The State appeals from a judgment of the Court of Claims for the balance found due under a contract for the removal and reinterment of human remains from a cemetery within the right of way of a projected highway.
The basic issue is whether the contract requires the payment of a unit price of $44.98 for the “ complete transfer of each body”, regardless of number, in accordance with claimant’s proposal-—-on which basis the trial court found the amount earned under the contract to be $125,198; or whether claimant is entitled to no more than the gross sum of $6,000 provided by the contract proper. If the unit price basis is the correct one, the parties’ dispute as to the number of units removed which actually constituted ‘ ‘ human remains ’ ’, within the meaning of the contract, must be determined.
In awarding contracts under the Highway Law, the lowest bid is to be “ determined by the superintendent on the basis of the gross sum for which the- entire work will be performed, arrived at by a correct computation of all the items specified in the estimate therefor at the unit prices contained in the bid.” (Highway Law, § 38, subd. 3.) In the preparation of the contract in this case there could be no actual “ computation ” because the number of “ items ” to which the unit price would apply was not known and no number was specified; no estimates were disclosed, if any were made; and apparently the parties never attempted to reach a common ground of understanding, upon consideration of the quantitative factor. Thus, claimant testified that he estimated the number of graves at 4,000 (but did not so advise the State), but whether or not the $6,000 price set forth in the contract reflects any estimate by the State, it would, after deduction of plot and monument costs fixed at
Against this background, we examine the contract documents. The notice to contractors that bids would be received stated nothing as to the number of units and while it announced that each proposal should “state the correct gross sum” it also required that the proposal be made upon the blank form provided therefor, upon which the blank spaces must be filled in and no change or any alteration or addition made; but the form thus provided, and which claimant properly completed, made provision only for insertion of the unit price bid and none for any gross price or any statement or estimate of items or number. In the contract proper, subsequently executed, the submission of proposals “ for removal of all human remains ” from the burial ground was recited and the contractor agreed to “ furnish the service required in connection with the above-mentioned items ” (not particularized beyond the words “removal of all human remains”), “in accordance with all the conditions and covenants contained in the Proposal and
For a complete transfer of each body, including all phases of the work, labor, materials and equipment outlined in subdiv. 2.3 hereof, the sum of Forty Four 98/100 Dollars ($44.98), per body, to be paid by the State.
The surrounding circumstances and the extrinsic proof, which have been outlined above and to which, under familiar principles, we must look to resolve the otherwise irreconcilable conflict and obvious ambiguity, point clearly to the intent that the unit price, without limit to the numbér of units, should constitute the consideration to be paid. That the provision in section 38 for a “ gross sum ” effective for all purposes is not sacrosanct has been recognized by this court upon construing a contract in which the gross figures would probably not be termed “arbitrary” (as the Department of Public Works memorandum above alluded to described the figure in this ease) and it was held that ‘ ‘ the State’s promise to pay was not the gross sum bid, but the quantities actually furnished multiplied by unit prices.” (Kent Constr. Co. v. State of New York, 212 App. Div. 197, 202, per Kellogg, J.) We note, although it is not' necessary to our decision, that the subsequent acts of the parties with reference to the contract supported, and were consistent only with, the construction at which we have arrived.
The computation of claimant’s damages must rest upon proper definition of the term “human remains ”, as used throughout the contract documents, sometimes interchangeably with the word ‘ ‘ body ’ ’. • The problem is best pointed up by a description of the removal process employed by claimant. From each space which he considered to be a grave he removed material which he placed in an individual, numbered box. In many cases the graves contained remains, consisting of bones or pieces and particles of bone, which were readily identifiable as those of a human being. In other graves — and these are referred to in the testimony as 1 ‘ moral graves ’ ’ — there was, as appears from claimant’s testimony upon direct examination, “ no visible bone ” but there were found sections or areas of earth of a color different from that of the surrounding soil and claimant in each instance removed from each supposed moral grave and placed in an individual box these portions of earth,
The ‘ ‘ supplemental agreement ’ ’ to which the decision below gave recognition as modifying the original contract, and to which the court resorted in computing damages, was not approved by the Comptroller or the Director of the Budget (State Finance Law, § 112, subd. 2; Highway Law, § 38, subd. 9) and never became effective, and there is no claim by anyone that it did.
The State contends, and correctly in our view, that the contract provisions for the removal of “ human remains ” and for the payment for a transfer “ of each body ” at a specified amount “per body” require, in reason and of necessity, the existence of some visible and identifiable portion of a human body, apart from the soil into which it may have disintegrated or the fittings of the casket in which it may have been enclosed. The word “ body ” as employed in the contract serves further to define “human remains” and to suggest a corporeal or tangible entity. Although we find no case directly in point, there is respectable authority pointing in this same direction. (Wilson v. Read, 74 N. H. 322; Carter v. City of Zanesville, 59 Ohio St. 170.)
The judgment should be modified, on the law and the facts, by reducing the award to $46,989.24 (being $52,671.58 less $5,682.34 payment), and interest, and, as so modified, affirmed, without costs.
Bergan, P. J., Coon, Gibson, Herlihy and Reynolds, JJ., concur.
Judgment modified, on the law and the facts, by reducing the award to $46,989.24 and interest, and, as so modified, affirmed, without costs. Settle order.