Legal Research AI

Time Warner Entertainment Co. v. Federal Communications Commission

Court: Court of Appeals for the D.C. Circuit
Date filed: 1998-05-22
Citations: 144 F.3d 75, 330 U.S. App. D.C. 126
Copy Citations
45 Citing Cases
Combined Opinion
                        United States Court of Appeals


                     FOR THE DISTRICT OF COLUMBIA CIRCUIT


              Argued February 3, 1998      Decided May 22, 1998


                                 No. 97-1263


                    Time Warner Entertainment Co., L.P., 

                                  Petitioner


                                      v.


                    Federal Communications Commission and 

                          United States of America, 

                                 Respondents


                  On Petition for Review of an Order of the 

                      Federal Communications Commission


     R. Bruce Beckner argued the cause for petitioner, with 
whom Aaron I. Fleischman, Seth A. Davidson, and Jill K. 
McClelland were on the briefs.

     James M. Carr, Counsel, Federal Communications Com-
mission, argued the cause for respondents, with whom Joel I. 
Klein, Assistant Attorney General, United States Department 



of Justice, Robert B. Nicholson and Robert J. Wiggers, Attor-
neys, Christopher J. Wright, General Counsel, Federal Com-
munications Commission, and Daniel M. Armstrong, Associ-
ate General Counsel, were on the brief.

     Before:  Silberman, Randolph, and Tatel, Circuit Judges.

     Opinion for the Court filed by Circuit Judge Silberman.

     Opinion concurring in part and dissenting in part filed by 
Circuit Judge Randolph.

     Silberman, Circuit Judge: Time Warner Entertainment 
Company petitions for review of an order of the Federal 
Communications Commission setting forth the manner in 
which cable system operators may recoup external cost in-
creases incurred between September 30, 1992 and the date 
their system first became subject to rate regulation.  The 
Commission contends that because it had no opportunity to 
pass on the issue, or to correct its error, section 405 of the 
Communications Act bars our review.  We grant the petition 
in part and remand.

                                      I.


     The Cable Television Consumer Protection and Competi-
tion Act of 1992, Pub. L. No. 102-385, 106 Stat. 1460 (codified 
in scattered sections of 47 U.S.C.), directed the FCC to 
regulate the rates that cable operators not subject to "effec-
tive competition," defined at 47 U.S.C. s 543(l)(1) (1994), 
could charge their subscribers.  The Commission designed a 
scheme intended to ensure that any system not facing such 
competition would nevertheless charge approximately the 
same rates as if it were in a competitive market.  Put simply, 
a system operator's initial permitted rate either was its rate 
in effect on September 30, 1992 reduced by a "competitive 
differential" (the "full reduction rate"), or was calculated in 
accordance with certain FCC formulas and worksheets with-
out reference to rates in effect on September 30, 1992 (the 



"transition rate").  See 47 C.F.R. s 76.922(b) (1997).  Most 
systems, the Commission has said, employed the former rate.  
See Implementation of the Cable Television Consumer Pro-
tection and Competition Act of 1992:  Rate Regulation, Mem-
orandum Opinion and Order (Order on Remand), 11 
F.C.C.R. 20206, p 22 (1996).

     In Time Warner Entertainment Co. v. FCC, 56 F.3d 151 
(D.C. Cir. 1995), we considered consolidated petitions for 
review of the FCC's orders implementing the Act.  One of 
the cable operators' complaints in that case (and the only one 
relevant to Time Warner's instant petition) was that the FCC 
unreasonably did not allow "cable operators to adjust their 
rates to reflect external cost increases incurred during the 
gap period."  Id. at 173.  "[E]xternal costs" were those 
"effectively beyond the cable operator's control," including:  
"(1) the retransmission consent fees cable operators pay to 
broadcasters;  (2) programming costs;  (3) [state and local] 
taxes;  and (4) franchise fees and the costs associated with 
other franchise requirements, including the provision of pub-
lic, educational, and governmental-access programming."  Id. 
at 171;  see also 47 C.F.R. s 76.922(f)(1) (1997).  The "gap 
period" refers to the time between September 30, 1992 and 
the date a system became subject to rate regulation.  An 
operator's initial permissible rate, at least for those using the 
full reduction rate, was derived from its rate in effect on 
September 30, 1992, not the actual rate in effect on the date 
each system became subject to regulation, "lest [the FCC] 
build into the permitted initial rates any unwarranted rate 
increases that cable operators took after passage of the 1992 
Cable Act."  Time Warner, 56 F.3d at 173.  The Commission 
did not permit operators to recoup any external cost increas-
es incurred during the gap period; 1  only those incurred after 
the date a system became subject to rate regulation could be 
taken into account.2  The length of the gap varied among full 

__________
     1  The FCC's counsel, however, indicates that operators were 
permitted to include one particular external cost increase--fran-
chise fees--incurred during the gap period.

     2  Our first Time Warner opinion did not address whether a 
system operator which used a transition rate rather than a full 



reduction rate-based operators because they became subject 
to rate regulation at different times, but was no shorter than 
11 and no longer than 17 months long.

     In Time Warner, we held that the Commission's "decision 
to preclude a rate adjustment designed to recover changes in 
external costs incurred during the gap period [was] arbitrary 
and capricious," id. at 174, and "vacate[d] the rule insofar as 
the FCC denied [cable operators] recovery of their gap-
period external cost increases."  Id. at 178.  In our view, the 
FCC had offered "no reason to doubt that cable operators 
incurred external costs during the gap period, yet under its 
regulations they would never be able to recoup those costs 
short of opting for cost-of-service regulation--which would be 
akin to shooting a fly with a blunderbuss."  Id. at 174.3  We 
also thought the Commission's defense of its rule--that allow-
ing recovery of the gap-period external cost increases would 
be too administratively burdensome, both for the cable opera-
tors and the FCC--"completely unacceptable."  Id.

     Eighteen months after our decision, and without issuing a 
proposed rule or seeking public comment on how to proceed, 
the Commission issued an order in response to our remand.  
See Order on Remand, WW 21-28.  The order "permit[s] oper-
ators to adjust their current permissible rates to [the level] 
the operators would currently be charging if they had been 

__________
reduction rate was subject to the same external cost adjustment 
problem, and the parties dispute the point.  The FCC's counsel 
argues that such an operator did not.  Time Warner, however, 
contends that an operator using the transition rate faced a slightly 
different gap, one that began on April 1, 1993 instead of September 
30, 1992, but likewise ended on the date the system first became 
subject to rate regulation.

     3  The rules permitted a system operator to opt into convention-
al cost-of-service regulation;  we said, however, that "because a cost-
of-service regulatory proceeding is expensive for the cable operator, 
the FCC can be confident that an operator will not lightly choose 
that option and it will indeed remain a limited exception to the 
general rule."  Time Warner, 56 F.3d at 170 (citation omitted).



permitted to include increases in external costs occurring 
between September 30, 1992 and their initial date of regula-
tion."  Id., p 25 (emphasis added).  But the Order does not 
allow cable operators to recover in future rates or otherwise 
the difference between the rates they would have charged in 
1994, 1995, 1996, and 1997, had they been allowed to account 
for external cost increases incurred during the gap period, 
and their allowable rates in those years.  Time Warner did 
not petition for reconsideration after the Commission issued 
its Order on Remand;  it instead sought review here.  Peti-
tioner claims that the FCC's order unreasonably denies oper-
ators the ability to recoup the revenue deficiency--which 
Time Warner estimates at more than $14 million dollars--
they sustained during the four years, and that the order does 
not comply with our mandate in the first Time Warner case.  
It also contends that those operators which employ a transi-
tion rate are unreasonably denied the opportunity to take 
advantage of the prospective relief afforded full reduction 
rate-based operators.

                                     II.


     The Commission did not explain why its order permitted 
cable operators to charge current rates as if the gap period 
external cost increases had been included, but did not allow 
them to recover their revenue deficiencies, other than to say 
that "[t]he scope of relief requested is reflected in Time 
Warner's Emergency Motion for Expedited Review (May 3, 
1994 ...)" filed in this court before argument on the first 
petition.  Id., p 24 n.40.  Petitioner had said in that motion 
that "cable operators lose millions of dollars in revenue every 
day.  If they eventually succeed in persuading this Court to 
rule in their favor, those losses cannot be recouped.  Their 
unrecoverable economic loss thus constitutes irreparable inju-
ry."  The FCC construed that statement as a concession (or 
waiver) that the cable operators were not even seeking to 
recover their revenue loss.

     Petitioner contends that it was absurd for the Commission 
to have drawn a distinction between past revenue deficiencies 



attributable to unrecovered external cost increases and pro-
spective rates predicated on, but not totally recovering, those 
past external cost increases;  its claim to the Commission 
never made that distinction.4  Even worse, Time Warner 
argues, the passage on which the FCC relied pertained solely 
to the Commission's choice of a 17% "competitive differen-
tial," see supra at 2, not the gap period at all.  The FCC's 
counsel insists that it was "entirely understandable" for the 
Commission to decide as it did because Time Warner never 
indicated that it had "changed" its position in a submission to 
the FCC after our remand, or in a petition for reconsidera-
tion.  He contends that the other arguments Time Warner 
raises in its petition--that it was unreasonable for the Com-
mission not to provide a way for operators to recoup all their 
revenue deficiencies, that the FCC's order treated full reduc-
tion rate-based operators more favorably than those using the 
transition rate, and that the order did not comply with our 
remand--were never presented to the Commission (presum-
ably in a petition for reconsideration because it was not 
foreseeable that the Commission would draw the remedial 
distinction that it did).  Petitioner therefore has not exhaust-
ed its administrative remedies and our review is foreclosed by 
section 405(a) of the Communications Act.  Time Warner's 
primary response is that the issues it raises were directly 
implicated in the reasoning of our prior decision and were 
therefore covered in the remand order.

     Section 405(a) is worded somewhat differently than the 
normal exhaustion provision.  It provides:

     After an order, decision, report, or action has been made 
     or taken in any proceeding by the Commission ... any 
     party thereto, or any other person aggrieved or whose 
     interests are adversely affected thereby, may petition for 
     reconsideration ... and it shall be lawful for ... the 
     Commission ..., in its discretion, to grant such a recon-
     sideration if sufficient reason therefor be made to ap-
     pear....  The filing of a petition for reconsideration 

__________
     4  The dissent's formulation of the issue, assertedly not present-
ed to the Commission, see Dissent at 1, is misstated.



     shall not be a condition precedent to judicial review of 
     any such order, decision, report, or action, except where 
     the party seeking such review ... (2) relies on questions 
     of fact or law upon which the Commission, or designated 
     authority within the Commission, has been afforded no 
     opportunity to pass.

47 U.S.C. s 405(a) (1994) (emphasis added).  Although we 
have said that this provision codifies the normal exhaustion 
doctrine, see Washington Ass'n for Television and Children 
v. FCC (WATCH), 712 F.2d 677, 681 (D.C. Cir. 1983), the text 
does not refer to the necessity of a party raising an argument 
before the Commission--as does the typical exhaustion stat-
ute--but only that the Commission have an "opportunity to 
pass" on a question of fact or law raised in the petition.5

     In determining whether the Commission has had an oppor-
tunity to pass on a question, we have, to be sure, asked 
whether a question was adequately presented to the Commis-
sion even if the Commission addressed the issue in some 
fashion.  Recently, for instance, in Bartholdi Cable Co. v. 
FCC, 114 F.3d 274 (D.C. Cir. 1997), we held section 405 was 
not satisfied because the party claiming the Commission 
improperly rejected attorney-client and work-product privi-
leges had not raised those claims before the Commission.  
The FCC discussed the privileges in dicta, but we concluded 
that because the issue was not "flagged" the Commission did 
not have a fair opportunity to pass on it.  Id. at 279-80.  
Bartholdi Cable thus fits within the category of cases in 
which we have said that even where an issue has been 
"raised" before the Commission, if it is done in a less than 
complete way, see Northwestern Ind. Tel. Co. v. FCC, 824 
F.2d 1205, 1210 n.8 (D.C. Cir. 1987) (appellant "point[ed] out" 
a circumstance, but did not make an argument);  WATCH, 

__________
     5  Our dissenting colleague does not take account of this statuto-
ry distinction, and relies on "common law" exhaustion doctrine.  
But judge made notions of "common law" always yield to statutes--
particularly in administrative law, see Darby v. Cisneros, 509 U.S. 
137 (1993) and Vermont Yankee Nuclear Power Corp. v. Natural 
Resources Defense Council, 435 U.S. 519 (1978).



712 F.2d at 681 (appellant "never explicitly" made its argu-
ment);  Alianza Federal de Mercedes v. FCC, 539 F.2d 732, 
739 (D.C. Cir. 1976) (the "grist" of appellant's argument was 
there, but "nothing was made of it"), or if the party seeking 
review "seem[s] to abandon its argument ... by taking 
inconsistent positions," Busse Broad.  Corp. v. FCC, 87 F.3d 
1456, 1461 (D.C. Cir. 1996), the Commission has not been 
afforded a fair opportunity.  Our reasoning reflects our expe-
rience as judges that unless an issue is squarely presented in 
a case, any discussion of the question in the opinion (dicta) is 
only a preliminary view and therefore not to be given prece-
dential weight.

     Because section 405 is worded as it is, however, it is not 
necessary that the issue of fact or law be presented to the 
Commission by the petitioner itself.  "There is no require-
ment that [the Commission's opportunity to pass] be afforded 
in any particular manner, or by any particular party."  Office 
of Communication of the United Church of Christ v. FCC, 
465 F.2d 519, 523 (D.C. Cir. 1972).  Indeed, in United Church 
of Christ we held that since two dissenting Commissioners 
had raised the "very argument pressed" before us, section 
405 was not an impediment to review.  Id.  Nor have we 
required that the precise issue be presented to the Commis-
sion in order to afford it a "fair opportunity."  So long as the 
issue is necessarily implicated by the argument made to the 
Commission, section 405 does not bar our review.  For exam-
ple, in National Ass'n for Better Broadcasting v. FCC 
(NABB), 830 F.2d 270 (D.C. Cir. 1987), the appellant com-
plained to the Commission that a television station had violat-
ed the Communication Act's advertising rules.  The FCC 
determined that the appellant's statutory claim was foreclos-
ed by its 1974 policy statement interpreting the statutory 
requirements.  We allowed the appellant to argue that the 
FCC's policy statement was contrary to the Act, although 
that exact argument was never presented to the Commission.  
We said that "the Commission not only understood that the 
gravamen of NABB's grievance was that [the station] was 
infringing [the Act], but the Commission actually purported 
to dispose of that charge in its order."  Id. at 274.  And in 



MCI Telecommunications Corp. v. FCC, 10 F.3d 842 (D.C. 
Cir. 1993), MCI claimed that AT&T had violated a "reason-
able charges" provision of the Act, and that it was therefore 
entitled to damages.  The Commission, however, determined 
that its "IXC orders" barred damages.  Because MCI never 
addressed the proper interpretation of its IXC orders, the 
FCC argued on appeal that it had been afforded no opportu-
nity to pass on the question, so section 405 barred review.  In 
accordance with our NABB decision, we said that "MCI's 
claim on review that the Commission decided [the] question 
[of whether it was entitled to damages] by invoking an 
authority inadequate to justify the decision does not itself 
raise a novel question of law;  it merely asks whether the 
original question was correctly decided."  Id. at 845.6

     The Commission properly points to an apparently conflict-
ing line of our cases in which we have been sticklers in 
insisting that "a party must first present its concerns to the 
Commission so that the agency is afforded an opportunity to 
cure any defect" and that the FCC must be given "the 
opportunity to ... correct any error" in its order as a 
precursor to judicial review.  See, e.g., Freeman Eng'g As-
socs., Inc. v. FCC, 103 F.3d 169, 182 (D.C. Cir. 1997).  But 
those are cases, as we explained, "where the challenge is 
predicated upon a technical defect in a Commission decision 
which could easily have been cured if called to the Commis-
sion's attention on reconsideration."  NABB, 830 F.2d at 274 
(emphasis added).  It is in these "technical defect" or proce-
dural oversight cases that we have made the statements 
about giving the agency an opportunity to correct errors.  
For example, in Rogers Radio Communication Services v. 
FCC, 593 F.2d 1225 (D.C. Cir. 1978), the appellant contended 
that the FCC failed, in violation of 47 U.S.C. s 309(a), to 
articulate its finding that a rival cellular carrier would serve 
the public interest, convenience, and necessity in granting the 
rival's application;  we determined that "[o]ne of the purposes 
of [section 405] is to afford the Commission the initial oppor-
tunity to correct errors in its decision or the proceeding 

__________
     6  The dissent ignores these three cases.



leading to decision."  Id. at 1229.  We said the same thing 
where the petitioners claimed the FCC violated the APA by 
failing to address comments in its rulemaking proceeding, 
Action for Children's Television v. FCC, 906 F.2d 752, 755 
(D.C. Cir. 1990);  see also Petroleum Communications, Inc. v. 
FCC, 22 F.3d 1164, 1169-71 (D.C. Cir. 1994) (FCC gave no 
opportunity for notice and comment before promulgating 
rule);  City of Brookings Municipal Tel. Co. v. FCC, 822 F.2d 
1153, 1163 (D.C. Cir. 1987) (APA and other procedural objec-
tions);  American Radio Relay League v. FCC, 617 F.2d 875, 
879 n.8 (D.C. Cir. 1980) (notice and comment procedures), 
where a petitioner claimed the FCC ignored certain record 
evidence, Freeman Eng'g, 103 F.3d at 182;  see also Southern 
Ind. Broad. v. FCC, 935 F.2d 1340, 1342 (D.C. Cir. 1991) 
(appellant claimed a deposition that the FCC reviewed was 
not part of the record), and where an appellant claimed the 
Commission erroneously ascribed a rival applicant's research 
methods to it.  Gencom Inc. v. FCC, 832 F.2d 171, 186-87 
(D.C. Cir. 1987);  see also Freeman Eng'g, 103 F.3d at 182 
(petitioner was required to present its claim that the FCC 
failed to explain why it treated a competitor's similar proposal 
differently to give the FCC "an opportunity to cure any 
defect").  But cf. Alabama Power Co. v. FCC, 773 F.2d 362, 
368 & n.12 (D.C. Cir. 1985) (argument that Commission used 
"a wholly irrelevant percentage figure" to discount certain 
costs did not need to be raised in a petition for reconsidera-
tion).

     To sum up, in our section 405 cases we have asked whether 
the issue that a petitioner brings to us was "flagged," or to 
use a sports metaphor, "teed up," before the Commission.  
But if petitioner complains of only a technical or procedural 
mistake, such as an obvious violation of a specific APA 
requirement, we have insisted that a party raise the precise 
claim before the Commission--if necessary, in a motion for 
reconsideration--because we assume the Commission simply 
overlooked the requirement.  In those instances, we are 
concerned that the petitioner, by bringing the issue first to 
us, is playing a game of "gotcha."  If, however, a petitioner 
makes a basic challenge to a Commission policy, but the 
formulation of the issue presented to us was not precisely as 



presented to the Commission, we ask whether a reasonable 
Commission necessarily would have seen the question raised 
before us as part of the case presented to it.

     We think it a close question here whether our remand itself 
should be thought to have, at least, adequately presented to 
the Commission the "issue" of whether petitioner was entitled 
to fully recover the excluded gap period external cost increas-
es.  We never explicitly addressed the scope of the remedy, 
but the logic of our opinion--that it was unreasonable for the 
Commission to justify its refusal to permit cable operators to 
recover gap external cost increases on administrative burden 
grounds--applies equally to past losses and future ones.  If 
the Commission had relied on a new consideration, other than 
the discredited administrative burden, that would be another 
matter, but it did not;  it offered no reasoning beyond its 
"concession" rationale.  Surely if the FCC had merely said 
that "we do not wish to grant full relief, as the court's opinion 
suggests we should, because it might prove politically unpopu-
lar" or, because "we do not like petitioner," it could not be 
argued that a petition seeking review brought into question a 
truly new issue of law.  On the other hand, we have warned 
that a party must be careful on remand to raise issues before 
the Commission before they come back to us.  See Illinois 
Bell Tel. Co. v. FCC, 988 F.2d 1254, 1264 n.12 (D.C. Cir. 
1993).7

     It is unnecessary for us to decide whether our remand put 
the issue to the FCC, however.  The Commission apparently 
recognized that the rationale of our decision did not easily 
support the distinction it wished to draw, and that petitioner's 
supposed "concession" allowed it to avoid confronting the 
problem.  But there is no question that the Commission 
expressly decided the concession issue--whether petitioner 
was even seeking to recover its revenue deficiency.  And, in 
that regard, we agree with petitioner that the FCC's inter-
pretation of petitioner's motion for expedition filed in this 
court was a disingenuous gimmick used to avoid a principled 
response to our remand.  (Indeed, as we have noted, it 

__________
     7  Given the apparent tension in our cases, a prudent counsel 
when in doubt should seek reconsideration before the Commission.



appears that the Commission took Time Warner's statement 
in its motion to expedite out of context.)  The truth is that 
parties often claim that drastic harm will occur when seeking 
expedited consideration.  But it is rather farfetched to inter-
pret such predictions as consent to their imposition.  In this 
case, we suspect petitioner was reflecting a natural fear that 
convincing the Commission to authorize cable operators to 
fully recover their past losses from consumers was a chancy 
proposition--at a minimum, that action is politically trouble-
some.  It appears to us that by seizing upon Time Warner's 
purported concession, the Commission avoided addressing the 
scope of relief question in an unfair way.  Cf. Illinois Public 
Telecommunications Ass'n v. FCC, 117 F.3d 555, 565-66 
(D.C. Cir. 1997) (rejecting FCC's argument that petitioner 
had abandoned its argument because the FCC had selectively 
quoted from petitioner's petition).  We do not look sympa-
thetically to the Commission playing "gotcha" either.  The 
Commission had an opportunity to pass on the question of 
whether operators should be allowed to recover their revenue 
deficiencies, but chose to duck--its failure to address the 
point was not an accidental mistake.

     Our view is different as to whether the Commission had a 
fair opportunity to consider Time Warner's argument that the 
Order on Remand unreasonably denied transition rate-based 
operators any recovery of their gap period external cost 
increases.  Petitioner does not claim that it or any party ever 
raised this argument to the Commission, arguing again that 
our decision in the first case put this issue before the Com-
mission.  While that may have been true as to the scope of 
relief argument, our opinion did not even recognize a distinc-
tion between full reduction rate-based and transition rate-
based operators, so it can hardly be said that our opinion put 
this second issue before the Commission.  Indeed, our opin-
ion only considered the problem as it affected the former 
class of operators.  Nor is this issue necessarily implicated by 
petitioner's more general argument.  As we noted above, 
supra note 2, Commission's counsel explains that transition 
rate-based operators' rates, set without reference to Septem-
ber 30, 1992, already reflect any external cost increases 



incurred during the gap period.  Time Warner objects that 
this is a "post-hoc explanation," and argues that transition 
rate operators do have a gap, albeit a different one.  But 
counsel's explanation is legitimate and persuasive as to why 
the Commission would not have thought this issue essential to 
resolving petitioner's more general complaint.  Unlike the 
scope of relief question, we do not perceive that here the 
Commission was trying to avoid a vexing problem.  It simply 
went unaddressed because the Commission apparently did 
not understand that it was an issue.  Time Warner therefore 
should have raised it to the Commission in a petition for 
reconsideration.

                                   * * * *


     We grant the petition with respect to the scope of relief 
question.  Because the Commission chose not to argue the 
merits in the alternative, we have no choice but to vacate the 
challenged portions of the order in so far as the Commission 
has not allowed full reduction rate operators to recover their 
revenue deficiencies.  The remainder of the petition is denied.

                                                                               So ordered.




     Randolph, Circuit Judge, concurring in part and dissent-
ing in part:  Time Warner's claim--that the Federal Com-
munications Commission should have allowed it to recoup 
external cost increases occurring during the so-called "gap" 
period--should not have been considered by this court.

     Not once during the administrative and judicial proceedings 
leading up to this case did Time Warner make that claim, or a 
single argument in support of it--not during the original 
rulemaking, not in its first petition for review in this court, 
not in its motion for expedited consideration, not in its briefs 
in this court, not during the Commission's proceedings on 
remand, and not in a petition for administrative reconsidera-
tion.  Our opinion in Time Warner Entertainment Co. v. 
FCC, 56 F.3d 151 (D.C. Cir. 1995), said nothing on the 
subject, and for good reason.  We usually do not pronounce 
on questions no one has presented.

     After we remanded the case, Time Warner could have 
placed its claim and its supporting arguments before the 
Commission.  Time Warner surely knew of the rules allowing 
this.  See 47 C.F.R. s 1.1206 (1995).  Yet during the ensuing 
eighteen months, while the case remained pending before the 
Commission, Time Warner chose to do nothing.  We have 
held time and again, in cases involving this and other adminis-
trative agencies, that if a party does not raise and argue an 
issue before the agency, the court will not consider it.  See, 
e.g., the cases cited below.  That "common law" or nonstatu-
tory rule of exhaustion, a rule we also apply on appeals from 
the district court, is enough to preclude Time Warner's claim 
in this court.  There is still another reason why we should not 
consider the claim.  Even after the Commission issued its 
Order on Remand, Time Warner could have filed a motion for 
reconsideration.  Again, it chose to remain silent.  Section 
405 of the Communications Act therefore stands as an addi-
tional bar to judicial review of Time Warner's recoupment 
claim.  In the words of s 405, 47 U.S.C. s 405, the Commis-
sion had "no opportunity to pass" upon the "legal questions" 
raised by arguments Time Warner is now making for the first 
time in this court.  Those legal arguments consist of analo-
gies to Commission decisions dealing with the "Exchange 



Network Facilities for Interstate Access," to decisions of the 
Federal Energy Regulatory Commission allowing gas pipe-
lines to impose retroactive surcharges, and so on.  To state 
the obvious, the Commission never had a chance to pass on 
Time Warner's legal arguments concerning the agency's re-
medial discretion because Time Warner never presented 
those arguments to the Commission.  "It is," we recently 
reiterated, "only through the adversarial process (or analo-
gous circumstances) that the Commission is afforded such an 
opportunity within the meaning of s 405."  Bartholdi Cable 
Co. v. FCC, 114 F.3d 274, 280 (D.C. Cir. 1997).  We also 
stressed that it is not up to the Commission to "sift pleadings 
and documents" in an effort to predict what might have been 
argued if the litigant had taken the trouble to present the 
claim.  Id. at 279;  see also, e.g., Russian River Vintage 
Broadcasting v. FCC, 5 F.3d 1518, 1521 (D.C. Cir. 1993).1

__________
     1  The majority is quite mistaken in supposing that s 405 ousts 
the judicially-imposed requirement that parties present their claims 
to the Commission before the agency decides the matter.  Maj. op. 
at 7 n.5.  Section 405 deals only with petitions for agency reconsid-
eration, which necessarily come after the Commission's decision.  
To read s 405 as the majority does sub silentio is to render it 
senseless:  parties would be free to hide their contentions, to say 
nothing while the proceedings wind their way to a final agency 
decision, and then, only after the decision comes down, spring their 
arguments on the Commission and march into court when the 
Commission refuses to consider them.  The courts of appeals do not 
allow anything of the sort.  New arguments--that is, arguments 
that could have been made but were not--may not be raised in 
petitions for rehearing.

     Section 405 thus does not deal with the question whether, in 
order to have claims considered on judicial review, parties must 
present those claims to the Commission before it renders its rule-
making or adjudicatory decision.  In light of this statutory gap, the 
federal courts may fill it by insisting that if parties fail to raise their 
claims prior to final agency action, those claims will not be consid-
ered on judicial review.  McCarthy v. Madigan, 503 U.S. 140, 144 
(1992), made this very point, adopting Justice White's statement in 
Patsy v. Board of Regents of Florida, 457 U.S. 496, 518 (1982) 
(concurring in part), that "exhaustion is a 'rule of judicial adminis-



     The majority refuses to follow this well-marked path.  In-
stead, it heads up a blind alley searching for a distinction 
between something called a "technical" defect and something 
described as a "policy" difference.  See maj. op. at 9-10.  As 
best I can make out, the majority thinks it has discovered a 
trend:  litigants trying to raise "technical" defects in court 
without having raised them before the Commission will lose, 
but litigants raising "policy" differences for the first time in 
court, without having presented their arguments to the Com-
mission, might just get away with it.2

     So far as I can tell, this technical-policy trend winds up 
playing no discernible role in the outcome.  Still, a few words 
about the majority's digression are in order.  For starters, 
the distinction lacks any coherent rationale.  The majority 
suggests that requiring a litigant to raise a procedural or 
"technical" point with the agency may allow the agency to 
correct its error before the case reaches the court.  See maj. 
op. at 9-10.  This is true, but it is also true about "policy" or 
"substantive" mistakes.  Besides, as any student of adminis-
trative law knows, allowing an agency the chance to correct 
its errors is only one of many reasons behind the raise-it-or-
waive-it rule.  For instance, the "exhaustion doctrine recog-
nizes the notion, grounded in deference to Congress' delega-
tion of authority to coordinate branches of Government, that 
agencies, not the courts, ought to have primary responsibility 
for the programs that Congress has charged them to adminis-
ter."  McCarthy v. Madigan, 503 U.S. 140, 145 (1992);  see, 
e.g., McKart v. United States, 395 U.S. 185, 192-95 (1969).  
"Exhaustion concerns," the Supreme Court added, "apply 
with particular force when the action under review involves 
exercise of the agency's discretionary power or when the 
agency proceedings in question allow the agency to apply its 
special expertise."  McCarthy, 503 U.S. at 145.  In its brief, 

__________
     tration,' ... and unless Congress directs otherwise, rightfully sub-
ject to crafting by judges."  Here, Congress has not directed 
otherwise.

     2  The majority suggests that exhaustion is entirely controlled 
by statute, see maj. op. at 7 n.5, and then contradicts itself by 
proposing a technical-policy distinction found in no statute.



Time Warner treats the Commission's authority to allow 
recoupment as a matter of agency "discretion" and so the 
Court's words in McCarthy should have had particular force 
here.  Of all things, remedial claims of the sort Time Warner 
raises in this court ought to be at the top of the list of items a 
litigant must first raise before the Commission.3

     It is therefore hardly surprising that careful attention to 
our decisions reveals that the majority's technical-policy line 
does not exist.  Take, for instance, Petroleum Communica-
tions, Inc. v. FCC, 22 F.3d 1164 (D.C. Cir. 1994), a case in 
which the petitioners claimed the Commission had failed to 
give notice and an opportunity to comment before promulgat-
ing a rule--a mere "technical defect" according to the majori-
ty.  See maj. op. at 10.  The majority seems to have forgotten 
the balance of the case.  The Petroleum Communications 
petitioners also argued that the rule had been applied in a 
discriminatory fashion.  See Petroleum Communications, 22 
F.3d at 1171.  Both claims were raised for the first time in 
the petition for review.  We refused to reach the merits of 
either issue for "substantially the same reasons," namely that 
"petitioners failed to exhaust their remedies ... by declining 
to bring [the alleged error] first before the Commission."  Id.  
To take another recent case, Freeman Engineering Associ-
ates, Inc. v. FCC, 103 F.3d 169, 182 (D.C. Cir. 1997), treated a 
so-called "technical defect" (petitioner argued that the Com-
mission failed to address certain record evidence) and an 

__________
     3 Darby v. Cisneros, 509 U.S. 137 (1993), cited by the majority in 
a footnote, see maj. op. at 7 n.5, has nothing to do with this case.  
Darby interpreted s 10(c) of the Administrative Procedure Act, 5 
U.S.C. s 706(2)(A), to mean that an "an appeal to 'superior agency 
authority' is a prerequisite to judicial review only when expressly 
required by statute or when an agency rule requires appeal before 
review and the administrative action is made inoperative pending 
that review."  509 U.S. at 154.  See Marine Mammal Conservancy, 
Inc. v. Department of Agric., 134 F.3d 409, 411 (D.C. Cir. 1998).  
No one is saying Time Warner should have, or could have, perfected 
an intra-agency appeal--the Commission rendered the decision 
under review and the Commission, of course, is the superior agency 
authority.



alleged substantive error (petitioner claimed the Commission 
treated him different than other similarly situated applicants) 
identically:  the court held that both claims were waived 
because petitioner failed to raise them first before the Com-
mission.  In Alianza Federal de Mercedes v. FCC, 539 F.2d 
732, 739 (D.C. Cir. 1976), we held that the Commission had 
not been given a "fair opportunity" to pass on petitioner's 
argument, raised for the first time before this court, that a 
television station's broadcast license should not have been 
renewed because it offered a minimal amount of public inter-
est programming devoted to minority community problems 
where minorities comprised 40% of the market.  In Washing-
ton Ass'n for Television & Children v. FCC, 712 F.2d 677, 
680-81 (D.C. Cir. 1983), we held that s 405 precluded our 
considering the challenge to the Commission's license renew-
als on the ground that the television stations had provided 
inadequate weekday programming for children.  In Illinois 
Bell Telephone Co. v. FCC, 988 F.2d 1254, 1264 n.12 (D.C. 
Cir. 1993), we invoked the exhaustion doctrine to refuse to 
pass on allegations that the Commission had been "impermis-
sibly inconsistent."  In Northwestern Indiana Telephone Co. 
v. FCC, 824 F.2d 1205, 1210 n.8 (D.C. Cir. 1989), we declined 
to reach the merits of petitioners' last minute argument that 
the Commission violated the First Amendment.  Petitioners, 
we held, could not "bypass statutory exhaustion require-
ments."  Id.  And in ASTV v. FCC, 46 F.3d 1173, 1177 (D.C. 
Cir. 1995), we refused to consider ASTV's argument that 
"wireless cable is a 'cable system' under the Act, because 
ASTV failed to raise it before the Commission"--surely a 
substantive, "policy" matter rather than what the majority 
would treat as a mere "technical" peccadillo.

     The majority ultimately comes to rest on grounds other 
than its technical-policy dichotomy.  The Commission loses 
because it was playing something called "gotcha," it was 
"unfair," its view of the matter was "farfetched," it relied on a 
"disingenuous gimmick."  Maj. op. at 11-12.  All this excite-
ment is directed at a footnote in the Commission's decision on 
remand.  The footnote quoted a Time Warner motion conced-
ing that cable operators could not recoup the losses they were 



incurring even if "they ultimately succeed in persuading this 
Court to rule in their favor," Memorandum of Law of Time 
Warner Entertainment Company, L.P. in Support of Its 
Emergency Motion for Expedited Consideration, at pp. 17-18.  
That concession directly contradicts Time Warner's current 
position.  The Commission rightly took the statement in 
context:  Time Warner was referring to the effect of delaying 
review of the entire "rate-regulation rulemaking."   Id. at 17.  
"The truth is," according to the majority, "that parties often 
claim that drastic harm will occur when seeking expedited 
consideration."  Maj. op. at 12.  Maybe so, but that misses 
the point.  If Time Warner believed that it was entitled to 
recoup its losses, if the company thought the question was 
still open despite what it told this court, it was incumbent 
upon Time Warner to make its views known to the Commis-
sion.  It had ample opportunity to do so, not only while the 
matter was pending before the agency on remand, but also 
after the Commission handed down its decision.  Time War-
ner nevertheless remained mute.

     Pure and simple, the majority has offered no good reason 
for rejecting the Commission's determination not to decide a 
legal claim Time Warner neither raised nor supported with 
pertinent authorities.  If "gotcha" and "disingenuous gim-
mick" are meant to embody a legal principle, I confess--the 
principle eludes me.  I therefore dissent from this portion of 
the majority opinion.