Restoration Preservation Masonry, Inc. v. Grove Europe Ltd.

          United States Court of Appeals
                        For the First Circuit


Nos. 01-1512
     01-1513
     01-1514
     01-1515

 RESTORATION PRESERVATION MASONRY, INC., in its own capacity and
           as subrogee of Dunlop Equipment Co., Inc.;
                   DUNLOP EQUIPMENT CO., INC.,

                       Plaintiffs, Appellees,

                                 v.

  GROVE EUROPE LTD.; GROVE WORLDWIDE CO., INC.; BRONTO SKYLIFT;
 BET, PLC & PTP, LTD; FEDERAL SIGNAL CORP.; FEDERAL SIGNAL CORP.
                         (FINLAND) OY AB,

                       Defendants, Appellants.


         ON APPEAL FROM THE UNITED STATES DISTRICT COURT
                FOR THE DISTRICT OF MASSACHUSETTS

               [Hon. Joseph Tauro, U.S. District Judge]


                               Before

                        Lynch, Circuit Judge,
                  Stahl, Senior Circuit Judge, and
                      Howard, Circuit Judge.


     John A. Sakakeeny, with whom were Stephen W. Sutton and Sutton
& Sakakeeny, LLP, on brief for appellee Restoration Preservation
Masonry, Inc.
     Edward L. Kirby, Jr., Lauren A. Boice, and Edward L. Kirby,
Jr. & Assoc., were on brief for appellee Dunlop Equipment Co., Inc.
     Barry Weiner, with whom were Christopher P. Litterio, and
Ruberto, Israel & Weiner, P.C., on brief for appellants Federal
Signal Corp. and Federal Signal Corp. (Finland) Oy Ab.
     David A. Hilton, with whom was Morrison, Mahoney & Miller, on
brief for appellants Bronto Skylift, Grove Europe, Ltd. and Grove
Worldwide Co., Inc.
     James P. Donohue, with whom was Sloan & Walsh, on brief for
appellants BET, PLC and PTP, Ltd.



                          April 1, 2003




                               2
           LYNCH, Circuit Judge.         In 1993, there was a tragic

construction accident caused by a collapsing mast climber --

mechanized scaffolding equipment with a mobile work platform that

can hydraulically ascend a mast -- leaving one man dead and another

with a life of pain and paralysis.               The families were paid

approximately    $8   million;    the    money   came   from   Restoration

Preservation Machinery, Inc. ("RPM") and Dunlop Equipment Co., Inc.

("Dunlop").     These two companies, the plaintiffs-appellees here,

then sought in two 1996 state court actions to recover the money on

theories   of   indemnification    or    contribution   from   five   other

companies, defendants-appellants here, in the complicated chain of

sale of the defective mast climber: Grove Europe, Ltd., Grove

Worldwide Co., Inc., Bronto Skylift ("Bronto"), BET, PLC, and PTP,

Ltd.   Two additional defendants were added in 2000: Federal Signal

Corp. ("Federal USA") and its subsidiary Federal Signal Corp.

(Finland) Oy Ab ("Federal Finland").       Asserting in 2000 that these

claims had to be arbitrated, the defendants removed the case to

federal court and sought to compel arbitration pursuant to the

Convention on the Recognition and Enforcement of Foreign Arbitral

Awards, 9 U.S.C. § 205 (2000).          The district court remanded and

then denied the motion to compel arbitration as moot.           We affirm.

                                    I.

           On September 2, 1993, Charles MacGlashing and another

brick mason, James Proctor, both employees of RPM, were working on


                                   -2-
a renovation project at the Longwood Towers complex in Brookline,

Massachusetts.      MacGlashing and Proctor were removing stone from

the parapet of one of the towers when the mast climber they were

using collapsed.        Both men fell eight stories to the ground.

Proctor died; MacGlashing survived, but suffered serious injuries

including    broken    bones,   internal    and    neurological     damage,   a

ruptured aorta and bladder, a perforated colon, and lung damage.

MacGlashing was hospitalized for six months after the accident, and

left partially paralyzed and in constant pain.

            MacGlashing and his wife filed suit against Dunlop in

federal court.      Dunlop filed a third-party complaint against RPM,

seeking indemnification pursuant to their lease agreement.                 The

court granted summary judgment to the MacGlashings and Dunlop on

Dunlop's third-party indemnification claim.                As a result of a

combined settlement with Dunlop and a verdict against RPM, the

MacGlashings collected approximately $5.7 million dollars from

Dunlop and RPM.       RPM appealed the summary judgment ruling, but it

was affirmed.      MacGlashing v. Dunlop Equip. Co., 89 F.3d 932, 941

(1st Cir. 1996).

            MacGlashing's ex-wife also filed suit against Dunlop, on

behalf of MacGlashing's minor children, in state court.             Proctor's

family filed suit against Dunlop in state court as well.              In both

of   the   state   court   actions,   Dunlop      also   entered   third-party

indemnification complaints against RPM.           In each, summary judgment


                                      -3-
was entered in Dunlop's favor on the indemnity claims against RPM.

In the MacGlashing state action, MacGlashing's children and Dunlop

received a judgment of $145,000 against RPM.   In the Proctor state

action, Dunlop and Proctor's heirs received a judgment of $2

million against RPM.   In total, RPM paid over $7 million dollars.

Dunlop paid approximately $1 million.      Dunlop and RPM now seek

indemnification or contribution from other companies in the chain

of sale of the defective mast climber.

          This chain dates back to 1993, when Bronto sold a number

of new aerial lifts to a joint venture comprised of BET and PTP.

As part of the purchase price, Bronto took in trade sixty used mast

climbers from BET and PTP.      At the same time, Grove Europe also

sold aerial lifts to BET and PTP, receiving in trade sixty-two used

mast climbers.    (The mast climbers were manufactured by still

another company, Access Engineering.) Grove Europe and Bronto then

sold the used mast climbers to Dunlop.     That sale took place on

August 2, 1993.   The bill of sale, which was signed by Bronto,

Grove Europe and Dunlop, contains an arbitration clause:

          The construction,     validity and performance of any
          contract shall be      governed by the laws of England
          (including English    conflict of laws) and all disputes
          which arise out of    or in connection with any contract
          shall be settled by   arbitration in England in accordance
          with provisions of     the Arbitration Acts for the time
          being in force.




                                 -4-
Dunlop took delivery of the mast climbers from BET and PTP depots.

It then leased four mast climbers to RPM on July 7, 1993.                   The

accident took place two months later.

            Following the judgments in suits brought by the families

of MacGlashing and Proctor, Dunlop and Restoration sought recovery

from Bronto, Grove Europe, Grove Worldwide, BET, and PTP.                 Grove

Worldwide is a U.S. company; its relation to Grove Europe, a

British company, is not specified in the record.             In August 1996,

Dunlop filed suit in Suffolk Superior Court against Bronto, Grove

Europe, BET, and PTP.       The following month, RPM filed a similar

suit in Middlesex Superior Court against Grove Europe, Grove

Worldwide, and Bronto, for indemnification and contribution, and

later   amended    the   complaint   to    include   negligence,       negligent

failure to warn, and breach of warranties. Grove Europe and Bronto

responded   by    filing   motions   to    dismiss   for   lack   of   personal

jurisdiction.     Grove Worldwide answered the complaint in June 1997

and asserted as one of its affirmative defenses that the parties

were bound to submit the matter to arbitration.              But it did not

move to compel arbitration.      RPM subsequently amended its claim to

add BET and PTP as defendants.             BET and PTP filed motions to

dismiss for lack of personal jurisdiction.           None of the motions to

dismiss were granted.      These two state court suits were ultimately

consolidated in July 2000.




                                     -5-
           The parties engaged in discovery from 1997 through 2000.

Five people were deposed, including two depositions in London. RPM

and Dunlop exchanged requests for production of documents and

interrogatories    with     defendants    other   than     Grove    Worldwide.

Experts   were    retained    to   conduct     failure     analyses       on   the

scaffolding equipment.       Thirteen status conferences were held in

the Middlesex Court litigation.          During the course of discovery,

plaintiffs learned that on August 4, 1995 Federal Finland had

purchased the assets and liabilities of Bronto.

           Federal USA, the sole shareholder of Federal Finland,

joined the asset purchase contract as a guarantor.                      Under the

contract, Federal Finland purchased all assets of Bronto, including

Bronto's proprietary information, records, trade rights, and causes

of   actions.     Federal    Finland   also    assumed    many     of    Bronto's

liabilities.      Product    liability    on   items     sold   prior     to   the

effective date of the transfer was excluded, except for claims

"arising under contract or warranty."1         The asset purchase contract

limited assignment of assumed contracts only where consent was

required and where the assignment itself constituted a breach of

the pre-existing contract.




      1
        Plaintiffs contend that this restriction does not include
the mast climbers at issue, because the asset sale contract
specifies products "manufactured, sold and delivered" prior to the
effective date. (emphasis added)     The mast climbers were not
manufactured by Bronto.

                                    -6-
           In December 1999, RPM amended its complaint to add

Federal USA, and in March 2000 further amended it to add Federal

Finland, as necessary defendants.          On June 12, 2000, Dunlop filed

an amended complaint adding Federal USA and Federal Finland as

defendants.   Federal USA responded to RPM's amended complaint by

filing a motion to dismiss in March 2000, asserting that Federal

Finland was the party that had purchased Bronto's assets.            Federal

USA then sought to withdraw its motion to dismiss in April 2000 so

that it could file for summary judgment.               In May 2000, both

Federals   filed   a   notice   of   removal   in   state   court   based   on

diversity jurisdiction. However, they never filed the notice of

removal in U.S. district court and shortly thereafter abandoned

this effort to remove the case. Meanwhile, neither of the Federals

conducted any discovery.

           A trial date of September 18, 2000 had been scheduled.

In June 2000, Federal USA moved to reset the tracking order to

allow for a motion for summary judgment.             At an August 2, 2000

status conference, all defendants filed a notice of removal to

federal court, citing their intention to exercise their arbitration

rights.    On August 14, 2000, the plaintiffs filed a motion to

remand the case to state court.             Two weeks later, before the

district court acted, the defendants filed a motion to compel

arbitration and to stay the district court proceedings.




                                     -7-
          On February 22, 2001, the district court allowed the

motion to remand to Middlesex Superior Court, citing this court's

decision in Menorah Insurance Co. v. INX Reinsurance Corp., 72 F.3d

218 (1st Cir. 1995), and denied the defendants' motion to compel

arbitration as moot.   No further reasons were given.      Defendants

appeal the district court's ruling, arguing that the jurisdictional

ruling was in error, and that there had been no waiver supporting

the district court's ruling against compelling arbitration.

                                  II.

          Plaintiffs argue that we lack jurisdiction to examine the

remand order because it was based on a determination of the

district court's lack of subject matter jurisdiction over the

removed case.    28 U.S.C. § 1447(d) mandates that "[a]n order

remanding a case to the State court from which it was removed is

not reviewable on appeal or otherwise . . . ."        Section 1447(d)

applies where the district court finds that it lacks subject matter

jurisdiction.   The district court's opinion here is notably terse;

we conclude from the citation to Menorah that the court reasoned

that subject matter jurisdiction was lacking because of a waiver of

the right to arbitrate by the defendants.    The parties agree that

is what the district court meant by the citation to Menorah.

          Plaintiffs   read   §   1447(d)   broadly   as   a   blanket

prohibition blocking any sort of appellate review of decisions

remanding arbitration cases that had been removed to federal court


                                  -8-
under 9 U.S.C. § 205 and subsequently remanded. See, e.g., Transit

Cas. Co. v. Certain Underwriters at Lloyd's of London, 119 F.3d

619, 625 (8th Cir. 1997) (remand order not reviewable on appeal).

But see Beiser v. Weyler, 284 F.3d 665, 672-74 (5th Cir. 2002)

(asserting     appellate      jurisdiction,            criticizing       conflation       of

jurisdictional and merits inquiries in remanding arbitration cases

"into a single step," and arguing that the consequences of such a

conflation     are    "both   irrational         and    inconsistent       with   .   .    .

precedents" because of the importance of international comity, the

goal   of   development       of   a   uniform     body       of   law   regarding    the

Convention,     the    international         business         community's     need    for

predictability, and the general federal policy of solicitude toward

arbitration).

             In Menorah, we confronted a similar argument but declined

to decide the jurisdictional issue, holding "Since [plaintiff]

easily wins an affirmance on the substantive issue of waiver, we

decline to decide the jurisdictional issues raised by it." 72 F.3d

at 223 n.9 (citing Norton v. Mathews, 427 U.S. 524, 528-33 (1976)

(where the merits can easily be resolved in favor of the party

challenging jurisdiction, resolution of complex jurisdictional

inquiry may be avoided)).          We follow a similar course here.               As the

plaintiffs concede, "jurisdiction does not have to be resolved for

this   Court   to     enter   a    final    ruling       on   the   merits    that    the

defendants have no right to arbitrate."


                                           -9-
           The decision in Steel Co. v. Citizens for a Better

Environment, 523 U.S. 83 (1998), does not require that we reach the

jurisdictional question.          In Steel Co., the Court attacked the

practice of so-called "hypothetical jurisdiction," id. at 94, and

concluded that "Article III jurisdiction is always an antecedent

question," id. at 101.       The Supreme Court itself has made it clear

that Steel    Co. does      not    establish   an    unyielding    sequence   of

decision-making regardless of circumstances.               See Ruhrgas AG v.

Marathon Oil Co., 526 U.S. 574, 578 (1999).             In Steel Co., Justice

Breyer, concurring, noted with approval that "[t]his Court has

previously made clear that courts may 'reserve difficult questions

of . . . jurisdiction when the case could alternatively be resolved

on the merits in the favor of the same party.'"                 523 U.S. at 111

(quoting Norton, 427 U.S. at 532).

           Steel Co. does not create an absolute rule against

bypassing questions of a jurisdictional nature.                 See Parella v.

Ret. Bd. of the R.I. Employees' Ret. Sys., 173 F.3d 46, 53-54 (1st

Cir. 1999).      Parella noted that while Article III jurisdictional

disputes   are    subject    to    Steel   Co.,     statutory    jurisdictional

disputes are not.      Id.        This rule is well established in this

circuit. See Davignon v. Clemmey, Nos. 01-1862, 02-1293, 02-1346,

2003 WL 721803, at *5 (1st Cir. Mar. 4, 2003) (holding that an

appellate court remains free to bypass problematic jurisdictional

issues provided those issues do not implicate Article III 'case' or


                                      -10-
'controversy' requirement); United States v. Woods, 210 F.3d 70, 74

n.2 (1st Cir. 1999) (following Parella and concluding that Steel

Co. is limited to Article III subject matter jurisdiction issues);

Kelly v. Marcantorio, 187 F.3d 192, 197 (1st Cir. 2000) (same,

emphasizing that courts should not reach constitutional issues in

advance of the necessity of deciding them); Cablevision of Boston,

Inc. v. Pub. Improvement Comm'n, 184 F.3d 88, 100 n.9 (1st Cir.

1999) (following Parella); see also Seale v. INS, No. 02-1431, slip

op. at 14 (1st Cir. Mar. 14, 2003) (identifying another exception

to Steel Co., consistent with Parella, where a court's prior case

law "foreordains" the outcome on the merits so as to deny recovery,

a Steel Co. inquiry into jurisdiction is not required).                Other

circuits similarly have held that Steel Co. applies only to Article

III constitutional limitations on jurisdiction. See Fama v. Comm'r

of Corr. Servs., 235 F.3d 804, 817 n.11 (2d Cir. 2000); Larsen v.

Senate of Pa., 152 F.3d 240, 245 (3d Cir. 1998); Kauthar SDN BHD v.

Sternberg, 149 F.3d 659, 663 n.4 (7th Cir. 1998); see also Ctr. for

Reprod. Law & Policy v. Bush, 304 F.3d 183, 195 (2d Cir. 2002)

(refraining from jurisdictional inquiry in case where outcome was

"foreordained" by circuit precedent and noting that "[w]here the

precise merits question has already been decided in another case by

the same court, it is the adjudication of the standing question

that resembles   an   advisory   opinion   --   the   very   concern    that

animates the Steel Co. rule").


                                 -11-
           Under Parella and its progeny, a jurisdictional inquiry

is not required here given that the question invokes statutory

jurisdiction.

                                       III.

           Review of a district court's determination of waiver of

arbitration is plenary.         Navieros Inter-Americanos, S.A. v. M/V

Vasilia Express, 120 F.3d 304, 316 (1st Cir. 1997).

           Analysis    of     the   question     of    whether      the   right   to

arbitration was waived takes place against a backdrop of strong

federal policy in favor of arbitration.               See Moses H. Cone Mem'l

Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24-25 (1983) ("[A]ny

doubts concerning the scope of arbitrable issues should be resolved

in favor of arbitration, whether the problem at hand is the

construction of the contract language itself or an allegation of

waiver, delay, or a like defense to arbitrability.").                 This policy

"applies     with   special    force     in    the    field   of    international

commerce."     Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth,

Inc., 473 U.S. 614, 631 (1985).                "[C]oncerns of international

comity, respect for the capacities of foreign and transnational

tribunals,    and   sensitivity     to   the    need    of    the   international

commercial system for predictability in the resolution of disputes

require that we enforce the parties' agreement, even assuming that

a contrary result would be forthcoming in a domestic context." Id.

at 629; see also Menorah, 72 F.3d at 220-21.


                                       -12-
            The policy in favor of arbitration does not supersede

basic contract principles, however.     "The FAA directs courts to

place arbitration agreements on equal footing with other contracts,

but it 'does not require parties to arbitrate when they have not

agreed to do so.'"    EEOC v. Waffle House, Inc., 534 U.S. 279, 293

(2002) (quoting Volt Info. Scis., Inc. v. Bd. of Trs. of Leland

Stanford Junior Univ., 489 U.S. 468, 478 (1989)).    "[A]rbitration

is simply a matter of contract between the parties; it is a way to

resolve those disputes -- but only those disputes -- that the

parties have agreed to submit to arbitration."     First Options of

Chicago, Inc. v. Kaplan, 514 U.S. 938, 943 (1995).

            Parties are free to waive their rights to arbitration by

contract.    Jones Motor Co. v. Teamsters Local Union No. 633, 671

F.2d 38, 42 (1st Cir. 1982) (Breyer, J.).      Waiver can either be

express or implied.     Id.   But "[w]aiver is not to be lightly

inferred, and mere delay in seeking arbitration without some

resultant prejudice to a party cannot carry the day."      Creative

Solutions Group, Inc. v. Pentzer Corp., 252 F.3d 28, 32 (1st Cir.

2001) (quotation omitted).      In considering whether an implied

waiver has taken place, federal courts traditionally consider an

array of factors:

            [W]hether the party has actually participated in the
            lawsuit or has taken other action inconsistent with his
            right, . . . whether the litigation machinery has been
            substantially invoked and the parties were well into
            preparation of a lawsuit by the time an intention to
            arbitrate was communicated by the defendant to the

                                -13-
              plaintiff, . . . whether there has been a long delay in
              seeking a stay or whether the enforcement of arbitration
              was brought up when the trial was near at hand . . . .
              Other relevant factors are whether the defendants have
              invoked the jurisdiction of the court by filing a
              counterclaim without asking for a stay of the
              proceedings, . . . whether important intervening steps
              (e.g., taking advantage of judicial discovery procedures
              not available in arbitration . . .) had taken place, . .
              . and whether the other party was affected, misled, or
              prejudiced by the delay . . . .

Jones Motor, 671 F.2d at 44 (quoting Reid Burton Constr., Inc. v.

Carpenters Dist. Council, 614 F.2d 698, 702 (10th Cir. 1980)).          In

Menorah, this court emphasized that "in order for plaintiffs to

prevail on their claim of waiver, they must show prejudice."            72

F.3d     at   221   (internal   quotation    omitted);   accord   Creative

Solutions, 252 F.3d at 32.

              A.     Waiver By Grove Europe, Grove Worldwide, Bronto,
                     PTP and BET

              Applying the Jones Motor factors to the parties that were

defendants before 2000 (Grove Europe, Grove Worldwide, Bronto, PTP,

and BET), the conduct of each constitutes an implied waiver.

              There are no per se rules as to the length of delay

necessary to amount to waiver, see Menorah, 72 F.3d at 222 (citing

case in which thirteen months' delay was found insufficient to

constitute waiver).         Here, the four years' delay from filing in

August 1996 to removal in August 2000, encompassing a period of

active    state     court   litigation,    greatly   exceeds   that   found

acceptable in this circuit. See Creative Solutions, 252 F.3d at 33

(delay of five months is not waiver); see also Navieros, 120 F.3d

                                    -14-
at   316   (one-month   delay      in   context       of   expedited   litigation

sufficient to find waiver); Menorah, 72 F.3d at 222 (delay of more

than fifteen months sufficient); Jones Motor, 671 F.2d at 42 (delay

of more than one year sufficient).

            The length of delay must be evaluated in the context of

litigation activities engaged in during that time.                     See, e.g.,

Creative Solutions, 252 F.3d at 33 (waiver not found when there was

no discovery or other activity aside from plaintiff's filing a

request for production); Jones Motor, 671 F.2d at 42 (waiver found

when party seeking arbitration engaged in deposition-taking, a pre-

trial conference, cross-motions for summary judgment, and oral

argument).     The defendants here were involved in at least five

depositions and thirteen pre-trial conferences.                  Prejudice to the

plaintiffs is easily inferred from the necessary expenditures over

that period of time.         See Menorah, 72 F.3d at 222 (no error in

finding that litigation expenses over the course of a more than

fifteen-month delay amounted to prejudice); see also Navieros, 120

F.3d at 316 (prejudice found as a result of expenses related to

litigation    that   would   not    have       been   incurred    in   arbitration

proceedings).

             Furthermore, the context of these defendants' belated

assertion of their right to arbitrate also points to waiver.

Removal to federal court to compel arbitration occurred in August

2000, less than two months before the scheduled trial date.                  Jones


                                        -15-
Motor directs attention to "whether the enforcement of arbitration

was brought up when the trial was near at hand."          671 F.2d at 44;

see Navieros, 120 F.3d at 316 (moving for arbitration the day

before trial considered as part of waiver analysis). Given a four-

year-long litigation, first raising arbitration less than two

months before trial unquestionably constitutes invoking it "when

the trial was near at hand."

              Grove Worldwide stands in a slightly different posture.

It asserted arbitration as an affirmative defense in its June 1997

answer   to    the   Middlesex     complaint.    Grove   Worldwide    never

participated in document discovery.         But it also never followed up

on its 1997 claim of arbitration and let the matter rest until

2000.    The length of its delay results in the same prejudice to

plaintiffs and so Grove Worldwide has also waived.

              B.     Waiver By Federal USA and Federal Finland

           Defendants Federal USA and Federal Finland argue that

they have not waived a right to arbitrate because the delay between

the time they were joined as defendants and the time they moved to

compel   arbitration    is   not   sufficient   to   establish   prejudice.

Federal USA was not served until January 2000 and Federal Finland

was not joined as defendant by RPM until March 2000.                 Dunlop,

meanwhile, did not join either of the Federals as defendants until

June 2000.      Subsequently, neither of the Federals participated in

discovery.


                                     -16-
            We assume arguendo, in the Federals' favor, that they, as

non-signatories to the contract containing the arbitration clause,

may assert a claim to arbitration based on their relationship with

Bronto.2    Still, Bronto clearly waived its right to enforce the

arbitration clause,3 and the Federals are bound by that waiver

because it occurred before the plaintiffs had notice of the asset

purchase.    See Restatement (Second) of Contracts § 336(2) (1981)

("The right of any assignee is subject to any defense or claim of

the obligor which accrues before the obligor receives notification

of the assignment, but not to defenses or claims which accrue

thereafter except as stated in this Section or as provided by


     2
        While it is generally true that "a contract cannot bind a
nonparty," Waffle House, 534 U.S. at 294, there are exceptions
allowing non-signatories to compel arbitration. A non-signatory
may be bound by or acquire rights under an arbitration agreement
under ordinary state-law principles of agency or contract. See 1
G.M. Wilner, Domke on Commercial Arbitration § 10:00, at 1-2 & 3
n.5 (rev. ed. 2002).    A number of circuits have allowed a non-
signatory to compel arbitration under a limited equitable estoppel
theory. See Grigson v. Creative Artists Agency, 210 F.3d 524, 527
(5th Cir. 2000); Sunkist Soft Drinks, Inc. v. Sunkist Growers,
Inc., 10 F.3d 753, 757 (11th Cir. 1993); Hughes Masonry Co. v.
Greater Clark County Sch. Bldg. Corp., 659 F.2d 836, 841 n.9 (7th
Cir. 1981); see also Med. Air Tech. Corp. v. Marwan Inv., Inc., 303
F.3d 11, 18-19 (1st Cir. 2002) (noting existence of equitable
estoppel).
     3
       Bronto did not raise arbitration as an affirmative defense;
instead it filed a motion to dismiss for lack of personal
jurisdiction in June 1998.     Bronto never raised its right to
arbitrate at any time before 2000. Moreover, Bronto participated
in discovery, moving in September 1997 for more time to respond,
and responding to RPM's request for document production in January
1998.    Through this delay, participation in litigation, and
resultant prejudice to plaintiffs, Bronto waived its right to
arbitrate before plaintiffs knew of the asset purchase.

                                 -17-
statute.") (emphasis added); cf. U.C.C. § 9-318(1)(b), 3A U.L.A.

460 (1992) (rights of an assignee are subject to "any other defense

or claim of the account debtor against the assignor which accrues

before       the    account    debtor     receives    notification     of     the

assignment"); In re Calore Express Co., 288 F.3d 22, 47 (1st Cir.

2002) (applying Massachusetts law and finding that timing of notice

of assignment under § 9-318(1)(b) governs outcome).4

               Nevertheless, the Federals argue that they are not bound

by Bronto's actions because those actions occurred after the August

1995       asset   purchase.    The     Federals   contend   their   rights   as

assignees are measured at the time of the assignment, and so

plaintiffs -- the obligors -- cannot raise a defense of waiver

based on Bronto's conduct.               But as said, basic contract law

principles do not limit obligors to only those defenses that arose

before the assignment.          Instead, the inquiry turns on when the



       4
        There is a lurking choice of law question. In diversity
cases, we apply the forum state's choice of law rules. See Auto
Europe, LLC v. Conn. Indem. Co., 321 F.3d 60, 64 (1st Cir. 2003).
We do not decide here whether Massachusetts would enforce the
contractual choice of law or its own law. The asset purchase
contract incorporates Finnish law. However, parties do not argue
that Finnish law governs the assignment, nor do they present
relevant Finnish law. Under Massachusetts law, "we need not take
judicial notice of the law of a foreign jurisdiction where, as
here, it is not brought to our attention by the record or the
briefs, and where, as here, counsel apparently tried the case on
the theory that the relevant [foreign] law was the same as our
own." Tsacoyeanes v. Canadian Pac. Ry. Co., 162 N.E. 23, 24 (Mass.
1959) (citations omitted). The parties have proceeded on state
contract law, as do we.


                                        -18-
obligor received notification of the assignment.          As a result, the

obligor can employ defenses that emerged subsequent to assignment:

          The assignee takes what the assignor had 'warts and all,'
          for an assignment does not deprive the obligor of any
          defenses or claims arising out of the agreement that the
          obligor could have asserted against the assignor absent
          assignment. The obligor may assert these defenses and
          claims against the assignee, regardless of whether the
          assignee knew of their existence at the time of
          assignment or whether they had even come into existence
          at that time.

3 E.A. Farnsworth, Farnsworth On Contracts § 11.8, at 106 (2d ed.

1998)(emphasis      added).   In   short,   the   Federals   are   bound   by

Bronto's actions prior to the plaintiffs' 1999 discovery of the

ownership change.

          For these reasons, the Federals do not have a right to

compel arbitration under the 1993 bill of sale.

                                    IV.

          The district court's rulings on the motion to remand and

denial   of   the    motion   to   compel   arbitration      are   affirmed.




                                   -19-