Legal Research AI

Union Pacific Fuels, Inc. v. Federal Energy Regulatory Commission

Court: Court of Appeals for the D.C. Circuit
Date filed: 1997-11-07
Citations: 129 F.3d 157, 327 U.S. App. D.C. 74
Copy Citations
18 Citing Cases

                        United States Court of Appeals


                     FOR THE DISTRICT OF COLUMBIA CIRCUIT


           Argued September 30, 1997     Decided November 7, 1997 


                                 No. 93-1463


                     Union Pacific Fuels, Inc., et al., 

                                 Petitioners


                                      v.


                    Federal Energy Regulatory Commission, 

                                  Respondent


                   Transwestern Pipeline Company, et al., 

                                 Intervenors


                              Consolidated with

                   Nos. 93-1505, 93-1595, 93-1601, 93-1603


                  On Petitions for Review of Orders of the 

                     Federal Energy Regulatory Commission


     Katherine B. Edwards argued the cause for petitioners, 
with whom Nancy J. Skancke, Donald Ayer and Norman A. 



Pedersen were on the briefs.  Kerry R. Brittain entered an 
appearance.

     Susan Court, Special Counsel, Federal Energy Regulatory 
Commission, argued the cause for respondent, with whom 
Jay L. Witkin, Solicitor, John H. Conway, Deputy Solicitor, 
and Eric Lee Christensen, Attorney, were on the brief.

     Jeffrey D. Komarow, Michael J. Thompson, Paul M. 
Flynn and Mark C. Moench were on the brief for intervenor 
Kern River Gas Transmission Company.

     Before:  Edwards, Chief Judge, Ginsburg and Tatel, 
Circuit Judges.

     Opinion for the Court filed by Chief Judge Edwards.

     Edwards, Chief Judge:  In January 1990, the Federal Ener-
gy Regulatory Commission ("FERC") approved the construc-
tion of a pipeline by Kern River Gas Transmission Company 
("Kern River") that would transport natural gas from the 
Wyoming "Overthrust Region" to California.  Kern River 
negotiated long term contracts with purchasers of its trans-
portation services ("shippers") using the rate structure pre-
vailing in the industry at the time.  The rate structure in the 
gas pipeline industry passes on pipeline costs to shippers in 
two components:  a reservation charge covering fixed costs, 
and a usage charge covering variable costs.  Under "straight 
fixed/variable" rating (hereinafter "straight f/v"), all fixed 
costs are assigned to the reservation charge, which does not 
vary with use, and all variable costs are assigned to the usage 
charge, which does.  Under "modified fixed/variable" rating 
(hereinafter "modified f/v"), some of the fixed costs are 
assigned to the reservation charge, but some of the fixed 
costs, including return on equity and income taxes, are as-
signed to the usage charge along with all the variable costs.  
In 1990, modified f/v prevailed in the pipeline industry;  Kern 
River's contracts with its shippers used modified f/v.

     In 1993, implementing Congress' gradual deregulation of 
the natural gas industry, FERC issued its landmark Order 



No. 636,1 which changed the basic rate structure in the gas 
pipeline industry from modified f/v to straight f/v in order to 
enhance competition between gas producers.  In two succes-
sive subsequent orders, FERC required Kern River to re-
place the modified f/v rate design for which it had contracted 
with straight f/v.  Kern River Gas Transmission Company, 
Docket No. RS92-65-000, et al.:  "Order on Compliance with 
Restructuring Rule," issued March 2, 1993, 62 FERC (CCH) 
p 61,191;  "Order Accepting Revised Compliance Filing, Deny-
ing Rehearing and Granting Clarification," issued July 9, 
1993, 64 FERC (CCH) p 61,049 (collectively, "Kern River 
orders").  Petitioners, shippers who contracted with Kern 
River to use its transportation services, challenge the rate 
change on the grounds that it arbitrarily and unjustifiably 
reallocates risk away from Kern River and onto them, and on 
the grounds that FERC may not abrogate existing contracts 
unless imperatively demanded by the public interest.

     We deny the petition for review.  The Kern River orders 
do not abrogate the parties' contracts, but rather alter some 
of their terms in a permissible manner anticipated by the 
contracts themselves.  While the orders do reallocate risk at 
the expense of Petitioners, FERC articulated a rational, non-
arbitrary policy basis for its decision.

                                I. Background


     FERC authorized construction of the Kern River pipeline 
to transport gas from the Wyoming "Overthrust Region" to 
California under special "Optional Certificate" procedures 
authorized by the Natural Gas Act ("NGA") s 7, 15 U.S.C. 
s 717f.  See Kern River Gas Transmission Co., 50 FERC 

__________
     1  Order No. 636, Pipeline Service Obligations and Revisions to 
Regulations Governing Self-Implementing Transportation Under 
Part 284 of the Commission's Regulations, and Regulation of Natu-
ral Gas Pipelines After Partial Wellhead Decontrol, III F.E.R.C. 
Stats. & Regs. (CCH) p 30,939, order on reh'g, Order No. 636-A, 
F.E.R.C. Stats. & Regs. (CCH) p 30,950, order on reh'g, Order No. 
636-B, 61 F.E.R.C. p 61,272 (1992), reh'g denied, 62 F.E.R.C. 
p 61,007 (1993).



p 61,069 (1990).  These Optional Certificate procedures allow 
a pipeline builder to forgo a lengthy showing of a pipeline's 
usefulness and necessity when the builder assumes the eco-
nomic risks associated with undertaking the project.  Kern 
River negotiated contracts of various terms with Petitioners 
for a total of 98% of its capacity for fifteen years using the 
modified f/v rate that prevailed at the time.  Joint Initial 
Brief of Petitioners 21.

     Each contract contained a "Memphis clause," so named for 
United Gas Pipe Line Co. v. Memphis Light, Gas and Water 
Div., 358 U.S. 103 (1958).  The Memphis clause specified that 
"rates, charges, classifications and service" were subject to 
FERC regulation, and allowed Kern River to request and 
implement rate changes.  Joint Appendix ("J.A.") 113-14.  
Two of the contracts, those between Kern River and Petition-
ers Mobil Exploration & Production U.S., Inc. ("Mobil") and 
Union Pacific Fuels, Inc. ("Union Pacific") expressly guaran-
teed that Kern River would not, without consent, "seek to 
change ... the modified fixed variable rate design."  J.A. 28, 
33.  The other contracts guaranteed what the parties call 
"most favored nations" status, under which purchasers would 
receive a rate as good as the most favorable rate negotiated 
by any other party.  The contracts, negotiated at arm's 
length, functioned in part as an allocation of risk between 
Kern River and Petitioners.  The more of the fixed cost paid 
in reservation fees by Petitioners, purchasers of transporta-
tion services, the greater the percentage of risk assumed by 
them.

     In 1992, FERC adopted Order No. 636, which effected a 
variety of changes in the natural gas market.  For purposes 
of this case, the significant aspect of Order No. 636 was its 
alteration of the required rate design from modified f/v to 
straight f/v.  See 18 C.F.R. s 284.8(d).  This court upheld the 
rate design change in United Distrib. Cos. v. F.E.R.C., 88 
F.3d 1105, 1161-76 (1996) (per curiam), cert. denied 117 S. Ct. 
1723 (1997).  FERC intended the rate change to facilitate the 
creation of a competitive, national gas market.  Gas from 
different producers is carried on different pipelines, each of 
which has different fixed costs.  When pipelines use modified 
f/v, the price paid by the purchaser varies depending on the 
fixed costs associated with the particular pipeline.  When 



pipelines use straight f/v, the price to the customer more 
closely reflects the incremental cost of producing and trans-
porting the gas, and thus, in FERC's view, will lead to a 
more competitive and efficient market.  See Order No. 636, 
III F.E.R.C. Stats. & Regs. at 30,434.

     In August 1992, after Order No. 636 took effect, Kern 
River applied to FERC to adopt straight f/v rate design for 
all of its shippers except Mobil and Union Pacific.  J.A. 1. 
FERC responded by requiring straight f/v for all Kern 
River's shippers.  62 FERC at 62,262.  Various parties, 
including Petitioners, filed for rehearing;  Kern River asked 
for further clarification.  In its second Kern River order, 
FERC concluded once more that straight f/v should be re-
quired for all customers.  64 FERC at 61,406.  Although 
Order No. 636 permits exceptions to the straight f/v policy, 
FERC refused to make an exception for Kern River.  It 
reasoned that the modified f/v rate design would artificially 
inflate the usage charges upon which gas purchasers base 
their buying decisions.  This would distort the market in 
natural gas by creating an incentive for end purchasers to 
buy gas transported through straight f/v pipelines.  62 FERC 
at 62,257-58;  64 FERC at 61,407-08.

     This challenge followed.  The gravamen of Petitioners' 
complaint is that modified f/v places the risk of the pipeline's 
failure primarily on the pipeline owner, while straight f/v 
spreads this risk by assigning virtually all the fixed costs to 
shippers such as Petitioners, who pay reservation charges to 
guarantee themselves pipeline capacity.  If, as here, the 
shippers reserve nearly all of a pipeline's capacity for a given 
period, a pipeline using straight f/v rate design will recover 
its fixed costs during that period irrespective of how much 
capacity the shippers actually use.  In other words, although 
Order No. 636 aimed to rationalize pricing of natural gas for 
end purchasers, implementing straight f/v in this case had a 
coincidental, different effect:  it altered the original risk allo-
cation for which the parties contracted, placing a higher 
burden on the shippers and reducing significantly the burden 
on Kern River.  Petitioners seek to escape this alteration in 



risk allocation that will bind them for the length of the 
contracts.

                                 II. Analysis


A. Standard of Review

     We review FERC orders under the arbitrary and capri-
cious standard of 5 U.S.C. s 706(2)(A).  City of Seattle v. 
F.E.R.C., 883 F.2d 1084, 1087 (D.C. Cir. 1989).  Petitioners 
argue that the orders here must also satisfy the higher 
Mobile-Sierra standard.  See United Gas Pipe Line Co. v. 
Mobile Gas Corp., 350 U.S. 332 (1956);  FPC v. Sierra Pacific 
Power Co., 350 U.S. 348 (1956).  Mobile-Sierra doctrine 
construes FERC's authority under NGA s 5 to order just 
and reasonable rates where FERC has found existing rates 
unjust and unreasonable.  15 U.S.C. s 717d.  Under Mobile-
Sierra, FERC may exercise this rate-making authority to 
abrogate existing contracts only where the public interest 
"imperatively demands" such action.  Metropolitan Edison 
Co. v. F.E.R.C., 595 F.2d 851, 856 n.29 (D.C. Cir. 1979).

     Whether Mobile-Sierra doctrine applies is a question of 
contract interpretation:

     The rule of Sierra, Mobile, and Memphis is refreshingly 
     simple:  The contract between the parties governs the 
     legality of the filing.  Rate filings consistent with con-
     tractual obligations are valid;  rate filings inconsistent 
     with contractual obligations are invalid.

Richmond Power & Light v. F.P.C., 481 F.2d 490, 493 (D.C. 
Cir. 1973).  Mobile-Sierra applies only where FERC abro-
gates private contracts that do not contemplate FERC re-
form.  Mississippi Indus. v. F.E.R.C., 808 F.2d 1525, 1551-52 
(D.C. Cir. 1987), cert. denied, 494 U.S. 1078 (1990).  A 
contract between private parties may preserve FERC's right 
to impose new rates by "leav[ing] unaffected the power of the 
Commission ... to replace not only rates that are contrary to 
the public interest but also rates that are unjust [or] unrea-
sonable."  Papago Tribal Util. Auth. v. F.E.R.C., 723 F.2d 
950, 953 (D.C. Cir. 1983).  Alternatively, parties may contract 
to permit their own rate changes subject to FERC review, or 



may contract in such a way as to invoke Mobile-Sierra and 
thereby restrict FERC's ratemaking power to replacing rates 
contrary to the public interest.  Id.

     The contracts between Kern River and Petitioners antici-
pated rate changes by FERC, and thus Mobile-Sierra doc-
trine does not apply.  The contracts were of the type that 
permitted FERC changes of unjust and unreasonable rates in 
addition to those contrary to the public interest.  See id.  All 
of the disputed contracts included Memphis clauses acknowl-
edging FERC regulation of rates and permitting Kern River 
to request rate changes from FERC.  The contracts provided 
for the possibility of rate changes in other ways, as well.  For 
example, the Mobil and Union Pacific contracts provided that 
if FERC ordered rate changes raising Kern River's costs, 
Kern River could pass on some of those costs.  64 FERC at 
61,412 n.49.  The contracts with the other Petitioners guaran-
teed the shippers rates as good as those offered to any other 
shipper.

     Kern River's contracts with Mobil and Union Pacific includ-
ed an additional clause providing that neither party shall 
"seek to change ... the modified fixed variable rate design."  
This language simply prohibited the parties from requesting 
from FERC, pursuant to NGA s 4, a change away from 
modified f/v.  Nothing in the contracts expressly exempted 
the private agreement from rate changes initiated by FERC 
under NGA s 5.  The parties could have, but did not adopt 
language that expressly limited FERC's right to change 
modified f/v to the public interest standard required by 
Mobile-Sierra.  See Papago, 723 F.2d at 953.  For example, 
the contracts could have stated expressly that modified f/v 
would apply unless FERC determined that it was not in the 
public interest.  While Petitioners protest that boilerplate 
language acknowledging rate changes by FERC should not 
render Mobile-Sierra doctrine inapplicable, and that the con-
tracts implicitly anticipated use of modified f/v, they do not 
explain why they could not have adopted language that would 
simply and clearly have invoked Mobile-Sierra.  Cf. North-



east Util. Serv. Co. v. FERC, 993 F.2d 937, 960 (1st Cir. 1993) 
(contract provided that "the FERC shall not change the rate 
charged under this Agreement unless such rate is found to be 
contrary to the public interest").  Because Mobile-Sierra 
doctrine did not apply to these contracts, FERC did not have 
to show that public interest demanded straight f/v in this 
case.

B. Alleged Arbitrariness of Risk Reallocation

     Petitioners challenge the rate change on the theory that, as 
shippers, they entered long term, modified f/v contracts in 
reliance on Optional Certificate procedures under NGA s 7, 
and that the switch to straight f/v arbitrarily altered the 
carefully negotiated risk allocation embodied in those con-
tracts.  They claim that FERC did not provide a reasoned 
explanation for its change, and that Kern River has reaped 
unearned benefits by the lessening of its share of the econom-
ic risk of the pipeline.

     In an order granting an Optional Certificate to one of Kern 
River's competitors, FERC stated:

     Although we cannot bind the actions of future Commis-
     sions, it is our intent that the negotiated rate design 
     would not be subject to change in a future section 4 or 
     section 5 rate proceeding, either by the applicant or by 
     the Commission, because that rate design reflects the 
     assessment of risk agreed to by the parties in order to 
     construct the project.

45 FERC p 61,234, 61,678 (1988).  In the first Kern River 
order, FERC acknowledged that "the intent and anticipation 
of the Commission's original order issuing the Kern River 
[optional] certificates was to be consistent with [this lan-
guage]."  62 FERC at 62,257.

     Petitioners and Kern River probably did intend to negoti-
ate risk allocation when they entered the long term contracts 
at issue here.  It is also likely that they did not specifically 
anticipate FERC Order No. 636 and the resulting change 
from modified f/v, on which they relied, to straight f/v.  Kern 
River may well have incurred some unexpected benefits as a 
result of the change, as Petitioners have incurred unexpected 



costs.  Kern River now shoulders less of the risk of the 
pipeline, since it can recover return on equity and taxes 
through reservation charges, which it could not do under the 
original contracts;  Petitioners now shoulder more of the risk.

     Even assuming the correctness of all Petitioners' factual 
claims, however, it does not follow that FERC's orders were 
arbitrary and capricious.  This case presents a paradigmatic 
example of an agency reasonably changing its policies, and 
implementing the consequences of those changes to the detri-
ment of some parties and the benefit of others.  Policy 
changes sometimes have distributive effects that may appear 
arbitrary from the perspective of their corporate victims, but 
in fact proceed logically from the reasoned premises underly-
ing the changes.  The policy changes may even have the 
effect of unsettling other policies that the agency has pursued 
or continues to pursue;  but this is occasionally inevitable 
given the complexity of economic relations and administrative 
intervention.  The problem of unsettling existing agency poli-
cies counsels caution, but does not bar policy changes.  By 
formulating its policy in a reasoned fashion, FERC acted in a 
non-arbitrary manner;  by justifying its decision to apply 
straight f/v to Kern River on the basis of promoting market 
efficiency, FERC satisfied its burden of providing reasoned 
explanation for its change in policy.

     FERC's formulation and structuring of its policies from the 
outset acknowledged the possibility of policy change.  
FERC's statement of its future intent, supra, began with the 
caveat that FERC, like a legislature, cannot bind itself with 
respect to future policy changes.  See 45 FERC at 61,678.  
Because of the possibility of future changes, the Optional 
Certificate regulations, which are still in effect, do not formal-
ly require that FERC maintain the rate structures negotiated 
by parties in their initial agreements.  Instead, the Optional 
Certificate regulations require a pipeline to abide by all 
operative FERC regulations.  The Optional Certificate regu-
lations permit a reservation charge "consistent with the con-
ditions in [18 C.F.R.] s 284.8(d)."  18 C.F.R. s 157.103(d)(3).  



Order No. 636 changed the content of 18 C.F.R. s 284.8(d) 
from a modified f/v design to a straight f/v design.  The 
Optional Certificate regulations continued to incorporate by 
reference the changed rate design.

     No doubt, the possibility of FERC intervention in rate 
design makes it more difficult for the parties to allocate risk 
by means of contracts adopted pursuant to the Optional 
Certificate procedures.  No rational corporation would, with-
out some trepidation, enter a long term contract whose terms 
might be altered by highly unpredictable government inter-
vention.  The possibility of FERC intervention makes risk 
allocation difficult.  Indeed, the Kern River orders conceiv-
ably could have the effect of chilling future Optional Certifi-
cate contracts, to the extent that pipeline builders and ship-
pers may believe that significant shifts in their bargained-for 
risk allocations can and sometimes do occur.  However, this 
possibility of future chilling belongs as one among the various 
factors that FERC could consider in exercising its adminis-
trative discretion.  The one dissenting Commissioner in the 
Kern River rehearing order raised the issue of regulatory 
certainty as a concern, and justly so.  64 FERC at 61,436.  
Yet this concern, appropriate for FERC itself, does not 
establish arbitrariness for the purposes of this court.

     In the first Kern River order, FERC justified its applica-
tion of straight f/v to Kern River in terms of the broad policy 
change of Order No. 636 under which straight f/v became the 
rate design for the entire natural gas industry.  First sketch-
ing the goal of competition at the wellhead, FERC pointed 
out that Kern River's usage rates under modified f/v of either 
$0.1852 or $0.2502 per thousand cubic feet ("Mcf") would 
drastically exceed its competitors' straight f/v charges of 
$0.0165 and $0.00478 per Mcf.  62 FERC at 62,258.  If Kern 
River kept modified f/v, "the competitive distortion which the 
Commission has tried to prevent could occur."  Id.  Price 
disparity in the new competitive environment, FERC further 
argued, could put Kern River at a significant disadvantage 
vis--vis its competitors, and might even put it at risk of not 
recovering its fixed costs.  FERC concluded:



     On balance, we believe that the fundamental changes 
     that are to occur in the natural gas industry under 
     restructuring greatly outweigh the anticipation of the 
     parties and the Commission when Kern River's original 
     certificate authorization was being considered that the 
     MFV methodology would not change....  Kern River's 
     customers are in essentially no different a position now 
     than the customers of any other pipeline who, in the past 
     expected the Commission's former policy favoring MFV 
     to continue.

Id.  FERC's explanation for its decision sufficiently articulat-
ed the basis for its actions:  the purposes of straight f/v 
"greatly outweigh" whatever harm might befall the parties as 
the result of a change in their initial expectations.  Similar 
harms affected all natural gas customers who relied on the 
continuity of modified f/v, yet the court found the change 
from modified f/v to straight f/v to be permissible in United 
Distrib. Cos., 88 F.3d at 1161-76.

     In its second, clarificatory order on rehearing, FERC 
explained once more that, by implementing straight f/v, it 
intended to serve the general policy aim of Order No. 636:  
facilitating competition at the wellhead for natural gas sales.  
Noting the usage rate disparity between Kern River and its 
competitors that would result from allowing Kern River to 
maintain modified f/v, FERC observed:

     Shippers with different supply options would look to the 
     usage charges of the competing pipelines to make market 
     decisions.  Therefore, Kern River's usage charge would 
     cause distortions in the wellhead markets where mer-
     chants purchase gas for sale in the California market.

64 FERC at 61,407-08.  In this second order, FERC ac-
knowledged that imposing straight f/v shifted risk away from 
Kern River.  "However," it reasoned, "the need to accomplish 
the important national policy goals established by Order No. 
636 outweighs any adverse effects of a change in the alloca-
tion of the risk of the Kern River project."  Id. at 61,408.  
Finally, FERC explained in some detail that requiring Kern 



River to keep modified f/v while its competitors used straight 
f/v might have the effect of making it difficult for Kern River 
to recover its fixed costs because Kern River's services would 
be less attractive than those of its competitors.  Id.

     Thus, in both Kern River orders, FERC provided reasoned 
explanation for its decision to impose straight f/v.  This 
decision resulted from the broad policy reorientation that 
favored creating competition at the wellhead by making gas 
prices reflect only the marginal cost of extraction and trans-
portation, and not any fixed pipeline costs.  Applying this 
policy generally meant that if Kern River, and none of its 
competitors, used modified f/v, the goal of price transparency 
and comparability would not be achieved in its market.  It 
thus made regulatory sense to require Kern River to use 
straight f/v, even though the consequence of this decision was 
to reallocate risk that Kern River and Petitioners had already 
allocated.  This was a reasoned trade-off, not an arbitrary 
decision, and lay within FERC's discretion.

C. Subsequently Granted FERC Exceptions

     Since the time when the Kern River orders were issued, 
FERC has permitted exceptions to its straight f/v rate re-
quirement in several cases, including those of two of Kern 
River's competitors.  Joint Initial Brief of Petitioners 34-36;  
Joint Reply Brief of Petitioners 20-21.  Because these excep-
tions occurred after the orders under review, they play no 
role in our determination of the orders' legality.  Although we 
may remand where FERC has formally altered its policy 
after issuing an order challenged before us, see, e.g., Panhan-
dle E. Pipe Line v. F.E.R.C., 890 F.2d 435, 438 (D.C. Cir. 
1989), here Order No. 636 remains in place, and straight f/v 
remains the FERC-required default rate structure.  Petition-
ers have the option to encourage Kern River to request a 
waiver of the straight f/v requirement similar to that obtained 
by its competitors.  Although straight f/v benefits Kern Riv-
er, the bargaining power of Kern River's customers is hardly 
negligible in light of the ongoing relationship and long term 
interests of pipeline and customers alike.



D. Factual Hearing Request

     Petitioners requested a hearing before FERC to determine 
whether justification existed for an exception to the straight 
f/v requirement, and now ask this court to remand for a 
hearing on the question because cost allocation "involves 
judgment on a myriad of facts."  United Distrib. Cos., 88 
F.3d at 1167.  This observation does not suffice to require a 
trial-type hearing where, as here, no material disputes exist-
ed.  See Moreau v. F.E.R.C., 982 F.2d 556, 568 (D.C. Cir. 
1993).  FERC may resolve factual issues on a written record 
unless motive, intent, or credibility are at issue or there is a 
dispute over a past event.  Louisiana Ass'n of Indep. Pro-
ducers & Royalty Owners v. F.E.R.C., 958 F.2d 1101, 1113 
(D.C. Cir. 1992).  A trial-type hearing would not have facili-
tated what was at bottom a policy determination as to the 
relative importance of facilitating wellhead competition and 
preserving parties' risk allocation.

                               III. Conclusion


     FERC's orders reasonably instituted policy decisions 
whose distributive effects disadvantaged Petitioners.  The 
orders were not arbitrary, capricious, or otherwise in violation 
of law, and they were adequately explained by FERC.  The 
petition for review is denied.

So ordered.