Suffolk City School Board v. Conrad Bros.

Present: All the Justices

SUFFOLK CITY SCHOOL BOARD

v.   Record No. 970414
                         OPINION BY JUSTICE LAWRENCE L. KOONTZ, JR.
                                                    January 9, 1998
CONRAD BROTHERS, INC.

           FROM THE CIRCUIT COURT OF THE CITY OF SUFFOLK
                     Westbrook J. Parker, Judge


      This appeal arises from a suit by the Suffolk City School

Board (the Board) against a general contractor engaged to build

two high schools.   The Board alleges that the contractor, Conrad

Brothers, Inc., installed defective roofs in the schools,

resulting in damage to both.   The trial court ruled that the suit

was barred by the applicable five-year statute of limitations.

Code § 8.01-246(2).   The issue we consider on appeal is whether

the trial court erred in this ruling.   Specifically, we determine

when the Board's cause of action accrued pursuant to the

provisions of Code § 8.01-230.
      The essential facts are not in dispute.   On February 26,

1986, the Board entered into a contract with Shriver and Holland

Associates (the architects) to provide architectural services and

representation throughout the various phases of the planned

construction of the two high schools (the architects' contract).

For purposes of determining the architects' obligations and

right to compensation, this contract contained a provision that

"[t]he Construction Phase . . . will terminate when final payment

to the Contractor is due, or in the absence of a final

Certificate for Payment or of such due date, sixty days after the

Date of Substantial Completion of the Work, whichever occurs
first."   On October 14, 1988, the Board entered into two

separate, but substantially similar, contracts with Conrad

Brothers as the general contractor for the construction of the

two high schools under the direction of the architects (the

construction contracts).   The construction contracts fixed the

time for final completion of construction as the date of issuance

of a "final Certificate for Payment" by the architects.

     Thereafter, Conrad Brothers commenced work on both schools

and the architects issued certificates noting substantial

completion for both schools as of September 3, 1990.    The

architects' "punch lists" appended to each certificate showing

what further work was to be completed by the contractor before

final payment would be authorized included references to

correction of the defective roofs.    On November 27, 1990, and on

several occasions thereafter, the Board contacted Conrad Brothers

to report leaks in the roofs of both schools.    Conrad Brothers

received these notices and took steps to remedy the defective

condition of the roofs.
     On February 4, 1991, Conrad Brothers submitted to the

architects an application for final payment with respect to

construction of both high schools.    The architects issued

certifications for payment of Conrad Brothers to the Board on

March 13, 1991.   The Board filed the present suit against Conrad

Brothers on February 13, 1996. 1   Conrad Brothers filed a plea of
     1
       The Board's suit also asserts a negligence claim against
Conrad Brothers. See Code § 8.01-272 (permitting a party to join
a claim in tort with one in contract provided that such claims
arise out of the same transaction or occurrence); see also Code
§ 8.01-243(B) (providing a five-year limitations period for
the statute of limitations, asserting that the Board had notice

of the defective conditions of the roofs on or before September

12, 1990.

     Following a hearing on Conrad Brothers' plea, the trial

court issued a letter opinion in which it referenced the

previously noted provisions of the architects' contract which

specified that the "construction phase" of the projects would

expire sixty days after the issuance of the certificates of

substantial completion.   Determining that this date was November

2, 1990, the trial court set the commencement of the limitations

periods at that point.    Based upon this determination, the trial

court held that the statute of limitations ran on November 2,

1995, more than three months prior to the filing of the Board's

motion for judgment.   A final order was entered on December 4,

1996, adopting by reference the reasons stated in the trial

court's initial opinion letter.   We awarded the Board this

appeal.
     We first consider the trial court's reliance on the terms of

the architects' contract to determine the termination date of the

construction contracts.   The construction contracts contain

express terms addressing their duration and termination, and

nothing within the construction contracts links their termination

to the termination of the construction phase defined in the

(..continued)
actions for injury to property). Because the trial court did not
specifically address this claim and the parties have not
addressed it on appeal, we will not address it in this opinion.
The Board also asserted a claim for breach of contract against
the architects, but that claim is not a part of this appeal.
architects' contract.    Although using similar terms and related

to the same projects, the contracts are independent expressions

of the agreements between the Board and the architects, on the

one hand, and the Board and Conrad Brothers on the other.

Accordingly, the trial court's determination that the Board's

cause of action against Conrad Brothers accrued on November 2,

1990 pursuant to the architects' contract was in error.    Under

the applicable provisions of the construction contracts the

construction was complete upon the issuance of a "final

Certificate for Payment," which did not occur here until March

13, 1991, less than five years before the litigation was

commenced.
     Conrad Brothers asserts, however, that the trial court's

judgment can be sustained under a "right result, wrong reason"

analysis.     See, e.g., Harrison & Bates, Inc. v. Featherstone

Associates Ltd. Partnership, 253 Va. 364, 369, 484 S.E.2d 883,

886 (1997).    Conrad Brothers contends that Code § 8.01-230

abrogates the common law rule permitting a party to an

indivisible executory contract to elect between pursuing his

remedy when an action which would constitute a breach occurs or

awaiting the time fixed by the contract for full and final

performance.    Continuing, Conrad Brothers contends that Code

§ 8.01-230 provides that the statute of limitations on any cause

of action for breach of contract involving damage to property

commences upon the occurrence of the breach, regardless of

whether the breaching party continues to perform.    Thus, in the

present case, Conrad Brothers asserts that the statute of
limitations began to run at least prior to November 27, 1990 when

the Board first acknowledged that the roofs were defective.

     Prior to the enactment of Code § 8.01-230, the rule with

respect to the running of a statute of limitations for a breach

of an indivisible executory contract was clear:
          In the case of an indivisible or entire contract,
     a party seeking to recover for a breach committed while
     the contract remained executory, or for an anticipatory
     breach committed before expiration of the time agreed
     upon for full and final performance, has the election
     of pursuing his remedy when the breach occurs, or of
     awaiting the time fixed by the contract for full and
     final performance. If he elects the latter course, the
     statute of limitations does not begin to run against
     his right of action until the time for final
     performance fixed by the contract has passed. Andrews
     v. Sams, 233 Va. 55, 58, 353 S.E.2d 735, 738 (1987);
     County School Bd. v. Beiro, 223 Va. 161, 163, 286
     S.E.2d 232, 233 (1982); Simpson v. Scott, 189 Va. 392,
     400, 53 S.E.2d 21, 24 (1949).


Roberts v. Coal Processing Corp., 235 Va. 556, 561, 369 S.E.2d

188, 190 (1988). 2

     When the present construction contracts were executed, Code

§ 8.01-230 provided in pertinent part: 3
          In every action for which a limitation period is
     prescribed, the cause of action shall be deemed to
     2
       Although Roberts and several of the cases cited therein
were decided after the enactment of Code § 8.01-230, these cases
dealt with contracts which predated the revision of the Code.
     3
       In 1996, Code § 8.01-230 was amended, and the term "right
of action" was substituted for "cause of action." The Board has
concentrated much of its argument on the distinction between
these two terms, asserting that its "right of action" accrued,
and, thus, in the Board's estimation, the running of the statute
of   limitations   commenced,  upon  the   termination  of   the
construction contracts, even if its "cause of action" accrued
earlier.   Cf. Stone v. Ethan Allen, Inc., 232 Va. 365, 368-70,
350 S.E.2d 629, 631-32 (1986). We express no opinion as to the
merits of this assertion, as the distinction between the Board's
"cause" and the "right" of action is not relevant to our
resolution of this appeal.
     accrue and the prescribed limitation period shall begin
     to run from the date . . . when the breach of contract
     or duty occurs in the case of damage to property and
     not when the resulting damage is discovered . . . .


     Conrad Brothers' essentially contends that Code § 8.01-230

eliminates the distinction between divisible and indivisible

executory contracts.   We disagree.

     The revisers' note to Code § 8.01-230 is instructive here:

"Section 8.01-230 retains the traditional rule of Virginia case

law that a cause of action accrues when the wrongful act or

breach of duty or contract occurs."   The express provisions of

this code section are consistent with the distinction we have

previously noted between divisible and indivisible contracts in

determining when a cause of action accrues.   Thus, we conclude

that Code § 8.01-230 merely codified existing law in this respect

and, accordingly, we reject Conrad Brothers' contention that it
                                                            4
overruled cases decided under the former common law rule.       That

being so, County School Bd. v. Beiro, 223 Va. 161, 286 S.E.2d 232

(1982), is almost directly on point with the facts of the present

case and controls the outcome of this appeal.

     In Beiro, the owner of a public school building brought an
action against the contractor claiming damages due to a defective

     4
        See Roberts, 235 Va. at 242, 368 S.E.2d at 247
(distinguishing Beiro not on the basis of the intervening
enactment of Code § 8.01-230 but based on the nature of the
contract itself). See generally Harris v. K & K Ins. Agency, 249
Va. 157, 161 at n.*, 453 S.E.2d 284, 286 at n.* (1995)(citing
Nelson v. Commonwealth, 235 Va. 228, 243, 368 S.E.2d 239, 248
(1988), and Virginia Military Inst. v. King, 217 Va. 751, 759,
232 S.E.2d 895, 900 (1977), and noting the distinction between
contracts divisible into separate and distinct phases and
contracts not set up in such phases).
roof.       There, as in the present case, the contract was not

divisible.      Although the contractor had completed his work on the

roof well before the architect issued the certificate of final

payment, we held that no cause of action accrued until the date

of that certificate.       Beiro, 233 Va. at 163, 286 S.E.2d at 233.

The circumstances of the present case are indistinguishable and

the same result must apply. 5

        For these reasons, we hold that with respect to Conrad

Brothers' potential liability for the defective condition of the

roofs, the five-year statute of limitations commenced upon the

date of the architects' submission of the "final Certificate[s]

for Payment" to the Board on March 13, 1991, and, thus, the

Board's suit was timely filed on February 13, 1996.
        We will reverse the judgment order of the trial court

sustaining Conrad Brothers' plea of the statute of limitations

and remand the case for a trial on the merits.

                                                Reversed and remanded.



        5
       As an alternative position that the Board's cause of
action for breach of contract accrued on the date of substantial
completion rather than upon the termination date, Conrad Brothers
relies upon a post-substantial completion warranty provision
which, by its express terms, was not to be "construed to
establish a period of limitation with respect to any other
obligation" under the contracts. The record is clear, however,
that at the time the certificate of substantial completion was
issued, the architects had not accepted the roofs as complete.
Thus, it is evident that the Board's requests to Conrad Brothers
to remedy the defective condition of the roofs were merely
requests for the contractor to comply with its duties under the
contract, and not notices that a previously accepted condition
had subsequently been found to be defective and was subject to
repair under the post-completion warranty.