73.



for departing from its general policy are irrational.  As the 
Commission did not set forth these equitable factors in the 
alternative or otherwise suggest that its decision would be the 
same in the absence of one or more of the four factors, we 
consider each one.  See Sundor Brands, Inc. v. NLRB, 1999 
WL 94803, *3 (D.C. Cir. Feb. 26, 1999) (citing SEC v. 
Chenery Corp., 318 U.S. 80, 87 (1943)).

     We bear in mind, however, that "[w]hen a federal court of 
appeals reviews an administrative agency's choice of remedies 
to correct a violation of a law the agency is charged with 
enforcing, the scope of judicial review is particularly narrow."  
National Treasury Employees Union v. FLRA, 910 F.2d 964, 
966-67 (D.C. Cir. 1990) (en banc);  see also ICC v. Transcon 
Lines, 513 U.S. 138, 145 (1995); Towns of Concord, 955 F.2d 
at 76 (explaining that the words "necessary or appropriate" in 
FPA s 309, 16 U.S.C. s 825h, evince Congress' intent to 
leave refund determinations to the Commission's "expert 
judgment").  Indeed, "the breadth of agency discretion is, if 
anything, at [its] zenith when the action assailed relates 
primarily not to the issue of ascertaining whether conduct 
violates the statute, or regulations, but rather to the fashion-
ing of policies, remedies and sanctions ... in order to arrive 
at maximum effectuation of Congressional objectives."  Niag-
ara Mohawk Power Corp. v. FPC, 379 F.2d 153, 159 (D.C. 
Cir. 1967).  Thus, we will set aside FERC's remedial decision 
only if it constitutes an abuse of discretion.  See, e.g., Public 
Utils. Comm'n of Calif. v. FERC, 143 F.3d 610, 617 (D.C. Cir. 
1998);  Koch Gateway, 136 F.3d at 816.  To the extent the 
Commission made factual determinations in the course of 
exercising its discretion, we of course ask whether those 
conclusions are supported by substantial evidence.  See 16 
U.S.C. s 8251(b) (1994).

                                      A.


     We begin with the Commission's "disincentive" rationale 
for denying a refund:



     [G]iven that there would have been a disincentive to 
     participate in the ERS program without Schedule MSS-1 
     treatment for the units, Entergy's actions, both in creat-
     ing the ERS program and in continuing to include these 
     units in Schedule MSS-1 calculations, resulted in consid-
     erable system-wide benefits, in the form of enhanced 
     system efficiencies and cost reductions, that ultimately 
     benefitted ratepayers.

Entergy Servs., 80 F.E.R.C. at 61,787 (footnotes omitted).  In 
other words, the Commission thought it inequitable to order a 
refund when the predicate tariff violation had conferred bene-
fits on the system, including the allegedly injured parties, 
that would not have come to pass absent the tariff violation.

     Petitioners' primary argument is that FERC is simply 
wrong in asserting that the operating companies needed any 
added incentive to place units in ERS.7  They submit that the 
enormous benefits expected to flow from the ERS program in 
terms of reduced operating, maintenance, and fuel costs, far 
outweigh any disincentive created by adverse MSS-1 treat-
ment.  One view of Entergy's own data supports this claim:  
company by company, over a roughly concurrent six-year 
period, the benefit of the ERS program in terms of operating 
and other cost savings outweighs the "cost" of adverse MSS-1 
treatment for all but Entergy New Orleans.  In the case of 
Entergy Louisiana and Entergy Mississippi, adverse MSS-1 
treatment, i.e., inclusion of ERS units in MSS-1, is what 

__________
     7  Petitioners also argue--half-heartedly--that treating ERS 
units as available capability for MSS-1 purposes would neither 
avoid a disincentive, nor create an incentive, for the operating 
companies to place units in ERS.  But, in a world where ERS units 
are excluded from treatment as available capability, an operating 
company will not be indifferent between receiving MSS-1 credit 
now (by keeping the unit in active service) and receiving MSS-1 
credit later (by putting the unit in ERS and later restoring it to 
active service)--money now is always more valuable than money 
later.  And petitioners overlook that treating ERS units as "avail-
able" for MSS-1 also creates an "extra" incentive in that the life of 
the unit is extended and the unit continues to receive MSS-1 credit 
(albeit at lower rates in the case of a long company) while in ERS.


actually occurred.  Yet Entergy Louisiana's ERS savings of 
$13.8 million outweigh its MSS-1 detriment of $10.6 million;  
Entergy Mississippi's ERS savings of $11.2 million similarly 
surpass its MSS-1 detriment of $8.8 million.  In the case of 
Entergy Arkansas and Entergy New Orleans, adverse 
MSS-1 treatment, i.e., exclusion of ERS units from MSS-1 
treatment, did not occur in fact.  Supposing that ERS units 
had been excluded from MSS-1 treatment, Entergy Arkansas 
would have lost $6.3 million in MSS-1 receipts but would still 
have enjoyed $33.9 million in ERS savings;  on the other 
hand, Entergy New Orleans would have faced $13.1 million 
more in MSS-1 payments and would have enjoyed only $6.8 
million in ERS savings.  (This assumes that Entergy Arkan-
sas and Entergy New Orleans would have placed the same 
number of units into ERS had those units been excluded from 
MSS-1 treatment.)  All this suggests that each company 
except Entergy New Orleans would have made roughly the 
same ERS "investment" even if it had received adverse 
MSS-1 treatment as a result.

     This analysis is inadequate, however, because it assumes 
that the companies make their ERS decisions with hindsight 
on a net basis, rather than at the margin looking forward.  
For each of the four pre-merger companies, if ERS units 
were excluded from MSS-1 treatment, there would be a cost 
to placing an extra unit into ERS;  the company will suffer in 
its MSS-1 standing vis-a-vis the other companies (and they 
could not be sure how the other companies would behave).  
To be sure, there is also a benefit, in terms of ERS savings, 
upon placing that marginal unit into ERS.  But, as the 
Commission and intervenor Entergy point out, the magnitude 
of the costs was certain whereas the scope of the benefits was 
not.  Accordingly, we cannot say the Commission abused its 
discretion in rejecting an analysis that itself ignored the 
distinction between ex ante and ex post reasoning.

     Be that as it may, petitioners argue that it makes little 
sense to talk of "providing incentives" or "avoiding disincen-
tives" to the operating companies' putting units into ERS.  
That analytical framework is, according to petitioners, a post 
hoc construct that ignores the reality that the operating 



companies are wholly owned subsidiaries of Entergy Corpora-
tion and therefore have neither the ability nor the inclination 
to flout the System's goals.  The only incentives that matter, 
petitioners submit, are those faced by the System as a whole.

     Petitioners acknowledge, as they must, however, the record 
testimony of several witnesses that the operating companies 
do in fact possess the authority to identify and recommend 
for final approval by the System's operating committee 
which--and how many--units to place in ERS.  One of 
FERC's trial staff testified, for example, that "each operating 
company ... made the decision as to which unit if any to 
place in ERS and when to place a unit in ERS."  There was 
further testimony that the visibility of the adverse MSS-1 
treatment felt by each of the companies on a unit-by-unit 
basis might raise the ire of state regulators ignorant of the 
less visible (and more uncertain) benefits of ERS.  To these 
witnesses, the aggravation of justifying the ERS program to 
state regulators might deter even the most System-loyal 
operating company officers from putting units into ERS.  As 
one witness summarized, "as long as there are individual 
Operating Companies with responsibilities to their regulators 
and ratepayers, such individual Operating Company interests 
cannot be ignored."  Surely this constitutes substantial evi-
dence in support of the Commission's finding.8

__________
     8  Petitioners submit that other record evidence casts doubt on 
the Commission's finding that the operating companies approached 
the ERS program in a self-interested way.  They point to the 
testimony of the operating committee's delegate that the System's 
final approval of units for ERS was not always documented careful-
ly, and suggest that if the operating companies really were looking 
out for themselves, they would have insisted on more fastidious 
record-keeping.  This testimony stands in contrast to the numerous 
other witnesses testifying that the operating companies did have 
some autonomy in ERS decisions, and surely cannot be said to tip 
the scales such that no "reasonable jury [could] reach the [Commis-
sion's] conclusion," Allentown Mack Sales & Serv., Inc. v. N.L.R.B., 
522 U.S. 359, 367 (1998).



     Still, petitioners claim that the Commission's, and our own, 
prior interpretations of the nature of the Entergy system 
support their conception of the operating companies as indis-
tinguishable (and unthinking) parts of a whole.  However, we 
think that precedent is not inconsistent with the Commis-
sion's findings here.  In Middle South Energy, Inc., 31 
F.E.R.C. p 61,305 (1985), the Commission, in the course of 
approving the 1985 (and still current) version of the System 
Agreement, rejected an ALJ's finding that the operating 
companies exhibited a "pattern of autonomy."  Id. at 61,645 
(quoting Middle South Energy, Inc., 30 F.E.R.C. p 63,030, at 
65,168 (1985)).  The Commission found that "major critical 
decisions, including decisions to build new generating units, 
are made by the Operating Committee for the benefit of the 
system as a whole."  Id.  But the Commission also acknowl-
edged that "it is clear that there is input from the individual 
companies and consideration of their needs in making coordi-
nated decisions."  Id.  And, in denying petitions for review of 
the Commission's decision in Middle South, we described the 
Commission as finding, inter alia, that the "individual operat-
ing companies were intimately involved in the planning stages 
of new generation units and sought to promote their own 
interests."  Mississippi Indus. v. FERC, 808 F.2d 1525, 
1555-56 (D.C. Cir. 1987), rev'd on other grounds, 822 F.2d 
1104 (D.C. Cir. 1987).  That the operating companies are 
involved in the "planning stages" of the ERS program--not 
that their decisions are final--is all the Commission found in 
this case.

     Taking the broadest tack, petitioners also seek to under-
mine the Commission's very premise that the ERS program 
"ultimately benefitted ratepayers."  Petitioners do not dis-
pute that the ERS program provided benefits;  but it is 
asserted that those benefits, rather than being passed on to 
ratepayers, stayed within the Entergy system, and thus 
within the pockets of Entergy's shareholders.  How could it 
be, petitioners ask, that ratepayers enjoyed the benefits of 
the ERS program--which predominantly take the form of 



reduced operating costs that are reflected in retail rates only 
when a new rate case is initiated--when no such rate case 
occurred during the first seven years of the program?  
FERC responds by pointing to several ERS-related benefits 
that flowed to ratepayers in Louisiana and Mississippi, the 
service areas regulated by petitioners.  For one, a 1994 rate 
case involving Entergy Mississippi resulted in a $28.1 million 
reduction in retail rates;  Entergy Louisiana was in the 
course of a similar rate proceeding not yet completed (based 
on the current record) but expected to have a similar out-
come.  For another, even before the 1994 rate cases, the 
Commission identifies certain benefits that flowed to Louisi-
ana and Mississippi ratepayers.  The ERS program produced 
some $2.6 million in energy cost savings, $2.1 million of which 
was passed on to Entergy Louisiana's and Entergy Mississip-
pi's ratepayers through the automatic fuel adjustment clauses 
in those companies' retail rate tariffs.  And perhaps more 
important, as the Commission explained in its order denying 
rehearing, the ERS savings support an inference that, ceteris 
paribus, the companies would have less need to seek rate 
increases.  See Entergy Servs., 82 F.E.R.C. at 61,370.

     There is ample evidence, therefore, supporting the Com-
mission's general finding that some ERS-related benefits 
accrued to Louisiana and Mississippi ratepayers.  Nor can we 
quarrel with the Commission's "expert judgment" that these 
benefits supported denying the requested refund, a proposi-
tion that we have endorsed in the past.  See Gulf Power Co. 
v. FERC, 983 F.2d 1095, 1100 (D.C. Cir. 1993).  Petitioners 
do not even respond to the Commission's point about the 
pass-through of fuel cost savings to retail ratepayers, or to 
the Commission's observation that the 1994 rate cases un-
doubtedly have captured some of the ERS-related benefits 
for ratepayers.  And the Commission's finding that the ERS 
program obviated the need for Entergy Louisiana and Enter-
gy Mississippi to seek rate increases is not, as petitioners 
suggest, suspect because based on an inference from the 
record.  Those sorts of "sound inference[s] from all the 
circumstances," Allentown Mack Sales & Serv., Inc. v. 



N.L.R.B., 522 U.S. 359, 379 (1998), are the stuff of which 
substantial evidence is made.

                                      B.


     Now to the Commission's second reason:  "[T]he non-Gulf 
States ERS units were planned and constructed for the 
benefit of all of the pre-merger Operating Companies."  En-
tergy Servs., 80 F.E.R.C. at 61,787 (footnote omitted).  In 
other words, the ERS units are really just another sort of 
excess capacity--albeit an "extended reserve"--that is avail-
able, once restored, to serve the System's needs, and there-
fore should receive the same cost equalization treatment 
under MSS-1 as does "ordinary" excess capacity.  See id.  
(Placing a unit in ERS, while significantly reducing the costs 
associated with that unit, does not eliminate those costs 
entirely.  See Entergy Servs., 82 F.E.R.C. at 61,370 n.9.)  
The Commission also pointed out that even during the units' 
ERS tenure, they provide System-wide benefits.  See Enter-
gy Servs., 80 F.E.R.C. at 61,788.  Most notably for present 
purposes, the companies' ability to return ERS units to active 
status allows the companies to defer the construction of costly 
new generation units.  Moreover, the Commission's approval 
of an amendment to the System Agreement specifically to 
address this situation would have been forthcoming if re-
quested (as it was in this proceeding).  See id.  Though 
petitioners attack this rationale--that extended reserves 
should be treated like ordinary reserves--insofar as it sup-
ported the Commission's decision on refunds, paradoxically 
they do not take issue with the identical concept underlying 
the amendment approved by the Commission, which express-
ly countenances the inclusion of ERS units in MSS-1 going 
forward.  In challenging the amendment solely on the ground 
that it is too vague, petitioners have de facto conceded the 
basic equitable argument.

     Even aside from petitioners' implied concession, they do 
not persuade us that the Commission has abused its "consid-
erable discretion in fashioning remedies."  Public Utils. 
Comm'n, 143 F.3d at 617.  Petitioners contend that ERS 
units provide no benefits to the System during their ERS 



tenure, and hence are properly excluded from MSS-1 cost 
equalization because they are not presently "used and useful" 
to the System.  But the Commission explained that ERS 
units are useful to the System in providing a backup reserve 
to the System and in allowing the companies to defer repairs 
of the ERS units and construction of new generating units, 
and we see no reason not to defer to the Commission's 
conception of usefulness.  Nor are we impressed with peti-
tioners' alternative point that, even though ERS units may be 
useful if restored to active service, Entergy officials have 
testified that some of the ERS units would be retired perma-
nently rather than restored.  The Commission reasonably 
concluded that all of the ERS units could be brought back to 
active service, and that this benefit was sufficient, especially 
when the decision to retire certain ERS units would be made 
in the future.  (Indeed, as we noted earlier, 40% of the units 
placed in ERS since the inception of the program in 1986 had 
already been restored to active service by 1993.)  FERC's 
judgments on these questions of benefits readily support its 
application of the well-settled principle that the costs associat-
ed with ERS units (whether construction expenses incurred 
in the past or maintenance costs incurred today) should be 
borne by those who benefit from them.  See, e.g., Gulf Power 
Co., 983 F.2d at 1100;  City of New Orleans v. FERC, 875 
F.2d 903, 905 (D.C. Cir. 1989).

     Petitioners, moreover, oversimplify in claiming that the 
appropriateness of MSS-1 cost equalization treatment at a 
given point in time hinges on whether the unit in question is 
"used and useful" to the System at that time.  We explored 
this issue in Town of Norwood v. FERC, 80 F.3d 526 (D.C. 
Cir. 1996), which involved the analogous context of a dispute 
over which assets a single utility could appropriately include 
in its rate base--analogous because an individual Entergy 
company's catalogue of MSS-1 eligible units is akin to a 
"cost-equalization rate base."  The utility in Norwood had 
shut down its nuclear power plant temporarily in response to 
a regulator's safety concerns, and four months later decided 
to retire the plant permanently because the costs of restart-
ing it and operating it through the remainder of its license 



exceeded the value of the energy it could produce.  See id. at 
528.  The Commission granted the utility's request to include 
in its rate base 100% of its $48.4 million investment in the 
plant that it would have recovered if it had operated the plant 
through the remainder of its license, and its post-shutdown 
operating and maintenance expenses of $68.9 million.  See id. 
at 528, 530.  A petition for review asserted, inter alia, that 
forcing ratepayers to pay for a plant no longer producing 
electricity conflicts with the principle that ratepayers should 
only pay for items "used and useful" in providing service.  
We rejected the argument:

     Although a utility's rate base normally consists only of 
     items presently "used and useful," see New England 
     Power Co. Mun. Rate Comm. v. FERC, 668 F.2d 1327, 
     1333 (D.C. Cir. 1981), cert. denied, 457 U.S. 1117 (1982), a 
     utility may include "prudent but canceled investments" in 
     its rate base as long as the Commission reasonably 
     balances consumers' interest in fair rates against inves-
     tors' interest in "maintaining financial integrity and ac-
     cess to capital markets."  Jersey Cent. Power & Light 
     Co. v. FERC, 810 F.2d 1168, 1178 (D.C. Cir. 1987) [(en 
     banc)].

Town of Norwood, 80 F.3d at 531 (emphasis and bracketed 
material added).  We held that the Commission had reason-
ably approved the requested cost recovery, in light of the 
nuclear plant's record of serving ratepayers for decades and 
the promise of savings going forward.  Here, no one disputes 
that the ERS units have a record of service as available 
capacity, or that placement of units into ERS yields savings 
going forward.9  And, unlike the nuclear plant in Norwood, 
many of the ERS units will be returned to active service in 

__________
     9  As noted earlier, there are ongoing costs associated with the 
ERS units, which are akin to the post-shutdown maintenance 
expenses approved for recovery in Norwood.  And petitioners 
themselves indicate that the ERS units still have some initial 
investment costs that have not yet been recovered, see Brief for 
Petitioners at 25, the recoupment of which we also sanctioned in 
Norwood.



the future.  So even were we to assume the ERS units are 
not presently "used and useful," our broader explication of 
the "used and useful" principle in Norwood provides ample 
support for the Commission's reasoning.

                                      C.


     The final two factors relied on by the Commission are not 
all that weighty.  FERC concluded that "there was no unjust 
enrichment as a result of the violation [of the tariff's defini-
tion of "available"], given that Entergy as a whole received no 
net gain from the inclusion of ERS units in Schedule MSS-1." 
Entergy Servs., 80 F.E.R.C. at 61,787.  The Commission 
explained that the only consequence of the decision to include 
or exclude ERS units for MSS-1 purposes is a different 
MSS-1 payment pattern among the operating companies;  but 
MSS-1 payments and receipts always cancel out from the 
perspective of the System as a whole, and so Entergy Corpo-
ration (the holding company) had nothing to gain by violating 
its tariff.  See id. at 61,787 n.37.  Petitioners appreciate this 
algebraic truth, but suggest that it is too superficial a charac-
terization of the holding company's motives.  Pointing to an 
Entergy official's testimony that one of the reasons for includ-
ing ERS units in MSS-1 was to maintain stability in MSS-1 
payments and receipts so as to avoid the initiation of rate 
cases by state regulators, petitioners contend that this strate-
gy--which proved successful until 1994--unjustly enriched 
the holding company by enabling it to keep the benefits of 
ERS for the shareholders for longer than if ERS units had 
been excluded from MSS-1.  The Commission responds by 
claiming that the benefits identified by petitioners flow from 
the ERS program, not from the tariff violation.

     We admit that petitioners cast doubt on the strength of this 
factor, especially given the Commission's failure squarely to 
address in its brief petitioners' notion that the tariff violation 
provided a benefit insofar as it made rate cases less likely by 
not "rocking the boat" of MSS-1 payments and receipts.  But 
under the deferential review we accord to the Commission's 
remedial decisions, we think the Commission's reasoning just 



passes muster.  A reasonable response to petitioners' point, 
although missing in the Commission's brief, can be found in 
the Commission's explanation in its orders of the separate 
disincentive rationale we discussed at the outset of our analy-
sis.  The Commission explained that the System (and its 
shareholders) did not retain all of the benefits of the tariff 
violation that facilitated the ERS program.  Even though no 
rate case was initiated before 1994, ratepayers were made 
better off insofar as the operating companies were less likely 
to seek rate increases.  See Entergy Servs., 82 F.E.R.C. at 
61,370.  And the 1994 rate cases appear to have captured 
benefits for ratepayers in the form of reduced retail rates.  
The Commission's view that this division of benefits between 
the Entergy System and the retail ratepayers was not "un-
just" deserves deference.  Indeed, it is hardly unusual for a 
utility whose rates are set by cost-of-service ratemaking 
principles to seek to reduce its costs, thereby increasing 
profits, during the interim between rate-setting proceedings.  
See National Rural Telecom Ass'n v. FCC, 988 F.2d 174, 178 
(D.C. Cir. 1993);  Stephen Breyer, Regulation and its Reform 
48 (1982).

     The Commission's final factor sounds in estoppel;  the 
Commission stated that "nearly every participant in this 
proceeding, including [petitioners], at one time either believed 
that the System Agreement permitted the inclusion of ERS 
units in Schedule MSS-1 calculations, or at least did not 
protest such treatment."  Entergy Servs., 80 F.E.R.C. at 
61,787-88 (footnote omitted).  Petitioners concede that they 
did not object until the Commission initiated its s 206 investi-
gation into the possible tariff violation, but argue that the 
timing of their protest is irrelevant.  They explain that in the 
merger review proceeding, their entire focus was on the 
treatment of Gulf States' ERS units, and thus they should not 
be faulted for missing the possibility that inclusion of ERS 
units in MSS-1 by the incumbent subsidiaries was working to 
the detriment of Entergy Louisiana and Entergy Mississippi.  
Only when they concentrated on the s 206 proceeding, peti-
tioners tell us, did they discover the disparity among the 
incumbent subsidiaries in ERS-eligible units and recognize 



the impact on Entergy Louisiana and Entergy Mississippi of 
including ERS units in MSS-1.  Petitioners also urge that 
even if they should have complained earlier, that failing 
should not be attributed to the retail ratepayers, the ultimate 
beneficiaries of the hoped-for refund.

     Again, though this factor is less weighty than the others--
particularly the first two--and perhaps would be inadequate 
standing alone, we do not regard it as objectionable.

                                     III.


     There remains petitioners' challenge to the amendment 
approved by the Commission to govern the MSS-1 treatment 
of ERS units going forward.  The amendment provides:

     A unit is considered available to the extent the capability 
     can be demonstrated and (1) is under the control of the 
     System Operator, or (2) is down for maintenance or 
     nuclear refueling, or (3) is in extended reserve shutdown 
     (ERS) with the intent of returning the unit to service at 
     a future date in order to meet Entergy System require-
     ments.  The Operating Committee's decision to consider 
     an ERS unit to be available to meet future System 
     requirements shall be evidenced in the minutes of the 
     Operating Committee and shall be based on consider-
     ations of current and future resource needs, the project-
     ed length of time the unit would be in ERS status, the 
     projected cost of maintaining such unit, and the project-
     ed cost of returning the unit to service.

Entergy Servs., 80 F.E.R.C. at 61,788-89 (emphasis in origi-
nal).  Petitioners contend that this amendment grants unfet-
tered discretion to Entergy, and thus is an effective abdica-
tion of the Commission's statutory responsibility to ensure 
that rates are just and reasonable.  See 16 U.S.C. s 824d(a).  
They explain that the amendment does not indicate in which 
direction the various factors point, and does not say anything 
about the relative weights of the factors. Petitioners bolster 
their claim by directing us to the testimony of an Entergy 



witness who opined that the factors could cut for or against 
MSS-1 inclusion depending on the circumstances.

     While the amendment is certainly closer to a standard than 
to a rule, we defer to the Commission's judgment that it is 
just and reasonable.  See Northern States Power Co. v. 
FERC, 30 F.3d 177, 180 (D.C. Cir. 1994) ("Because '[i]ssues of 
rate design are fairly technical and, insofar as they are not 
technical, involve policy judgments that lie at the core of the 
regulatory mission,' our review of whether a particular rate 
design is 'just and reasonable' is highly deferential." (quoting 
Town of Norwood v. FERC, 962 F.2d 20, 22 (D.C. Cir. 1992)) 
(alteration in original)).  FERC understandably concluded 
that the amendment set out the parameters of the operating 
committee's discretion, and that discriminatory implementa-
tion of the amendment could be remedied in a proceeding 
under FPA s 206, 16 U.S.C. s 824e, a review facilitated by 
the requirement that the operating committee record the 
reasons for its decisions in writing.  The amendment, more-
over, is a far cry from the vacuous tariff provisions that the 
Commission has rejected in the past.  See, e.g., Southern 
Natural Gas Co., 47 F.E.R.C. p 61,205, at 61,708 (1989) 
(rejecting portion of proposed tariff that granted oil pipeline 
authority to construct facilities to serve shippers "in its sole 
discretion");  Tennessee Gas Pipeline Co., 45 F.E.R.C. 
p 61,236, at 61,693 (1988) (same);  cf. Farmers Union Cent. 
Exch., Inc. v. FERC, 734 F.2d 1486 (D.C. Cir. 1984) (vacating 
Commission order setting permissible oil pipeline rates so 
high that "regulation" would be left to market forces, reason-
ing that the Commission thereby contravened its statutory 
responsibility to ensure that rates are just and reasonable).

                                   * * * *


     For the foregoing reasons, the petition for review is denied.

     So ordered.