Palmer & Palmer v. Waterfront Marine

PRESENT:    All the Justices

PALMER & PALMER COMPANY, LLC,
T/A PALMER & COMPANY

v.         Record No. 071373                  OPINION BY
                                      JUSTICE S. BERNARD GOODWYN
WATERFRONT MARINE CONSTRUCTION,              June 6, 2008
INC.

     FROM THE CIRCUIT COURT OF THE CITY OF VIRGINIA BEACH
                   Thomas S. Shadrick, Judge


     In this appeal, we consider whether the trial court erred

in its interpretation of a contract between Palmer & Palmer

Company, LLC (“Palmer”) and Waterfront Marine Construction,

Inc. (“Waterfront”) and in its imposition of liability on

Palmer for damage resulting from Waterfront’s crane falling

into an abandoned, disconnected septic tank on Palmer’s

property.

     Waterfront filed a complaint alleging breach of contract

against Palmer and seeking damages primarily related to repair

of its crane.   Palmer and Waterfront filed joint stipulations

as to the facts of the case, agreed that no material issues of

fact remained in dispute, and submitted the matter for the

trial court’s consideration on competing motions for summary

judgment.   The trial court denied Palmer’s motion for summary

judgment and, holding that Palmer breached the contract,

granted Waterfront’s motion for summary judgment.   The trial
court awarded Waterfront damages plus attorneys’ fees.      Palmer

appeals to this Court.

        The facts are undisputed.    Waterfront, a marine

construction and pile driving company, and Palmer, the owner

of the property and the general contractor for construction of

a house on 856 South Atlantic Avenue, Virginia Beach (“Lot

2”), entered into a contract.       The contract specified that

Waterfront would drive foundation piles into the ground on

Lot 2.

        On August 5, 2004, an employee of Waterfront was

operating a crane owned by Waterfront on Lot 2 when the crane

fell into a buried septic tank and was damaged.      The septic

tank was empty and covered with approximately four to ten

inches of sand.    Prior to the accident, neither Waterfront nor

Palmer was aware of the existence of the septic tank.       The

house previously located on Lot 2 had been demolished before

Palmer bought the property; however, the house utilized the

City of Virginia Beach public sewage system from at least

1990.    No recorded plat, survey, or drawing disclosed a septic

tank on the property.    Also, the Department of Public Health

for the City of Virginia Beach, which is the agency that keeps

records of private septic systems in the City of Virginia

Beach, had no record of any septic system or tank as having

been located on the subject property.

                                    2
     Waterfront sought damages from Palmer on a purely

contractual basis because of the damage to Waterfront’s crane

and other expenses related thereto.    The relevant provisions

of the contract are as follows:

          2.1   EXCLUSIONS: . . . Waterfront . . .
     assumes no responsibility for the following:

                             . . . .

            2. Removal of underground or overhead
     obstructions.

                             . . . .

          2.2   WORK AND/OR SERVICES TO BE PERFORMED BY
     OWNER PRIOR TO PILE DRIVING:

                             . . . .

            6. Location, protection, and removal of all
     utilities in area.

            7. Protection of existing structures.

                             . . . .

          4.1   ADDITIONAL WORK: Should additional work
     such as, but not limited to, underground
     obstructions such as trees, stumps, rocks, debris,
     etc. be encountered, an extra charge for equipment,
     labor, overhead and profit will be charge [sic] at
     $250.00/hour for removal or augering.

     The trial court concluded that Palmer was liable based on

the court’s combined reading of sections 2.1(2) and 4.1,

reasoning that reading those provisions together indicates

that Palmer was responsible for removal of underground

obstructions.   Additionally, the trial court found that the


                                  3
septic tank was either a utility or an existing structure that

Palmer was responsible for under sections 2.2(6) or 2.2(7) of

the contract.   On March 30, 2007, the trial court awarded

Waterfront damages in the amount of $22,696.05 plus attorneys’

fees in the amount of $11,006.55.

     Palmer argues that the trial court erred in interpreting

the contract and imposing liability and damages.   Focusing on

the language of the contract, Palmer contends that the

contract does not reflect an agreement that Palmer would

remove or locate an abandoned septic tank.    According to

Palmer, the trial court created a duty that was not

memorialized in the contract.

     Waterfront argues that the trial court correctly

interpreted the contract.   Waterfront states that Palmer is

liable under the contract for primarily three reasons.   First,

Waterfront asserts that sections 2.1(2) and 4.1 demonstrate it

was Palmer’s responsibility to prepare the work site, which

included removing underground obstructions.   Second, Palmer

failed to “locate and protect existing structures,

specifically the septic tank, as required by Paragraph

2.2(7).”   Third, section 2.2(6) provides that Palmer was

responsible for the location and removal of “all utilities.”

Arguing that the septic tank is a utility, Waterfront contends



                                4
that Palmer breached the contract by failing to comply with

section 2.2(6).

     Interpretation of a contract is a question of law that is

reviewed de novo.    PMA Capital Ins. Co. v. US Airways, Inc.,

271 Va. 352, 357-58, 626 S.E.2d 369, 372 (2006).   When a

contract is clear and unambiguous, it is the court’s duty to

interpret the contract, as written.    Winn v. Aleda Constr.

Co., 227 Va. 304, 307, 315 S.E.2d 193, 194 (1984).    On appeal,

this Court is not bound by the trial court’s determinations

regarding the interpretation of an unambiguous contract.

Gordonsville Energy, L.P. v. Virginia Elec. & Power Co., 257

Va. 344, 353, 512 S.E.2d 811, 816 (1999).

     In a breach of contract claim, the parties’ contract

becomes the law governing the case unless it is repugnant to

some rule of law or public policy.    Winn, 227 Va. at 307, 315

S.E.2d at 194.    This Court must construe the contract as it is

written.   Christopher Assocs. v. J.C. Sessoms, Jr., 245 Va.

18, 22, 425 S.E.2d 795, 797 (1993).   “The guiding light in the

construction of a contract is the intention of the parties as

expressed by them in the words they have used, and courts are

bound to say that the parties intended what the written

instrument plainly declares.”    W.F. Magann Corp. v. Virginia-

Carolina Elec. Works, Inc., 203 Va. 259, 264, 123 S.E.2d 377,

381 (1962).

                                 5
     We hold that sections 2.1(2) and 4.1 of the contract do

not subject Palmer to liability in this case.   In section

2.1(2), the contract states that Waterfront assumed no

responsibility for the removal of underground obstructions.

The plain meaning of that provision is that the contract price

did not include the removal of underground obstructions.

Section 4.1 further confirms such an interpretation by stating

that Waterfront would charge $250 per hour for additional work

resulting from underground obstructions.

     The contract indicates that the parties anticipated

underground obstructions might be encountered during the

project.   The contract provides for payment to Waterfront for

the removal of any such obstructions.   However, the contract

does not impose any obligation upon Palmer to remove such

underground obstructions or to be responsible for damages

caused thereby.   Thus, contract sections 2.1(2) and 4.1,

whether considered together or separately, do not impose

contractual liability upon Palmer for damage to Waterfront’s

crane caused by a previously unknown underground obstruction.

Therefore, the trial court erred in granting Waterfront’s

motion for summary judgment based on a reading of sections

2.1(2) and 4.1.

     Palmer also assigns error to the trial court’s ruling

that Waterfront is entitled to contractual damages because the

                                6
septic tank was an existing structure.    Under section 2.2(7)

of the contract, Palmer is responsible for protecting existing

structures.    Assuming the septic tank is an existing

structure, section 2.2(7) clearly means that Palmer could not

hold Waterfront responsible for any damage to the septic tank.

However, section 2.2(7) does not make Palmer liable for damage

to Waterfront’s crane caused when the crane fell into the

septic tank.    The trial court’s holding that the septic tank

was such an existing structure therefore does not provide a

contractual basis for imposing liability upon Palmer for

Waterfront’s damages.

       Palmer further assigns error to the trial court’s holding

that the abandoned, disconnected septic tank could be the

basis for imposing liability upon Palmer, pursuant to section

2.2(6) of the contract. Section 2.2(6) states that Palmer was

responsible for the location, protection, and removal of all

utilities.    This Court must therefore consider whether an

abandoned, disconnected septic tank is a utility.    We hold

that it is not.

       When the interpretation of a contract involves a term

that is clear and unambiguous, the term is given its plain

meaning.     PMA Capital Ins. Co., 271 Va. at 358, 626 S.E.2d at

372.   A contractual term, absent a definition in the contract,

is construed according to its usual, ordinary, and popular

                                  7
meaning.    See Christopher Assocs., 245 Va. at 23, 425 S.E.2d

at 797.    The term “utility” is defined as “a service provided

by a public utility” and as “a unit composed of one or more

pieces of equipment usually connected to or part of a

structure and designed to provide a service (as heat, light,

power, water, or sewage disposal).”    Webster’s Third New

International Dictionary 2525 (1993).

     Assuming, without deciding, that an operational septic

system is a utility, the septic tank involved in this case is

not a utility because there is no evidence that this septic

tank is, or ever was, part of an operational septic system.

The evidence is uncontroverted that the house previously on

the property utilized the public sewer system since 1990.

There is no evidence that this septic tank was ever connected

to the house that was previously located on Lot 2 or that it

was part of an operational septic system.    At best, the septic

tank is part of a disconnected septic system that had been

abandoned for years; it is one part of a unit that, if

operational, would be a utility.     Thus, we hold that the

empty, abandoned septic tank was not a “utility” within the

intendment of Section 2.2(b) of the parties’ contract.

     Under the terms of the contract, Palmer did not have a

duty to locate or remove an abandoned, disconnected septic



                                 8
tank.    The trial court erred in holding such a duty existed

under the contract.

        Palmer also argues that the trial court erred in awarding

attorneys’ fees.    In view of our disposition concerning

Palmer’s liability, we hold that Waterfront is not entitled to

attorneys’ fees pursuant to the terms of the contract.

        This Court concludes that the contract contains no

provision that would make Palmer liable for Waterfront’s

damages.    We will reverse the judgment of the trial court and

enter final judgment in favor of Palmer.

                                      Reversed and final judgment.




                                  9