PUBLISHED
UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT
MCI CONSTRUCTORS, LLC,
Plaintiff-Appellant,
v.
CITY OF GREENSBORO, a
municipality, organized under the
laws of the State of North
Carolina,
Defendant-Appellee,
and No. 09-1600
HAZEN AND SAWYER, P.C., a New
York Corporation,
Defendant,
v.
NATIONAL UNION FIRE INSURANCE
COMPANY OF PITTSBURGH, PA, a
Pennsylvania Corporation,
Third Party Defendant.
2 MCI CONSTRUCTORS v. CITY OF GREENSBORO
MCI CONSTRUCTORS, LLC,
Plaintiff,
v.
CITY OF GREENSBORO, a
municipality, organized under the
laws of the State of North
Carolina,
Defendant-Appellee,
and No. 09-1606
HAZEN AND SAWYER, P.C., a New
York Corporation,
Defendant,
v.
NATIONAL UNION FIRE INSURANCE
COMPANY OF PITTSBURGH, PA, a
Pennsylvania Corporation,
Third Party Defendant-Appellant.
Appeals from the United States District Court
for the Middle District of North Carolina, at Greensboro.
William L. Osteen, Jr., District Judge.
(1:99-cv-00002-WO-WWD)
Argued: April 8, 2010
Decided: July 1, 2010
Before TRAXLER, Chief Judge, and DUNCAN and
DAVIS, Circuit Judges.
MCI CONSTRUCTORS v. CITY OF GREENSBORO 3
Affirmed by published opinion. Judge Duncan wrote the opin-
ion, in which Chief Judge Traxler and Judge Davis joined.
COUNSEL
ARGUED: C. Allen Foster, GREENBERG TRAURIG, LLP,
Washington, D.C., for MCI Constructors, LLC. William P. H.
Cary, George W. House, BROOKS, PIERCE, MCLENDON,
HUMPHREY & LEONARD, Greensboro, North Carolina,
for City of Greensboro. ON BRIEF: Eric C. Rowe, David
Samuel Panzer, GREENBERG TRAURIG, LLP, Washing-
ton, D.C., for MCI Constructors, LLC; John M. Gillum,
MANIER & HEROD, Nashville, Tennessee, for National
Union Fire Insurance Company of Pittsburgh, PA. Michael D.
Meeker, Joseph A. Ponzi, BROOKS, PIERCE, MCLENDON,
HUMPHREY & LEONARD, Greensboro, North Carolina,
for City of Greensboro.
OPINION
DUNCAN, Circuit Judge:
This appeal arises from a contract dispute concerning the
construction of a wastewater treatment plant. This dispute has
been before us once before. See MCI Constructors, Inc. v.
City of Greensboro, 125 F. App’x 471 (4th Cir. 2005). Fol-
lowing that decision, all concerned parties agreed to submit
the outstanding issues to arbitration. Arbitration yielded an
award to Appellee City of Greensboro (the "City") of
$14,939,004. The district court then granted the City’s motion
to confirm that award. This appeal followed. For the reasons
that follow, we affirm.
4 MCI CONSTRUCTORS v. CITY OF GREENSBORO
I.
A.
On January 16, 1996, the City entered into a contract with
Appellant MCI Constructors, LLC ("MCI") for the expansion
and upgrade of a wastewater treatment plant in Greensboro,
North Carolina, for a cost of roughly $29 million. The con-
tract explains that "[t]o prevent disputes and litigations, the
City Manager shall . . . decide every question which may arise
relative to the fulfillment of the Contract on the part of the
Contractor." J.A. 227. As required by North Carolina law,
after signing the contract, MCI obtained a performance bond
from National Union Fire Insurance Company ("National
Union") of Pittsburgh, Pennsylvania, which incorporated the
terms of the contract between the City and MCI and guaran-
teed that MCI would perform the contract.
When construction of the wastewater plant became sub-
stantially delayed, the City terminated the contract. MCI then
commenced this diversity action in the Middle District of
North Carolina against the City and Hazen and Sawyer, P.C.
("Hazen and Sawyer"), the engineering firm that designed the
project. The complaint alleged, inter alia, claims for breach of
contract, negligent misrepresentation, and wrongful termina-
tion. In response, the City filed a counterclaim for breach of
contract, and a third-party complaint against National Union
on its bond. The district court declined to entertain most of
these claims, concluding that the contract required that all dis-
putes regarding the fulfillment of the contract be resolved by
the City Manager. Accordingly, the parties submitted their
claims to the City Manager.
After a two-day hearing, on April 16, 2002, the City Man-
ager issued an order. In that order, the City Manager held that
the City had properly terminated MCI for cause, and denied
MCI’s wrongful termination claim. Thereafter, a hearing was
held to determine the City’s damages. After that proceeding,
MCI CONSTRUCTORS v. CITY OF GREENSBORO 5
on February 5, 2003, the City Manager issued an order find-
ing that MCI owed the City $13,377,842.73.
The City then filed a motion for summary judgment, seek-
ing to enforce the City Manager’s decision. National Union
filed a cross-motion for summary judgment seeking to avoid
liability as the surety for payment of the $13,377,842.73. On
March 10, 2004, after finding that the City Manager’s deci-
sion was not "influenced by fraud, bad faith, or gross mis-
take," the district court issued an order granting summary
judgment in favor of the City on all of MCI’s claims. J.A.
2510. The district court determined that "the City Manager’s
award [was] a complete defense to [MCI’s] claims."1 Id. Fur-
ther, having found the City Manager’s award binding and
enforceable, the district court awarded judgment to the City
on its counterclaim. Thus, the district court held that the City
was to recover from MCI the sum of $13,377,842.73. In a
separate order, the district court held that the City Manager’s
award was enforceable against National Union.
MCI and National Union appealed the district court’s rul-
ings. On appeal, we "affirm[ed] all the rulings of the district
court except its application of the ‘fraud, bad faith, or gross
mistake’ standard, which [the district court] applied to review
the decision of the City Manager." MCI Constructors, 125 F.
App’x at 474. Specifically, we held that
since the City Manager signed the contract for the
City and in essence was adjudicating his own perfor-
mance, rights, and liabilities under the contract,
North Carolina law requires that the City Manager’s
performance be measured by a standard of objective
1
The court recognized that in a previous opinion it had not required
MCI to submit its claims for breach of warranty and negligent misrepre-
sentation to the City Manager, but nevertheless granted judgment because
those "claims were within the ambit of the City Manager’s contractual
decision-making authority." J.A. 2511.
6 MCI CONSTRUCTORS v. CITY OF GREENSBORO
reasonableness "based upon good faith and fair play"
—a standard that must be read into the contract so as
to prevent the contract from being rendered illusory.
Id. Thus, we reversed and vacated the judgment insofar as the
judgment depended on application of this standard.
B.
Trial was then set for February 6, 2006. On January 26,
2006, however, the City, MCI, and National Union advised
the district court that they had "entered into a binding Arbitra-
tion Agreement to resolve all issues between them" arising
from the contract and that "[u]pon conclusion of the arbitra-
tion, all matters currently set for trial w[ould] be moot." J.A.
2621. In that agreement, the parties stipulated that an arbitra-
tion panel would be selected by the parties, that the "rules
would be standard AAA Complex Commercial or JAMS
rules," J.A. 2634, and that the "[p]roceedings [would] be
bifurcated between liability and damages," J.A. 2635. Further,
the parties agreed that "[a]t the conclusion of the arbitration,
the award [would] be confirmed and a judgment [would be]
entered," and that "[u]pon confirmation, MCI [would] take a
voluntary dismissal with prejudice of all claims and proceed-
ings against the City . . . and the City [would] take a voluntary
dismissal with prejudice of all claims against MCI." J.A.
2637. Accordingly, as requested by the parties, the district
court stayed the case pending arbitration.
On September 26, 2006, the parties presented their liability
arguments to a panel of three arbitrators. On June 20, 2007,
the arbitration panel issued an award finding that "[t]he City’s
termination of MCI’s performance under [the] contract . . . for
expansion of a waste water treatment plant . . . was for cause."
J.A. 4113. In response, on September 17, 2007, MCI filed a
motion with the district court seeking to vacate the award.
Specifically, MCI argued, inter alia, that "the Panel refused to
hear material evidence[,] . . . repeatedly . . . refus[ed] to con-
MCI CONSTRUCTORS v. CITY OF GREENSBORO 7
sider [its] submissions and [did] not allow[ ] [it] to respond to
the City’s Closing Arguments in the Liability Phase of the
Arbitration." J.A. 4120. Further, MCI argued that "the City
obtained the ‘Award’ by undue means by misrepresenting
facts outside the record during Closing Arguments and acting
to prevent MCI from being able to respond." Id. At MCI’s
request, however, the district court issued an order explaining
that it would not entertain MCI’s motion until thirty days after
the arbitration was complete.
The parties then presented their damages arguments to the
arbitration panel. On April 17, 2008, the arbitration panel
found that "the City [was] entitled to recover from MCI"
$14,939,004. J.A. 7403. Contending that the award was
unclear, on April 24, 2008, MCI sent an email to the arbitra-
tion panel, requesting the panel to modify it. Specifically,
MCI argued that the arbitration panel failed to deduct the con-
tract balance from the award, and that the arbitration panel
was required to provide a reasoned award that addressed the
disposition of all the claims submitted. On May 8, 2008, the
panel issued an order denying MCI’s request. The panel
explained that because none of the parties requested a rea-
soned award prior to the panel’s appointment, it was not obli-
gated to provide one. Further, the panel noted that "[t]he
Damages Award did not contain any errors." J.A. 7416.
Thereafter, the City moved to have the liability and dam-
ages awards confirmed by the district court. MCI and
National Union moved to vacate the arbitration awards. In the
alternative, MCI also moved to remand the damages award.
On the substantive motions, the district court received a total
of twenty-two briefs and held oral arguments. After reviewing
all these materials, on March 9, 2009, the district court issued
two opinions denying MCI’s and National Union’s motions.
Thereafter, on April 28, 2009, the district court entered an
order confirming the arbitration awards. The court also
entered final judgment pursuant to Federal Rule of Civil Pro-
cedure 54(b). MCI and National Union then appealed.
8 MCI CONSTRUCTORS v. CITY OF GREENSBORO
II.
On appeal, MCI and National Union present three main
arguments. First, they argue that the district court erred in cer-
tifying the judgment as final under Rule 54(b). Second, they
maintain the district court should have vacated the awards
because the liability award was obtained through undue
means, the arbitration panel exceeded the scope of its powers
to issue the damages award, and the damages award does not
draw its essence from the parties’ contract. Finally, they con-
tend that the district court should have remanded the damages
award because the award fails to specify whether it includes
the contract balance, and because the arbitrators were required
to issue a reasoned award. We consider each argument in turn.2
A.
We turn first to MCI and National Union’s argument that
the district court erred in certifying the judgment as final
under Federal Rule of Civil Procedure 54(b). We review the
district court’s Rule 54(b) certification for abuse of discretion.
Fox v. Baltimore City Police Dep’t, 201 F.3d 526, 531 (4th
Cir. 2000); Braswell Shipyards, Inc. v. Beazer E., Inc., 2 F.3d
1331, 1336 (4th Cir. 1993). In doing so, we recognize that our
role is "not to reweigh the equities or reassess the facts but to
make sure that the conclusions derived from those weighings
and assessments are juridically sound and supported by the
record." Curtiss-Wright Corp. v. Gen. Elec. Co., 446 U.S. 1,
10 (1980).
Federal Rule of Civil Procedure 54(b) provides that
"[w]hen an action presents more than one claim for relief—
whether as a claim, counterclaim, crossclaim, or third-party
claim—or when multiple parties are involved, the court may
2
MCI and National Union raised several other arguments in their briefs.
Any arguments not discussed in this opinion were found to be without
merit.
MCI CONSTRUCTORS v. CITY OF GREENSBORO 9
direct entry of a final judgment as to one or more, but fewer
than all, claims or parties only if the court expressly deter-
mines that there is no just reason for delay." Fed. R. Civ. P.
54(b). "The task which the district court must follow to effec-
tuate a Rule 54(b) certification involves two steps." Braswell,
2 F.3d at 1335. "First, the district court must determine
whether the judgment is final." Id. A judgment "must be
‘final’ in the sense that it is ‘an ultimate disposition of an indi-
vidual claim entered in the course of a multiple claims
action.’" Curtiss-Wright, 446 U.S. at 7 (quoting Sears, Roe-
buck & Co. v. Mackey, 351 U.S. 427, 436 (1956)). "Second,
the district court must determine whether there is no just rea-
son for the delay in the entry of judgment." Braswell, 2 F.3d
at 1335. In determining whether there is no just reason for
delay in the entry of judgment, factors the district court
should consider, if applicable, include:
(1) the relationship between the adjudicated and
unadjudicated claims; (2) the possibility that the
need for review might or might not be mooted by
future developments in the district court; (3) the pos-
sibility that the reviewing court might be obliged to
consider the same issue a second time; (4) the pres-
ence or absence of a claim or counterclaim which
could result in a set-off against the judgment sought
to be made final;3 (5) miscellaneous factors such as
delay, economic and solvency considerations, short-
ening the time of trial, frivolity of competing claims,
expense, and the like.
3
On this factor, the Supreme Court has explained "that counterclaims,
whether compulsory or permissive, present no special problems for Rule
54(b) determinations; counterclaims are not to be evaluated differently
from other claims." Curtiss-Wright Corp., 446 U.S. at 9. Like other
claims, the Court has explained, "their significance for Rule 54(b) pur-
poses turns on their interrelationship with the claims on which certification
is sought." Id.
10 MCI CONSTRUCTORS v. CITY OF GREENSBORO
Braswell, 2 F.3d at 1335-36 (footnote call number added)
(quoting Allis-Chalmers Corp. v. Phila. Elec. Co., 521 F.2d
360, 364 (3d Cir. 1975)).
MCI and National Union argue that because "[t]he record
. . . is replete with examples of [Hazen and Sawyer]’s failure
to monitor and control the completion costs, resulting in costs
that the City never should have incurred and that MCI should
not be called upon to pay," the district court erred in entering
a Rule 54(b) certification. Appellants’ Br. at 58. Instead, they
contend, the district court should have held in abeyance the
motion to certify the judgment as final pending the resolution
of MCI’s claims against Hazen and Sawyer, particularly since
"both MCI and the City agree that the responsibility for
improperly certified charges of the completion contractors
must fall upon [Hazen and Sawyer]." Appellants’ Br. at 59. In
essence, they argue that there was a just reason for delaying
the entry of judgment here.4
Our review of the record supports the conclusion that there
was no just reason for delaying the entry of judgment here.
First, "[a]lthough the present matter and the Hazen [and] Saw-
yer litigation arise out of a common set of facts, i.e., the cir-
cumstances surrounding City’s termination of MCI’s
performance under the Contract," J.A. 7947-48, the relation-
ship between the adjudicated and unadjudicated claims was
severed by virtue of the parties’ own admissions, such that the
4
MCI and National Union do not seem to dispute that the judgment here
was final. Nevertheless, we note that the parties, in their Joint Motion to
Stay, stipulated as much to the district court. They submitted that the arbi-
tration panel would resolve "all outstanding issues between them," J.A.
2621, that "[u]pon conclusion of the arbitration, all matters . . . set for trial
w[ould] be moot," id., that "[a]rbitration w[ould] be final and binding,"
J.A. 2634, and that "[a]t the conclusion of the arbitration, the award . . .
[would] be confirmed and a judgment [would be] entered," J.A. 2637. In
accordance with this agreement, the arbitration panel stated in its damages
award, "This AWARD is in full and final settlement of all issues submit-
ted in the Damages Phase of this Arbitration." J.A. 7403.
MCI CONSTRUCTORS v. CITY OF GREENSBORO 11
results of the arbitration have no binding or preclusive effect
on the litigation of the remaining claims against Hazen and
Sawyer. The parties represented to the district court that
"[u]pon conclusion of the arbitration, all matters . . . set for
trial w[ould] be moot," and that "[f]urther proceedings involv-
ing Hazen [and] Sawyer c[ould] take place at that time." J.A.
2621; see also J.A. 2628 ("Defendant Hazen [and] Sawyer . . .
has already consented to bifurcation of issues involving it
until after the resolution of certain claims between MCI and
the City, which will now be resolved through arbitration
instead of litigation in this Court."). Second, MCI and
National Union point to nothing in the record, nor are we able
to find anything, to suggest that review of the issues here
might be mooted by future developments in the district court.
On the contrary, "the possibility that [we] might be obliged to
consider the same issue[s] [explored here] a second time,"
Braswell, 2 F.3d at 1335, is unlikely because all that remains
to be resolved is whether the arbitration awards are valid, and
Hazen and Sawyer was not a party to the arbitration agree-
ment and did not participate in the arbitration proceedings.
Third, MCI and National Union have not identified the pres-
ence or absence of a pending claim or counterclaim which
could result in a set-off against the judgment made final by
the district court. Finally, we do not believe any "miscella-
neous factors such as delay, economic and solvency consider-
ations, . . . frivolity of competing claims, expense, and the
like" change the analysis here. Braswell, 2 F.3d at 1336.
Accordingly, we hold that the district court did not abuse
its discretion in certifying its judgment as final under Rule
54(b).
B.
We next consider MCI and National Union’s argument that
the district court should have vacated the arbitration awards.
In order for a reviewing court to vacate an arbitration award,
the moving party must sustain the heavy burden of showing
12 MCI CONSTRUCTORS v. CITY OF GREENSBORO
one of the grounds specified in the Federal Arbitration Act
(the "FAA") or one of certain limited common law grounds.5
Patten v. Signator Ins. Agency, Inc., 441 F.3d 230, 234 (4th
Cir. 2006). The FAA provides that a court may only vacate
an arbitration award on one of the following grounds:
(1) where the award was procured by corruption,
fraud, or undue means;
(2) where there was evident partiality or corruption
in the arbitrators, or either of them;
(3) where the arbitrators were guilty of misconduct
in refusing to postpone the hearing, upon sufficient
cause shown, or in refusing to hear evidence perti-
nent and material to the controversy; or of any other
misbehavior by which the rights of any party have
been prejudiced; or
(4) where the arbitrators exceeded their powers, or
so imperfectly executed them that a mutual, final,
and definite award upon the subject matter submitted
was not made.
9 U.S.C. § 10(a). The permissible common law grounds for
vacating such an award "include those circumstances where
an award fails to draw its essence from the contract, or the
award evidences a manifest disregard of the law." Patten, 441
F.3d at 234.
5
The district court noted that the common-law grounds may or may not
be available to MCI after Hall Street Associates, L.L.C. v. Mattel, Inc., 552
U.S. 576 (2008). In Hall Street, the Supreme Court held that "the statutory
grounds are exclusive," id. at 578, and that "the FAA confines its expe-
dited judicial review to the grounds listed in 9 U.S.C. §§ 10 and 11," id.
at 592. Because we find that MCI and National Union’s common-law
arguments do not entitle them to relief, we need not decide whether courts
may still vacate an arbitration award if the award fails to draw its essence
from the controlling agreement, or if it flows from a manifest disregard of
the applicable law.
MCI CONSTRUCTORS v. CITY OF GREENSBORO 13
MCI and National Union contend in this appeal that the dis-
trict court should have vacated the arbitration awards under
several of the permissible statutory and common law bases.
Specifically, they contend that the liability award was pro-
cured by undue means in violation of § 10(a)(1) of the FAA.
They also argue that to issue the damages award, the arbitra-
tion panel exceeded the scope of its powers. Finally, they
assert that the damages award does not draw its essence from
the contract. We consider each argument in turn.
In doing so, we review for clear error the district court’s
findings of fact and review de novo its conclusions of law,
including its decision not to vacate the arbitration awards.
Choice Hotels Int’l, Inc. v. SM Prop. Mgmt., LLC, 519 F.3d
200, 207 (4th Cir. 2008). We are mindful that "[o]ur authority
to review the arbitration award[s] at issue, like the authority
of the district court to do the same, is ‘substantially circum-
scribed.’" Id. (quoting Patten, 441 F.3d at 234). As we have
said previously, "the scope of judicial review for an arbitra-
tor’s decision is among the narrowest known at law because
to allow full scrutiny of such awards would frustrate the pur-
pose of having arbitration at all—the quick resolution of dis-
putes and the avoidance of the expense and delay associated
with litigation." Three S Delaware, Inc. v. DataQuick Info.
Sys., Inc., 492 F.3d 520, 527 (4th Cir. 2007) (citation and
internal quotations omitted).
1.
We first consider whether the liability award was "procured
by . . . undue means" in violation of § 10(a)(1). 9 U.S.C.
§ 10(a)(1). "The term ‘undue means’ has generally been inter-
preted to mean something like fraud or corruption." Three S
Delaware, 492 F.3d at 529; see also Nat’l Cas. Co. v. First
State Ins. Group, 430 F.3d 492, 499 (1st Cir. 2005) ("The best
reading of the term ‘undue means’ under the maxim noscitur
a sociis ["it is known from fellows or allies"] is that it
describes underhanded or conniving ways of procuring an
14 MCI CONSTRUCTORS v. CITY OF GREENSBORO
award that are similar to corruption or fraud, but do not pre-
cisely constitute either."). Typically, to prove that an award
was procured by undue means, the party seeking vacatur
must show that the fraud [or corruption] was (1) not
discoverable upon the exercise of due diligence prior
to the arbitration, (2) materially related to an issue in
the arbitration, and (3) established by clear and con-
vincing evidence.
A.G. Edwards & Sons, Inc. v. McCollough, 967 F.2d 1401,
1404 (9th Cir. 1992); see also Bonar v. Dean Witter Reynolds,
Inc., 835 F.2d 1378, 1383 (11th Cir. 1988) (collecting cases).
MCI and National Union contend that the arbitration
awards here were procured through undue means because the
City engaged in unfair and fraudulent actions. They explain
that the City (1) actively sought to prevent MCI from present-
ing the facts of the case de novo; (2) misrepresented facts to
the arbitration panel; and (3) elected to present its principal
arguments on rebuttal, thereby robbing MCI of its opportunity
to present a meaningful response at closing. Thus, they main-
tain, the arbitration awards should be vacated under
§ 10(a)(1).
MCI and National Union’s difficulty, however, is that no
court has ever suggested that the term "undue means" should
be interpreted to apply to actions of counsel that are merely
legally objectionable. See A.G. Edwards, 967 F.2d at 1403-04
(defining "undue means" as conduct "that is immoral if not
illegal"; holding that the term does not apply to defendant’s
raising of frivolous defenses during arbitration, or "sloppy or
overzealous lawyering").
Further, while there is some evidence in the record to sup-
port MCI and National Union’s assertions that the City pres-
ented its main arguments on rebuttal and that—on at least one
occasion—it referred to evidence outside the record, Appel-
MCI CONSTRUCTORS v. CITY OF GREENSBORO 15
lants fail to establish that these actions led to the procurement
of the award. See PaineWebber Group, Inc. v. Zinsmeyer
Trusts P’ship, 187 F.3d 988, 994 (8th Cir. 1999) ("[T]here
must be some causal relation between the undue means and
the arbitration award."); Bonar, 835 F.2d at 1385 (finding an
arbitration award was procured through undue means where
"[t]he arbitrators’ written award, although brief, reflects the
influence of [the fraudulent] testimony"); see also Black’s
Law Dictionary 1327 (9th ed. 2009) (defining "procurement"
as "the act of getting or obtaining something or of bringing
something about"). As § 10(a)(1) "does not provide for vaca-
tur in the event of any fraudulent conduct, but only where the
award was procured by corruption, fraud, or undue means,"
Forsythe Int’l, S.A. v. Gibbs Oil Co. of Tex., 915 F.2d 1017,
1022 (5th Cir. 1990) (internal quotations omitted) (emphasis
in original), and MCI and National Union have not proffered
any evidence that the undue means in dispute actually fac-
tored into the arbitration panel’s liability determination,6 we
find the district court did not err in denying MCI and National
Union’s motion to remand on this basis.7
6
MCI and National Union argue that requiring the showing of a causal
connection would impose an impossible burden because the arbitration
panel did not state the reasons for its decision in this case. We disagree.
Arbitration panels are not required to explain their decisions. See Wilko v.
Swan, 346 U.S. 427, 436 (1953), overruled on other grounds, Rodriguez
de Quijas v. Shearson/Am. Express, Inc., 490 U.S. 477, 484 (1989). Thus,
eliminating the need to prove a causal connection whenever an award is
unexplained would effectively read the "procured by" requirement out of
the statute, and would be inconsistent with the limited nature of judicial
review of arbitration awards. See A.G. Edwards, 967 F.2d at 1403. Such
a result could lead to parties attempting to circumvent the narrow scope
of our review by purposefully declining to request reasoned awards and
thereby avoiding the burden of showing the "procured by" requirement if
they later chose to challenge the award.
7
MCI and National Union also argue that the district court erred in con-
firming the award, because by breaching the arbitration agreement, the
City lost the ability to proceed under that agreement, and consequently,
any award arising out of that agreement cannot be enforced. Specifically,
MCI and National Union maintain that the City breached the arbitration
16 MCI CONSTRUCTORS v. CITY OF GREENSBORO
2.
We next determine whether the arbitration panel exceeded
the scope of its powers in issuing the damages award. MCI
and National Union argue that the arbitration panel exceeded
its powers in awarding any money to the City, because there
is no reasonable interpretation of the contract that excused the
City’s failure to comply with Articles 9.11 and 11 of the con-
tract. They assert that the City’s failure to comply with these
articles bars the City from recovering any money from MCI
and National Union.
MCI and National Union’s argument flows from their inter-
pretation of specific provisions of the contract. Article 15,
entitled, "Suspension of Work and Termination," provides
that
if CONTRACTOR persistently fails to perform the
Work in accordance with the Contract Documents
agreement by actively seeking to prevent MCI from fully and fairly pre-
senting its case to the arbitrators, and by preventing MCI from arguing the
facts of the case de novo. Thus, they maintain the district court should not
have confirmed the award because there no longer was a valid agreement
between the parties to arbitrate. In support of this argument, MCI and
National Union rely on Hooters of America, Inc. v. Phillips, 173 F.3d 933,
938 (4th Cir. 1999), in which we held that a party "materially breached the
arbitration agreement by promulgating rules so egregiously unfair as to
constitute a complete default of its contractual obligation to draft arbitra-
tion rules and to do so in good faith."
Hooters is distinguishable. In Hooters, this court emphasized that it
"only reach[ed] the content of the arbitration rules because their promulga-
tion was the duty of one party," id. at 941, and the case involved the
unique situation where the procedural rules were "so one-sided that their
only possible purpose [was] to undermine the neutrality of the proceed-
ing," id. at 938. By contrast, here MCI received a fundamentally fair hear-
ing and the arbitrators applied the procedural rules governing the
arbitration in an impartial manner. Further, there is nothing to indicate that
one party, namely, the City, was solely responsible for selecting the arbi-
tral rules. Thus, we find Hooters inapposite and MCI and National
Union’s argument without merit.
MCI CONSTRUCTORS v. CITY OF GREENSBORO 17
. . . OWNER may, after giving CONTRACTOR . . .
seven days’ written notice . . . terminate the services
of CONTRACTOR . . . and finish the Work as
OWNER may deem expedient. In such case CON-
TRACTOR shall not be entitled to receive any fur-
ther payment until the Work is finished. . . . If [all]
claims, costs, losses and damages [arising out of or
resulting from completing the Work] exceed [the]
unpaid balance [of the Contract Price], CONTRAC-
TOR shall pay the difference to OWNER. Such
claims, costs, losses and damages incurred by
OWNER will be reviewed by ENGINEER as to their
reasonableness and when so approved by ENGI-
NEER incorporated in a Change Order, provided
that when exercising any rights or remedies under
this paragraph OWNER shall not be required to
obtain the lowest price for the Work performed.
J.A. 207 (emphasis added). There is evidence in the record
showing that the City detailed its claims, costs, losses and
damages, submitted them to Hazen and Sawyer, and that
Hazen and Sawyer approved those claims, costs, losses and
damages in a Change Order, which ultimately changed the
Contract Price. MCI and National Union note, however, that
pursuant to Article 11, entitled "Change of Contract Price,"
the Contract Price could only be changed if "[the] claim for
an adjustment in the Contract Price [was] based on written
notice delivered by the party making the claim to the other
party and the ENGINEER," or if the parties could not agree
on the amount involved, the "claim[ ] for adjustment in the
Contract Price [was] determined by ENGINEER in accor-
dance with [Article] 9.11."8 J.A. 198-99. Article 9.11 states:
8
As further evidence of this requirement, MCI and National Union point
to Article 1.9 of the contract. That article defines a "Change Order" as "[a]
document recommended by ENGINEER, which is signed by CONTRAC-
TOR and OWNER and authorizes . . . an adjustment in the Contract
Price." J.A. 179. MCI and National Union explain that MCI would have
signed this Change Order only if it had been submitted to Hazen and Saw-
yer pursuant to the requirements of Articles 9 and 11.
18 MCI CONSTRUCTORS v. CITY OF GREENSBORO
"Claims, disputes and other matters relating to . . . the inter-
pretation of the requirements of the Contract Documents per-
taining to the performance and furnishing of the Work and
Claims under Articles 11 and 12 in respect of changes in the
Contract Price . . . will be referred initially to ENGINEER in
writing with a request for a formal decision." J.A. 197.
Because MCI and the City did not agree on the amount of
the Contract Price, MCI and National Union maintain that the
City was required to submit this issue to Hazen and Sawyer
pursuant to Article 9.11. The City, however, never did so, and
thus, MCI and National Union insist that, pursuant to Article
11.2, the City was barred from adjusting the Contract Price,
especially since Article 11 specifies that "[n]o claim for an
adjustment in the Contract Price will be valid if not submitted
in accordance with . . . paragraph 11.2." J.A. 198-99 (empha-
sis added). MCI and National Union maintain that, without an
adjustment to the Contract Price, the City cannot be entitled
to any monetary award.
Contrary to MCI and National Union’s assertions, however,
the contract can be reasonably interpreted not to require the
City to submit its claim for an adjustment in the Contract
Price to Hazen and Sawyer, as otherwise required by Articles
9.11 and 11 of the contract. See Walton v. City of Raleigh, 467
S.E.2d 410, 412 (N.C. 1996) ("Parties can differ as to the
interpretation of [contract] language without its being ambig-
uous."). Article 15 is divided into two parts: when the City
may suspend the work, and when the City may terminate
MCI’s services. Under Article 15.1, entitled "OWNER May
Suspend Work," there is a direct reference to Article 11:
"CONTRACTOR shall be allowed an adjustment in the Con-
tract Price . . . directly attributable to any . . . suspension if
CONTRACTOR makes an approved claim therefor as pro-
vided in Articles 11 and 12." J.A. 206. By contrast, Article
15.2, entitled "OWNER May Terminate"—the article impli-
cated here—makes no mention of Article 11, thereby suggest-
ing that the contract did not require the City to submit Change
MCI CONSTRUCTORS v. CITY OF GREENSBORO 19
Order disputes to Hazen and Sawyer when termination was
involved. See Marcoin, Inc. v. McDaniel, 320 S.E.2d 892, 897
(N.C. App. 1984) ("[A] contract must be construed as a
whole, considering each clause and word with reference to all
other provisions and giving effect to each whenever possi-
ble."). Thus, the City’s failure to comply with Articles 9.11
and 11 of the contract, under this interpretation of the con-
tract, would not bar recovery.
Even if Articles 9.11 and 11 were controlling here, we find
that MCI and National Union would not be entitled to relief.
We have held as a matter of law that "neither misinterpreta-
tion of a contract nor an error of law constitutes a ground on
which an award can be vacated." Apex Plumbing Supply, Inc.
v. U.S. Supply Co., Inc., 142 F.3d 188, 193-94 (4th Cir. 1998)
(internal quotations omitted). As the City notes, MCI and
National Union’s argument that the arbitration panel exceeded
its authority is essentially a disagreement with the arbitration
panel’s construction of the contract. MCI and National Union
present no facts to support their allegation that the arbitration
panel exceeded its authority, and the evidence reveals that the
parties’ claims were referred to the arbitration panel pursuant
to an arbitration agreement, signed by the parties indepen-
dently of the contract, which authorized the panel to resolve
"all outstanding issues between them," J.A. 2621, and to issue
a decision that "w[ould] be final and binding," J.A. 2634. In
fact, this exact question—that is, the validity of the Change
Order and whether, under Articles 9.11 and 11, the City was
required to submit the issue of the Contract Price to Hazen
and Sawyer first—was decided by the arbitration panel and
factored into the damages award. "As long as the arbitrator[s]
[are] even arguably construing or applying the contract," as
they were here, their awards will not be disturbed. Norfolk &
W. Ry. Co. v. Transp. Commc’ns Int’l Union, 17 F.3d 696,
700 (4th Cir. 1994). We thus find the arbitration panel did not
exceed the scope of its powers in issuing the damages award.
20 MCI CONSTRUCTORS v. CITY OF GREENSBORO
3.
MCI and National Union maintain that the damages award
must be vacated because that award irrationally disregards
unambiguous provisions of the contract. They contend that
the arbitration panel’s award does not "draw its essence" from
the parties’ contract because it does not discuss whether argu-
ments offered by MCI regarding Articles 9.11 and 11 of the
contract defeated the City’s damages claim. In support of this
argument, MCI and National Union cite Clinchfield Coal Co.
v. District 28, United Mine Workers of America, 720 F.2d
1365, 1369 (4th Cir. 1983), in which we held that "[w]here
. . . the arbitrator fails to discuss critical contract terminology,
which terminology might reasonably require an opposite
result, the award cannot be considered to draw its essence
from the contract."
Clinchfield is distinguishable. In that case, we found the
arbitration award did not draw its essence from the contract
because the arbitrator’s decision seemed impossible to square
with certain provisions of the contract. See id. ("[A] reason-
able interpretation of [the operative] clause . . . require[s] a
contrary result."). Here, as explained above, Articles 9.11 and
11 of the contract do not require an opposite result from that
reached by the arbitration panel, and thus, the panel was not
required to discuss these articles in its awards. See Upshur
Coals Corp. v. United Mine Workers of Am., Dist. 31, 933
F.2d 225, 230 (4th Cir. 1991) ("We do not and need not
decide whether any of these analyses constitute the best or
most accurate reading of the contract. We hold only that they
are plausible readings of the agreement. . . . Consequently, . . .
we cannot say that the arbitration award failed to draw its
essence from the agreement.").
Further, it bears noting that an arbitration award "does not
fail to draw its essence from the agreement merely because a
court conclude[s] that an arbitrator has misread the contract."
Patten, 441 F.3d at 235 (internal quotation marks omitted). As
MCI CONSTRUCTORS v. CITY OF GREENSBORO 21
explained above, "as long as the arbitrator is even arguably
construing or applying the contract and acting within the
scope of his authority, that a court is convinced he committed
serious error does not suffice to overturn his decision." U.S.
Postal Serv. v. Am. Postal Workers Union, AFL-CIO, 204
F.3d 523, 527 (4th Cir. 2000) (internal quotations omitted).
We thus find that the district court did not err in denying
MCI and National Union’s motion to vacate the arbitration
awards. The record does not support MCI and National
Union’s arguments that the liability award was procured by
undue means. Nor have MCI and National Union sufficiently
shown that to issue the damages award, the arbitration panel
had to exceed the scope of its powers, or that this award does
not draw its essence from the contract.
C.
Finally, we consider MCI and National Union’s argument
that the district court should have remanded the case to the
arbitrators. MCI and National Union present two arguments
on this issue. First, they maintain that the damages award is
ambiguous and thus remand was required. Second, they con-
tend that the arbitration agreement required the arbitration
panel to issue a reasoned award, and as such, the district court
erred in denying MCI’s motion to remand. We consider each
argument in turn. We review the district court’s decision not
to remand the award to the arbitration panel for an abuse of
discretion. Raymond James Fin. Servs., Inc. v. Bishop, 596
F.3d 183, 190 (4th Cir. 2010).
1.
We first consider MCI and National Union’s argument that
because the arbitration panel did not specify the basis for its
damages award, that award is ambiguous, thus requiring
remand to the arbitrators. MCI and National maintain that
"[r]emand is required because the [damages award] fails to
22 MCI CONSTRUCTORS v. CITY OF GREENSBORO
answer how much must be paid to satisfy the award." Appel-
lants’ Br. at 44. MCI and National Union explain that the
award provides that the City "is entitled to recover from MCI
the sum of $14,939,004," id., but does not explain whether
MCI must pay that full amount to the City, or whether that
amount must be processed under Article 15.2 of the contract,
which provides that "[i]f . . . claims, costs, losses and dam-
ages exceed [the] unpaid balance, CONTRACTOR shall pay
the difference to the OWNER." J.A. 207 (emphasis added).
Because the arbitration panel did not explain whether it sub-
tracted the unpaid balance of the Contract Price from the
Award ($9,667,357), MCI and National Union insist that the
award must be remanded for further explanation—that is, to
explain whether MCI owes $14,939,004 or $5,271,647. We
disagree.
It is well settled that arbitrators are not required to disclose
the basis upon which their awards are made and courts will
not look behind a lump-sum award in an attempt to analyze
their reasoning process. See United Steelworkers of Am. v.
Enter. Wheel & Car Corp., 363 U.S. 593, 598 (1960); see
also Remmey v. PaineWebber, Inc., 32 F.3d 143, 151 (4th Cir.
1994) ("[A]rbitrators need not state reasons for reaching a
particular result"); In re Arbitration No. AAA13-161-0511-85
Under Grain Arbitration Rules, 867 F.2d 130, 135 (2d Cir.
1989) ("[A]rbitrators may render a lump sum award without
disclosing their rationale for it, and . . . when they do, courts
will not inquire into the basis of the award unless they believe
that the arbitrators rendered it in ‘manifest disregard’ of the
law or unless the facts of the case fail to support it.") (internal
quotations omitted); Sargent v. Paine Webber Jackson & Cur-
tis, Inc., 882 F.2d 529, 532 (D.C. Cir. 1989) ("We reject the
idea that a lump-sum award can be rejected for want of expla-
nation (or, what is in effect almost the same thing, remanded
for an explanation) in the absence of facts making it appear
probable that the arbitrators committed an error justifying
vacation of the award.").
MCI CONSTRUCTORS v. CITY OF GREENSBORO 23
Further, this exact issue was presented to the arbitration
panel in MCI’s email to the panel on April 24, 2008. See J.A.
7409 ("[I]t appears that th[e] Panel failed to deduct MCI’s
$9,667,357 Contract Balance from the $14,939,004 amount
that the Panel determined was owed to the City. MCI formally
requests that the Award be modified . . . to reflect that, after
taking into account MCI’s Contract Balance, MCI must pay
the City $5,271.647 plus interest."). In response, the arbitra-
tion panel explained that "[t]he Damages Award did not con-
tain any errors and the arbiters have already decided all claims
submitted to them. MCI’s request to modify the Damage
Award is [therefore] DENIED." J.A. 7416. In light of the
arbitration panel’s response, we find there is no ambiguity
here that would require a remand.9
2.
MCI and National Union also insist that remand was neces-
sary because the arbitration panel failed to issue a reasoned
award as was required by the arbitration agreement. MCI and
National Union maintain that the arbitration agreement is gov-
erned by the Judicial Arbitration Mediation Services
("JAMS") Rule 24(h), which requires arbitration awards to
contain, "[u]nless all Parties agree otherwise, . . . a concise
written statement of the reasons for the Award[s]." JAMS,
Comprehensive Arbitration Rules & Procedures 23 (July 15,
2009), http://www.jamsadr.com/files/Uploads/Documents/
JAMS-Rules/JAMS_comprehensive_arbitration_rules-2009.
9
Further, the record reflects that MCI and the City submitted separate
estimates detailing how much the City is entitled to recover, and their
arguments as to these amounts are clearly set forth in the record of the
arbitration proceedings. In fact, we note that the City requested an award
of over $17 million, after subtracting the Contract Balance. Thus, as the
district court found, the panel’s award seems reasonable under the circum-
stances. See Apex Plumbing, 142 F.3d at 194 ("Where no mathematical
error appears on the face of the award . . . an arbitration award will not
be altered.") (internal quotations omitted) (alteration in original).
24 MCI CONSTRUCTORS v. CITY OF GREENSBORO
pdf. Thus, they argue, a reasoned award was mandated here.
We disagree.
MCI and National Union misinterpret the nature of the
arbitration agreement. As explained by the district court, the
arbitration agreement provides that "[e]xcept as provided
herein or otherwise agreed," the arbitration "would be [con-
ducted pursuant to] standard AAA Complex Commercial or
JAMS rules." J.A. 2634 (emphasis added). The only excep-
tion specified in the arbitration agreement is that "[i]f MCI
prevail[ed] at the [Liability] Phase," the arbitration panel was
required to apply the AAA Rules and Procedures for Large,
Complex Construction Disputes. J.A. 2636. Because MCI did
not prevail at the liability phase, the arbitration panel was free
to apply either the AAA Complex Commercial Arbitration
Rules or the JAMS Comprehensive Arbitration Rules and
Procedures. The arbitration panel elected to proceed under the
AAA Complex Commercial Arbitration Rules. Under Rule
42(b) of these rules, an arbitration panel "need not render a
reasoned award unless the parties request such an award in
writing prior to appointment of the arbitrator or unless the
arbitrator determines that a reasoned award is appropriate."
American Arbitration Association, Commercial Arbitration
Rules and Mediation, http://www.adr.org/sp.asp?id=
22440#R42 (last visited June 7, 2010). In the instant case,
none of the parties requested a reasoned damages award
before the appointment of the arbitrators, and thus, the arbitra-
tion panel was not required to issue such an award.
Nevertheless, MCI and National Union argue that "[t]he
District Court committed clear error in concluding that ‘none
of the parties requested a reasoned Damages Award before
the Panel rendered its damages decision.’" Appellants’ Br. at
46 (citing J.A. 7917). They note that MCI requested a rea-
soned damages award during the hearing, before the panel
rendered its damages decision. See, e.g., J.A. 7381 ("I agree
with Mr. Meeker that the rules are contradictory. We think the
proper resolution of that contradiction is for the requirement
MCI CONSTRUCTORS v. CITY OF GREENSBORO 25
of the more fulsome award should govern, and we would like
a reasoned award."). Even so, we find the district court did
not abuse its discretion in denying MCI’s motion to remand.
The AAA Complex Commercial Arbitration Rules require the
party seeking a reasoned award to submit its request "prior to
the appointment of the arbitrator[s]," not prior to the issuance
of the arbitration award. American Arbitration Association,
Commercial Arbitration Rules and Mediation, http://
www.adr.org/sp.asp?id=22440#R42 (last visited June 7,
2010). Here, the request was not made prior to the appoint-
ment of the arbitrators, and thus, the panel was not required
to provide a reasoned award. Therefore, the factual error
made by the district court does not affect the resolution of this
issue.
Accordingly, we find the district court did not abuse its dis-
cretion in denying MCI’s motion to remand.
III.
In conclusion, we hold that the district court did not abuse
its discretion in certifying the judgment as final under Rule
54(b), primarily because the relationship between the adjudi-
cated and unadjudicated claims was severed by virtue of the
parties’ own admissions. We also hold that the district court
did not err in denying MCI and National Union’s motion to
vacate the arbitration awards. The record does not support
MCI and National Union’s contentions that the liability award
was obtained through undue means, that the arbitration panel
exceeded the scope of its powers to issue the damages award,
or that the damages award does not draw its essence from the
contract. Finally, we hold that the district court did not abuse
its discretion in denying MCI’s motion to remand. The dam-
ages award is not ambiguous, and the arbitration agreement
did not require the arbitration panel to issue a reasoned award.
26 MCI CONSTRUCTORS v. CITY OF GREENSBORO
For the foregoing reasons, we affirm the judgment of the
district court.10
AFFIRMED
10
The City asks that we impose sanctions against MCI and National
Union pursuant to B.L. Harbert International, LLC v. Hercules Steel Co.,
441 F.3d 905 (11th Cir. 2006), overruled on other grounds, Hall Street,
552 U.S. 576, as recognized by, Frazier v. CitiFinancial Corp., LLC, Nos.
08-15188, 08-15709, 2010 WL 1727446 (11th Cir. Apr. 30, 2010). In that
case, the Eleventh Circuit explained that "it may be that we can and should
insist that if a party on the short end of an arbitration award attacks that
award in court without any real legal basis for doing so, that party should
pay sanctions." Id. at 913. Because we find that MCI and National Union
did have a real legal basis for pursuing this appeal, we decline to grant the
City’s request.