Licari v. Ferruzzi

                UNITED STATES COURT OF APPEALS
                    FOR THE FIRST CIRCUIT
                                         

No. 93-2047

            ARTHUR J. LICARI, AS HE IS TRUSTEE OF
                 COLONIAL DRIVE REALTY TRUST,

                    Plaintiff, Appellant,

                              v.

            JOSEPH FERRUZZI, PATRICK J. McNALLY, 
           STANLEY I. BORNSTEIN, KENNETH J. SAVOIE
           WILLIAM E. BINGHAM, CATHERINE LEFEBVRE,
           ELIZABETH WARE AND THE TOWN OF IPSWICH,

                    Defendants, Appellees.

                                         

         APPEAL FROM THE UNITED STATES DISTRICT COURT

              FOR THE DISTRICT OF MASSACHUSETTS

           [Hon. Rya W. Zobel, U.S. District Judge]
                                                  

                                         

                            Before

                     Selya, Circuit Judge,
                                         
                Bownes, Senior Circuit Judge,
                                            
                  and Stahl, Circuit Judge.
                                          

                                         

Paul F. Denver, with whom Rossman,  Rossman & Eschelbacher were on
                                                          
brief for appellant.
Patrick  M. Hamilton,  with whom  Richard E.  Brody and  Morrison,
                                                                  
Mahoney  &  Miller were  on brief  for  appellees Patrick  J. McNally,
              
Stanley I. Bornstein, Kenneth J. Savoie, William E. Bingham, Catherine
Lefebvre,  Elizabeth Ware and the Town of Ipswich, Nancy Merrick, with
                                                            
whom  Douglas I.  Louison  and Merrick  & Louison  were  on brief  for
                                             
appellee Joseph Ferruzzi.
                                         
                        April 22, 1994
                                         

          BOWNES, Senior Circuit  Judge.  This appeal  arises
          BOWNES, Senior Circuit  Judge.
                                       

from  an action for damages brought by a developer frustrated

by  town planning  and  permitting authorities.    Plaintiff-

appellant,  Arthur J.  Licari, as  trustee of  Colonial Drive

Realty Trust  (hereinafter "Colonial"), appeals from an order

granting summary judgment  for defendants-appellees, the Town

of Ipswich,  the town  building inspector, the  town planner,

and members of the planning board.  The complaint alleged due

process  violations under  42  U.S.C.     1983,  as  well  as

violations of  Massachusetts civil rights  laws and  tortious

interference  with  contract.   We  affirm  the decision  for

defendants on the    1983 claims, but vacate the  judgment on

the pendent state claims and remand so that those claims will

be adjudicated, or dismissed without prejudice.  

                              I.

                          BACKGROUND
                                    

          In 1987, Colonial's predecessor in  interest sought

to develop property in Ipswich, Massachusetts, and obtained a

"special permit" from the planning board  to comply with town

zoning laws.1    One  part  of  the  project  included  three

buildings.  The building  plans incorporated into the special

permit   stated   that  Building   3   would   be  set   back

                    

1.  A  special permit  is  analogous to  a  variance.   Under
Massachusetts  law,  a  town's  zoning  ordinances may  allow
particular developments, such as multifamily dwellings, to be
constructed in a given zoning district only upon the issuance
of a special permit.  Mass. Gen. Laws ch. 40A,   9.  

                             -2-
                              2

"approximately forty-five (45) feet" from the road.  Colonial

acquired three  building  permits and  began construction  in

1988.  

          At a hearing held on October 12, 1989, the planning

board discussed whether the  location of Building 3 conformed

with the dimensions in the plans incorporated in  the special

permit.  One week  later, the town planner wrote  to Colonial

that Building 3 was  seven feet closer to  the road than  the

special permit  allowed.   The  letter  requested  Colonial's

confirmation or  denial of those charges,  in writing, before

the  next board  meeting on  October 26  and stated  that any

further  work would be at  the developer's risk.   The record

does not  indicate whether Colonial attended  that meeting or

submitted any information  to the board.   During the October

26 meeting,  the  board  issued  and later  recorded  at  the

registry  of deeds a "Notice  of Noncompliance," based on the

discrepancy between  the special  permit and the  location of

Building 3.

          Building 3's proximity to the road was discussed in

planning board  meetings over the following  months.  Members

of  the board informed Colonial at a hearing in November 1989

that Buildings  1 and 2 also contravened  the special permit.

In November 1989, Colonial sought an amendment to the special

permit  to cure the problems,  but the board  did not approve

that application until April 2, 1990.  Meanwhile, on February

                             -3-
                              3

1, 1990, Colonial once  again argued to the board  that there

were  no discrepancies  between  the special  permit and  the

project as built.  

          On February 2, 1990, defendant Joseph Ferruzzi, the

town building inspector, revoked  all three building  permits

and ordered that  further work  cease.  The  reasons for  the

revocation  were that the buildings  did not conform with the

special permit, and that Colonial had represented in applying

for building  permits that the project was in compliance with

"project documents" and with zoning requirements.   According

to Colonial, the board ordered the permits revoked.  Colonial

initiated,  but later  abandoned,  an  appeal  of  Ferruzzi's

action to the Massachusetts Building Code Appeals Board.

          Until new building permits were issued, work on the

project could not continue, and bank financing was suspended.

In  May 1990, Ferruzzi promised to issue new permits, but did

not actually issue them until  August.  The bank's  financing

commitment  also  expired  in  August.   Colonial  failed  to

complete the project and defaulted on its loan. 

          In January 1993, Colonial  filed suit in the United

States District Court for the District of Massachusetts.  The

complaint  alleged  that  Ferruzzi  and the  town  failed  to

provide due process by  revoking the building permits without

a proper inquiry, notice, or hearing.  The complaint included

claims  that  the arbitrary  acts  of  defendants other  than

                             -4-
                              4

Ferruzzi violated Colonial's  due process  rights.   Finally,

the   complaint  alleged  that   defendants  interfered  with

Colonial's   contractual   relations,  and   that  defendants

violated Massachusetts civil rights laws.  Defendants filed a

motion  for   summary  judgment,  which  the  district  court

granted.

                             II.

                            ISSUES
                                  

          Colonial argues  on  appeal [1]  that the  district

court  erred  in  granting summary  judgment  on  the    1983

claims; [2] that the court erred in denying Colonial's motion

for leave to engage in discovery under Fed. R. Civ. P. 56(f);

and [3] that the court erred in granting summary judgment for

defendants  on  the state  law  claims.   We  consider  those

arguments seriatim.  
                  

          The first issue is whether the district court erred

in  granting  summary judgment  on  the  federal due  process

claims.  Our review of the district court's order is de novo.
                                                            

Nestor Colon Medina &  Sucesores, Inc. v. Custodio,  964 F.2d
                                                  

32, 39 (1st Cir. 1992).  Summary judgment  is proper where no

material  facts  are in  dispute,  and  the moving  party  is

entitled to judgment  as a matter  of law.   Fed. R. Civ.  P.

56(c).  

          Defendants argue  that summary judgment  was proper

because this case is analogous to our line of cases upholding

                             -5-
                              5

pretrial  orders  disposing  of    1983  due  process  claims

brought by  frustrated  applicants against  local  permitting

officials.    See,  e.g.,  Nestor Colon,  964  F.2d  32;  PFZ
                                                             

Properties, Inc.  v. Rodriguez, 928 F.2d 28  (1st Cir. 1991),
                              

cert.  dismissed, 112  S. Ct.  1151 (1992);  Creative Env'ts,
                                                             

Inc. v. Estabrook, 680 F.2d 822 (1st Cir.), cert. denied, 459
                                                        

U.S. 989 (1982).  We agree.  In this case, as in those cases,

the procedural  and substantive  due process claims  were not

actionable under   1983.

                             III.

                     DUE PROCESS CLAIMS 
                     DUE PROCESS CLAIMS
                                       

          To  avoid summary  judgment  on  a  procedural  due

process  claim, Colonial must show [1] that it had a property

interest  defined  by state  law;  and  [2] that  defendants,

acting under color of state law, deprived it of that interest

without adequate process.  PFZ Properties, 928 F.2d at 30.  A
                                         

viable substantive due process  claim requires proof that the

state  action was  "in  and  of  itself  .  .  .  egregiously
                                       

unacceptable,  outrageous, or conscious-shocking."  Amsden v.
                                                          

Moran, 904  F.2d  748,  754  (1st  Cir.  1990)  (emphasis  in
     

original), cert.  denied, 498  U.S. 1041 (1991).   Procedural
                        

due process guarantees that  a state proceeding which results

in a deprivation  of property is fair,  while substantive due

process  ensures that such state action  is not arbitrary and

capricious.  Id. at 753-54.       
                

                             -6-
                              6

A.  Revocation of Building Permits
                                  

          Colonial  argues that its  right to  procedural due

process was violated when defendant Ferruzzi, at the planning

board's behest, revoked the  building permits in violation of

state law without prior notice and a hearing.  Ferruzzi acted

under color  of state law;  the letter  revoking the  permits

cited the  discrepancies between  the special permit  and the

project as built and  stated that he could "revoke a permit .

.  . in case of  any false statement  or misrepresentation of

fact in the application or the plans on which the  permit . .

.  was based."    22  Mass. Regs.  Code  tit.  780,    114.7.

Because  we assume  for  the purposes  of  this opinion  that

Colonial  held a  property interest in  the permits,  see PFZ
                                                             

Properties,  928 F.2d  at  30-31, the  key  issue is  whether
          

Colonial was afforded adequate process. 

          To  determine  whether  a  procedural  due  process

violation has occurred, "it is necessary to  ask what process

the State  provided,  and  whether  it  was  constitutionally

adequate.    This  inquiry   would  examine  the   procedural

safeguards   built  into  the   statutory  or  administrative

procedure . .  . effecting the deprivation,  and any remedies

for erroneous deprivations provided  by statute or tort law."

Zinermon  v. Burch, 494 U.S. 113,  126 (1990).  We assess the
                  

adequacy of procedures by balancing the government's interest

against the private interest affected by the action, the risk

                             -7-
                              7

of  an erroneous  deprivation,  and the  value of  additional

safeguards.  Mathews v. Eldridge, 424 U.S. 319, 335 (1976).  
                                

          We  begin our analysis by describing the procedural

protections  afforded Colonial.   Prior  to  the deprivation,

Colonial  was notified of the board's  allegations and had an

opportunity  to rebut them.  We take as true Colonial's claim

that  the  planning  board  was  the  ultimate  decisionmaker

because  it  ordered  the  permits  revoked.    Colonial  was

notified at  planning board meetings in  October and November

1989, by  a letter from the  town planner in October,  and by

the "Notice of Noncompliance" filed  at the registry of deeds

in November that there were alleged discrepancies between the

plans incorporated in  the special permit and  the project as

built.   Those  allegations underlay  the finding  that there

were false  statements  in the  building permit  application.

Colonial had an opportunity to contest those allegations with

respect  to Building 3 during  the October 12  hearing and in

the two weeks preceding the planning  board's issuance of the

Notice of  Noncompliance.   Although it is  unclear from  the

record   whether  Colonial   actually   responded  to   those

allegations, it  is enough to satisfy the  Due Process Clause

that  the   opportunity   for  such   a   response   existed.

Furthermore,  on  February  1,  1990,  Colonial  disputed the

allegations  with  respect to  all  three buildings,  several

                             -8-
                              8

months after receiving notice  of them, and one day  prior to

the revocation.

          The   notice  Colonial   received   prior  to   the

revocation   never  specifically   informed   it   that   the

inconsistency  between  the  special permit  and  the project

might be  a basis for  finding a  "misrepresentation" in  the

building permit application, justifying the revocation of the

permits.   Colonial  argues that  it  was thereby  denied  an

opportunity to be heard on that issue.   We disagree.  First,

Colonial received  a letter from the  town planner describing

the discrepancy  between the special permit  and the location

of  Building 3 and indicating  that further work  would be at

the   developer's  risk.     That   letter,  the   Notice  of

Noncompliance, and later discussions  with the board informed

Colonial  that   town  officials  deemed   the  discrepancies

significant.    Furthermore, Ferruzzi's  letter  revoking the

building permits claimed that plans submitted to him prior to

the issuance  of the permits stated that the project complied

with  zoning  and with  "project documents."   A  letter from

Colonial's architect  appended  to Colonial's  Opposition  to

Defendants'  Motion   for  Summary  Judgment   supports  that

statement of the facts, and nothing in the record contradicts

it.   Cf. 22 Mass. Regs.  Code tit. 780,   113.5 (application
         

for building  permit must include  site plans).   Finally,  a

state  regulation  authorized  Ferruzzi  to  revoke  building

                             -9-
                              9

permits  based  on   false  statements  in  building   permit

applications.2     Id.     114.7.    The  existence  of  that
                      

regulation, the warning in the planner's letter, the repeated

discussions  with  the  board,  and  the  contents  of  plans

submitted  on  Colonial's  behalf to  the  building inspector

provided Colonial  with sufficient notice and  an opportunity

to respond. 

          There is a further reason why the revocation of the

building   permits  did  not   violate  Colonial's  right  to

procedural   due  process:    postdeprivation  remedies  were

available.      See  Zinermon,   494   U.S.   at  126   ("The
                             

constitutional  violation actionable  under     1983  is  not

complete  when the  deprivation  occurs; it  is not  complete

unless and until  the State fails to  provide due process.").

Colonial  had  numerous opportunities  to  meet  formally and

informally  with town officials to  recover the permits.  See
                                                             

Amsden,  904 F.2d at  755 (informal negotiations  are part of
      

process  provided).  Such negotiations ultimately yielded the

result  Colonial   desired,  the  issuance  of  new  permits.

Moreover, Colonial had the  right to an administrative appeal

                    

2.  An affidavit of Jason Sokolov, Colonial's attorney before
the planning board, states, "On information and belief, th[e]
accusation  [of  a misrepresentation  in the  building permit
application] was untrue."  We  express no opinion on whether,
as  a  matter of  state law,  those  statements in  the plans
submitted  to  Ferruzzi constituted  "misrepresentation[s] of
fact in the  [building permit] application."  22  Mass. Regs.
Code tit., 780   114.7.   

                             -10-
                              10

of the  building inspector's decision, which  could have been

heard by the zoning board of appeals or by the state Building

Code  Appeals   Board,  and   a  right  to   judicial  review

thereafter.   See  22 Mass.  Regs. Code  tit. 780,     126.1,
                 

126.6; 126.7.1.  

          Colonial  misses the  mark  by  arguing that  those

remedies  are insufficient  solely  because  relief might  be

delayed,  and damages are  unavailable.  In  the first place,

delays,  while endemic to  administrative and  judicial fora,

are minimized in these  proceedings because the Appeals Board

adheres to  a timetable.   22 Mass.  Regs. Code tit.  780,   

126.3.4, 126.4.3.   Furthermore,  a damage  remedy is  not an

essential  component  of  constitutionally   adequate  review

procedures.  Chongris v. Board of Appeals, 811 F.2d 36, 44-45
                                         

(1st  Cir.), cert. denied, 483 U.S. 1021 (1987).  We conclude
                         

that Colonial had  sufficient notice and an opportunity to be

heard prior  to the revocation,  and adequate  administrative

and judicial review procedures afterwards; no further process

was exigible.  Id. at 40.  
                  

B.  Notice of Noncompliance
                           

          Colonial adverts  that the planning  board violated

procedural due process by  summarily issuing and recording at

the registry of deeds a Notice of Noncompliance, which stated

that   Colonial's  buildings   did   not  comply   with   the

requirements of the  special permit.   That issue appears  in

                             -11-
                              11

the brief without citation to legal authority, and with scant

elaboration  on whether or  how the board's  act affected any

property  right.  We express no opinion on the merits because

we  deem  it waived.    "Issues adverted  to  on appeal  in a

perfunctory   manner,   unaccompanied   by   some   developed

argumentation,  are deemed  to have  been abandoned."   Gamma
                                                             

Audio & Video, Inc. v. Ean-Chea, 11 F.3d 1106, 1113 (internal
                               

quotation marks and citation omitted). 

C.  Delays
          

          Colonial  contends  that   the  board's  delay   in

approving the  application  for  an  amended  special  permit

violated its right to procedural  due process.  Assuming that

Colonial  held a property interest in the permit prior to its

issuance,   and  that   the   delay   itself  constituted   a

"deprivation," we disagree  with Colonial's  contention.   We

take  as true  the allegation  that the  delay  resulted from

defendants' unauthorized intransigence  and illegal  demands.

We have rejected similar   1983 claims, however, where--as in

this  case--the deprivation  was unauthorized,  the  value of

further  process  was  negligible,  and  the  state  provided

adequate remedies.  E.g.,  Nestor Colon, 964 F.2d at  40; PFZ
                                                             

Properties, 928 F.2d at 31; see also Mass. Gen. Laws ch. 40A,
                                    

  9 (failure of permitting board to act on permit application

within  90 days after public hearing deemed to be approval of

                             -12-
                              12

application); id.    17 (final decisions  of permitting board
                 

subject to expedited judicial review). 

D.  Substantive Due Process Claims
                                  

          The substantive due process claims are based on the

same  factual  allegations  underlying  the   procedural  due

process claims, i.e., the revocation of the building permits,
                    

the  unauthorized issuance  of  enforcement  orders, and  the

delays  in  the   processing  and   approval  of   Colonial's

application  for an  amended  permit.   Those acts  allegedly

manifest "a  persistent and consistent  hostility and  animus
                                                             

toward [Colonial]," aimed at  coercing Colonial to reduce the

size of the project. 

          "This  Court  has  repeatedly   held  .  .  .  that

rejections  of development  projects  and  refusals to  issue

building permits do not ordinarily  implicate substantive due

process."   PFZ Properties, 928  F.2d at 31;  see also, e.g.,
                                                            

Creative Env'ts, 680 F.2d at 832 n.9,  833.  There is nothing
               

in  the record to differentiate this case from those in which

we have found no  viable basis for a    1983 claim.   We note

that Colonial  has neither argued, nor  offered evidence that

defendants' "hostility and animus" was aimed at any political
                                 

affiliation, belief, stance,  or immutable characteristic  of

Colonial.   Rather, Colonial's  brief states that defendants'

improper conduct "was motivated by the defendants'  wrongful,

outrageous goal" of compelling  it to reduce the size  of the

                             -13-
                              13

project.  Cf. Creative Env'ts, 680 F.2d at 833 ("Every appeal
                                                      

.  . .  from an  adverse ruling  by a  . .  . planning  board

necessarily  involves some  claim  that the  board  exceeded,

abused  or `distorted' its legal  authority . .  ., often for

some allegedly perverse (from  the developer's point of view)

reason.  It  is not  enough simply  to give  these state  law

claims  constitutional labels  .  . .  in  order to  raise  a

substantial  federal question under  section 1983." (emphasis

in original)).  

          Colonial argues that  this court should  "overrule"

the cases  in this circuit rejecting  substantive due process

claims in local  planning disputes, so that  its claims might

be litigated.   Colonial contends that  there are cases  from

other circuits  permitting   1983 actions  based on arbitrary

or  capricious conduct by local land  use officials, and that

this  court  should follow  suit in  this  case.   See, e.g.,
                                                            

Littlefield  v. City of Afton,  785 F.2d 596  (8th Cir. 1986)
                             

(collecting cases).  But  see Lemke v. Cass County,  846 F.2d
                                                  

469, 470-71 (8th Cir. 1987) (en banc) ("Whether a substantive

due process claim may arise from a denial  of a zoning permit

is an open question in this circuit . . . .").   

          There is a  problem with  Colonial's argument  that

goes  beyond its  assumption that  this panel  would overrule

precedent  in this circuit:   we have never  announced a rule

precluding  district  courts  from  finding  substantive  due

                             -14-
                              14

process violations  by land  use planning officials  in every
                                                             

conceivable case.   Rather,  "[o]ur cases make  clear that  a

regulatory  board  does  not  transgress  constitutional  due

process   requirements  merely   by  making   decisions  `for

erroneous  reasons' or  by  making  `demands  which  arguably

exceed  its authority  under the  relevant state  statutes.'"

Amsden, 904 F.2d at 757 (quoting Creative Env'ts, 680 F.2d at
                                                

832 n.9); see also, e.g., Chiplin Enters. v. City of Lebanon,
                                                            

712 F.2d 1524, 1528 (1st Cir.  1983).  "We have left the door

slightly ajar  for federal  relief [based on  substantive due

process] in truly horrendous  situations."  Nestor Colon, 964
                                                        

F.2d at  45.   Nevertheless, "the threshold  for establishing

the  requisite  `abuse of  government  power' is  a  high one

indeed."  Id.  
             

          There is  a sound basis  for our  approach to  such

claims in land use planning disputes:  

          Substantive due process, as a  theory for
          constitutional  redress, has  . .  . been
          disfavored,  in  part   because  of   its
          virtually standardless reach.   To  apply
          it  to  claims [alleging  that permitting
          officials  were  motivated  by  political
          factors  and  parochial  views  of  local
          interests]  would  be  to  insinuate  the
          oversight   and  discretion   of  federal
          judges into  areas traditionally reserved
          for state and local tribunals.

Id. 
   

          We  are   not  persuaded  by   Colonial  that   the

allegations  and evidence  in this  case distinguish  it from

                             -15-
                              15

Nestor Colon and  the other cases  in this circuit  rejecting
            

substantive  due  process claims  in  similar  disputes.   In

Amsden, 904 F.2d at 757, for example, in deciding an issue of
      

qualified immunity, we stated that plaintiff had not produced

evidence of  conduct so  "shocking or violative  of universal

standards  of decency" as to violate  the Due Process Clause,

although the evidence suggested  that plaintiff's license was

revoked  to force his partner out of business.  Id. (internal
                                                   

quotation  marks and citation  omitted).  Defendants' conduct

in this case, allegedly designed to  force Colonial to reduce

the  size  of  its  project, is  similarly  not  sufficiently

"conscious-shocking."  Id. at 754.  We hold that the district
                          

court properly  granted summary  judgment on the  due process

claims.  

                             -16-
                              16

                             IV.

                 DENIAL OF RULE 56(f) MOTION
                                            

          Colonial argues  that the district  court erred  in

denying its  motion under Fed. R. Civ.  P. 56(f) for leave to

engage in discovery.   The district court stated that  it was

denying  the  motion  because  "defendants  are  entitled  to

judgment as a matter of law."  

          "To satisfy Rule 56(f),  a party must `articulate a

plausible  basis for the  belief that  discoverable materials

exist which would raise a trialworthy issue.'"  Nestor Colon,
                                                            

964  F.2d  at 38  (citation omitted).    With respect  to the

federal claims  that we  consider in this  appeal, Colonial's

motion  asserted  that  discovery  would  yield  evidence  of

defendants' "animus"  towards Colonial, and evidence  of what

defendants "knew or believed" about the location of the three

buildings.   We consider whether the denial of the motion was

an abuse of discretion.  Id.
                            

          We find no abuse of discretion in this case because

the  evidence sought by Colonial  is not the  type that would

render the     1983 claims  viable.   Colonial  alleged  that

defendants' improper conduct was motivated by the defendants'

goal  of compelling  it to  reduce the  size of  the project.

Such a motive might be illegitimate as a matter of state law,

but  it is  not a  basis for  a    1983 claim.   See  Chiplin
                                                             

Enters.,  712 F.2d  at 1528.   Similarly,  there would  be no
       

                             -17-
                              17

basis  for  relief under    1983,  even if  discovery yielded

proof that defendants knew  that the buildings conformed with

the special permit.  Id. ("A mere bad faith refusal to follow
                        

state law  in such  local administrative matters  simply does

not  amount to a deprivation  of due process  where the state

courts are available to  correct the error.").  Consequently,

we  conclude that the district  court did not  err in denying

the Rule 56(f) motion.  

                              V.

                  DISMISSAL OF STATE CLAIMS
                                           

          Finally, we consider whether judgment  was properly

entered  on  the pendent  state  law  claims.   The  district

court's  summary judgment  order  consists  of the  following

notation on the first page  of defendants' motion:  "Allowed,

Nestor  Colon Medina & Sucesores, Inc.  v. Custodio, 964 F.2d

32 (1st Cir.  1992), PFZ Properties,  Inc. v. Rodriguez,  928

F.2d  28  (1st  Cir. 1991).    Judgment  may  be entered  for

defendants."  We read  that order as resting on  Nestor Colon
                                                             

and PFZ Properties, not as an endorsement of all arguments in
                  

defendants' brief.  

          The reference  to Nestor  Colon and  PFZ Properties
                                                             

makes clear  that the district court  considered Colonial's  

1983  claims.   Nothing,  however, indicates  that the  state

civil rights  and tort claims  were weighed.   That  adequate

state   appeals  procedures  and  remedies  might  protect  a

                             -18-
                              18

developer's federal  due process rights, and  thus preclude  

1983  litigation, see Nestor Colon,  964 F.2d at  40, 45; PFZ
                                                             

Properties, 928 F.2d  at 31-32, is not  germane to Colonial's
          

state law claims.  

          Although there is no  indication that the  district

court ever  considered the pendent claims,  the court's order

effectively  dismissed  those  claims with  prejudice.    The

court's  order on those  claims was  an abuse  of discretion.

Defendants have not answered  the complaint; there is support

in  the record for the  pendent claims; and  Colonial has not

yet   had   the   opportunity   to   engage   in   discovery.

Consequently,  while we  affirm the  judgment on  the    1983

claims,  we vacate the judgment  on the state  law claims and

remand  the case so that those claims will be adjudicated, or

dismissed  without  prejudice.    See  28  U.S.C.     1367(c)
                                     

(district court  may  decline to  exercise jurisdiction  over

pendent  claims  if it  has  dismissed  all federal  claims);

Mercado-Garcia v.  Ponce Federal Bank, 979 F.2d 890, 896 (1st
                                     

Cir.  1992); Figueroa Ruiz v. Alegria, 896 F.2d 645, 650 (1st
                                     

Cir. 1990).  

          It is so ordered.
                           

                             -19-
                              19