The claimant entered into a contract with the State by which it undertook the construction of the superstructure and part of the substructure of a precast, prestressed continuous concrete girder bridge consisting of three spans across the Oneida River at Brewerton in Onondaga County. Subsequent to the completion and acceptance of the contract work, claimant filed a claim against the State which included four causes of action.
In its first cause of action, claimant sought to recover the conceded contract balance, with interest on the amount of that balance from the date of the acceptance of the work by the State. Claimant contends that interest was properly awarded by the Court of Claims and that the decision of this court in Higgins & Sons v. State of New York (20 N Y 2d 425), decided after the decision of the Appellate Division in this case, indicates that the award of interest on the undisputed contract balance should not have been reversed. The work was accepted by the State on October 20, 1961, but the claimant did not present the affidavits required as conditions precedent to payment until October 24, 1962. The State tendered final payment of that amount on November 2,1962, nine days after the affidavits were submitted by the claimant. The claimant refused that tender because of a contract provision to the effect that acceptance of final payment would constitute a waiver of all additional claims
In its second cause of action, claimant sought to recover the increased cost of fabricating the bridge’s cantilever girders in a vertical position, the one approved by the State, rather than in the less expensive horizontal position, the one claimant desired to use. Claimant contends that the State committed a breach of contract by refusing to approve the claimant’s proposal to use horizontal fabrication and that, therefore, claimant is entitled to recover the increased costs involved in using the vertical method. In support of its contention, claimant relies principally on a single paragraph of the design specifications, leaving the method of forming the girders in the claimant’s discretion, as indicating that the entire method of fabrication (including forming) was to be in the claimant’s discretion. The Court of Claims, however, from an examination of the specifications as a whole found that the contract and specifications contemplated vertical casting. The Appellate Division affirmed on the ground that the proof amply supported the findings and conclusions of the Court of Claims. Without extended discussion of the intricacies of the specifications and drawings, the record does indeed amply indicate that the contract, taken as a whole, called for vertical casting and that the State’s refusal to approve the horizontal method, therefore, did not constitute a breach of contract by the State. Illustrative are those portions of the specifications which showed that the “ soffit ”, or under side, of the girders was to be on the bottom when the girder
Claimant’s fourth cause of action sought recovery for two items of alleged “ extra ” work not called for by the contract. The State, however, contends that the items were provided for by the original contract and by a supplemental agreement entered into between the claimant and the State. As to the first item of asserted extra work, the preparation of the concrete deck prior to the application of the waterproofing substance, the original specifications called for such preparation and the mere fact that the supplemental agreement referred to such preparation as work to be done under the agreement cannot alter the fact that such work was already required to be done by the terms of the original contract specifications and was, therefore, not ‘ ‘ extra ’ ’ work. The second item of alleged extra work involved the surface area required by the contract specifications to be covered with the waterproofing substance. The Court of Claims found that claimant covered only the area called for by the contract and was paid in full therefor and the Appellate Division affirmed. Suffice it to say that there is ample evidence to support that determination. Accordingly, the dismissal of the fourth cause of action was properly affirmed by the Appellate Division.
The order of the Appellate Division is modified to the extent that the claim for interest is allowed to the extent limited above and is otherwise affirmed.
Chief Judge Fuld and Judges Scileppi, Beegan, Keating. Beeitel and Jasen concur.
Order modified, with costs, in accordance with the opinion herein, and, as so modified, affirmed.