Legal Research AI

Southwest Gas Corp. v. Federal Energy Regulatory Commission

Court: Court of Appeals for the D.C. Circuit
Date filed: 1998-06-02
Citations: 145 F.3d 365, 330 U.S. App. D.C. 238
Copy Citations
6 Citing Cases

                        United States Court of Appeals


                     FOR THE DISTRICT OF COLUMBIA CIRCUIT


              Argued February 23, 1998      Decided June 2, 1998


                                 No. 92-1623


                         Southwest Gas Corporation, 

                                  Petitioner


                                      v.


                    Federal Energy Regulatory Commission, 

                                  Respondent


                  Southern California Gas Company, et al., 

                                 Intervenors


                              Consolidated with


                            Nos. 93-1627, 94-1310


                  On Petitions for Review of Orders of the 

                     Federal Energy Regulatory Commission


     Douglas M. Canter argued the cause and filed the briefs 
for petitioner.



     Patricia L. Weiss, Attorney, Federal Energy Regulatory 
Commission, argued the cause for respondent, with whom 
John H. Conway, Deputy Solicitor, and Susan J. Court, 
Special Counsel, were on the brief.  Edward S. Gelderman 
and Timm L. Abendroth, Attorneys, entered appearances.

     Before:  Edwards, Chief Judge, Ginsburg and Sentelle, 
Circuit Judges.

     Opinion for the Court filed by Circuit Judge Sentelle.

     Sentelle, Circuit Judge:  In this consolidated proceeding, 
we consider petitions filed by Southwest Gas Corporation 
("petitioner" or "Southwest"), a local distribution company 
("LDC"), seeking review of six orders of the Federal Energy 
Regulatory Commission ("FERC" or "the Commission") ap-
plying the changes in the natural gas pipeline regulatory 
regime under Order No. 636 1 to the pipeline operated by El 
Paso Natural Gas Company ("El Paso") which serves South-
west.  Because we find that each challenge is either moot, 
previously disposed of, or without merit under applicable 
standards of review, we deny all petitions.

                                I. Background


     A. The Regulatory Landscape

     For most of the last two decades, the Commission has been 
engaged in a major restructuring of the natural gas industry, 
designed to produce a less regulated, more market-oriented 
regime.  See generally United Distrib. Cos. v. FERC, 88 F.3d 
1105, 1121-30 (D.C. Cir. 1996) ("UDC"), and authorities col-
lected therein.  In this undertaking, FERC determined that 

__________
     1 Order No. 636, Pipeline Service Obligations and Revisions to 
Regulations Governing Self-Implementing Transportation;  and 
Regulation of Natural Gas Pipelines After Wellhead Decontrol, 
F.E.R.C. Stats. & Regs. (CCH) P 30,939, order on reh'g, Order No. 
636-A, F.E.R.C. Stats. & Regs. (CCH) P 30,950, order on reh'g, 
Order No. 636-B, 61 F.E.R.C. (CCH) P 61,272 (1992), aff'd in part, 
rev'd in part, United Distrib. Cos. v. FERC, 88 F.3d 1105 (D.C. Cir. 
1996), cert. denied, 117 S. Ct. 1723 (1997), order on remand, Order 
No. 636-C, 78 F.E.R.C. P 61,186 (1997).



the prior practice of "bundling" sales and transportation 
service--in which a pipeline functioned both as a gas mer-
chant and transporter, selling gas to local distribution compa-
nies connected with its system and delivering the gas to those 
customers--prevented buyers from reaching competitively 
priced wellhead gas as Congress had intended.  See Order 
No. 636 at 30,393 (citing H.R. Rep. No. 29, 101st Cong., 1st 
Sess. 6 (1989)).  The Commission therefore undertook a 
process of "unbundling" with a view to requiring all pipelines 
to separate transportation and sales services, culminating in 
Order No. 636.  See UDC, 88 F.3d at 1123-27 (reciting 
history of mandatory unbundling);  Pennsylvania Office of 
Consumer Advocate v. FERC, 131 F.3d 182, 184 (D.C. Cir. 
1997), corrected and affirmed, 134 F.3d 422 (D.C. Cir. 1998).  
The present controversy involves Southwest's complaints con-
cerning the application of two regulations promulgated under 
Order No. 636 to El Paso's pipeline serving Southwest.

     The first regulation requires pipelines to devise a mecha-
nism whereby firm shippers, such as Southwest, can release 
previously purchased but unneeded firm transportation ca-
pacity to third parties.  18 C.R.R. s 284.243 (1997).  The 
Commission concluded that such a mechanism would promote 
the efficient use of pipeline capacity and enable more buyers 
to access more sellers of gas, at the same time facilitating 
nondiscriminatory open-access transportation and maximizing 
the benefits of a competitive wellhead market.  See Order No. 
636 at 30,418;  see also UDC, 88 F.3d at 1149.

     The second regulation at issue is a requirement that pipe-
lines provide their firm shippers with flexibility to choose 
among the locations at which the pipeline will receive gas 
from or deliver it to them.  18 C.F.R. ss 284.221(g) & (h) 
(1997).  The Commission intended this flexibility to achieve 
the goals of the capacity release program we have just 
described.  Order No. 636 at 30,428-29.  Firm shippers tak-
ing advantage of this flexibility may use any delivery points 
which they have under contract on an interruptible basis 
without losing priority for firm service.  Thus, a firm shipper 
may change delivery points in order to permit another entity 
to ship gas using the firm shipper's unneeded capacity with-



out losing capacity rights.  However, Order No. 636 does not 
permit unlimited flexibility in the choice of delivery points.  A 
firm shipper may resell its capacity at no additional charge 
only for delivery within the firm transportation area to which 
it is entitled and for which it pays.  Id.  As relevant to the 
present controversy, this means that an LDC in a down-
stream portion of a region served by a pipeline can arrange 
delivery of gas to another LDC in an upstream portion (that 
is between the production field and the seller) but not in a 
downstream portion outside the contract delivery area.  Id.  
In FERC parlance, the shipper may sell capacity at no 
additional charge only "within the path" of its firm service.  
Order No. 636-A at 30,582.  A shipper's right to flexible use 
of delivery points is subject to the rights of firm shippers 
using those points as primary delivery points, but is superior 
to the rights of interruptible shippers at those same points.  
Id. at 30,583.

     B. The Factual Background

     Southwest is an LDC that buys natural gas transported 
through an interstate pipeline owned and operated by El 
Paso.  See Southwest Gas Corp. v. FERC, 40 F.3d 464, 465-
66 (D.C. Cir. 1994).2  The distribution systems of Southwest 
and other LDCs are connected to El Paso's San Juan main-
line pipeline facility at five pipeline connection points, known 
as "delivery points," at the western terminus of El Paso's 
pipeline near Topock, Arizona ("Topock delivery points").

     As part of the Commission's transition to a market-based 
regime, and pursuant to a Commission order authorizing El 
Paso to offer separate sales and transportation services under 
a so-called "Global Settlement," see El Paso Natural Gas Co., 
54 F.E.R.C. %57 61,316 (1991), El Paso entered into a "full 
requirements" transportation service agreement with South-
west to deliver all of Southwest's gas requirements at two of 
the Topock delivery points.  Subsequently, the Commission 
authorized El Paso to construct and operate a major expan-
sion of its mainline pipeline facility.  See El Paso Natural 

__________
     2 Our exposition of the facts of this case is drawn, in large 
measure, from Judge Buckley's opinion in Southwest Gas Corp.



Gas Co., 56 F.E.R.C. P 61,198 at 61,774-75 (1991).  Based on 
the expanded pipeline capacity, El Paso executed contracts in 
1991 with seven new shippers ("Expansion Shippers") for 
delivery of gas at any of the five Topock delivery points, 
including the two delivery points utilized by Southwest.  
These contracts provided the Expansion Shippers with "firm 
service rights" (which the regulations define as rights that are 
not subject to a prior claim from another customer, see 18 
C.F.R. s 284.8(a)(3) (1997)), up to the maximum volumes 
specified in their contracts.  Nonetheless, an Expansion Ship-
per could only receive delivery at either of the two Topock 
delivery points utilized by Southwest with Southwest's prior 
agreement.

     On August 17, 1992, Southwest filed a complaint with the 
Commission alleging that, by contracting with the Expansion 
Shippers for firm service rights at the Topock delivery points, 
El Paso had unlawfully overbooked capacity at these points, 
thereby undermining its pre-existing commitments to South-
west, a "full requirements" customer.  On December 28, 1992, 
the Commission dismissed the complaint, finding that South-
west "made no allegations that it has actually been harmed by 
the actions of El Paso...."  Southwest Gas Corp. v. El Paso 
Natural Gas Co., 61 F.E.R.C. P 61,368 at 62,464 (1992).

     On January 27, 1993, Southwest filed a petition for rehear-
ing.  The Commission denied Southwest's request, again find-
ing no impairment of Southwest's contractual rights.  South-
west Gas Corp. v. El Paso Natural Gas Co., 63 F.E.R.C. 
P 61,111 at 61,763-64 (1993).  The Commission emphasized 
that Southwest "retain[ed] the ability to call on the entire 
capacity of" the two Topock delivery points and failed to 
provide "any reason why Southwest would be forced to 
contract with the expansion shippers...."  Id.

     We subsequently denied Southwest's petition for review, 
holding that Southwest had failed to demonstrate an "injury 
in fact."  Southwest Gas Corp., 40 F.3d at 468 (citing Lujan 
v. Defenders of Wildlife, 504 U.S. 555, 559-60 (1992)).  We 
concluded that Southwest had failed to show that the expan-
sion contracts had disrupted the flow of gas at the two 



Topock delivery points, or that it was likely to do so in the 
future.  Id.

     As required by Order No. 636, El Paso submitted a propos-
al to the Commission in which it sought to implement a 
capacity release program.  See El Paso Natural Gas Co., 61 
F.E.R.C.P 61,333 at 62,283-84 (1992).  According to South-
west, the orders arising out of those proceedings in effect 
permit the Expansion Shippers to sell their rights to capacity 
at the Topock delivery points to other shippers on the second-
ary market.  Southwest petitioned for review of those orders.

     After FERC rejected one El Paso proposal to implement a 
capacity release mechanism, El Paso proposed to FERC that 
shippers use as primary delivery points any available delivery 
points within their delivery zone which do not include those 
downstream from their ultimate delivery point.  El Paso next 
proposed that shippers use any receipt points located within 
the part of El Paso's system covered by the shipper's con-
tract.  See El Paso Natural Gas Co., 62 F.E.R.C. P 61,311 at 
62,981 (1993).  Finally, El Paso proposed to limit the capacity 
that a full requirements customer could release to its maxi-
mum "billing determinants," a measure of customer demand 
or entitlement to a pipeline's services.

     As part of a group of El Paso's customers located east of 
California, Southwest objected to El Paso's flexible delivery 
point proposal, arguing--as it had during the 1992 complaint 
proceeding--that its right to capacity had priority over the 
rights of any Expansion Shippers at the Nevada Topock 
delivery point utilized by it.  Southwest also quarreled with 
El Paso's receipt point proposal, arguing that it ought to be 
able to use receipt points outside its contracted-for zone at no 
extra charge.  In particular, Southwest wanted to use the 
California Topock delivery points, "downstream" from its 
contract zone, without paying an additional charge, by means 
of "backhaul" or "displacement."

     The Commission rejected Southwest's challenges and ap-
proved El Paso's proposal.  In rejecting Southwest's claim for 
priority at the Nevada Topock delivery point, the Commission 
repeated a point it had made when ruling on Southwest's 



earlier complaint:  any Expansion Shipper wanting to use that 
delivery point would be required to make arrangements with 
Southwest, the sole owner of the facilities at that point.  Id. 
at 62,989.  The Commission also rejected Southwest's request 
that it be able to use the California Topock delivery points at 
no extra charge.  Noting that that delivery point was down-
stream from the rate zone covered by Southwest's reservation 
charges, the Commission determined that Southwest's re-
quest was foreclosed by the requirements of Order No. 636.  
The Commission added that Southwest was free to use the 
California Topock delivery points if it wished to pay the 
applicable zone reservation charge.

     Southwest petitioned for rehearing.  It argued that the 
Commission had deferred certain issues in the 1992 complaint 
proceeding to the restructuring proceeding.  Southwest then 
complained that the Commission had failed to address these 
issues in the restructuring proceeding, despite what South-
west considers FERC's earlier promise to do so.  The Com-
mission rejected Southwest's arguments and denied its peti-
tion for rehearing.  Notwithstanding Southwest's arguments 
to the contrary, FERC stated that the deferred issues (the 
impact of El Paso's flexible receipt and delivery point mecha-
nism on shippers) had been resolved in an earlier order.  It 
also found that requiring shippers to pay reservation charges 
for the zone in which the receipt point is located was consis-
tent with Order No. 636, which is premised on requiring 
shippers to pay for the facilities and capacity on the portion of 
the system they use.

     After El Paso submitted revised tariff sheets to comply 
with FERC's most recent order, a group of El Paso shippers 
taking gas deliveries in Arizona (the "Arizona Directs") peti-
tioned for rehearing of that order.  See El Paso Natural Gas 
Co., 65 F.E.R.C. P 61,134 at 61,675-77 (1993).  They asked the 
Commission to make it clear that a full requirements custom-
er could not use capacity at its primary delivery points in 
excess of its billing determinants.  If this were not the case, 
they explained, a full requirements customer could block the 
use of its delivery points by others by claiming that its total 
capacity could be applied to each of its primary delivery 



points.  Southwest opposed this request, arguing that the 
clarification would undermine its right to release up to the 
total amount of capacity for which it had contracted.

     The Commission agreed with the Arizona Directs, and 
clarified its prior order accordingly.  It concluded that limits 
should be applied at each delivery point, not the aggregate of 
all delivery points.  Id. at 61,677.  The Commission found 
that this result was reasonable since it would help small 
shippers like the Arizona Directs with one or a few primary 
delivery points and would give such shippers more flexibility 
in releasing capacity.  At the same time, the Commission 
found that this result would not interfere with the partic-
ipation of full requirements customers in the capacity release 
program.

     Southwest sought rehearing of the Commission's order, 
arguing, among other things, that the Commission improperly 
placed limitations on its ability to use delivery point capacity.  
In other words, it took issue with the Commission's insistence 
that full requirements customers must designate in advance 
of a capacity release what portion of their capacity rights they 
wished to retain at each primary delivery point.  In addition, 
Southwest complained about individual capacity caps to be 
imposed on each of its delivery points in Arizona.

     FERC largely rejected Southwest's arguments.  It further 
explained that it was necessary to limit full requirements 
customers' rights at their receipt and delivery points so that a 
full requirements customer would not be able to "effectively 
tie up capacity on all delivery points despite being able to 
release capacity" and thereby gain an unfair competitive 
advantage over the other customers competing in the capacity 
release market.  El Paso Natural Gas Co., 66 F.E.R.C. 
P 61,183 at 61,381 (1994).  By adopting the Arizona Directs' 
proposal--requiring full requirements customers to announce 
in advance of a capacity release what portion of their capacity 
rights they wished to retain at each primary delivery point--
FERC ensured that other shippers would learn what delivery 
point capacity was available for their use.



     Although the Commission denied Southwest's petition for 
rehearing, it stated that it would review El Paso's capacity 
release program after one year to determine if the adminis-
trative difficulties Southwest had predicted had actually oc-
curred.  Id. at 61,380.  It is in this posture that we consider 
Southwest's consolidated petitions for review.

                                 II. Analysis


     At the outset, we note that we need not discuss Southwest's 
petition in No. 92-1623 at length.  That petition, which 
challenged the Commission's failure to require El Paso to 
provide "no notice" service, has been rendered moot by 
FERC's later decision requiring such service.  See Order No. 
636-C, 78 F.E.R.C. P 61,186 at 61,771-72.  Southwest tacitly 
admits this mootness.  Petitioner's brief at 6 & n.4.  None of 
petitioner's other issues need detain us much longer.

     A. Southwest's Claimed Historic Rights to Firm Capacity

     In a rather muddled manner, Southwest describes one of 
the issues presented for review:

     Where the law requires natural gas pipelines to provide 
     unbundled firm transportation service that is equal in 
     quality to the bundled firm gas service formerly provid-
     ed, may a pipeline offer a local distribution company 
     capacity rights at delivery points that are inferior to that 
     LDC's capacity rights prior to unbundling, and inferior 
     to the capacity rights of subsequent purchasers of firm 
     capacity?

Petitioner's brief at 1.  What Southwest really seems to be 
seeking is what it calls "first-in-time delivery point capacity 
allocation."  In other words, Southwest contends that because 
it had delivery rights before Expansion Shippers were added 
to the customer mix on El Paso's line, it should have a 
priority right to capacity over the Expansion Shippers.  
FERC dismissed that claim, stating:

     The parties expressed concerns regarding historical pri-
     mary delivery points and flexible/alternate delivery 
     points.  This issue seems more properly to be one of the 
     allocation of delivery point capacity which must, there-



     fore, be addressed by El Paso in El Paso's restructuring 
     proceedings....

Southwest Gas Corp. v. El Paso Natural Gas Co., 61 
F.E.R.C. P 61,368 at 62,464 (1992).  In the restructuring 
proceeding, the Commission granted some of the relief that 
Southwest sought by reserving to Southwest and the Expan-
sion Shippers priority rights at fully booked delivery points, 
but did not grant Southwest's claim to "vested" or "historical" 
rights as against the Expansion Shippers.  El Paso Natural 
Gas Co., 64 F.E.R.C. P 61,265 at 62,827 (1993).  The Commis-
sion contends that this ruling, addressing the priority rights 
as against all parties except the Expansion Shippers, disposed 
of all allocation claims left open by its original order, and that 
all other issues raised were not properly before it, having 
been disposed of in prior orders.  Southwest contends that 
the Commission erred by failing to address its other argu-
ments relating to delivery point capacity.  We agree with the 
Commission.

     Insofar as Southwest's rather confused and confusing argu-
ment questions the Commission's interpretation of the 
breadth of its own prior order, "it is well established that an 
agency's interpretation of the intended effect of its own 
orders is controlling unless clearly erroneous."  Transconti-
nental Gas Pipe Line Corp. v. FERC, 922 F.2d 865, 871 (D.C. 
Cir. 1991) (citation omitted).  Southwest has done nothing to 
convince us that the Commission's interpretation of its own 
prior order is clearly erroneous.  Insofar as the petition 
rehashes the issue previously litigated--that is, the Commis-
sion's permitting El Paso to book, and in Southwest's view to 
overbook, capacity at the two Topock delivery points utilized 
by Southwest--we already ruled in Southwest Gas Corp. that 
Southwest has not demonstrated that the Commission's deci-
sion injured it in fact and thus made it an aggrieved party for 
purposes of standing before this court.  40 F.3d at 467-68.  
The present petition adds nothing new, nor does it change our 
view.  Finally, insofar as it is necessary to address the 
substantive question of "historic" or "vested" rights claimed 
by Southwest, the Commission not only reasonably but cor-
rectly points out that Southwest had no such rights, because 



the flexibility available under El Paso's proposal did not exist 
before Order No. 636 restructuring.  64 F.E.R.C. at 62,827.  
The Commission further reasonably concluded that anything 
lost by Southwest was at least "counterbalanced" by "other 
more expansive rights" that Southwest gained under restruc-
turing.  Id. at 62,828.

     B. FERC's Refusal to Allow Southwest to Use California 
Interconnection Points as Receipt Points

     Southwest contends that it was arbitrary and capricious for 
the Commission to deny it the use of California interconnec-
tion points with El Paso's pipelines as receipt points.  Those 
points were already available to Southwest as delivery points.  
Had FERC approved Southwest's application, petitioner 
would have been permitted to deliver gas to its system in 
southern Nevada by "backhaul," which involves the displace-
ment of gas but not physical reversal of a forwardhaul flow of 
gas.  However, FERC rejected the request, concluding that 
petitioner could use the California Topock delivery points as 
receipt points only if it paid an additional zonal delivery 
charge for the displacement service.  64 F.E.R.C. at P 62,830.  
Southwest contends that FERC's decision denying the use of 
less costly displacement service to an existing firm customer 
without payment of higher forwardhaul charges is unrea-
soned, and therefore arbitrary and capricious.  FERC replies 
that this ruling is a rather straightforward application of the 
Order No. 636 requirement that the flexibility given firm 
shippers to choose among specific locations on the transport-
ing pipeline is limited to receipt and delivery points "within 
the path" of the shipper's firm service.  See Order No. 636-A 
at 30,582.

     We agree with FERC.  The Commission need not revisit 
the reasoning of a general order every time it applies it to a 
specific circumstance.  This part of Southwest's petition is no 
more than an impermissible collateral attack on Order No. 
636.  Cf. Transwestern Pipeline Co. v. FERC, 988 F.2d 169, 
174 (D.C. Cir. 1993) (denying challenge to a specific applica-
tion of a general order).



     C. FERC's Requirement of Capacity Release Specifica-
tion

     The Commission imposed two conditions on the partic-
ipation of full requirements customers, such as Southwest, in 
El Paso's capacity release program.  First, it required those 
customers to limit their capacity releases to a defined level.  
Second, it required them to designate the amount of capacity 
they plan to release at each specific delivery point.  South-
west attacks these limitations as arbitrary and capricious.  
The Commission defends them as reasonable measures de-
signed to balance the interests of full requirements and 
contract demand customers.  The Commission's opinion in 
the administrative proceeding offers a succinct defense of its 
decision:

     Assuming that Southwest would otherwise have to desig-
     nate [contract demands] for its other delivery points that 
     are less than the physical capacity of each point, South-
     west could nonetheless tie up 100 percent of the capacity 
     at each point if it retains its full requirements rights at 
     each point.  There would be no way for other shippers to 
     acquire any primary rights at any of those points because 
     of Southwest's full requirements rights.  It merely would 
     not be able to demand more than its total billing determi-
     nant level from all of its delivery points in the aggregate.

El Paso Natural Gas Co., 66 F.E.R.C. P 61,183 at 61,381 n.9 
(1994).  We find this explanation, taken together with the rest 
of the Commission opinion, more than adequate to meet the 
familiar arbitrary and capricious standard of administrative 
procedure review.  See 5 U.S.C. s 706(2).  We therefore 
conclude that we must deny Southwest's petition.

                               III. Conclusion


     For the reasons set forth above, we find that none of the 
petitions offered by Southwest entitles it to the relief sought.  
Although we have not addressed each of the arguments 
raised by Southwest, we have carefully considered them all 
and determined that none warrants reversal of the Commis-
sion's decisions.  Therefore, the petitions for review are 
denied.