Legal Research AI

Midland Cogn Vntrs v. FERC

Court: Court of Appeals for the D.C. Circuit
Date filed: 1998-01-16
Citations: 133 F.3d 34
Copy Citations
23 Citing Cases
Combined Opinion
                        United States Court of Appeals


                     FOR THE DISTRICT OF COLUMBIA CIRCUIT


              Argued November 13, 1997 Decided January 16, 1998 


                                 No. 96-1200


                    Southeastern Michigan Gas Company and 

                            Michigan Gas Company, 

                                 Petitioners


                                      v.


                    Federal Energy Regulatory Commission, 

                                  Respondent


             Northern States Power Company (Minnesota), et al., 

                                 Intervenors 


                              Consolidated with

          Nos. 96-1207, 96-1211, 96-1213, 96-1216, 96-1307, 96-1324,

             96-1366, 96-1376, 96-1377, 96-1412, 96-1441, 97-1079


 


                                   ________


 


                  On Petitions for Review of Orders of the 

                     Federal Energy Regulatory Commission


     Clinton A. Vince argued the cause for joint petitioners and 
supporting intervenors, with whom Deborah A. Swanstrom, 



Emmitt C. House, Mary Ann Walker, Neil L. Levy, David I. 
Bloom, Randall B. Palmer, Shaheda Sultan, Elizabeth W. 
Whittle, Gordon J. Smith, Ronald N. Carroll, Charles H. 
Shoneman, Eileen G. Stanek, David D'Alessandro, Kelly A. 
Daly, Thomas L. Casey, Solicitor General, State of Michigan, 
Don L. Keskey and Henry Boynton, Assistant Attorneys 
General, Frederick J. Killion, Allan W. Anderson, Jr., and 
David B. Ward were on the joint briefs.

     Deborah A. Moss argued the cause for petitioner Consum-
ers Energy Company, with whom William M. Lange was on 
the briefs.

     Frederick J. Killion argued the cause for petitioners 
Northern States Power Company, et al., with whom John H. 
Burnes, Jr., and Theresa I. Zolet were on the briefs.

     Philip F. Cronin, Jr. argued the cause for petitioner 
Rochester Gas and Electric Corporation, with whom Eliza-
beth W. Whittle was on the briefs.

     William W. Brackett argued the cause for petitioner Mid-
land Cogeneration Venture Limited Partnership, with whom 
Terry O. Brackett was on the briefs.

     Joel M. Cockrell, Attorney, Federal Energy Regulatory 
Commission, argued the cause for respondent, with whom 
Jay L. Witkin, Solicitor, and John H. Conway, Deputy Solici-
tor, were on the brief.

     James D. McKinney, Jr., argued the cause for intervenor 
Great Lakes Gas Transmission Limited Partnership, with 
whom G. William Stafford and John J. Wallbillich were on 
the brief.

     Allan W. Anderson, Jr., argued the cause for intervenors in 
support of respondents, with whom David B. Ward, Shaheda 
Sultan, Charles H. Shoneman,and Elizabeth W. Whittle were 
on the brief.

     Before:  Edwards, Chief Judge, Ginsburg and Sentelle, 
Circuit Judges.

     Opinion for the Court filed by Circuit Judge Sentelle.



     Sentelle, Circuit Judge:  This case grows out of a long-
running dispute between the Great Lakes Gas Transmission 
Partnership ("Great Lakes"), various factions of its shippers, 
and the Federal Energy Regulatory Commission ("FERC").  
We first reviewed FERC's resolution of this matter in Trans-
Canada Pipelines Ltd. v. FERC, 24 F.3d 305 (D.C. Cir. 1994), 
where we remanded the case to FERC for further consider-
ation.  On remand, FERC abandoned its initial position and 
issued new orders adverse to the parties that had prevailed in 
the pre-TransCanada administrative proceedings.  We now 
consider whether FERC's latest ratesetting orders concern-
ing the Great Lakes Natural Gas Transmission Pipeline com-
plied with Section 4 of the Natural Gas Act ("NGA"), see 15 
U.S.C. s 717c, and were not otherwise arbitrary and capri-
cious.

                                      I.


     FERC orders issued in 1989 and 1990 authorized Great 
Lakes, which already operated a 2,000-mile interstate pipe-
line, to build a series of mainline loops that substantially 
enlarged the system's shipping capacity and that increased its 
rate base from $202 million to $953 million.  FERC tradition-
ally approved pipelines' proposals to roll expansion costs into 
their general rates (thereby allocating expansion costs to all 
users pro rata regardless of the extent to which they use the 
new facilities) so long as the pipeline could show both that the 
system was integrated and that qualitative benefits accrued 
to all customers as a consequence of the expansion.  See 
TransCanada, 24 F.3d at 308 (citing Great Lakes Gas Trans-
mission Co., 45 FERC p 61,237, 61,695 (1988)); Great Lakes 
Gas Transmission L.P., 57 FERC p 61,140, 61,520 (1991), 
reh'g denied, 62 FERC p 61,101, 61,713 (1993).  When FERC 
reviewed Great Lakes' proposal, however, it abruptly aban-
doned its traditional standard (called the "Battle Creek test" 
after the case in which we first approved of its application, see 
Battle Creek Gas Co. v. FPC, 281 F.2d 42 (D.C. Cir. 1960)).  
Rather than the two-part Battle Creek test, FERC applied a 
"commensurate benefits" test, in which it compared the cost 
of expansion with the benefits accruing to existing users.  57 
FERC at 61,520-21.  Because it found that construction costs 



far exceeded any consequent benefit to existing users, FERC 
ordered Great Lakes to price its services incrementally (i.e., 
recovering expansion costs only from those customers that 
use the new facilities ("expansion shippers")).  See 57 FERC 
at 61,512;  Great Lakes Gas Transmission L.P., 57 FERC 
p 61,141, 61,534 (1991), reh'g denied, 62 FERC p 61,102, 
61,731 (1993).  The expansion shippers petitioned this court 
for relief, claiming that FERC's orders were arbitrary, dis-
criminatory, impermissibly retroactive, and issued in violation 
of the Administrative Procedure Act.  See TransCanada, 24 
F.3d at 307.

     We held that FERC failed to provide a "reasoned explana-
tion" for having abandoned the Battle Creek test and remand-
ed the case.  See 24 F.3d at 310.  While not holding that the 
commensurate benefits test was itself invalid, we nonetheless 
found that FERC's sudden abandonment of Battle Creek 
required more elaborate explanation and more substantial 
consideration of the consequences.1  See id. at 311.

     On remand FERC again altered its course.  Rather than 
elaborate its rationales for adopting the commensurate bene-
fits test, FERC reverted to the Battle Creek test and held 
that rolled-in pricing would be more equitable than incremen-
tal pricing.  See Great Lakes Gas Transmission L.P., 72 
FERC p 61,081, 61,423 (1995).  FERC's Chair dissented, 
arguing that the outcome was inequitable and not mandated 
by TransCanada.  See id. at 61,431-33.  The FERC majority 
justified its return to Battle Creek by finding that the expan-
sion parties had reasonably relied at the time of construction 
on an expectation that FERC would apply the Battle Creek 
standard.  See id. at 61,427.  FERC concluded that its initial 

__________
     1 FERC has since issued a rule that establishes a presumption in 
favor of incremental pricing when rolling in expansion costs would 
increase rates to existing customers more than five percent.  See 
Pricing Policy for New and Existing Facilities Constructed by 
Interstate Natural Gas Pipelines, 75 FERC p 61,105 (1996).  Be-
cause FERC issued its rule after this case had begun and did not 
rely on it in this proceeding, we do not consider what effect its 
application would have had.



decision to apply a commensurate benefits test was "legal 
error" and ordered "Great Lakes to refund to the expansion 
shippers the principal amounts that they paid in excess of the 
lawful systemwide rolled-in rate....  [FERC also] per-
mit[ted] Great Lakes to impose offsetting surcharges on the 
pre-expansion shippers."  Id. at 61,430.  FERC found that, in 
the interests of equity, interest charges should not apply 
retroactively (though a dispute exists over when interest 
began to accumulate).  See id.

     Nonexpansion customers filed a petition for rehearing.  
FERC rejected the petition, see Great Lakes Gas Transmis-
sion L.P., 75 FERC p 61,089, 61,268 (1996), affirming its 
earlier decision, reemphasizing the significance of the expan-
sion shippers' reliance interest in the application of the Battle 
Creek standards, and permitting Great Lakes to retain a 
$15.7 million difference between surcharges and refunds.  Id. 
(The surplus was later recomputed to be $17.5 million.  See 
Great Lakes Gas Transmission L.P., 76 FERC p 61,157, 
61,935 n.29 (1996).)  Furthermore, FERC clarified that 
rolled-in pricing applied to all nonexpansion shippers, regard-
less of the nature of their shipping contracts.  See 75 FERC 
at 61,293-94.  FERC's Chair again dissented.  FERC later 
granted Great Lakes' motion to clarify the interest provisions 
of the earlier orders, see 76 FERC p 61,926, and held, among 
other things, that interest began to accrue on all surcharges 
on October 1, 1995, when rolled-in rates took effect.  Id. at 
61,936-38.  Various parties now petition for review of nearly 
every element of FERC's orders.

                                      II.


     In TransCanada, we remanded the case to FERC to 
permit it to elaborate its factual findings and to explain its 
decision to apply the commensurate benefits test retroactive-
ly.  See TransCanada Pipelines, 24 F.3d at 310-11; cf.  
Checkosky v. SEC, 23 F.3d 452, 465 (D.C. Cir. 1994) (Silber-
man, J., concurring) (stating that remand without vacating is 
proper when court is "unsure and [wants] ... clarification of 
[the agency's] position and the rationale therefor").  On re-



mand, FERC abandoned the commensurate benefits test and 
readopted the Battle Creek test.  Natural Gas Pipeline of 
America and a number of other natural gas shippers (collec-
tively "Natural") challenge both FERC's authority to return 
to the Battle Creek test and its application thereof.

                                      A.


     Natural initially contends that FERC's decision to readopt 
the Battle Creek test was arbitrary and capricious because it 
misinterpreted TransCanada's mandate, arguing that in 
TransCanada we remanded solely to permit FERC to clarify 
its reasoning.  While Natural is correct that the remand 
provided that option, once FERC reacquired jurisdiction, it 
had the discretion to reconsider the whole of its original 
decision.  See Radio Television S.A. de C.V. v. FCC, No. 
96-1438, 1997 WL 761854, at *6 (D.C. Cir. Dec. 12, 1997).  
We therefore reject Natural's contention that FERC misun-
derstood the ambit of its authority following the Trans-
Canada remand.

     Natural next argues that FERC lacked substantial evi-
dence to support its finding that Great Lakes and the expan-
sion shippers had a settled expectation that FERC would 
apply the Battle Creek test to its review of their Section 4 
ratesetting petition.  Natural again misunderstands FERC's 
position.  FERC does not purport to have made factual 
findings regarding the parties' reliance interests.  Rather, 
FERC inferred from the significant costs incurred by Great 
Lakes in building the expansion facilities that it and the 
expansion shippers anticipated application of Battle Creek at 
the time that they undertook construction.  See 75 FERC at 
61,274 & n.40.  Because such a conclusion is not a factual 
finding, it did not require specific evidentiary underpinnings.  
Thus, we adopt the same standard of review we applied in 
Adelphia Comm. Corp. v. FCC, 88 F.3d 1250 (D.C. Cir. 1996), 
where we reviewed a Federal Communications Commission 
presumption that was premised upon Commission experience 
rather than factual findings to ensure that it was not arbi-
trary or capricious.



     According to Natural, FERC's invocation of the reliance 
rationale was an abuse of discretion because the expansion 
shippers could not reasonably have relied either on the 
outcome of administrative proceedings or on the standard 
that would be applied.  FERC did not premise readoption of 
Battle Creek on the expansion shippers' reliance upon the 
outcome of the Battle Creek test; it merely concluded that 
the expansion shippers were entitled to rely on their expecta-
tion that FERC would apply that test to Great Lakes' Section 
4 petition.  Thus, we review only FERC's justification of its 
return to Battle Creek on that basis.  The nonexpansion 
parties' objection to FERC's invocation of the reliance ratio-
nale is without foundation.  In a long line of cases beginning 
with Retail, Wholesale & Dep't Store Union v. NLRB, 466 
F.2d 380 (D.C. Cir. 1972), we have held that, in some circum-
stances, parties are entitled to rely on the consistent applica-
tion of administrative rules.  See, e.g., Williams Natural Gas 
Co. v. FERC, 3 F.3d 1544, 1554-55 (D.C. Cir. 1993).  So long 
as courts are permitted to consider parties' reliance on old 
rules in determining whether the retroactive application of a 
new rule is arbitrary and capricious, it follows that agencies 
may consider the benefits of doctrinal stability when deciding 
whether to apply new rules retroactively.

     Natural also contends that Great Lakes and the expansion 
shippers were on notice of pending changes to FERC's rate 
design policy, see Pricing Policy, 75 FERC p 61,105, when 
they decided to build their new facilities and that such 
knowledge bars them from now claiming that they relied on 
the application of the Battle Creek test.  In fact, there was no 
notice of pending changes in the applicable standard (or at 
least none to which we have been referred) at the time of the 
original Section 7 proceeding, and notice of imminent admin-
istrative recalibration therefore cannot be the basis for chal-
lenging the reliance rationale in this instance.  Compare 
Chadmoore Comm., Inc. v. FCC, 113 F.3d 235, 240 (D.C. Cir. 
1997) (noting that adjudication under review was part of 
broader--and already publicized--plan to modify the distribu-
tion of construction licenses).



     Finally, Natural asserts a vague claim that FERC violated 
the pre-expansion shippers' constitutional rights by inducing 
the very reliance upon which FERC ultimately justified appli-
cation of the Battle Creek test.  Before Great Lakes began 
construction of the expansion facilities, some pre-expansion 
shippers moved FERC to consolidate Great Lakes' Section 7 
permitting and Section 4 ratesetting proceedings.  FERC 
refused and instead granted the construction permits and 
deferred ratesetting until after construction was complete.  
See Great Lakes Gas Transmission L.P., 48 FERC p 61,127 
(1990); Great Lakes Gas Transmission L.P., 48 FERC 
p 61,273 (1989).  Natural claims that FERC's decision to 
permit construction prior to resolution of the rate issue, 
coupled with its later invocation of the reliance rationale, 
made the outcome of the Section 4 proceeding a foregone 
conclusion and thereby denied the nonexpansion shippers a 
meaningful hearing.

     Not only does Natural fail to refer us to any applicable 
constitutional provision, but it also mistakes FERC's conclu-
sion that Great Lakes relied on the application of Battle 
Creek for a finding that Great Lakes relied on the outcome of 
the Battle Creek test.  Even if FERC's disaggregation of the 
Section 4 and Section 7 proceedings induced the expansion 
shippers to rely on application of the Battle Creek test, 
FERC's invocation of the reliance rationale was wholly unre-
lated to its disposition of the merits of Great Lakes' petition.  
In short, Natural does not refer us to any procedural irregu-
larity in its application, let alone any procedural or substan-
tive shortcoming of constitutional dimension in FERC's hear-
ings.

     FERC's readoption of the Battle Creek test was a permissi-
ble exercise of administrative discretion, and we therefore 
turn to whether FERC correctly applied the test.

                                      B.


     Natural further contends that even if FERC was entitled to 
readopt Battle Creek, FERC erred in its application of the 



test.2  While our standard for reviewing ratesettings is defer-
ential, see Time Warner Entertainment Co. v. FCC, 56 F.3d 
151, 163 (D.C. Cir. 1995), cert. denied, 116 S. Ct. 911 (1996), it 
is "not ... an empty gesture."  Northern States Power Co. v. 
FERC, 30 F.3d 177, 180 (D.C. Cir. 1994); see Tarpon Trans-
mission Co. v. FERC, 860 F.2d 439, 442 (D.C. Cir. 1988) 
(stating that we will not "rubberstamp[ ] unsupported, and 
perhaps unsupportable, agency decisions").

     The Battle Creek test permits rolled-in pricing when expan-
sion facilities are part of an integrated pipeline system and 
when the expansion provides system-wide benefits, such as 
additional capacity, increased reliability, or enhanced expansi-
bility.  See Battle Creek, 281 F.2d at 47.  Section 4 of the 
NGA, pursuant to which FERC has the authority to regulate 
natural gas sales and transportation pricing, mandates "just 
and reasonable" rates.  15 U.S.C. s 717c(a).  Natural and 
FERC disagree over whether application of the Battle Creek 
test in this instance generated "just and reasonable" rates.  
Natural argues both that FERC neglected to satisfy its 
statutory obligation to ensure the equity of its orders and 
that, even if the rates in question here were reasonable, 
FERC's application of the test was infected with error.

     Natural claims at the outset that FERC failed to comply 
with its statutory mandate to ensure "just and reasonable 
rates" because its application of Battle Creek was mechanical 
and failed to consider the equity of the additional costs with 
which the nonexpansion parties would be saddled after rates 
were rolled in.  Although Natural is, of course, correct that 

__________
     2 At oral argument, Natural contended that because of the affili-
ate relationship between Great Lakes and TransCanada Pipelines 
Ltd., which is also Great Lakes' largest customer and the largest 
expansion shipper, FERC should have exercised heightened scruti-
ny over the effects of rolling in rates.  After relegating this 
argument to a single footnote in its briefs, Natural referred to it 
repeatedly at argument.  Natural's tactic smacks of sandbagging, 
and we need "not resolve issues raised so fecklessly."  Koger v. 
Reno, 98 F.3d 631, 634 (D.C. Cir. 1996);  cf. DiCola v. FDA, 77 F.3d 
504, 506 n.* (D.C. Cir. 1996) ("As the parties have argued the issue 
in the margins, so too do we dispose of it.").



all FERC ratemaking is "subject to the statutory 'fair and 
equitable' standard," ANR Pipeline Co. v. FERC, 71 F.3d 
897, 902 (D.C. Cir. 1995), fairness and equity do not require 
FERC to compute the actual costs and benefits accruing to 
each shipper before approving or modifying proposed rates.  
See TransCanada, 24 F.3d at 309.

     Natural argues that our decision in Algonquin Gas Trans-
mission Co. v. FERC, 948 F.2d 1305 (D.C. Cir. 1991), man-
dates that FERC compute quantitative costs and benefits in 
determining the equity of a rate scheme and that because 
FERC did not consider the actual costs and benefits associat-
ed with the expansion facilities, its decision was arbitrary and 
capricious.  The Algonquin opinion is composed of two parts.  
In the first section of the opinion, which addressed the 
proposed roll-in of facilities expansion costs, we held that 
when FERC imposes rates of its own design (rather than 
merely reviewing those submitted by the parties) under Sec-
tion 5 of the NGA, see 15 U.S.C. s 717d, it must "offer more 
than a conclusionary statement that the existence of system-
wide benefits renders it unjust to allocate facilities costs 
incrementally."  Id. at 1313.  We held that FERC must 
"show[ ] that the incremental facilities produce specific, sys-
tem-wide benefits...."  Id. at 1314.  FERC's remand orders 
in the present case reviewed the various benefits that would 
accrue to all users from Great Lakes' expansion, and FERC 
thereby satisfied this element of Algonquin.  See 75 FERC 
at 61,280-83.

     As both parties noted at oral argument, our decision in 
TransCanada seems in some tension with the second section 
of Algonquin.  In that portion of Algonquin, we addressed 
FERC's decision to permit the roll-in of increased gas costs 
caused by increased demand from new customers and the gas 
company's consequent use of higher-priced suppliers.  We 
held that where FERC rejects the parties' pricing scheme 
and instead mandates a pricing plan that causes existing 
customers to pay more for service that is unchanged from 
that which they received before the ratemaking, FERC must 
"explicitly consider the cost shifting that its order might 
effect."  Algonquin, 948 F.2d at 1315.  In TransCanada, we 
stated that:



     Algonquin undoubtedly does require a reasonably specif-
     ic qualitative description of the systemwide benefits of an 
     integrated facility.  But the Court was careful not to 
     require a balancing of costs and benefits (much less a 
     quantification thereof), and indeed confirmed that the 
     general test for rolling-in was the same that Great Lakes 
     discerns in Commission precedent [relying on Battle 
     Creek].

TransCanada, 24 F.3d at 309.  Our TransCanada holding 
therefore seems to accentuate the first Algonquin holding to 
the detriment of the second.  The two holdings, however, are 
reconcilable upon consideration of their underlying factual 
bases.

     In Algonquin, we held that FERC had to consider the cost-
shifting effect of its order because existing users in that case 
got no benefit in exchange for increased rates.  See Algon-
quin, 948 F.2d at 1314-15.  When FERC approves a rate 
application under the Battle Creek standard, it must have 
found that expansion provided existing users with qualitative 
benefits.  See TransCanada, 24 F.3d at 308 (pointing out the 
two Battle Creek prongs).  Thus, where no discernable differ-
ence existed between pre- and post-expansion service, FERC 
was obligated to consider the cost shifting implicit in its 
order, see Algonquin, 948 F.2d at 1315, but where benefits 
accrue to nonexpansion customers, there is no cost shifting--
rather, existing users merely are being charged for the 
quantum of the new facilities and its attendant benefits 
attributable to their demand.  The second part of Algonquin 
involved a roll-in of gas costs rather than facilities costs, and 
the result in Algonquin depends critically upon the unique 
nature of gas as a fungible commodity.  In most ratesettings, 
including the one currently before us, changes to an integrat-
ed system's facilities lead to qualitative improvements in 
service to all customers, and the Battle Creek test will apply.  
The cost-shifting portion of Algonquin therefore is consistent 
with the Battle Creek requirement that a transporter show 
qualitative benefits that accrue to existing users before 
rolling in expansion costs.  Compare id. with Battle Creek, 
281 F.2d at 47-48.



     As for Natural's claim that the statute requires a specific 
finding that rates are equitable, FERC addressed the ques-
tion when it noted that:

     Under the Battle Creek test, once facilities are found to 
     be integrated into the mainline system and to provide a 
     positive benefit to all customers, the costs of those facili-
     ties are considered to be part of the pipeline's cost of 
     serving all its customers.  That is because the demand of 
     all customers for system capacity creates the need for 
     system expansion.

75 FERC at 61,284 (emphasis added).  Because every shipper 
is economically marginal, the costs of increased demand may 
equitably be attributed to every user, regardless when it first 
contracted with the pipeline.  See 1 Alfred E. Kahn, The 
Economics of Regulation 140 (1970).  Thus, when an expan-
sion is both integrated and to the benefit of existing users, 
FERC is not bound to study the quantitative effect of rolling-
in construction costs.

     Natural next contends that FERC's application of the 
Battle Creek test was infected with bad faith (and is therefore 
arbitrary and capricious) because the remand orders' findings 
contradict FERC's pre-TransCanada findings on the same 
factual record.  FERC responds that whatever tension exists 
between its original findings and those it made on remand 
reflects only that the Battle Creek standard is less exacting 
than the commensurate benefits test.  Natural refers the 
court specifically to four of FERC's findings:  reliance, cross-
subsidization, efficiency, and capacity.  The first three find-
ings may be dealt with summarily because it is plain that any 
alleged contradictions are the direct consequence of FERC's 
readoption of the more lenient Battle Creek standard on 
remand.  For example, on the cross-subsidization findings, 
while Natural is correct that FERC initially found impermis-
sible cross-subsidization, the standard applied on remand 
required only that the expansion parties show some qualita-
tive improvement to satisfy the system-wide benefits element 
of the Battle Creek test.  On both a theoretical and practical 
basis, it is perfectly possible for both cross-subsidization and 



system-wide benefits to exist on the same facts.  Indeed, both 
can logically be said to occur any time that a system change 
benefits all customers but to differing degrees.  Thus, the 
first series of orders' finding of cross-subsidization is not 
inconsistent with the remand orders' finding that some quali-
tative system-wide benefits may accrue to all shippers.

     The fourth alleged contradiction, which concerned FERC's 
findings regarding system capacity, gives us greater pause--
indeed FERC's own counsel conceded at oral argument that 
"[m]aybe [FERC] misspoke a little on capacity."  In its 
original orders, FERC found that "it has not been shown that 
the additional capacity will inure to the benefit of existing 
customers by providing additional interruptible and overrun 
["I/O"] capacity."  57 FERC at 61,524.  In the remand 
orders, however, FERC made two capacity-related findings:  
(1) expansion "will accommodate greater variation in demands 
on the system," and (2) it will "increase the opportunity for 
overrun and interruptible service for all of Great Lakes' 
customers."  72 FERC at 61,428.  FERC's first finding on 
remand is not inconsistent with its original findings.  That 
additional I/O capacity does not exist does not necessarily 
imply that the system could not accommodate greater varia-
tion in demand (e.g., increased ability to moderate supply 
when undertaking maintenance).  See 75 FERC at 61,281.  
As for the second finding, FERC supports its conclusion with 
specific references to the testimony of one of Great Lakes' 
experts, Mr. Elkouri.  Mr. Elkouri testified that the expan-
sion facilities increase capacity for existing users.  And that 
is, of course, true--increased demand with no increase in 
capacity would decrease every shipper's capacity to use the 
pipeline at some point (no contract is perpetual), and to the 
extent that there is greater capacity, there is consistently 
more opportunity for its use by I/O shippers (regardless of 
projected load, intermittent capacity will inevitably arise).  
Whatever apparent contradictions are embedded in the rec-
ord are therefore the product of a change in the governing 
legal standard and of FERC's reexamination of the adminis-
trative record.  See Troy Corp. v. Browner, 120 F.3d 277, 283 
(D.C. Cir. 1997) ("we only determine whether the decision 



was arbitrary and capricious, or otherwise contrary to law.  
In so doing, we examine whether the decision was based on 
the relevant factors and was not 'a clear error of judgment.' " 
(quoting Citizens to Preserve Overton Park, Inc. v. Volpe, 401 
U.S. 402, 416 (1971))).3

                                     III.


     After it had applied the Battle Creek test and concluded 
that Great Lakes' proposal to roll in expansion costs was 
reasonable, FERC found that the expansion shippers should 
be refunded the difference between the amount they were 
charged when rates were incremental and that which they 
would have been charged if expansion costs had been rolled 
in.  FERC therefore required Great Lakes to reimburse the 
expansion shippers for their excess costs and permitted Great 
Lakes to charge nonexpansion shippers an offsetting sur-
charge.  FERC further held that interest accrued on refunds 
and surcharges only as of October 1, 1995, when rolled-in 
prices took effect.

                                      A.


     Natural contends that FERC improperly awarded the ex-
pansion shippers a retroactive remedy because of a mistaken 

__________
     3 In its reply brief, Natural appears to contest the sufficiency of 
the factual bases for FERC's findings regarding integration and the 
existence of system-wide benefits.  Natural claims that those find-
ings have been in dispute throughout this proceeding.  In support 
of its argument, Natural refers us to the administrative record.  We 
have consistently held that "[c]onsidering an argument advanced for 
the first time in a reply brief ... is not only unfair to an appellee 
but also entails the risk of an improvident or ill-advised opinion on 
the legal issues tendered."  McBride v. Merrell Dow & Pharmaceu-
ticals, Inc., 800 F.2d 1208, 1211 (D.C. Cir. 1986) (citations omitted).  
A party does not preserve factual issues on appeal by raising them 
in the administrative proceeding and then referring to them without 
elaboration in a reply brief.  Not only does the opposing party lose 
its opportunity to contest the merits of the factual challenge, but 
the court does not get the benefit of the adversarial process.  
Natural has forfeited any factual objections to FERC's orders.



belief that its original orders were infected with legal error.  
See, e.g., 72 FERC at 61,430.  According to Natural, because 
TransCanada did not mandate readoption of the Battle Creek 
test, the original FERC orders were not "erroneous," and on 
remand, FERC was free to choose any pricing scheme.  
Thus, contrary to FERC's orders, the expansion parties were 
not "entitled" to be "made whole," and FERC was not 
authorized to impose a retroactive remedy.

     Natural misapprehends the nature of FERC's original er-
ror.  Regardless of whether incremental rates could have 
been justified, they were not.  FERC's failure to explain 
itself was itself error, see TransCanada, 24 F.3d at 309-10, 
and the rates it imposed without adequate reasoning there-
fore were invalid.  Thus, although Natural is correct that 
incremental rates were not per se impermissible, their appli-
cation was erroneous in this case.  And because FERC may 
"undo what [was] wrongfully done by virtue of [a prior] 
order," United Gas Improvement Co. v. Callery Properties, 
Inc., 382 U.S. 223, 229 (1965), its decision to approve a 
retroactive remedy was within its discretion.  See Natural 
Gas Clearinghouse v. FERC, 965 F.2d 1066, 1073-74 (D.C. 
Cir. 1992) (noting presumption in favor of retroactive reme-
dies for erroneous FERC decisions).

                                      B.


     In its July 26, 1995, Order, FERC held that "refunds and 
surcharges shall not include interest."  72 FERC at 61,430.  
FERC permitted non-expansion parties to amortize their 
payments, but if they chose amortization, they were liable for 
interest "for the amortization period."  Id.  FERC declined 
to require interest for the entire period because it hoped to 
"ease the adverse effects of [its] legal error on non[expansion] 
shippers, while also ensuring that Great Lakes is kept whole."  
75 FERC at 61,294.  Great Lakes moved for clarification of 
whether interest accumulated on all balances from October 1, 
1995 (when rolled-in rates took effect) or whether it did not 
begin to accumulate until 90 days after Great Lakes' amended 
compliance filing, which occurred roughly ten months later.  



See 76 FERC at 61,937.  FERC held that it intended only to 
exclude the accrual of interest until October 1, 1995.  Interest 
accumulated every day after that, regardless of whether 
payment was ultimately lump-sum or amortized.  Id.  Peti-
tioners challenge both FERC's interest exemption and its 
imposition of interest on all payments made after October 1, 
1995.

     Midland Cogeneration Venture Limited Partnership 
("MCV"), one of the expansion shippers, asserts that FERC's 
decision to deny interest on the period prior to October 1, 
1995 was legal error and was an abuse of discretion.  15 
U.S.C. s 717c(e), provides that

     the Commission may, by order, require the natural-gas 
     company to furnish a bond, to be approved by the 
     Commission, to refund any amounts ordered by the 
     Commission, to keep accurate accounts in detail of all 
     amounts received by reason of such increase, specifying 
     by whom and in whose behalf such amounts were paid, 
     and, upon completion of the hearing and decision, to 
     order such natural-gas company to refund, with interest, 
     the portion of such increased rates or charges by its 
     decision found not justified.

MCV claims that FERC misread this statutory provision to 
permit it discretion in the award of interest.  See MCV br. at 
4.  MCV contends that while the award of remedial damages 
is discretionary, the imposition of interest is not.  Thus, as 
MCV reads the statute, the auxiliary verb "may" serves 
"order" but not "with interest," which itself modifies only 
"refund."  See 15 U.S.C. s 717c(e).  Second, MCV refers the 
court to FERC's own regulations, which state that:

     Any natural gas company that collects rates or charges 
     ... must refund that portion of any increased rates or 
     charges ... found by the Commission not to be justified 
     ... together with interest as required in paragraph (d) of 
     this section.

18 C.F.R. s 154.501(a)(1).  Paragraph (d) requires that inter-
est be computed from the date of collection to the date of 
refund.  Id. at s 154.501(d).  FERC argues that the statute 



gives it discretion whether to award interest and that case 
law supports its authority not to award interest.  See Estate 
of French v. FERC, 603 F.2d 1158, 1162-63 (5th Cir. 1979).

     There is no doubt that section 717c(e) is ambiguous--
indeed if read literally, the clause would permit FERC "by 
order[ ] [to] require the natural gas company ... to order 
such natural gas company to refund, with interest, the 
portion of such increased rates ... found not justified."  15 
U.S.C. s 717c(e) (emphasis added).  Because the statute is at 
best unclear (and at worst incomprehensible), obedient to 
Chevron U.S.A., Inc. v. NRDC, 467 U.S. 837, 843 (1984), we 
defer to the agency's reasonable interpretation, which in this 
case is embodied in 18 C.F.R. s 154.501.

     FERC, however, ignored its own regulation when inter-
preting the statute.  As we have previously held, "[t]he 
Commission may not ... rely solely on its equitable discre-
tion to justify straying from well-established rules and proce-
dures.  [It] must articulate valid reasons for its departure."  
FERC v. Triton Oil & Gas Corp., 750 F.2d 113, 116 (D.C. Cir. 
1984).  In the instant case, FERC decided to exclude interest 
payments because it sought to "ease the adverse effects on 
the pre-expansion shippers of [its] legal error, while also 
ensuring that Great Lakes is kept whole."  72 FERC at 
61,430.  In its disposition of the interest issue, FERC did not 
mention its regulation governing refunds and surcharges.  
Because FERC failed to give a "valid reason[ ] for ... 
depart[ing] [from the regulation]," Triton Oil, 750 F.2d at 
116, its decision to exempt the nonexpansion shippers from 
paying interest for the whole period was error.  Further-
more, because FERC has had ample opportunities to resolve 
this matter on its own but has neither heeded its own 
regulation nor explained its failure to do so, we reverse 
FERC's decision to exempt the refunds and surcharges from 
interest assessments and hold that interest shall be assessed 
on all surcharges for the entire period that incremental rates 
were in effect.  Because we decide this matter in favor of 
MCV, we need not consider Natural's petition challenging 
FERC's decision to require interest on all payments made 
after October 1, 1995.



                                     IV.


     In 1991 FERC held that Great Lakes' proposal to price I/O 
service at $0.275 per thousand cubic feet ("Mcf"), which 
reflected a 100 percent load factor rate (i.e., equivalent to the 
rate paid by shippers with firm contracts), was unreasonable 
because "the maximum [load factor] rate is always higher 
than needed to ration daily usage."  57 FERC at 61,548.  
FERC instead fixed the I/O rate at a 140 percent load factor 
or $0.16 per Mcf.  See id. at 61,547-49.  In the remand 
orders, FERC retroactively modified the I/O rate, applying 
the 140 percent load factor to the full rolled-in price and 
consequently imposed $0.10 per Mcf surcharge for I/O service 
prior to the rolling in of expansion costs.  The resulting price 
for I/O service, $0.26 per Mcf, was only $0.015 lower than the 
price rejected by FERC in 1991.4  In its remand orders, 
FERC held that when I/O shippers agreed to pay the "maxi-
mum rate" in their contracts and were aware of the pending 
Section 4 proceedings, their final rates were contingent on the 
outcome of the underlying rate proceedings.  See 75 FERC 
at 61,297.

     Northern States Power ("NSP") and other I/O shippers 
assert on appeal that FERC's decision was arbitrary and 
capricious because it conflicts with the earlier FERC finding 
that $0.275 was "too high at all times" and because the I/O 
shippers' contracts with Great Lakes do not permit retroac-
tive modification.  FERC never held that $0.275 per Mcf was 
per se excessive.  Rather, FERC decided in 1991 that a 100 
percent load factor rate was too high;  the consequent price 
per Mcf was incidental.  NSP confuses the rate that it pays 
(i.e., the price per Mcf) with the load factor according to 
which the price is computed.  In its remand orders, FERC 
imposed a surcharge on the basis of a load factor of 140 
percent, which is consistent with its 1991 decision.  See 76 
FERC at 61,934 ("Great Lakes' interruptible rate for all 
periods is volumetric, and the only issue is what that volumet-

__________
     4 Although Northern States Power claims that the $0.015 per Mcf 
difference is de minimis, we need not decide whether that 6 
percent difference in the price per Mcf is significant.



ric rate should be.").  As to whether the I/O shippers' con-
tracts with Great Lakes permitted retroactive changes in 
pricing, we defer to FERC's reasonable interpretation of 
contracts within its jurisdiction.  See Williams, 3 F.3d at 
1549.  FERC's decision that the I/O shippers' agreement to 
pay the "maximum rates plus all applicable surcharges," see 
76 FERC at 61,934, subjected them to retroactive surcharges 
is eminently reasonable.  See Clearinghouse, 965 F.2d at 
1075-76.

                                      V.


     Between 1991 and 1994, Great Lakes received three Sec-
tion 7 certificates to build facilities to serve Rochester Gas & 
Electric ("RG&E").  See Great Lakes Gas Transmission, 
L.P., 56 FERC p 61,052 (1991);  Great Lakes Gas Transmis-
sion, L.P., 56 FERC p 61,051 (1991); Great Lakes Gas Trans-
mission, L.P., 66 FERC p 61,115 (1992).  The third order is 
not at issue here.  Both certificates issued by FERC stated 
that RG&E would be liable for "the currently effective maxi-
mum applicable FT rate."  76 FERC at 61,929 (internal 
quotations omitted); see 56 FERC at 61,205; 56 FERC at 
61,210.  The second order also stated that "[t]he initial rate 
... shall be subject to the Commission's final determination 
in Docket Nos. RP89-186-000 and RP90-20-000."  56 FERC 
at 61,210.  Despite the different wording of the orders, they 
were consolidated into a single contract, which provided that 
RG&E would "pay ... the rates and charges in effect from 
time to time under Rate Schedule FT, or any effective 
superseding rate schedule...."  Rate Schedule FT was de-
fined elsewhere in the contract as the "FERC Gas Tariff ... 
as filed with the Commission and as changed and adjusted 
from time to time by [Great Lakes] in accordance ... with 
any final Commission order affecting such rates."  76 FERC 
at 61,931.

     In the remand orders, FERC held that because RG&E's 
rate was contingent on the current FT price, the pending 
proceedings applied retroactively to RG&E as if it were a 
pre-expansion shipper.  See 76 FERC at 61,928-29.  On 
appeal, RG&E makes a series of arguments whose underlying 
principle is the same:  the rate set in the underlying orders 



and contract was not contingent, and retroactive application 
of the rolled-in rate therefore is impermissible.  Resolution of 
that issue turns upon the meaning of the phrase "maximum 
FT rate" in RG&E's contract with Great Lakes and in 
FERC's certificate orders authorizing service.  "FERC's in-
terpretation of [a] contract[ ] [within its jurisdiction] is enti-
tled to deference under the principles articulated in Chevron 
...."  Williams, 3 F.3d at 1549.  Thus, the agency's inter-
pretation will be upheld "as long as [it] is reasonable."  
LILCO v. FERC, 20 F.3d 494, 497 (D.C. Cir. 1994).  The 
court similarly "sustain[s] the Commission's interpretation of 
[an][o]rder if it is reasonable."  Natural Gas Clearinghouse 
v. FERC, 108 F.3d 397, 399 (D.C. Cir. 1997).

     The two certificate orders were issued on the same day, 
and their incorporation into a single consolidated contract 
suggests that the parties saw no material difference between 
them.  Although only the second order includes a clause 
stating explicitly that the "authorized rate ... shall be sub-
ject to the Commission's final determination in [certain pend-
ing dockets]," 56 FERC at 61,210, FERC may reasonably 
have read the orders together and concluded that the more 
specific language of the second order clarified the ambiguity 
in the first order.

     RG&E argues that the clause in the second order noting 
the reservation of the right to modify rates refers only to the 
cost-of-service settlement rather than to the roll-in proceed-
ings.  FERC disposed of that argument in the remand orders 
by finding that "the settlement [to which RG&E claims that 
the provision refers] expressly reserved for litigation the 
pricing issue ultimately resolved in the remand order [in 
favor of rolled-in rates]."  Id. at 61,932.  FERC's reading of 
the clause's reservation is reasonable.  Where a rate is set by 
reference to a pending proceeding, the substance of that 
proceeding may reasonably be read into the order.  Cf. 
Clearinghouse, 965 F.2d at 1075 (holding that "there could be 
no violation of the filed rate doctrine so long as the users of 
Tarpon's service received adequate notice that the rate stated 
in Tarpon's 1987 filing might replace the Commission-ordered 
rate even for service originally provided under the latter").



                                     VI.


      In the initial order on remand, FERC mandated that 
Great Lakes refund expansion shippers the difference be-
tween what they had paid when rates were incremental and 
what they should have paid had expansion costs been rolled 
in.  See 72 FERC at 61,430.  FERC consequently permitted 
Great Lakes to collect an offsetting surcharge from nonex-
pansion shippers.  See id.  In a motion for rehearing, various 
nonexpansion shippers objected to the $15.7 million surplus 
(reflecting the difference between projected surcharges and 
refunds) that Great Lakes proposed to retain after distribu-
tion of all refunds.  See 75 FERC at 61,295.  FERC held that 
Great Lakes was entitled to retain whatever funds remained 
after all refunds were disbursed.  See id. at 61,296.  Based on 
revised estimates of the amount that Great Lakes would 
collect in surcharges, the projected surplus was later recom-
puted to be $17.5 million.  See 76 FERC at 61,935 n.29. 
RG&E and Consumers Energy Company ("Consumers") 
challenge Great Lakes' authority to retain the $17.5 million 
difference.  They contend that FERC acted arbitrarily and 
capriciously and ignored the terms of its own orders when it 
permitted Great Lakes to retain the surplus.

     FERC explains that "[v]irtually all of th[e] [surplus] was 
due to the addition of new customers after the cost-of-service 
rate design settlement was approved."  76 FERC at 61,935;  
see 75 FERC at 61,296.  FERC supports that finding by 
reference to Great Lakes' "May 10 revised refund/surcharge 
plan."  See id. at 61,935 n.29.  That finding is corroborated 
by RG&E's brief--RG&E, which was a "new customer," 
claims that it will be liable for an additional $8 million in 
surcharges.  See RG&E br. at 4.  Furthermore, Great Lakes' 
November 1, 1995 filing shows that an additional $3.7 million 
is attributable to additional service to ANR Pipeline.  This 
prong of Consumers' argument is therefore a restatement of 
RG&E's claim.  To the extent that RG&E and similarly 
situated petitioners agreed to rates that would incorporate 



the rate setting at issue in this appeal, they are apparently 
subject to the remand orders.  See Part V. supra.

     Consumers next contends that Algonquin Gas Transmis-
sion Co., 63 FERC p 61,326, 63,170 (1993), compels FERC to 
ensure that surcharges and refunds exactly match.  Any 
other outcome, according to Consumers, is inconsistent with 
Commission policy and unsupported by sound reasoning.  In 
its orders, FERC distinguished the situation in Algonquin 
from the one at issue here.  See 75 FERC at 61,296.  In 
Algonquin, FERC required exactly offsetting surcharges and 
refunds because "the pipeline ... failed to submit workpapers 
reflecting the ... rate design for the appropriate time frame, 
and ... generally [failed to] support[ ] its refund and sur-
charge calculations."  Id. (citing 63 FERC at 63,180).  Con-
sumers responds that Algonquin is indistinguishable from the 
instant case and that the reasons for which FERC required 
exactly offsetting charges in Algonquin apply with equal 
force here.

     FERC is correct that its Algonquin holding was premised 
upon Algonquin's inadequate explanation of its proposed sur-
charges and refunds.  See 63 FERC at 63,180 ("We ... find 
Algonquin's plan more counter-intuitive and less supportable 
(given the paucity of explanation that has been so far provid-
ed) ... than a more straightforward, common-sense approach 
that provides for an equal dollar amount of refunds and 
surcharges.").  By contrast, Great Lakes' plan and FERC's 
rationales for approving it explain in detail why Great Lakes 
should be permitted to retain the surplus.  See 75 FERC at 
61,296-97 (noting that the surplus is due in large part to the 
introduction of new services and that no party disputes Great 
Lakes' computations).  Because FERC's distinction is reason-
able, its decision to depart from Algonquin was not arbitrary 
or capricious.

     Consumers reads the term "offsetting discharges" as a 
narrow mandate for Great Lakes to assess surcharges and to 
distribute refunds only if they were exactly offsetting.  
FERC's initial order permitted Great Lakes to devise the 
means by which rates would be assessed in order to minimize 
harm to Great Lakes and to place all parties in as nearly as 



possible the position in which they would have been absent 
the original imposition of incremental rates.  See 75 FERC at 
61,295-97.  FERC's later explanation of that order should be 
upheld if it is reasonable.  See Natural Gas Clearinghouse, 
108 F.3d at 399; K N Energy, Inc. v. FERC, 968 F.2d 1295, 
1299 (D.C. Cir. 1992).  Because the word "offset" is not 
unambiguous and because FERC's policy rationales support 
the reasonableness of its reading of "offset," its interpretation 
of the phrase "offsetting discharge" is valid.

     Consumers' final contention is that permitting Great Lakes 
to retain the $17.5 million would allow it to exceed its 
permissible rate of return in violation of the NGA.  Because 
FERC approved all the rate orders that contained contingent 
pricing schemes, the assessment did not violate the NGA.  
Despite Consumers' contention that a new Section 4 rate 
proceeding was required to increase rates to account for new 
service, the roll-ins were not truly retroactive--"notice ... 
'changes what would be purely retroactive ratemaking into a 
functionally prospective process by placing the relevant audi-
ence on notice at the outset that the rates being promulgated 
are provisional only and subject to later revision.' "  Clearing-
house, 965 F.2d at 1075 (quoting Columbia Gas Transmis-
sion Corp. v. FERC, 895 F.2d 791, 797 (D.C. Cir. 1990)).  
Thus, as FERC points out, Consumers' disagreement with 
the legality of the retroactive application of the roll-in is 
really disapproval of the underlying rate, which, as we have 
already held, is permissible.

                                  Conclusion


     For the reasons stated above, we deny all the petitions 
except MCV's.  We grant MCV's petition and reverse 
FERC's decision not to award interest for the entire period to 
which surcharges and refunds apply.  The joint petitioners 
also have moved to strike Addendum A of MCV's brief.  Joint 
petitioners' motion is granted.  Addendum A is beyond the 
scope of the issue that MCV was entitled to brief, and its 
content is inconsistent with Circuit Rule 28(a)(3).

So ordered.