Combined Opinion
                                                                  F I L E D
                                                           United States Court of Appeals
                                                                   Tenth Circuit
                                    PUBLISH
                                                                 March 28, 2006
                 UNITED STATES COURT OF APPEALS
                                                               Elisabeth A. Shumaker
                                                                   Clerk of Court
                               TENTH CIRCUIT



TROUT UNLIMITED; COLORADO
TROUT UNLIMITED; RONALD W.
ALBERT,

            Plaintiffs-Appellees-
            Cross-Appellants,

v.

UNITED STATES DEPARTMENT
OF AGRICULTURE; USDA FOREST
SERVICE; DAN GLICKMAN; JACK                   Nos. 04-1317, 04-1346
WARD THOMAS, Chief, United
States Forest Service; JAMES R.
LYONS, Under Secretary for Natural
Resources and Conversation, U.S.
Department of Agriculture;
ELIZABETH ESTILL, Regional
Forester, Rocky Mountain Region,
U.S. Forest Service; M. M.
UNDERWOOD, Forest Supervisor,
Arapaho and Roosevelt National
Forests,

            Defendants-
            Cross-Appellees,

and

THE WATER SUPPLY AND
STORAGE COMPANY, a
Colorado nonprofit corporation;
CITY OF GREELEY, a Colorado
municipal corporation; CITY OF
GREELEY WATER AND SEWER
BOARD; COLORADO WATER
CONSERVATION BOARD;
COLORADO STATE ENGINEER,

              Defendants-Intervenors-
              Appellants-Cross-
               Appellees,

------------------------------------

STATE OF IDAHO; STATE OF
NEVADA; STATE OF NORTH
DAKOTA; STATE OF UTAH; STATE
OF WYOMING; SOUTHEASTERN
COLORADO WATER
CONSERVANCY DISTRICT;
COLORADO FARM BUREAU;
NORTHERN COLORADO WATER
CONSERVANCY DISTRICT; UPPER
ARKANSAS WATER
CONSERVANCY DISTRICT;
SOUTHWESTERN CONSERVATION
DISTRICT; RIO GRANDE WATER
CONSERVATION DISTRICT;
BUILDING INDUSTRY
ASSOCIATION OF WASHINGT0N;
WASHINGTON STATE FARM
BUREAU; WASHINGTON STATE
GRANGE; IDAHO FARM BUREAU
FEDERATION; EARLY WINTERS
DITCH COMPANY, INC.; PACIFIC
LEGAL FOUNDATION,

       Amici Curiae.




                                        -2-
                 Appeal from the United States District Court
                         for the District of Colorado
                         (D.C. No. 96-WY-2686-WD)


Carol D. Angel, First Assistant Attorney General, Colorado State Attorney
General’s Office (Ken Salazar, Attorney General, Alan Gilbert, Solicitor General,
Peter J. Ampe, Assistant Attorney General, Colorado State Attorney General’s
Office with her on the briefs, and John W. Suthers, Attorney General and Allison
Eid, Solicitor General, with her on the reply brief), Denver, Colorado, for
Defendant-Intervenor-Appellant-Cross-Appellee Colorado State Engineer and
Colorado Water Conservation Board.

William R. Fischer, Fischer, Brown & Gunn, P.C., Fort Collins, Colorado (James
S. Witwer, Trout, Raley, Montano, Witwer & Freeman, P.C., Denver, Colorado,
John A. Kolanz, Assistant City Attorney, Greeley City Attorney’s Office, Greeley,
Colorado, with him on the brief for Defendants-Intervenors-Appellants-Cross-
Appellees The City of Greeley and Greeley Water and Sewer Board), for
Defendant-Intervenor-Appellant-Cross-Appellee The Water Supply and Storage
Company.

Michael K. Murphy, Of Counsel, Gibson, Dunn & Crutcher, LLP, Washington,
D.C. (Christopher H. Buckley, Jr., Of Counsel, Gibson, Dunn & Crutcher, LLP,
Washington, D.C., J. Gregory Whitehair, Robert C. Marshall, Gibson, Dunn &
Crutcher, LLP, Denver, Colorado, with him on the briefs) for Plaintiffs-
Appellees-Cross-Appellants Trout Unlimited, Colorado Trout Unlimited and
Ronald W. Albert.

Ellen J. Durkee, United States Department of Justice, Washington, D.C. (Kelly A.
Johnson, Acting Assistant Attorney General, Environment & Natural Resources
Division, David W. Gehlert, Todd Aagaard, Robert H. Oakley, U.S. Department
of Justice, Washington, D.C., Lois Witte, Of Counsel, Office of the General
Counsel, Department of Agriculture, Denver, Colorado, with her on the briefs) for
Defendants-Cross-Appellees.

Lawrence G. Wasden, Attorney General, Clive J. Strong, Chief, Natural
Resources Division, Clay R. Smith, Deputy Attorneys General, Boise, Idaho, for

                                       -3-
State of Idaho, Brian Sandoval, Attorney General, Carson City, Nevada, for State
of Nevada, Wayne Stenehjem, Attorney General, Bismarck, North Dakota, for
State of North Dakota, Larry Long, Attorney General, Pierre, South Dakota, for
State of South Dakota, Mark Shurtleff, Attorney General, Salt Lake City, Utah,
for State of Utah, Patrick J. Crank, Attorney General, Cheyenne, Wyoming, for
State of Wyoming, filed a combined amici curiae brief.

Robin L. Rivett, Pacific Legal Foundation, Sacramento California, Russell C.
Brooks, Pacific Legal Foundation, Bellevue, Washington, filed an amici curiae
brief on behalf of Building Industry Association of Washington, Washington State
Farm Bureau, Washington State Grange, Idaho Farm Bureau Federation, Early
Winters Ditch Company and Pacific Legal Foundation.

Lee E. Miller, Alix L. Joseph, Burns, Figa & Will, P.C., Englewood, Colorado,
for Southeastern Colorado Water Conservancy District and Colorado Farm
Bureau, Robert V. Trout, Trout, Witwer & Freeman, P.C., Denver, Colorado, for
Northern Colorado Water Conservancy District, Julianne M. Woldridge,
MacDougall, Woldridge & Worley, P.C., Colorado Springs, Colorado, for Upper
Arkansas Water Conservancy District, David W. Robbins, Hill & Robbins, P.C.,
Denver, Colorado, for Southwestern Water Conservation District and Rio Grande
Water Conservation District, filed a combined amici curiae brief.


Before MURPHY, ANDERSON and O’BRIEN, Circuit Judges.


MURPHY, Circuit Judge.


I.    INTRODUCTION

      After conducting an environmental review, the United States Forest Service

issued a special-use permit authorizing the Water Supply and Storage Co.

(“WSSC”) to store water on certain National Forest lands underlying the Long

Draw Reservoir west of Fort Collins, Colorado. The United States District Court

for the District of Colorado determined the Forest Service’s decision violated the

                                        -4-
Federal Land Policy and Management Act (“FLPMA”). The district court

reversed and remanded the Forest Service’s decision. WSSC, the City of Greeley,

the Greeley Water and Sewer Board, the State Engineer of the State of Colorado,

and the Colorado Water Conservation Board seek review of the district court’s

order. Because this court lacks jurisdiction, we dismiss the appeal.

II.   BACKGROUND

      Long Draw Reservoir is a water storage facility in the Roosevelt National

Forest. It is located on La Poudre Pass Creek, a tributary of the Cache La Poudre

River. The original reservoir was formed following completion of the Long Draw

Dam in 1929. Almost thirty years later, the reservoir was expanded. The

expansion inundated an additional 390 acres of National Forest land.

      WSSC holds an easement which permits it to store water on National Forest

land flooded by the original Long Draw Reservoir. It has no comparable

easement, however, on the additional 390 acres of National Forest land that was

submerged when Long Draw Reservoir was expanded. WSSC’s authority to store

water on this additional land stems from special-use permits issued by the Forest

Service.

      The Forest Service first authorized WSSC to operate and maintain the

expanded Long Draw Reservoir in 1980. The agency amended the permit a year

later, extending its terms until December 31, 1991. The amended permit noted


                                        -5-
future permits would be subject to conditions imposed by the Forest Service. In

1991 and thereafter, the agency further extended the term of the permit to allow it

time to analyze potential environmental impacts associated with renewing

WSSC’s authorization to store water on National Forest land.

      The upper Cache La Poudre drainage provides habitat for a variety of fish

species, and water from La Poudre Pass Creek is vital to several threatened and

endangered species. Typically, however, WSSC releases no water from Long

Draw Reservoir to La Poudre Pass Creek between November and March or April.

As a result, La Poudre Pass Creek between the Long Draw Dam and the

confluence with the Cache La Poudre River is effectively dry during the winter

months. The Forest Service has concluded lack of winter flow causes a nearly

complete loss of aquatic habitat in some locations and may preclude the

maintenance of self-sustaining fish populations in La Poudre Pass Creek below

Long Draw Reservoir.

      In 1993, the Forest Service issued a Draft Environmental Impact Statement

(“DEIS”) on permit renewal for Long Draw Reservoir. The DEIS identified four

alternatives. Alternative B, the Forest Service’s proposed action, suggested

issuing a special-use permit to WSSC with the understanding that WSSC would

voluntarily commit to operating Long Draw Reservoir in accordance with a joint

operating plan (“JOP”) submitted by WSSC and the cities of Fort Collins and


                                         -6-
Greeley, Colorado. The JOP purported to provide for additional winter flows to

the Cache La Poudre River, but did not provide for winter flow in La Poudre Pass

Creek. Alternative C, the “Environmentally Preferred Alternative,” proposed

issuing the special-use permit with a “bypass flow” requirement. The bypass flow

requirement would compel WSSC to release water from Long Draw Reservoir

during the winter months in order to maintain minimum flows in La Poudre Pass

Creek.

      The Region VIII Administrator for the Environmental Protection Agency,

the Acting Superintendent of Rocky Mountain National Park, and the Forest

Service’s own interdisciplinary team urged the Forest Service to impose a bypass

flow requirement when it issued the Long Draw Reservoir permit. Nevertheless,

the agency granted WSSC its land use authorization without a bypass flow

requirement. Instead, the agency conditioned the permit upon WSSC’s

participation in a revised version of the JOP. Six months after the Forest Service

issued its decision, it executed a fifty-year water facility easement to WSSC for

the use and operation of Long Draw Dam and the expanded reservoir.

      Following an unsuccessful administrative appeal, Trout Unlimited (“TU”)

challenged the Forest Service’s decision in federal court and moved for summary

judgment. WSSC, the City of Greeley, the Greeley Water and Sewer Board, the

State Engineer of the State of Colorado, and the Colorado Water Conservation


                                         -7-
Board intervened as defendants. The district court dismissed or denied all but one

of TU’s claims for relief. It granted summary judgment, however, on TU’s claim

that the Forest Service’s issuance of the Long Draw permit violated FLPMA. The

court reversed the Forest Service’s decision and remanded the matter to the

agency “for further consideration in accordance with its obligations under

FLPMA.” Trout Unlimited v. U.S. Dep’t of Agric., 320 F. Supp. 2d 1090,

1115–16 (D. Colo. 2004).

      Defendant-Intervenors appeal the district court’s decision. They assert the

Forest Service lacks authority to impose bypass flow requirements as a condition

of permit issuance and claim the district court erred in granting summary

judgment to TU. TU cross-appeals, raising claims under the National Forest

Management Act (“NFMA”) and the National Environmental Policy Act

(“NEPA”).

      In addition to the merits issues, the parties have submitted three motions

for this court’s consideration. First, the Forest Service, with the support of TU,

moves to dismiss for lack of appellate jurisdiction. Second, Defendant-

Intervenors move to certify questions of state law. Third, Washington

Agricultural Legal Foundation, Washington State Potato Commission,

Washington State Dairy Federation, and New Mexico Cattle Growers Association

(collectively Washington Agricultural) move for leave to submit an amicus brief.


                                         -8-
III.   ANALYSIS

       Before addressing the substance of the parties’ claims, this court must first

resolve the jurisdictional issue raised by the Forest Service in its motion to

dismiss. See In re Universal Serv. Fund Tel. Billing Practice Litig., 428 F.3d

940, 942 (10th Cir. 2005) (noting this court’s “first responsibility is to determine

whether [it has] jurisdiction”). The Forest Service claims the district court’s

decision that the Long Draw permit violated FLPMA is not a final, appealable

order because the court remanded the matter for further consideration by the

agency. Defendant-Intervenors, on the other hand, contend appellate jurisdiction

is appropriate under § 1291 whenever a case raises an important issue of

federalism. They allege jurisdiction is proper in this case because the district

court’s order raises an important question of federalism by “sow[ing] great

uncertainty and eviscerat[ing] the traditional state power over . . . water allocation

systems.” Defendant-Intervenors’ Resp. to Mot. to Dismiss at 9.

       This court has jurisdiction over final decisions of the federal district courts

pursuant to 28 U.S.C. § 1291. Jurisdiction under § 1291 generally is contingent

upon “the existence of a decision by the District Court that ends the litigation on

the merits and leaves nothing for the court to do but execute the judgment.”

Coopers & Lybrand v. Livesay, 437 U.S. 463, 467 (1978) (quotations omitted).

Under § 1291, “remand by a district court to an administrative agency for further


                                          -9-
proceedings is ordinarily not appealable because it is not a final decision.”

Bender v. Clark, 744 F.2d 1424, 1426–27 (10th Cir. 1984). Nonetheless, this

court has recognized that the “administrative-remand rule” is not without

exception. Baca-Prieto v. Guigni, 95 F.3d 1006, 1008 (10th Cir. 1996).

         In the context of a district court order remanding a matter to an

administrative agency, jurisdiction may be appropriate when the issue presented is

both urgent and important. Bender, 744 F.2d at 1427. If these two conditions are

met, this court will apply a balancing test and assert jurisdiction if “the danger of

injustice by delaying appellate review outweighs the inconvenience and costs of

piecemeal review.” Id.; see also Cotton Petroleum Corp. v. U.S. Dep’t of

Interior, 870 F.2d 1515, 1522 (10th Cir. 1989). This court has warned, however,

that Bender and Cotton Petroleum “must be narrowly construed . . . to preserve

the vitality of § 1291.” Boughton v. Cotter Corp., 10 F.3d 746, 752 (10th Cir.

1993).

         In Bender, this court applied the exception to the administrative-remand

rule when we determined the case involved a “serious and unsettled” question

regarding federal oil and gas leasing and was urgent because refusal to assert

jurisdiction might have foreclosed future appellate review of the issue at later

stages in the proceeding. Id. at 1428; see also id. at 1428 n.3 (stating both

urgency and importance elements contributed to the court’s determination that it


                                           -10-
had jurisdiction to hear the appeal). In fact, we noted the possibility of injustice

due to delay was “perhaps [the] most important” factor in our jurisdictional

calculus. Id. at 1428. 1 Likewise, when this court applied the exception to the

administrative-remand rule in Cotton Petroleum, we did not rely solely on the

importance of the issue presented when we resolved the jurisdictional question.

Instead, this court stated explicitly that jurisdiction was appropriate because

“delay in review . . . would likely result in further disputes and litigation,

confusion and danger of injustice.” Cotton Petroleum, 870 F.2d at 1522.

      Defendant-Intervenors make the conclusory allegation that delaying

appellate review of the district court’s Long Draw decision will “result in

uncertainty, additional litigation, confusion and a very real danger of injustice.”

Defendant-Intervenors’ Resp. to Mot. to Dismiss at 11. They offer no support for

this statement, however, and we can discern no reason why this case requires

urgent or immediate judicial consideration. In this case, delayed review will not



      1
        We recognize Bender cites Paluso v. Matthews, 573 F.2d 4, 8 (10th Cir.
1978), for the proposition that an “important issue of federalism alone [is] enough
to tip the scale in favor of immediate review.” Bender v. Clark, 744 F.2d 1424,
1428 (10th Cir. 1984). This dictum, however, does not change our analysis.
Paluso itself recognized that denial of justice due to delay was necessary for this
court to exercise its jurisdiction over a district court’s remand to an administrative
agency. See 573 F.2d at 8. In that case, the court resolved the jurisdictional
question by “balancing the inconvenience and costs that accompany piecemeal
reviews, on the one hand, and the danger of denying justice by delay, on the other
hand.” Id. (emphasis added).

                                         -11-
result in injustice. Defendant-Intervenors do not claim the Forest Service will

require implementation of bypass flows during the remand process. 2 If the Forest

Service’s decision on remand is not satisfactory, Defendant-Intervenors can

pursue administrative remedies and, if necessary, seek review in the district and

appellate courts at a later stage in the proceedings. Finally, Defendant-

Intervenors have not supported their bare assertion that delay in judicial review

has resulted in, or will result in, additional disputes and litigation.

      In sum, this case does not fall within the narrow exception to the

administrative-remand rule. Although the issues presented may be important, the

need for judicial review is not urgent. 3 Accordingly, this court lacks jurisdiction

to hear the appeal.

IV.   CONCLUSION




      2
       Defendant-Intervenors contend postponed review will result in cost, delay,
and uncertainty during the remand process. These inconveniences, however, do
not create appellate jurisdiction where it does not otherwise exist. See Boughton
v. Cotter Corp., 10 F.3d 746, 752 (10th Cir. 1993) (noting that while the “rules of
appealability” may sometimes add time or expense to the litigation process, they
have “the great virtue of forestalling the delay, harassment, expense, and
duplication that could result from multiple or ill-timed appeals” (quotation
omitted)).
      3
       Because we conclude at the outset that appellate review is not urgent, there
is no need to balance “the danger of injustice by delaying appellate review”
against “the inconvenience and costs of piecemeal review.” Bender, 744 F.2d at
1427.

                                          -12-
      For the reasons stated above, Defendant-Appellee’s motion to dismiss is

granted. Defendant-Intervenors’ appeal and TU’s cross-appeal are dismissed for

lack of jurisdiction. Because this court does not have jurisdiction over the issues

raised in Defendant-Intervenors’ motion to certify questions of state law, that

motion is dismissed as moot. Similarly, because we lack jurisdiction over the

issues raised in its proposed amicus brief, Washington Agricultural’s motion for

leave to file an amicus brief is dismissed as moot.