This action was brought by appellants against appellees for damages. Each of the appellees filed a separate demurrer to the complaint and each of these demurrers was sustained. Appellants abided the ruling on demurrers and appealed. The only question presented is the sufficiency of the complaint.
The complaint is in two paragraphs, both of which are very long. Each paragraph shows that appellee board of commissioners of Lake County, after taking the legal preliminary steps, .advertised for bids for the reconstruction of the jail of Lake County with additions, according to certain plans and specifications previously adopted. The board reserved the right to let the contract for the steelwork and steel cells in a separate contract, and this work was let to appellee Adams Steel and Wire Works, and the remainder of the contract was let to appellants, John W. Reed and Edwin W. Bremp, doing business as partners. The board of commissioners entered into a contract with appellee Adams Steel and Wire Works for the furnishing of material and
It is alleged that the custom and the law of the State required that a building of three or more stories, such as the Lake County jail should be constructed story by story, and that such custom and law were known to appellants and to each of appellees. It is also alleged in substance that appellants could not go forward with the work contemplated by their contract, except as appellee Adams Steel and Wire Works performed that portion of the steelwork necessary to the framework and construction of the building and that the progress of the work under. appellant’s contract depended upon the progress of the work under the contract between the board of commissioners and appellee, Adams Steel and Wire Works. It is shown that appellants entered upon the performance of the contract and carried the work forward with all possible speed until they reached a point where steelwork and structural steel beams became necessary to the further progress of the work, at which time they notified appellees of the necessity of furnishing such steelwork and repeatedly requested that it be furnished. The steelwork was not furnished, however, as stated in the complaint until six months after the time when it should have been supplied, and not until a period of inclement weather had set in, thus causing great damages to appellants. Each paragraph of the complaint states in what particulars appellants were damaged and the amount of the damages suffered by reason of the failure to furnish the structural steel, steelwork and steel cells, in proper time.
For the sake of brevity a mere skeleton or outline of the
1. It is apparent from appellants’ reply brief that they do not contend that the complaint states a cause of action sounding in tort. On the contrary they expressly state that each paragraph is based upon the principle that a builder may recover all damages occasioned him by a breach of contract on the part of the owners or employers. We are thus called upon to determine whether the contracts upon which the complaint is based, when considered in the light of the facts alleged in the complaint, imposed such an obligation upon either or both of appellees with respect to furnishing and constructing the steelwork and cells as to
It will be observed that the board of commissioners did not by the agreement with appellants undertake that the steelwork or steel cells should be completed by any particular time or that this part of the work should be so carried forward as not to interfere with the work under appellants’ contract. It is true that the board of commissioners by its contract with Adams Steel and Wire Works provided that the contractor should furnish all material, not governed by the schedule, at such time as should be for the best interest of all contractors concerned, to the end that the combined work of all might be completed on contract time, but this did not obligate the board of commissioners to see to it, that the Adams Steel and Wire Works did furnish the material and do the work in such time as not to delay the work under appellants’ contract, and to answer in damages to appellants in ease it failed in this respect. The provision of the contract by which the board of commissioners reserved the right to require the employment of an adequate force of men to complete the work on contract time, and the further provision by which the board was given the right to direct the application of this force to such parts of the work as to it seemed best, was not intended to impose any obligation upon the board in favor of appellants. It is apparent that the board of commissioners was desirous that the whole contract should be completed within the time provided by the contract and that these provisions were inserted to protect the interest of the county, and not for the purpose of affording a remedy to another contractor who might be damaged by delay.
The case of Louisville, etc., R. Co. v. Hollerbach (1886), 105 Ind. 137, 5 N. E. 28, is cited by appellants as tending
On behalf of appellants it is contended that the provisions heretofore quoted were inserted in the contract between the board of commissioners and the Adams Steel and Wire Works for the benefit of other contractors engaged in constructing other parts of the jail under contracts with the board, and that such provisions were intended to impose an obligation on the Adams Steel and Wire Works in favor of appellants for the breach of which it must answer in damages as to one of such contractors.
2. Under the common law of England none other than the parties to a contract could base an action thereon. The parties to a contract could not by its terms confer contractual rights upon a third person who was a stranger to the consideration, even though the contract was made for his special benefit. Tweddle v. Atkinson (1861), 1 Best & S. 393, 30 L. J. Q. B. 265; Gandy v. Gandy (1885), 30 Ch. Div. L. R. 57, 53 L. T. (N. S.) 306. Some of the states adhere to this ancient common-law rule, but the majority, including Indiana, recognize the right of a
It may appear that the performance of the terms and stipulations of a contract as between the parties to it would
1. Works should furnish all labor and material at such time as should be for the best interest of all contractors concerned, to the end that the combined work of all might be fully completed on contract time, was not intended to impose an obligation in favor of other contractors whereby the Adams Steel and Wire Works could be required to respond to them in damages for any loss occasioned by delay. On the contrary it is apparent that such provisions were intended for the benefit of the county in securing a prompt completion of the entire work.
The complaint does not state facts sufficient to constitute
Note. — Reported in 106 N. E. 882. As to contract promises for the benefit of third persons, see 3 Am. Dec. 305; 9 Am. Dec. 155; 71 Am. St. 178. See, also, under (1) 9 Cyc. 380; (2) 9 Cyc. 377, 380.