Legal Research AI

Seaboard Surety Co. v. Town of Greenfield Ex Rel. Greenfield Middle School Building Committee

Court: Court of Appeals for the First Circuit
Date filed: 2004-06-09
Citations: 370 F.3d 215
Copy Citations
44 Citing Cases

           United States Court of Appeals
                      For the First Circuit


No. 03-1453

                     SEABOARD SURETY COMPANY,

                       Plaintiff, Appellee,

                                v.

                        TOWN OF GREENFIELD,
                     acting by and through the
           GREENFIELD MIDDLE SCHOOL BUILDING COMMITTEE,

                       Defendant, Appellant.


           APPEAL FROM THE UNITED STATES DISTRICT COURT
                 FOR THE DISTRICT OF MASSACHUSETTS
           [Hon. Frank H. Freedman, U.S. District Judge]


                              Before

                     Torruella, Circuit Judge,
                       Lipez, Circuit Judge,
                     and Lisi,* District Judge.


     Wendy Sibbison, for appellant.
     Thomas H. Hayman, with whom Bert J. Capone and Cetrulo &
Capone LLP, were on brief, for appellee.



                            June 9, 2004




*
    Of the District of Rhode Island, sitting by designation.
          TORRUELLA, Circuit Judge.               Defendant-appellant Town of

Greenfield, acting by and through the Greenfield Middle School

Building Committee ("GMSBC")(hereinafter referred to collectively

as "Greenfield"), appeals the district court's grant of summary

judgment in favor of plaintiff-appellee Seaboard Surety Company

("Seaboard") discharging Seaboard from liability on a construction

performance bond.      After careful review, we affirm.

                                 I.     Background

          We     summarize       the    lengthy    narrative    of   the     failed

relationship     between    the       parties,    relating   only    those    facts

relevant to our review.          On June 18, 1998, Greenfield contracted

with Interstate Construction Company ("ICC") to renovate its Middle

School building.     ICC provided the performance bond required by

Massachusetts law, with Seaboard as surety. The bond is a standard

performance bond, Form A312, issued by the American Institute of

Architects in 1984.     It provides that the Contractor (ICC) and the

Surety (Seaboard), jointly and severally, bind themselves to the

Owner   (Greenfield)       for    the    performance    of     the   Construction

Contract, which the bond incorporates by reference.

           Paragraph 3 of the bond provides that the surety's

obligation under the bond arises after:

           3.1      The Owner has notified the Contractor
                    and the Surety . . . that the Owner is
                    considering declaring a Contractor
                    Default and has requested and attempted
                    to arrange a conference with the
                    Contractor and the Surety to be held

                                         -2-
                 not later than fifteen days after
                 receipt of such notice to discuss
                 methods of performing the Construction
                 Contract. If the Owner, the Contractor
                 and the Surety agree, the Contractor
                 shall be allowed a reasonable time to
                 perform the Construction Contract, but
                 such an agreement shall not waive the
                 Owner's right, if any, subsequently to
                 declare a Contractor Default; and

          3.2    The Owner has declared a Contractor
                 Default and formally terminated the
                 Contractor's right to complete the
                 contract.    Such Contractor Default
                 shall not be declared earlier than
                 twenty days after the Contractor and
                 the Surety have received notice as
                 provided in Subparagraph 3.1; and

          3.3    The Owner has agreed to pay the Balance
                 of the Contract Price to the Surety in
                 accordance with the terms of the
                 Construction    Contract   or    to   a
                 contractor selected to perform the
                 Construction Contract in accordance
                 with the terms of the contract with the
                 Owner.

Once the owner has complied with the provisions of Paragraph 3, and

the surety's obligations are triggered, Paragraph 4 provides that

the surety "shall promptly and at the Surety's expense" take one of

a list of specified "actions."    The action at issue in this case,

as described in subparagraph 4.2, is to "[u]ndertake to perform and

complete the Construction Contract itself, through its agents or

through independent contractors."

          Paragraph 5 provides that "[i]f the Surety does not

proceed as provided in Paragraph 4 with reasonable promptness, the

Surety shall be deemed to be in default on the Bond fifteen days

                                 -3-
after receipt of an additional written notice from the Owner to the

Surety demanding that the Surety perform its obligations under this

Bond, and the Owner shall be entitled to enforce any remedy

available to the Owner."

           In compliance with subparagraph 3.1, Greenfield notified

ICC and Seaboard on November 12, 1998, and again on March 23, 2000,

that it    was    considering    declaring    a    Contractor    Default.      On

August    24,    2000,   after   continuous       struggle    regarding     ICC's

tardiness, Greenfield sent ICC a notice of default and termination

and filed suit in state court.       That same day, Greenfield notified

Seaboard of ICC's termination and agreed to pay the balance of the

contract price to Seaboard or to a replacement contractor, as

required by Paragraphs 3.2 and 3.3 of the bond.

            On August 25, 2000, Seaboard responded, asserting its

need for a reasonable time to investigate, requesting documentation

of ICC's default, and reminding Greenfield of the owner's duty to

mitigate   the    surety's   damages.        Greenfield      hired    an   Interim

Construction       Management     Consultant,        Baybutt         Construction

Corporation ("Baybutt"), to evaluate and to advise the town on the

emergency work needed in the interim. Greenfield notified Seaboard

that moisture had caused the subflooring of the new floors to

buckle and the carpets to detach, and that the allocation of

responsibility      for this damage (between Greenfield and ICC) was

already before the state court.


                                     -4-
            On September 26, 2000, Greenfield sent Seaboard further

documentation regarding ICC's termination and "formally ask[ed] the

surety to undertake to perform and complete the construction

itself, or through its agents or independent contractors as set

forth in the surety contract, paragraph 4.2," with a response

requested from Seaboard by October 20, 2000, so that work might

begin by November 4, 2000.

            On October 11, 2000, representatives of Greenfield, ICC,

and Seaboard met.         Seaboard agreed to prepare a proposal by

October 18th addressing the emergency work.               After some delay,

Seaboard delivered a proposal to perform the emergency work -- not

including the floor remediation – stating that this was not an

offer to perform under the bond because ICC's termination remained

contested and Seaboard was still investigating its position with

respect to the completion of the project and the remediation of the

floors.

            On October 31, 2000, Greenfield and Seaboard signed an

Emergency    Work    Agreement   to    mitigate   both    parties'   damages.

Seaboard    agreed   to   perform     the   emergency    work,   beginning   on

November 6th and finishing by December 31st, for which Greenfield

would pay $207,000.       Seaboard hired a Construction Manager, Wayne

Sheridan, for the emergency work.

            On November 15, 2000, Greefield's attorney faxed three

letters to Seaboard's attorney.         The first conveyed the conclusion


                                      -5-
of Greenfield's interim consultant, Baybutt, that work would need

to be commenced by December 1st for the building to be ready for

school    the    next   fall.    Estimated    costs,     including   moisture

remediation, were $5.6 million -- $3.8 million more than the

remaining contract funds. The second letter informed Seaboard that

the    Building     Committee   had   approached   the    Town   Council    to

appropriate these funds "if Seaboard declines to complete" and

insisted again that work needed to commence by early December. The

third letter demanded that Seaboard "soon decide if it will honor

its obligations . . . under the performance bond and complete the

project."      This letter reiterated the necessity that work begin by

early December and asked Seaboard to commit by November 20th.

               On November 20, 2000, Seaboard responded that, while its

investigation of ICC's termination continued, Seaboard was "willing

to perform the remedial and contract work," and was "prepared to

take     all    necessary   action    to    expeditiously     arrive   at    a

comprehensive agreement with [Greenfield] so that the remedial and

contract work can be commenced as soon as possible."                 Seaboard

requested further documentation regarding the floor remediation

work.

               On November 21, 2000, Greenfield sent Seaboard further

documentation and, on November 22nd, objected to the Town being

required to pay for the entire cost of the floor remediation.

While the allocation of responsibility for the floors was still in


                                      -6-
dispute, Greenfield offered to split the costs, under reservation

of rights.     Greenfield also expressed concern about Seaboard's

management team and timely completion.          Greenfield was concerned

that Seaboard's project manager, Wayne Sheridan, was frequently

absent from the work site.       Greenfield sought the right to review

and to approve any new project management team.          Greenfield warned

Seaboard that if construction did not begin by December 1st,

Greenfield "will be compelled to proceed with its other completion

options."

            Eventually, Greenfield acceded, under reservation of

rights, to cover the costs of the floor remediation, and on

December 1st, Seaboard sent Greenfield a draft Takeover Agreement.

Greenfield proposed revisions and further negotiations ensued.              On

December 8th, Greenfield's attorney notified Seaboard that the

Building Committee would meet on December 11th to decide how to

proceed.    On December 11th, Seaboard faxed Greenfield a new draft

of   the    Takeover   Agreement     which    identified     Sheridan,     the

Construction Manager with whom Greenfield was dissatisfied, as the

proposed Project Manager.        At the Building Committee meeting that

night, the Committee decided to hire Baybutt to complete the

project.     The   next   day,   Greenfield   notified     Seaboard   of   the

decision to proceed without Seaboard's involvement.

            On December 22, 2000, Seaboard filed a complaint in the

district court seeking a declaratory judgment discharging it from


                                    -7-
obligation     under   the    performance    bond   on     the   grounds   that

Greenfield had materially breached the bond by hiring its own

contractor.     Seaboard claimed that it had elected to complete the

contract, as permitted under the bond, but that Greenfield had

refused to allow the takeover, and that Seaboard was thus denied

the opportunity to limit its financial exposure.             Greenfield filed

counterclaims, alleging Seaboard's breach of the bond.                     After

discovery, cross motions for summary judgment were filed.

             On March 7, 2003, the district court granted Seaboard's

motion   for    summary      judgment.       Rejecting     any    anticipatory

repudiation     defense      for      Greenfield    as     disallowed      under

Massachusetts law, the court held that "[b]ecause a clear and

direct default notice was not served pursuant to Paragraph 5, . . .

Greenfield was in material breach of the Bond when it ceased its

dealings with Seaboard and hired another company."               Seaboard Sur.

Co. v. Town of Greenfield, 266 F. Supp. 2d 189, 198 (D. Mass.

2003).

                                II.    Analysis

          Summary judgment is appropriate when the evidence before

the court shows "that there is no genuine issue as to any material

fact and that the moving party is entitled to a judgment as a

matter of law."        Fed. R. Civ. P. 56(c).            For the purposes of

summary judgment, "'genuine' means that 'the evidence is such that

a reasonable jury could return a verdict for the nonmoving party',


                                       -8-
and a 'material fact' is one which 'might affect the outcome of the

suit under the governing law.'"         Hayes v. Douglas Dynamics, Inc.,

8 F.3d 88, 90 (1st Cir. 1993)(quoting Anderson v. Liberty Lobby,

Inc., 477 U.S. 242, 248 (1986)).            We review de novo the district

court's grant of summary judgment, viewing the facts and making all

reasonable inferences in favor of Greenfield, the nonmoving party.

Rodríguez v. Smithkline Beecham, 224 F.3d 1, 5 (1st Cir. 2000).              We

may affirm on any ground supported by the record.                Id.

               The parties agree that Greenfield complied with the

notice requirements regarding ICC's default provided by Paragraph

3   of   the    performance   bond.     Seaboard    argues,      however,   that

Greenfield failed to provide notice of Seaboard's default before

terminating Seaboard's involvement, as required by Paragraph 5.

Greenfield contends that Seaboard had previously breached the

performance bond by failing to take prompt action following ICC's

default    as     required    by   Paragraph    4   and   that     Greenfield's

communications with Seaboard complied with Paragraph 5's notice

requirements.1



1
   Greenfield argues in the alternative that Paragraph 5 does not
make notice a condition precedent of surety default but instead
simply provides an optional vehicle through which the owner may
protect itself from any future claims of the surety. We find this
reading of Paragraph 5 contrary to the unambiguous language of the
bond, and, under Massachusetts law, "when the wording of a contract
is unambiguous, the terms will be enforced." Paterson-Leitch Co.,
Inc. v. Mass. Mun. Wholesale Elec. Co., 840 F.2d 985, 991 (1st Cir.
1988)(citing Edmonds v. United States, 642 F.2d 877, 881 (1st Cir.
1981)).

                                      -9-
          We find it unnecessary to address Seaboard's compliance

with Paragraph 4.   The district court examined the evidence on the

issue and denied Greenfield's motion for summary judgment because

"the Court cannot find as a matter of law that Seaboard committed

a material breach of the terms and conditions of the Bond by

failing to promptly select and undertake action under paragraph 4."

Seaboard Sur. Co., 266 F. Supp. 2d at 195.               The district court

opinion ultimately rests, however, on Greenfield's failure to

comply with    Paragraph   5.         The   district   court    concludes   that

Greenfield's Paragraph 4 claims against Seaboard "necessarily fail

. . . due to Greenfield's material breach of the Bond," and

describes Greenfield's breach thus:            "Because a clear and direct

default notice was not served pursuant to Paragraph 5, the Court

finds that Greenfield was in material breach of the Bond when it

ceased its dealings with Seaboard and hired another company to

complete the Project."     Id. at 198.        The district court therefore

concludes that "Greenfield's refusal to allow Seaboard to complete

the Project renders the Bond null and void and discharges Seaboard

from any and all liability under the Bond."             Id. (citing St. Paul

Fire & Marine Ins. Co. v. City of Green River, 93 F. Supp. 2d 1170

(D. Wyo. 2000), aff'd, 6 Fed. Appx. 828 (10th Cir. 2001)).

          We   agree   with     the    district   court's      conclusion   that

Greenfield's compliance with Paragraph 5 is dispositive of both

parties' claims. Even assuming that Seaboard failed to provide the


                                       -10-
prompt response to contractor default required by Paragraph 4, the

surety default provision of Paragraph 5 constitutes an important

contractual right of the surety.             Paragraph 5 provides the surety

fifteen days during which it may attempt to cure the alleged breach

prior to default and thus to minimize its economic exposure.

Failure to provide this notice constitutes a material breach of the

bond.   School Bd. of Escambia Cty. v. TIG Premier Ins. Co., 110 F.

Supp. 2d 1351, 1353 (N.D. Fla. 2000)("[F]ailure to adhere to a

performance bond notification requirement is a material breach,

resulting in the loss of an obligee's rights under the bond."); St.

Paul, 93 F. Supp. 2d at 1178 ("Courts have consistently held that

an obligee's action that deprives a surety of its ability to

protect itself pursuant to performance options granted under a

performance bond constitutes a material breach, which renders the

bond null and void."); cf. Dragon Constr., Inc. v. Parkway Bank &

Trust, 678 N.E.2d 55, 58 (Ill. App. Ct. 1997)(owner's "failure to

provide    adequate    notice   of    [contractor's]       termination   .   .   .

stripped    [surety]    of   its     right    to   limit   its   liability   and

constituted a material breach of contract which rendered the surety

bonds null and void.").

            Greenfield seeks refuge in the contention that under

Massachusetts law "compensated sureties . . . ought not to be

relieved from their obligations on merely technical grounds, not

affecting substantially the character of the undertaking which they


                                      -11-
assumed."     Bayer & Mingolla Constr. Co, Inc. v. Deschenes, 205

N.E.2d 208, 211 n.4 (Mass. 1965)(quoting Maryland Cas. Co. v.

Dunlap, 68 F.2d 289, 291 (1st Cir. 1933)).       While it is true that

"Massachusetts courts have held that lack of prompt notice to the

compensated surety of a contractor's default (as required by a

Performance Bond) does not discharge the surety if it is not

harmed," notice requirements "exist[] precisely to provide the

surety   an   opportunity   to     protect   itself   against   loss   by

participating in the selection of the successor contractor to

ensure that the lowest bidder is hired and damages mitigated."

Enterprise Capital, Inc. v. San-Gra Corp., 284 F. Supp. 2d 166, 177

(D. Mass. 2003)(citations omitted).          In the context of surety

default, the notice provision similarly provides an opportunity for

the surety to cure the breach and thus mitigate damages.          As the

court concluded in Enterprise Capital, "even if [Seaboard] must

show injury, loss, or prejudice, it meets this hurdle, given its

deprivation of mitigation opportunities."       Id.

            We must therefore determine whether the record creates a

triable issue of fact as to Greenfield's compliance with Paragraph

5 of the performance bond.       Paragraph 5 provides that:

            If the Surety does not proceed as provided in
            Paragraph 4 with reasonable promptness, the
            Surety will be deemed to be in default on this
            Bond fifteen days after receipt of an
            additional written notice from the Owner to
            the Surety demanding that the Surety perform
            its obligations under this Bond, and the Owner


                                   -12-
           shall be entitled to            enforce    any   remedy
           available to the Owner.

Greenfield contends that several letters it sent to Seaboard, and

particularly two letters dated November 15th, constituted "an

additional written notice . . . demanding that the surety perform

its obligations" in compliance with Paragraph 5 and that Seaboard

was thus properly deemed in default fifteen days thereafter and

prior to Greenfield's December 11th decision to hire Baybutt to

complete the project.

           We describe and quote these letters at some length, as

our decision rests on whether a reasonable jury could find them to

constitute the "additional written notice" required by Paragraph 5.

The   first,   dated   September    26,    2000,   responds   in     detail   to

Seaboard's requests for documentation regarding ICC's termination

and concludes thus:

                  Lastly, the Building Committee is
           formally asking the surety to undertake to
           perform and complete the construction contract
           itself, or through its agents or independent
           contractors as set forth in the surety
           contract, paragraph 4.2.    Please be further
           advised that owner believes that they will
           require a decision by the surety no later than
           October 20, 2000 so that work may begin in
           earnest to move forward on the project by
           November 4, 2000.

Two   additional   letters   were    sent     to     Seaboard's    counsel    on

November 15th.     The first informs Seaboard that Greenfield Middle

School Building Committee ("GMSBC") has presented a proposal to

obtain additional funding in case Seaboard declines to complete.

                                    -13-
It then discusses a report prepared by Baybutt indicating that work

must commence by early December in order for the school to be ready

for the 2001 school year.       The pertinent paragraphs read:

                 The   GMSBC    believes   Seaboard  has
          substantial financial exposure to the Town.
          It would appear that one way for Seaboard to
          minimize that financial exposure would be to
          assume performance and complete the contract.
          The alternative to completion by Seaboard is
          completion by the GMSBC through a totally
          different construction team, possibly after
          receipt of competitive bids.      If the GMSBC
          must   obtain    competitive   proposals,  the
          completion costs could rise even higher than
          Baybutt's estimate.
                 The    Greenfield    Town   Council  is
          scheduled to vote on the GMSCB's $4.35 million
          request for additional funding on November 21,
          2000.    The GMSBC has asked that Seaboard
          provide me with a statement of Seaboard's
          intentions by Monday, November 20, 2000.

The second letter of November 15th begins thus: "Seaboard Surety

Co. must soon decide if it will honor its obligations to the

Greenfield    Middle   School   Building   Committee   .    .   .   under   the

performance bond and complete the project."                It explains the

GMSBC's insistence that Seaboard respond promptly:

                    The GMSBC must now decide how it will
             complete the project. It is still the GMSBC's
             preference   to   have    Seaboard   complete.
             Seaboard has been aware of the problems with
             ICC for several years and Seaboard has had two
             and one half months since ICC's termination to
             assess   and   determine   its   position   on
             completion. The time for Seaboard to make a
             decision is here.
                    The GMSBC is concerned by Seaboard's
             indecision regarding completion of the Project
             and is concerned that Seaboard may be giving
             too much credit to ICC's explanations and

                                   -14-
         excuses as to what went wrong on the project.
         The GMSBC asks that Seaboard undertake an
         objective review of the facts that culminated
         in the GMSBC's decision to terminate ICC,
         before it decides if it will honor its
         performance bond.

The letter then presents a detailed explanation of Greenfield's

decision to terminate ICC.   It concludes thus:

                 The critical issue, at this time, is to
          determine how the project will be completed.
          The GMSBC believes it is in the best interests
          of the Town and Seaboard to work together to
          complete the Project since a mutual effort
          will be required to get the school opened as
          quickly as possible. If there are differences
          in our positions that cannot immediately be
          resolved, the GMSBC will entertain the
          adoption of solutions that will allow the
          parties to "agree to disagree" over those
          differences,    as    long    as    construction
          progresses. If Seaboard assumes completion of
          the Project and adheres to a reasonable
          construction schedule, the GMSBC's consultants
          believe that the Project can still be
          completed before the September 2001 school
          opening. If, however, the GMSBC is compelled
          to develop new bid packages and receive
          competitive   proposals    to    complete,   the
          increases in project cost and the delay in
          completion could be even more severe than the
          GMSBC's current projections.
                 Should Seaboard decide to honor its
          performance bond, there will be a substantial
          amount of work that will need to be completed
          in a timely manner.     Seaboard will need an
          experienced project management team on site to
          carefully direct the work.
                 Please ask Seaboard to give this matter
          its immediate and careful consideration. The
          GMSBC has asked that Seaboard provide it with
          an   indication    of    its     intentions   by
          November 20, 2000, since an important vote in
          the   Town   government    on    financing   the
          completion of the work, has been scheduled for
          November 21, 2000.

                               -15-
The final letter is dated November 22, 2000, and begins thus:

                 The [GMSBC] is somewhat encouraged by
          your   November   20,    2000    correspondence
          indicating [Seaboard's] position on completing
          the Project.    The GMSBC wants Seaboard to
          complete the Project and is anxious to get the
          work underway.      However, the GMSBC has
          concerns with Seaboard's position that the
          GMSBC must pay for all the costs to remedy the
          floor damage . . . In addition to resolving
          the question of who between Seaboard and the
          GMSBC   pays  what   portion   of    the   floor
          remediation work, the GMSBC has a number of
          additional     concerns     that     must     be
          satisfactorily   addressed    in   a    takeover
          agreement.

The letter proceeds to describe the GMSBC's position on the floor

remediation costs and proposes that Seaboard and the GMSBC split

the costs, reserving their rights against one another and against

ICC, until the allocation of responsibility is determined in court.

The letter then lists and discusses seven "other key issues that

must be satisfactorily addressed in any takeover agreement."    It

concludes thus:

                 Please contact me at your earliest
          opportunity, to discuss Seaboard's position
          regarding the above issues. The GMSBC would
          like to be able to reach a general agreement
          on the issues to be covered in the takeover
          agreement   by   the  end   of   the   day  on
          November 27, 2000, with a written takeover
          agreement to follow a few days thereafter.
          Should we be able to successfully negotiate a
          takeover       agreement,       construction
          representatives of all parties should be
          prepared to meet on short notice at the site .
          . . .
                 Time is truly of the essence in
          negotiating    a   takeover    agreement   and
          commencing the completion of the work.     The

                               -16-
             GMSBC has targeted December 1, 2000 as the
             date by which work on the completion of the
             contract should commence.      The GMBSC is
             prepared to do what is necessary to meet that
             date.   If the takeover agreement cannot be
             reached, the GMSBC will be compelled to
             proceed with its other completion options.

             The district court found that none of the letters, taken

together or separately, constituted the additional written notice

required by Paragraph 5 of the bond, because the letters do not

demand performance in a manner sufficient to alert Seaboard to a

presumed default,     nor   do   they   indicate   that   Seaboard   was   in

material breach for failing to choose or to undertake performance

with reasonable promptness, nor do they reference the Paragraph 5

default provisions or warn that Seaboard will be deemed in default

in fifteen days.     Seaboard Sur. Co., 266 F. Supp. 2d at 197.            We

agree.

            In the context of contractor default, courts have found

that "[a] declaration of default sufficient to invoke the surety's

obligations . . . must be made in clear, direct, and unequivocal

language."     L & A Contracting Co. v. S. Concrete Serv., Inc., 17

F.3d 106, 111 (5th Cir. 1994)(finding insufficient notice of

default when owner's letters never mentioned the word "default");

Elm Haven Constr. Ltd. P'ship v. Neri Constr., LLC, 281 F. Supp. 2d

406   (D.   Conn.   2003)   (insufficient    notice   when   letters   only

complained about performance and financial status); Balfour Beatty

Constr., Inc. v. Colonial Ornamental Iron Works, Inc., 986 F. Supp.


                                   -17-
82, 86 (D. Conn. 1997) (insufficient notice when letters only

mention delay in performance).        The district court applied this

standard in the related context of surety default before us and

concluded that Greenfield's letters failed to provide "a clear and

direct default notice" to Seaboard.         Seaboard Sur. Co., 266 F.

Supp. 2d at 198.

            While the standard for sufficiency of notice applied by

the   district   court   comports   with   the   general    standard   that

"[n]otice must be clear, definite, explicit, and unambiguous,"           58

Am. Jur. 2d Notice § 2, there is no dispute that the performance

bond at issue here is governed by Massachusetts law.             Although

neither party before us nor the decision below suggests that

Massachusetts law provides a relevant standard for sufficiency of

notice meaningfully distinct from that applied by the district

court, we must address the issue.          In introducing the "clear,

direct and unequivocal" standard, the district court states, citing

Comm'r of Corps. & Taxation v. Springfield, 321 Mass. 31, 35

(1947), that     "[l]ikewise,   contractually    required    notices   must

always be clear and unambiguous in order to fulfill their intended

purpose."    Seaboard Sur. Co., 266 F. Supp. 2d at 196.         Comm'r of

Corps., however, states the requirement under Massachusetts law

that "[n]otices required by law or by contract to be given by one

party to the other in order to establish rights or obligations must

state with reasonable certainty the essential facts required by law


                                    -18-
or by contract."      Comm'r of Corps., 321 Mass. at 35.       This

principle has been applied to suggest that the "form [of notice] is

not important but it must convey with reasonable certainty the

information reasonably needed to serve the statutory purpose."

Carey v. Planning Bd. of Revere, 335 Mass. 746, 748 (1957).      In

both Carey and Comm'r of Corps., the notice in question was found

to be insufficient because it failed to supply the information

necessary to serve the purpose of the statutory notice provision at

issue.   Carey, 335 Mass. at 747; Comm'r of Corps., 321 Mass. at 35.

           As discussed earlier, the purpose of the notice provision

in Paragraph 5 of the performance bond is to provide the surety

with a fifteen-day period during which it might attempt to cure the

alleged breach prior to default.       As Greenfield's letters to

Seaboard did not alert Seaboard to a presumed default, nor indicate

that Seaboard was in material breach, nor refer to Paragraph 5, nor

warn that Seaboard would be deemed in default in fifteen days, no

reasonable jury could find that Greenfield's letters "convey[ed]

with reasonable certainty the information reasonably needed" to

serve the purpose of Paragraph 5's notice requirement.   Carey, 335

Mass. at 748.   Therefore, as Greenfield's letters to Seaboard fail

to create a triable issue of fact under this threshold standard for

sufficiency of notice under Massachusetts law, we need not explore

the question further. Paragraph 5 of the performance bond provided

Seaboard with a fifteen-day period during which it might attempt to


                                -19-
cure the alleged breach.          No reasonable jury could find that

Greenfield's letters put Seaboard on notice that this fifteen-day

period had commenced.2

                           III.    Conclusion

          Greenfield     failed   to   provide   an   "additional   written

notice" that could reasonably be found to put Seaboard on notice

that the fifteen-day period had begun after which Seaboard would be

deemed in default under Paragraph 5.             This material breach by

Greenfield discharges Seaboard from liability under the bond as a


2
  The negotiations and exchanges of proposed and revised takeover
agreements that ensued and continued until the day of the Building
Committee's vote also belie Greenfield's claim that the letters
served as notice of default.        Whether or not Seaboard was
inappropriately demanding concessions in the negotiations, as
Greenfield alleges, the record shows that neither Seaboard nor
Greenfield framed the proceedings in the context of impending
default.   Greenfield argues that its efforts to work toward a
compromise after December 1st should not be held against it,
contending that Greenfield's efforts "to obtain even dilatory
performance" did not excuse Seaboard from its contractual duty to
act promptly.   Bayer & Mingolla Const. Co., 205 N.E.2d at 212.
Similarly,   however,   Greenfield's   continued  efforts   toward
compromise do not excuse Greenfield from its obligation to provide
an additional written notice of default to Seaboard as required by
Paragraph 5.

     Greenfield also argues that Seaboard's complaint conceded that
the November 15th letter complied with Paragraph 5. The complaint
states that "[o]n or about November 15, 2000, Greenfield (through
its attorneys) called upon Seaboard to undertake completion of the
Project, and called for a response by November 20, 2000. Seaboard
duly responded on November 20, 2000, stating that Seaboard was
willing to undertake the work in question." No reasonable jury
could find that Seaboard's characterization of Greenfield's
November 15th letter as "call[ing] upon Seaboard to undertake
completion" conceded that the letter provided notice to the surety
that the fifteen-day period before it would be deemed in default
under Paragraph 5 had begun.

                                   -20-
matter of law.   The district court's grant of summary judgment is

therefore affirmed.

          Affirmed.




                   "Dissenting opinion follows"




                               -21-
           LIPEZ, Circuit Judge (Dissenting).       Paragraph 5 of the

surety bond provides in relevant part:

           If the Surety does not proceed as provided in
           Paragraph 4 with reasonable promptness, the
           Surety shall be deemed to be in default on
           this Bond fifteen days after receipt of an
           additional written notice from the Owner to
           the Surety demanding that the Surety perform
           its obligations under this Bond, and the Owner
           shall be entitled to enforce any remedy
           available to the Owner.

On August 24, 2000, Greenfield notified Seaboard of ICC's default

and termination, and agreed to pay the balance of the contract

price to Seaboard or to a replacement contractor pursuant to

Paragraphs 3.2 and 3.3 of the bond.       Thus, after August 24, 2000,

Seaboard was required to "proceed as provided in Paragraph 4 with

reasonable promptness."    If it did not, Greenfield was entitled to

deliver    the   "additional   written   notice"   under   Paragraph   5,

beginning the 15 day period before Seaboard would be deemed in

default.

            As the majority recognizes, Massachusetts law governs the

provisions of the surety bond.           In Massachusetts, "[n]otices

required by law or by contract to be given by one party to the

other in order to establish rights or obligations must state with

reasonable certainty the essential facts required by law or by

contract, as the case may be."       Comm'n of Corps. & Taxation v.

Springfield, 321 Mass. 31, 35 (1947).       See also Carey v. Planning

Bd. of Revere, 335 Mass. 746, 748 (1957) ("[The] form [of the


                                  -22-
notice]   is   not   important   but   it   must   convey   with   reasonable

certainty the information reasonably needed to serve the statutory

purpose.").    In this case, the essential information required by

Paragraph 5 was a "demand[] that the Surety perform its obligations

under [the] Bond."       Thus, our task is to determine whether a

reasonable jury could find that Greenfield's communications to

Seaboard constituted an "additional written notice" that, with

reasonable certainty, "demand[ed] that the Surety perform its

obligations under [the] Bond."

           In my view, there are several communications between

Greenfield and Seaboard that a reasonable jury might find meet this

requirement.     As early as September 26, 2000, Greenfield had

formally asked Seaboard to perform its obligations under the bond

and had laid out a timetable for Seaboard's decision:

           Lastly, [Greenfield] is formally asking the
           surety to undertake to perform and complete
           the construction contract itself, or through
           its agents or independent contractors as set
           forth in the surety contract, paragraph 4.2.
           Please be further advised that [Greenfield]
           believes that they will require a decision by
           the surety no later than October 20, 2000 so
           that work may begin in earnest to move forward
           on the project by November 4, 2000.

A November 15, 2000, letter again called on Seaboard to decide

whether it would complete the project:

           [Greenfield] must now decide if it will
           complete   the   project.    It  is   still
           [Greenfield's] preference to have Seaboard
           complete.   Seaboard has been aware of the
           problems with ICC for several years and

                                   -23-
            Seaboard has had two and one half months since
            ICC's termination to assess and determine its
            position on completion. The time for Seaboard
            to make a decision is here.

The November 15th letter concluded by asking that "Seaboard provide

[Greenfield] with an indication of its intentions by November 20,

2000," setting yet another deadline for Seaboard's decision.

            Finally, a November 22, 2000, letter set a third deadline

and clearly indicated that Greenfield was prepared to pursue

completion by another contractor if Seaboard did not perform its

obligations under the bond:

            Time is truly of the essence in negotiating a
            takeover   agreement   and    commencing   the
            completion of the work.      [Greenfield] has
            targeted December 1, 2000 as the date by which
            work on the completion of the contract should
            commence. [Greenfield] is prepared to do what
            is necessary to meet that date.        If the
            takeover   agreement    cannot   be   reached,
            [Greenfield] will be compelled to proceed with
            its other completion options.

Each   of   these   letters   asked    Seaboard   to   either   perform   its

obligations under the bond or allow Greenfield to pursue other

options.     In my view, a reasonable jury could find that these

letters constituted an "additional written notice" that, with

reasonable certainty, "demand[ed] that the Surety perform its

obligations under the Bond."

            The majority reasons that "[a]s Greenfield's letters to

Seaboard did not alert Seaboard to a presumed default, nor indicate

that Seaboard was in material breach, nor refer to Paragraph 5, nor


                                      -24-
warn that Seaboard would be deemed in default in fifteen days, no

reasonable jury could find that Greenfield's letters 'convey[ed]

with reasonable certainty the information reasonably needed' to

serve the purpose of Paragraph 5's notice requirement."           Paragraph

5, however, does not require that Greenfield's notice contain any

of these provisions.       It merely requires a "demand[] that the

Surety perform its obligations under the Bond." If the parties had

wished to require a more comprehensive notice -- including explicit

reference to Paragraph 5 and a recitation of the consequences of

Greenfield's notice -- they could have altered Paragraph 5's

requirements.    They did not do so, and it is not our province to

read more stringent requirements into that provision.

           Moreover, Greenfield was not required by principles of

contract   law   to   educate   Seaboard   as   to   the    consequences   of

Greenfield's demand that Seaboard perform its obligations under the

bond. "[U]nder Massachusetts law, 'one who signs a writing that is

designed to serve as a legal document . . .           is presumed to know

its contents.'"       Salois v. Dime Sav. Bank, 128 F.3d 20, 26 n.10

(1st Cir. 1997) (quoting Hull v. Attleboro Sav. Bank, 33 Mass. App.

Ct. 18, 24 (1992)). Thus, we must presume that Seaboard understood

Paragraph 5's requirements, including that it would be deemed in

default 15 days after receiving additional written notice demanding

that it perform its obligations under the bond.            It was Seaboard's

responsibility to protect its rights by acting within its 15 day


                                   -25-
window of opportunity.         Greenfield's only duty was to provide the

notice required by Paragraph 5 in compliance with the Massachusetts

"reasonable certainty" standard, regardless of whether Seaboard

recognized      that   the   notice   formally    triggered      the    terms   of

Paragraph 5.        See, e.g., Univ. Emergency Med. Found. v. Rapier

Inves., Ltd., 197 F.3d 18, 21 (1st Cir. 1999) (holding that the

parties   to    a   contract    may   specify    the   manner    of    sufficient

termination notice in the terms of the contract); Westmoreland v.

Gen. Acc. Fire & Life Assur. Corp., 144 Conn. 265, 270 (1957) ("It

is always competent for parties to contract as to how notice shall

be given, unless their contract is in conflict with law or public

policy.     When they do so contract, the giving of a notice by the

method contracted for is sufficient whether it results in actual

notice or not.") (collecting cases).

            Greenfield and Seaboard have been engaged in a long and

bitter dispute over their respective obligations under the surety

contract.      The financial stakes are considerable for both parties.

We should not resolve this case with a legal ruling that rewrites

the content of the notice required by Paragraph 5 of the bond.

Rather,   whether      Greenfield's    multiple    letters      constituted     an

adequate "demand[] that the Surety perform its obligations under

[the] Bond" is a quintessential jury question.             I would therefore

vacate the entry of summary judgment and remand to the district




                                      -26-
court so that this issue could be resolved by the appropriate fact

finder.

          I respectfully dissent.




                              -27-