UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
No. 93-2178
PERDONI BROTHERS, INC.,
Plaintiff, Appellee,
v.
CONCRETE SYSTEMS, INC.,
Defendant, Appellant.
APPEAL FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MASSACHUSETTS
[Joyce L. Alexander, U.S. Magistrate Judge]
Before
Breyer,* Chief Judge,
Campbell, Senior Circuit Judge,
and Cyr, Circuit Judge.
John M. Lovely, with whom Daniel F. Cashman and Gelerman &
Cashman were on brief for appellant.
Valeriano Diviacchi, with whom Diviacchi Law Office was on brief
for appellee.
September 2, 1994
*Chief Judge Stephen Breyer heard oral argument in this matter,
but did not participate in the drafting or the issuance of the panel
opinion. The remaining two panelists therefore issue this opinion
pursuant to 28 U.S.C. 46(d).
CYR, Circuit Judge. Defendant-appellant Concrete
CYR, Circuit Judge
Systems, Inc. (CSI), a New Hampshire producer of pre-cast con-
crete products, contracted in 1985 with plaintiff-appellee
Perdoni Brothers, Inc. (Perdoni), a Massachusetts-based construc-
tion firm, to manufacture and deliver 121 custom-designed man-
holes, at a total contract price of $51,670.47, for installation
in a new sewer system in the Town of Ashland, Massachusetts. CSI
contends that the district court committed reversible error in
denying its post-verdict motion for judgment as a matter of law.
See Fed. R. Civ. P. 50. For the reasons hereinafter discussed,
we affirm the district court judgment.
I
BACKGROUND
The first five manholes were delivered to the Perdoni
job site by CSI on July 2, 1985. The remaining 116 manholes were
delivered intermittently in twenty-six shipments extending over
the next thirteen months and invoiced by individual shipment.
Dissatisfied with the CSI manholes (which leaked and
had to be patched),1 Perdoni brought this diversity action in
1Sewer line manholes must be watertight. A common point of
leakage is the area where the sewer lines enter the manhole
structure. Precise casting, as well as installation of rubber
"boots" to ensure a tight fit between the wall of the structure
and the sewer line itself, is necessary to ensure the integrity
of the manhole. At trial, Perdoni adduced evidence that CSI had
used a defective hole former to cast the manholes for the Ashland
project. Consequently, the pipe openings in the sides of the
manholes were misshapen and the seals between the boot and rim of
the openings were not watertight.
2
federal district court on April 25, 1990, demanding $134,000 in
compensatory damages for breach of the implied warranties of
merchantability and fitness for a particular purpose (implied
warranty claims), see Mass. Gen. L. ch. 106 2-314, 2-315, and
additional damages based on a deceptive trade practices claim
under Mass. Gen. L. ch. 93A ("Chapter 93A"). CSI counterclaimed
for $18,561 allegedly due from Perdoni on the Ashland project and
another contract.
Trial was held before a magistrate judge, with the
consent of the parties. See 28 U.S.C. 636(c). The implied
warranty claims were tried to a jury, while the Chapter 93A claim
was tried to the presiding magistrate judge. It was not until
after the close of all the evidence that CSI first moved for
judgment as a matter of law on the implied warranty claims
relating to 108 of the 121 manholes. The uncontroverted evidence
demonstrated that only 13 manholes had been delivered by CSI
within four years of the commencement of the present action. CSI
accordingly contended that Perdoni's implied warranty claims
relating to the other 108 manholes were time-barred under Mass.
Gen. L. ch. 106 2-725(1) (prescribing four-year limitation on
Uniform Commercial Code warranty actions); id. 2-725(2) (action
for breach of warranty under UCC accrues on "tender of delivery"
of goods). The magistrate judge denied CSI's motion for judgment
as a matter of law.
Thereafter, the magistrate judge convened a charge
conference to consider the jury instructions, including the
3
instruction on the statute-of-limitations defense. Neither party
requested an instruction on the law governing the severability-
entirety issue. Although Perdoni unsuccessfully sought an
instruction that the contract should be considered an entirety,
CSI made no corresponding request for an instruction that the
contract be considered severable. Consequently, the magistrate
judge simply instructed the jury that CSI had the burden of
proving that the action was time-barred, and that the four-year
limitation period ran from the "time of delivery." Although both
parties argued the severability-entirety issue, the court made no
explicit reference to it and neither party objected to the jury
instruction as given.2 The jury found in favor of Perdoni-
2The instruction relating to the statute of limitations
follows:
[T]here is also an issue arising from [CSI's]
asserted defense based on . . . the statute
of limitations.
This is simply a provision that a suit
be commenced on certain types of claims with-
in a prescribed period of time, otherwise,
the suit is barred or precluded. For a
breach of warranty claim, the applicable
statute of limitations for an action on a
contract for the sale of goods is four years.
That means that a plaintiff has four
years to bring a suit for a breach of war-
ranty. The time limit placed upon Perdoni
began to run at the time of delivery of the
manholes, regardless of whether Perdoni knew
of the breach. Thus within four years of the
time which Perdoni received the manholes, it
must have commenced this lawsuit.
* * *
It is [CSI's] burden to show that Perd-
oni has not complied with the statute of
limitations, thus [CSI] has the burden of
establishing that Perdoni filed a suit more
than four years after the delivery of the
4
for $48,961, and in favor of CSI for $18,561 on its counter-
claim. CSI then renewed its Rule 50 motion for judgment as a
matter of law and, alternatively, moved for a new trial under
Fed. R. Civ. P. 59. The magistrate judge did not address the
merits of the CSI motion, however, ruling instead that CSI had
waived its severability claim, both by failing to object to the
jury instruction and by failing to raise the severability argu-
ment in its pre-verdict Rule 50 motion.3 Nonetheless, the
manholes, and if Perdoni did not commence the
suit within the four-year period, Perdoni may
not recover on its warranty theories.
Trial Tr. at 168 (April 16, 1993) (emphasis added).
3The magistrate judge noted that:
This Court instructed [the jury] that,
as an affirmative defense, CSI had the burden
of proving . . . that Perdoni filed the suit
more than four years after delivery of the
manholes. CSI did not object to this
instruction. Nor did CSI submit an
instruction based on the law governing divis-
ibility of performance, entire contracts,
separate contracts and installment contracts.
CSI was apparently content to treat the
question of what constitutes the time of
delivery as an issue of fact. CSI did move
for a directed verdict on this issue, but,
again, this motion was predicated on the
evidence being clear as to the tender of
delivery and included no argument as to the
law governing divisibility of performance,
entire contracts, separate contracts and
installment contracts. CSI's pretrial
memorandum was no more edifying on this
point. . . . This court finds it late in the
day to be raising the legal issue, and deems
the issue waived.
Perdoni Bros., Inc. v. Concrete Sys., Inc., Civ. 90-11046-WF,
Memorandum Order at 7-8 (D. Mass. August 27, 1993) (emphasis
added).
5
magistrate judge, sitting as trier of fact, found Perdoni's
Chapter 93A claim time-barred as it pertained to 108 of the 121
manholes. CSI appealed the denial of its post-verdict motion for
judgment as a matter of law or for a new trial on the implied
warranty claims. See Fed. R. Civ. P. 50(b), 59. CSI's primary
appellate target is the district court's waiver ruling on the
severability issue.
II
DISCUSSION
Leaving aside CSI's failure to object to the jury
instruction on the statute-of-limitations defense, the district
court waiver ruling is fully supported by CSI's failure to raise
the severability argument in its pre-verdict motion for judgment
as a matter of law. The law is crystal clear that a "party may
not base its motion for a judgment n.o.v. on a ground that was
not argued in its motion for directed verdict." Sweeney v.
Westvaco Co., 926 F.2d 29, 37 (1st Cir.) (citing Systemized of
New England, Inc. v. SCM, Inc., 732 F.2d 1030, 1035 (1st Cir.
1984)), cert. denied, 112 S. Ct. 274 (1991); see also 9 Charles
A. Wright & Arthur R. Miller, Federal Practice & Procedure 2537
(1971) ("Since it is technically only a renewal of the motion . .
. made at the close of evidence, [a post-verdict Rule 50 motion]
cannot assert a ground that was not included in the motion for a
directed verdict."); 5A James W. Moore, Moore's Federal Practice
50.08 (2d ed. 1994) (same). Sweeping invocations of conclusory
6
theories or abstract principles will not suffice: "The motion
must . . . be made with sufficient specificity to allow the
district court to understand precisely why the evidence is
insufficient." Wells Real Estate, Inc. v. Greater Lowell Bd. of
Realtors, 850 F.2d 803, 810 (1st Cir.), cert. denied, 488 U.S.
955 (1988); Pstragowski v. Metropolitan Life Ins. Co., 553 F.2d
1, 3 (1st Cir. 1977) (where Rule 50 motion was silent as to the
legal theory that plaintiff was obliged to establish malice on
the part of the defendant, there was no basis for an appellate
challenge to the sufficiency of the evidence on the element of
malice). Ultimately, of course, "[a]ppellate review may be
obtained only on the specific ground stated in the motion for
directed verdict." Wells Real Estate, 850 F.2d at 810; Pstragows-
ki, 553 F.2d at 3 (same).
The pre-verdict motion for judgment as a matter of law,
see Fed. R. Civ. P. 50(a),(b), stressed the undisputed fact that
108 manholes were delivered more than four years prior to suit,
but presented no authority or argumentation whatever that the
contract should be considered severable (i.e., that Massachusetts
law permitted or required that the individual shipments of
manholes receive separate treatment for statute-of-limitation
purposes, rather than as an entire contract for 121 manholes).
The consequences of CSI's cryptic approach were foreordained.
Most importantly, the district court was never fore-
warned of the legal basis for the severability claim first
surfaced by CSI following the adverse jury verdict. Under our
7
precedent, therefore, on appeal CSI was not entitled to challenge
the sufficiency of the evidence supporting the jury verdict on
the limitations issue. See Wells Real Estate, 850 F.2d at 10;
Pstragowski, 553 F.2d at 3. The magistrate judge correctly ruled
that CSI was bound by its own pre-verdict decision to entrust its
severability claim to the jury with no further legal definition
than the unchallenged instruction that "accrual" under the
Massachusetts UCC occurs at the "time of delivery." See United
California Bank v. Eastern Mountain Sports, Inc., 546 F. Supp.
945, 964 (D. Mass. 1982) ("Under Massachusetts law, 'it is clear
that a cause of action . . . accrues when delivery is made
regardless of the buyer's knowledge of the breach.'") (quoting
Wolverine Ins. Co. v. Tower Iron Works, 370 F.2d 700, 702 (1st
Cir. 1966)), aff'd, 705 F.2d 439 (1st Cir. 1983); accord Bay
State-Spray & Provincetown S.S., Inc. v. Caterpillar Tractor Co.,
533 N.E.2d 1350, 1353 (Mass. 1989).4
Under Article 2 of the Uniform Commercial Code, the
severability or entirety of a contract of sale turns on the
4Counsel argued the severability-entirety issue in their
closings. CSI argued that the parties' performance under the
contract demonstrated their practice of treating each separately
invoiced shipment of manholes as a distinct transaction. See
Trial. Tr. at 141 ("really what is occurring here is a series of
contracts . . . . All the manholes were made to order. The
manholes that were shipped . . . in 1986 have no relation to the
manholes that were delivered as of November 14, 1985.") Perdoni,
on the other hand, urged the jury to view the contract as a
unitary whole, and to recognize that Perdoni required all of the
manholes in order to complete its contract project. Id. at 157
("if you ordered 12 eggs, and you get 10, you don't say, 'Thank
you for delivering my eggs.' . . . . [T]he full quantity ordered
was not delivered until July of 1986.").
8
intent of the contracting parties, see, e.g., Carlo Bianchi & Co.
v. Builders' Equip. & Supplies Co., 199 N.E.2d 519, 528 (Mass.
1964) (severability or entirety of contract dependent on intent
of parties) (citing, inter alia, Bianchi Bros., Inc. v. Gendron,
198 N.E. 767, 770 (Mass. 1935)); Belanger v. Haverlock, 537 A.2d
604 (Me. 1988) (same); Lake LBJ Mun. Util. Dist. v. Coulson &
C.A.E., Inc., 771 S.W.2d 145 (Tex. 1988) (same); Scruggs v.
Quality Elec. Serv., Inc., 320 S.E.2d 49 (S.C. 1984) (same); In
re Estate of Wilson, 405 N.E.2d 220 (N.Y. 1980); 1901 Wyoming
Ave. Coop. Assoc. v. Lee, 345 A.2d 456 (D.C. 1975); see also 17A
Am. Jur. 2d 415 (1991) ("Whether a contract is entire or
severable is a question of fact"), a quintessential jury ques-
tion. There can be no question that CSI elected to forego a more
definitive jury instruction on the law governing the severabili-
ty-entirety issue pressed on appeal. As was its right, CSI
simply attempted to persuade the jury that the parties intended a
severable contract. Having once embarked on this course, howev-
er, CSI was not entitled to set out on a new one after its chosen
litigation tactic failed. See Brody v. President & Fellows of
Harvard College, 664 F.2d 10, 12 (1st Cir. 1981) (noting that
litigants ordinarily are bound by their tactical decisions at
trial), cert. denied, 455 U.S. 1027 (1982). Thus, the district
court did not err in denying the motion for judgment as a matter
of law, since CSI "forfeited its right to raise the [severability
claim] by waiting to raise it until after the jury reached its
9
verdict." Sweeney, 926 F.2d at 37.5
Next, even assuming that it failed to preserve its
severability claim for appeal, CSI argues that a new trial is
required due to alleged inconsistencies between the jury's award
of damages on the implied warranty claims and the magistrate
judge's resolution of the limitations defense relating to the
Chapter 93A claim. We do not agree.
First, as no special interrogatory was submitted to the
jury on the limitations defense relating to the implied warranty
claims, it would be conjectural to conclude that the damages
awarded by the jury and the finding made by the magistrate judge
are irreconcilable. See Fed. R. Civ. P. 49(a) (right to trial on
particular issue waived absent request for specific jury find-
ing); Kavanaugh v. Greenlee Tool Co., 944 F.2d 7, 11 (1st Cir.
1991) (applying Rule 49 waiver provision). In determining the
intent of the contracting parties in this case, the jury may
either have found (1) that the contract was severable, and made a
generous award of damages (i.e., 37% of the total damages re-
quested by Perdoni on only 11% of the units supplied by CSI); or
(2) that the contract was not severable, and made a meager award
(i.e., 37% of the total damages requested by Perdoni on 100% of
the units supplied by CSI). The inconsistency posited by CSI is
5As CSI advances the same arguments in support of its appeal
from the denial of its Rule 59 motion, we conclude that the
district court likewise acted well within its discretion in
denying CSI's motion for new trial on the merits. See Phav v.
Trueblood, Inc., 915 F.2d 764, 766 (1st Cir. 1990) ("abuse of
discretion" standard governs review of denial of Rule 59 motion).
10
predicated on the assumption that the jury made a meager award of
damages, yet there is no record basis for such a conclusion.
Given the strong presumption of regularity attending jury ver-
dicts, see, e.g., Veiga v. McGee, 26 F.3d 1206, 1215 (1st Cir.
1994) (noting that reviewing court is compelled to uphold jury
verdict under Rule 50 "even in a close case" unless no reasonable
jury could have reached the same conclusion), we decline to
disturb the verdict on the basis of the assumed inconsistency
posited by CSI.
Second, CSI posits an inconsistency between the results
reached by different decisionmakers on distinct claims, and
incorrectly assumes that the jury verdict must yield. Where an
irreconcilable inconsistency exists between a bench decision and
a jury verdict on different claims arising out of the same
transaction, the jury finding must take precedence in the Seventh
Amendment context: "when a party has a right to a jury trial on
an issue involved in a legal claim, the judge is of course bound
by the jury's determination of that issue as it affects his
disposition of an accompanying equitable claim." Lincoln v.
Board of Regents, 697 F.2d 928, 934 (11th Cir.) (citing Curtis v.
Loether, 415 U.S. 189, 196 n.11 (1974); Dairy Queen, Inc. v.
Wood, 396 U.S. 469, 470-73 (1962)), cert. denied, 464 U.S. 826
(1983); Los Angeles Police Protective League v. Gates, 995 F.2d
1469, 1473 (9th Cir. 1993) (same); Fowler v. Land Management
Groupe, Inc., 978 F.2d 158, 163 (4th Cir. 1992) (same); Wade v.
Orange Cty. Sheriff's Office, 844 F.2d 951, 954 (2d Cir. 1988)
11
(same); see also Walsh v. Chestnut Hill Bank & Trust Co., 607
N.E. 2d 737, 740-41 (Mass. 1993) (noting "equitable" nature of
claims under Chapter 93A; no right to jury trial). Moreover, in
the Chapter 93A context, the court has recognized that judge and
jury, sitting as independent triers of fact, may reach
conflicting conclusions. Wallace Motor Sales, Inc. v. American
Motors Sales Corp., 780 F.2d 1049, 1063-67 (1st Cir. 1985)
(rejecting claim that judge's findings must always conform to
those of the jury; upholding findings made by district judge on
Chapter 93A claim and by jury on Dealers Act claim); accord
Fowler, 978 F.2d at 162-63 (concluding that under certain circum-
stances "it is entirely acceptable that the two fact-finders
reach conflicting conclusions on the issues"). Thus, even
assuming inconsistent findings, CSI's claim must fail. Cf.
Kavanaugh, 944 F.2d at 9 (noting this court's "substantial
reluctance to consider inconsistency [within] civil jury verdicts
a basis for new trials.")
Finally, permitting CSI to employ the bench ruling on
the severability issue as a lever with which to upset the jury
verdict would circumvent the important Rule 50 corollary that "a
party who move[s] for a directed verdict may obtain appellate
review only on the specific ground stated in the motion."
Pstragowski, 553 F.2d at 3 (emphasis added); accord Fleming James
Jr. et al., Civil Procedure 7.30 (4th ed. 1992) (observing that
post-judgment motions for judgment as a matter of law are "limit-
ed to the assertion of issues or grounds specifically raised in
12
the prior motion"); see also Doty v. Sewall, 908 F.2d 1053, 1057
n.4 (1st Cir. 1990) (noting that failure to bring issue underly-
ing new trial claim to district court's attention is significant
because "'[b]y doing so . . . [the party] got a chance to see the
verdict and then to seek to overturn it.'") (quoting Caldarera v.
Eastern Airlines, Inc., 705 F.2d 778, 782 (5th Cir. 1983).
Challenges to jury verdicts must be evaluated against the back-
drop of the case "as submitted" to the jury. See, e.g., Griffin
v. Matherne, 471 F.2d 911, 915 (5th Cir. 1973), quoted in 1
Steven A. Childress & Martha S. Davis, Federal Standards of
Review 3.10 (2d ed. 1992).
Affirmed.6
Affirmed.
6Although counsel fees have been awarded on occasion for an
appellate defense of a judgment on a Chapter 93A claim, see,
e.g., Manzaro v. McCann, 401 Mass. 880, 885 (1988), there is no
basis for a fee award to Perdoni, since CSI did not challenge the
district court judgment on the Chapter 93A claim.
13