SQUARE D ENVIRONMENTAL CORPORATION
v.
AERO MECHANICAL, INC.
Docket No. 57481.
Michigan Court of Appeals.
Decided September 22, 1982.Ginn, Kramer & Jacobson, P.C. (by Marty A. Burnstein), for plaintiff.
Federlein & Grylls, P.C. (by Walter J. Federlein), for defendants.
Before: V.J. BRENNAN, P.J., and D.C. RILEY and V.R. PAYANT,[*] JJ.
*742 PER CURIAM.
The sole issue on appeal is whether as a prerequisite to recover against a payment bond pursuant to MCL 129.201 et seq.; MSA 5.2321(1) et seq., a subcontractor needs to strictly comply with the provisions of that statute. The trial court concluded that strict compliance was necessary and, therefore, granted a motion for summary judgment dismissing plaintiff's claim against the payment bond.
Square D Environmental Corporation (Square D) was a subcontractor of Aero Mechanical, Inc. (Aero), which was a subcontractor of the principal general contractor, Elgin Builders, Inc. (Elgin). The Insurance Company of North America (INA) was the surety to the City of Detroit in the amount of $3,695,000, on behalf of Elgin. Square D took a default judgment against now-bankrupt Aero for $154,819.94, which has not been appealed, set aside or satisfied. The instant action was commenced on March 14, 1980, for unpaid labor and material in the amount of $154,819.94 against the statutory payment bond.
The basis of Square D's claim is MCL 129.207; MSA 5.2321(7), which states:
"A claimant not having a direct contractual relationship with the principal contractor shall not have a right of action upon the payment bond unless (a) he has within 30 days after furnishing the first of such material or performing the first of such labor, served on the principal contractor a written notice, which shall inform the principal of the nature of the materials being furnished or to be furnished, or labor being performed or to be performed and identifying the party contracting for such labor or materials and the site for the performance of such labor or the delivery of such materials, and (b) he has given written notice to the principal contractor and the governmental unit involved within 90 days from the date on which the *743 claimant performed the last of the labor or furnished or supplied the last of the material for which the claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed." (Emphasis added.)
There existed no direct contractual relationship between Elgin and Square D. Elgin stipulates that it had knowledge that Square D was a subcontractor performing labor and furnishing materials on the public project. A stipulation signed and dated on August 8, 1980, between Elgin and Square D, sets forth that the former had actual knowledge of the materials furnished or to be furnished, of the labor performed or to be performed, and the site of such labor and materials used. On appeal, Elgin claims that the stipulation only acknowledges Square D's presence on the site and not the specific material and labor furnished. A plain reading of the stipulation does not bear out this contention.
The multifaceted argument that the public bond statute should be liberally construed has been considered in Charles W Anderson Co v Argonaut Ins Co, 62 Mich. App. 650; 233 NW2d 691 (1975), lv den 395 Mich. 815 (1975) (BRENNAN, J., dissenting), and John A Hall Construction Ck v Boone & Darr, Inc, 102 Mich. App. 786; 302 NW2d 850 (1981). The Anderson and Hall Courts concluded that strict compliance with the notice requirements was necessary.
Plaintiff argues that by analogy to the Michigan mechanics' lien act, MCL 570.1 et seq.; MSA 26.281 et seq., and the federal projects bonding act, 40 USC 270(a) et seq., both of which are liberally construed, the public bond statute at issue should also be liberally construed. The mechanics' lien act *744 specifically states it is to be liberally construed. MCL 570.27; MSA 26.307.
The analogy to the mechanics' lien act is unpersuasive because of the difference in the applicable areas of the law involved. Mechanics' liens have been statutorily provided since 1827 and furnished protection for large and small businessmen against sophisticated and unsophisticated customers. As a result of the nature of the transactions, often very unbusinesslike, the act must be liberally construed. Municipal law, on the other hand, is highly regulated by nature and governed by contracts and statutes which precisely define the rights and remedies of the parties. Liberal construction, therefore, is unnecessary as the parties need only follow the specific step-by-step procedures enacted to protect their interests.
The federal public bond act has been liberally construed by the federal courts since well before the 1973 amendment of the Michigan public bond statute. American Surety Co v Lawrenceville Cement Co, 110 F 717, 719 (D Me, 1901). The Michigan Legislature was aware, or should have been, of the liberal interpretation given the federal act, but chose not to specify that the state act be liberally construed.
We conclude that the rationale of Anderson and Hall is controlling and, therefore, the trial court did not err in concluding that the law of this state requires strict construction of the public bond act.
Plaintiff also raises a constitutional issue that the public bond statute violates due process and equal protection. In Shavers v Attorney General, 402 Mich. 554, 612-613; 267 NW2d 72 (1978), the Court stated:
"`The test to determine whether legislation enacted *745 pursuant to the police power comports with due process is whether the legislation bears a reasonable relation to a permissible legislative objective. See Michigan Canners v Agricultural Bd, 397 Mich. 337, 343-344; 245 NW2d 1 (1976).
"`The test to determine whether a statute enacted pursuant to the police power comports with equal protection is, essentially, the same. As the United States Supreme Court declared in United States Dep't of Agriculture v Moreno, 413 U.S. 528, 533; 93 S. Ct. 2821; 37 L. Ed. 2d 782 (1973):
"`"Under traditional equal protection analysis, a legislative classification must be sustained, if the classification itself is rationally related to a legitimate governmental interest."'"
This Court reviews plaintiff's claim with the above principles in mind, as well as the presumption of constitutionality that the statute enjoys. O'Brien v Hazelet & Erdal, 410 Mich. 1, 17; 299 NW2d 336 (1980). The notice provision bears a reasonable relation to the legislative objective of establishing an orderly and systematic presentment of claims. We conclude that the statute is constitutional.
Affirmed.
No costs, a statutory interpretation being involved.
V.J. BRENNAN, P.J. (dissenting).
I respectfully dissent. In Charles W Anderson Co v Argonaut Ins Co, 62 Mich. App. 650; 233 NW2d 691 (1975), lv den 395 Mich. 815 (1975), relied upon by the majority in the present case, I dissented because I disagreed with the majority's conclusion that strict compliance with the notice requirement of MCL 129.207; MSA 5.2321(7) was necessary. Because the Supreme Court denied leave to appeal in that case *746 and has not addressed the issue, I adhere to the opinion that I expressed in my dissent:
"It is my considered opinion that under the present law, MCL 129.201 et seq.; MSA 5.2321(1) et seq., substantial compliance with the terms of the statute by a `claimant not having a direct contractual relationship with the principal contractor' is sufficient to allow the claimant to proceed against the payment bond for the amount due and owing for labor or materials furnished for the performance of the contract and that in the absence of some showing of prejudice a surety may not benefit by a subcontractor's noncompliance with the statute." Anderson, supra, 655.
The basis of my opinion is fully set forth in my dissent in Anderson, supra, 655-657, and need not be repeated here. Therefore, I would reverse the decision of the trial court.
NOTES
[*] Circuit judge, sitting on the Court of Appeals by assignment.