TLT Construction Corp. v. RI, Inc.

          United States Court of Appeals
                     For the First Circuit


No. 06-2214

                     TLT CONSTRUCTION CORP.,

                      Plaintiff, Appellee,

                               v.

               RI, INC., d/b/a Seating Solutions,

                      Defendant, Appellant.


          APPEAL FROM THE UNITED STATES DISTRICT COURT

                FOR THE DISTRICT OF MASSACHUSETTS

          [Hon. Leo T. Sorokin, U.S. Magistrate Judge]


                             Before

                      Lynch, Circuit Judge,

                  Stahl, Senior Circuit Judge,

                   and Howard, Circuit Judge.



     Terry Klein, with whom Henshon Parker Vyadro P.C. was on
brief, for appellant.
     James G. Grillo, with whom Patrick J. Sullivan and Heaftiz &
Sullivan were on brief, for appellee.



                         April 19, 2007
            STAHL, Senior Circuit Judge.          This diversity case arises

out of a common situation in commercial dealings: the failure of

negotiations and the resulting bad blood between the parties.

Here, after a protracted -- and ultimately failed -- nine-month

negotiation    between    a     general       contractor    and     a   potential

subcontractor, the general contractor brought suit against the

subcontractor for breach of contract, claiming that at some point

during the negotiations a binding contract had been formed.                After

cross-motions for summary judgment on the question of contract

formation,    the   district    court    ruled    in   favor   of   the   general

contractor.      Because we hold that no contract was formed, we

reverse.

                                I. Background

            TLT Construction Corp. ("TLT"), a Massachusetts company,

was the general contractor on renovation and expansion projects for

Reading    Memorial   High     School    in    Reading,    Massachusetts    (the

"Reading Project"), and Wachusett Regional High School in Holden,

Massachusetts (the "Wachusett Project"). In April 2004, as TLT was

preparing its bid for the Reading Project, RI Inc., d/b/a Seating

Solutions ("Seating"), a New York company specializing in selling

and installing spectator seating for athletic facilities, submitted

a bid to TLT to install bleachers for the Reading Project as a

subcontractor.      In its proposal, Seating stated, "We have worked

very closely with this architect and have helped them design this

                                        -2-
bleacher from the very first steps."          On the record before us, it

does not appear that Seating's bid was a filed sub-bid, nor does

TLT makes such a claim.        See Mass. Gen. Laws ch. 149, § 44F.

           On May 10, 2004, TLT, having been awarded both the

Reading and the Wachusett Projects, requested that Seating submit

a new quote that would include both projects.            On May 12, Seating

quoted a price of nearly $568,000 for both.         TLT responded that the

price was too high, and Seating replied on May 17 with a revised

quote of $480,000.      Seating said that the price was "contingent on

a letter of intent being received [May 18] and an AIA contract

being   executed   by   Friday."       TLT   responded   that   day,   seeking

clarification of a few terms, including whether or not bonding was

included in the quote, since a bond was required and had been

included   in   the   quotes    from   Seating's   competitors.        Seating

responded later that day that bonding was not included in the

quote, and that it did not feel bonding was necessary, since it

would be paid in progress payments.          TLT replied, "We have a deal

if we can split the bond" and if TLT could have retainage of 5%

(Seating had originally proposed no retainage). TLT also said that

it would not be able to draft a contract in Seating's time frame,

but that it could provide a letter of intent.             Seating agreed to

accept a letter of intent, and granted TLT two weeks to draft and

execute a final contract, but said that it could not hold the price




                                       -3-
any longer than that.   On the record before us, it appears that no

letter of intent was ever sent.

            Rather, four days later, on May 21, 2004, TLT sent

Seating a draft contract,1 along with manuals and specifications,

and asked that the contract be signed and returned within five

days, along with payment and performance bonds and certificates of

insurance.    The contract package included standard bond forms.

            The record becomes more opaque at this point. It appears

that a revised draft contract may have been sent on June 7, but

that draft does not appear in the record.2   A handwritten notation

on the cover letter to the May 21 draft contract shows that the

same cover letter may have been resent on June 7, with the only

change being that a previous line asking for return of the payment

and performance bonds had been excised.      The record contains no

response from Seating with respect to either contract until TLT

contacted Seating on June 21 to request return of the signed

contract.

            On June 22, Seating wrote to TLT to say that it had

several issues with the draft contract.    First, Seating said that

it had understood that no bonding would be required, and that there



     1
      TLT actually sent two contracts, one for each project.
Because the differences between the contracts are not relevant to
this appeal, we treat them as one contract for simplicity.
     2
      We are assuming that the draft contract in the record dated
May 21 is the May 21 draft contract, not the June 7 revised draft.

                                  -4-
would be a 10% retainage in lieu of bonding.        Second, Seating

wanted to clarify the timing for submission of shop drawings.

Third, Seating said that its quote was made using prevailing wages,

not union labor, and if TLT were to require union labor (as the May

21 draft contract did), then there would be a price increase.

Fourth, Seating noted that the quote was exclusive of taxes,

permits, and fees.   This letter was apparently returned to Seating

with notations by TLT, but that response is not in the record.

          On June 28, Seating wrote to TLT, responding to TLT's

notations to Seating's June 22 letter, saying that after "only a

few comments" it could "get this thing executed."    First, Seating

said that its insurance company would not make a certain change to

the language on the certificates that TLT had presumably requested.

Second, it said that an umbrella policy was cost-prohibitive.

Third, it requested a six-week time frame for return of engineered

shop drawings.   On June 29, TLT accepted the first two changes, but

did not reply to the third.   TLT also requested that Seating mark

up the original contract with these changes and return it to TLT.

          On July 5, Seating returned a marked-up version of the

May 21 draft contract.    The changes covered five areas.    First,

Seating struck all language related to payment and performance

bonds and struck out the bonding forms that had been attached.

Second, Seating struck the language requiring union labor.   Third,

Seating struck the language requiring that insurance coverage be


                                -5-
"in the same Limits as required by the Owner's contract of the

general contractor," and inserted language that Seating's "standard

insurance limits to apply to this contract."       Fourth, Seating

struck the language making it responsible for permits and fees

(though it kept the language making it responsible for taxes).

Fifth, Seating added language saying that it would provide shop

drawings within six weeks of receiving the executed contract. With

these changes, Seating signed the draft contract and returned it to

TLT. TLT neither signed nor returned this version of the contract.

          The next writing in the record, perhaps after some verbal

communication between the parties, is a July 12 letter from Seating

to TLT.   The letter provided a break-down of additional cost if

union labor was to be required.    Then the letter continued:

          Regarding the bonding, it was agreed that 10%
          retainage would be held in lew [sic] of
          bonding. We will bond this and pass the cost
          along to you as an add-on to the contract.
          When bonding is required we reserve the right,
          depending on our current bonding capacity at
          that time[,] to have our factory supply the
          required bonds.

          The letter closed, "If all is acceptable please forward

new contracts for us to execute."




                                  -6-
            On July 21, TLT sent a new draft contract to Seating.3

The draft no longer required union labor, but it was otherwise

unchanged with respect to Seating's July 5 edits.

            On July 29, TLT wrote to Seating to request the return of

the signed contracts.     On August 13, Seating wrote to say that its

price would have to increase by $19,236 to account for an I-beam

that it had not realized was in the plans.

            On   August   18,   Seating   provided      a   certification    of

insurance from Outdoor Aluminum, an affiliated company that ran

Seating's factory, asking if it was "acceptable." In addition, the

letter said, "Per our conversation, bonding will not be an issue.

They [Outdoor Aluminum] bond many projects [for] us and unless

there is something out of the ordinary all will be done."

            On August 19, TLT wrote back to challenge the price

increase, saying that Seating had the specifications showing the I-

beam when it made the bid.      At that point, relations deteriorated.

Over the next few months, the parties continued to try to reach

agreement,   but   with   decreasing      levels   of   cooperation.        TLT

ultimately had the work performed by another company, at a cost of

$514,160.

            In December 2004, TLT brought suit in Massachusetts state

court for breach of contract and violation of the Massachusetts


     3
      Only the contract for the Wachusett Project is in the record,
so we assume that its terms mirror the July 21 draft contract for
the Reading Project.

                                    -7-
consumer protection law, Mass. Gen. Laws ch. 93A, § 11.                       Seating

removed the case to the United State District Court for the

District of Massachusetts on February 3, 2005.                   The parties agreed

to have the case tried by a magistrate judge.                     The parties then

cross-moved       for   summary    judgment       on   the      issue   of   contract

formation.     The district court held that a contract existed and

that Seating had breached.4            The court awarded damages of $34,160.5

Seating now appeals.

                                  II. Discussion

            We review the district court's grant of summary judgment

de novo, with all reasonable inferences resolved in favor of

Seating.    See Fenton v. John Hancock Mut. Life Ins. Co., 400 F.3d

83,   87   (1st    Cir.   2005).        Although    the    question     of   contract

formation is typically a question for the factfinder, and would

thus be subject to clear error review, see Crellin Tech., Inc. v

Equipmentlease Corp., 18 F.3d 1, 7 (1st Cir. 1994), where "the

evidentiary       foundation     for    determining       the    formation    of   the

parties'     contract     [is]     either       undisputed      or   consist[s]     of

writings," contract formation is instead a question of law for the

court, Lambert v. Kysar, 983 F.2d 1110, 1114 n.4 (1st Cir. 1993);


      4
      The court also denied summary judgment on the 93A claim.
Following a bench trial, the court found that Seating had not
violated 93A. That claim is not relevant to this appeal.
      5
      We note that, including the original 93A claims, the amount
in controversy originally pleaded satisfied the jurisdictional
requirement. See 28 U.S.C. § 1332.

                                          -8-
see Mass. Eye & Ear Infirmary v. QLT Phototherapeutics, Inc., 412

F.3d 215, 229 (1st Cir. 2005); Jewelers Mut. Ins. Co. v. N.

Barquet, Inc., 410 F.3d 2, 9-10 (1st Cir. 2005).           Here, both

parties moved for summary judgment on the basis of undisputed

facts.6

          Under   Massachusetts    law   of   contract,   it   is   well

established that "the fact that parties contemplate the execution

of a final written agreement effects a strong inference that the

parties do not intend to be bound by earlier negotiations or

agreements until the final terms are settled."     Rosenfield v. U.S.

Trust Co., 290 Mass. 210, 195 N.E. 323, 325 (1935); see McCarthy v.



     6
      TLT argues, in so many words, that the fact of cross-motions
for summary judgment meant that the parties had submitted the case
as a "case stated," and thus that clear error review should apply.
See Garcia-Ayala v. Lederle Parenterals, Inc., 212 F.3d 638, 643
(1st Cir. 2000). In a case stated, the parties waive trial and
present the case to the court on the undisputed facts in the pre-
trial record. The court is then entitled to "engage in a certain
amount of factfinding, including the drawing of inferences."
United Paperworkers Int'l Union Local 14 v. Int'l Paper Co., 64
F.3d 28, 31 (1st Cir. 1995). Such findings would then be subject
to clear error review. Id. at 32. However, in cases where the
parties have not explicitly presented their case to the court as a
case stated, we must "inquire into the intentions of the parties
and the district court judge."     Garcia-Ayala, 212 F.3d at 644.
Such an inquiry should be done "quite carefully," id. at 644 n.44,
for such cases are "somewhat unusual," United Paperworkers, 64 F.3d
at 31. The fact that cross-motions were filed is not dispositive.
Jewelers, 410 F.3d at 10. Here, we see no indications beyond the
filing of cross-motions that the parties intended this to be a case
stated.   Indeed, a bench trial on the 93A claim followed the
resolution of the contract claim. Furthermore, it's not clear that
a different standard of review would apply here, since the question
we face is a legal one, see id. at 9-10, and thus still subject to
de novo review, United Paperworkers, 64 F.3d at 32.

                                  -9-
Tobin, 429 Mass. 84, 706 N.E.2d 629, 632 (1999).        "If, however, the

parties orally agree to the essential terms of the transaction, it

may be inferred that they intended to bind themselves at that time

and that the 'writing to be drafted and delivered is a mere

memorial of the contract, which is already final by the earlier

mutual assent of the parties to those terms.'"          Novel Iron Works,

Inc. v. Wexler Constr. Co., 26 Mass. App. Ct. 401, 528 N.E.2d 142,

146 (1988) (quoting Rosenfield, 195 N.E. at 325); see McCarthy, 706

N.E.2d at 632.     "It is not required that all terms of the agreement

be   precisely    specified,   and     the   presence   of   undefined    or

unspecified terms will not necessarily preclude the formation of a

binding contract." Situation Mgmt. Sys., Inc. v. Malouf, Inc., 430

Mass. 875, 724 N.E.2d 699, 703 (2000). "The parties must, however,

have progressed beyond the stage of 'imperfect negotiation.'"            Id.

(quoting Lafayette Place Assocs. v. Boston Redev. Auth., 427 Mass.

509, 694 N.E.2d 820, 826 (1998)); see Rosenfield, 195 N.E. at 326.

          In a case such as this, with faxes, phone discussions,

and multiple draft contracts going back and forth over nearly eight

months, it is worth taking a step back to recall that "[t]here is

no surer way to find out what parties meant, than to see what they

have done."      Pittsfield & N. Adams R.R. Corp. v. Boston & Albany

R.R. Co., 260 Mass. 390, 157 N.E. 611, 614 (1927) (quoting Brooklyn

Life Ins. Co. of N.Y. v. Dutcher, 95 U.S. 269, 273 (1877))

(internal quotation marks omitted); see T.F. v. B.L., 442 Mass.


                                     -10-
522, 813 N.E.2d 1244, 1248 (2004).      With this in mind, we note two

things about the instant case.

          First, at no point did either party behave as if it had

a contract.     Indeed, negotiations continued for nearly six months

after the date TLT claims a contract was formed.         TLT does not

appear to have taken any action in reliance on a contract having

been formed.     See Novel Iron Works, 528 N.E.2d at 146-47 (party

successfully asserting contract formation was told it was the

general contractor, came up with drawings and specifications,

solicited bids from subcontractors, was authorized to purchase

materials, obtained a building permit, etc.).     TLT appears to have

first approached litigation from a theory of a general contractor's

reliance on a subcontractor's bid.       See Loranger Constr. Co. v.

E.F. Hauserman Co., 376 Mass. 757, 384 N.E.2d 176, 179 (1978).     It

ultimately pursued the contract theory after it became clear that

Loranger did not apply.

          Second, the record shows that obtaining signed contracts

was important to TLT.    TLT repeatedly pressed Seating for executed

contracts, stating that it would not proceed with the project

without them.    This suggests that the parties did not intend to be

bound before executing a final written agreement.     See Rosenfield,

195 N.E. at 325; see also Salem Laundry Co. v. N.E. Teamsters &

Trucking Indus. Pension Fund, 829 F.2d 278, 280 (1st Cir. 1987)

("Parties can agree on every term in a contract, yet not be bound


                                 -11-
until they sign a written agreement, if they so indicate."); Bates

v. Southgate, 308 Mass. 170, 31 N.E.2d 551, 553 (1941) ("Even

though previous oral conversations would be enough in themselves to

establish an oral contract the parties may, nevertheless, by mutual

understanding postpone the culmination of their negotiations into

a contract to the later preparation and delivery of a written

instrument."); Tull v. Mister Donut Dev. Corp., 7 Mass. App. Ct.

626, 389 N.E.2d 447, 451 (1979) ("Businessmen would be undesirably

inhibited in their dealings if expressions of intent and the

exchange of drafts were taken as legally binding agreements.").

          Neither of these points necessarily precludes a holding

that a contract had formed. But neither will a failed negotiation,

even one that causes damage to one or both parties, be necessarily

a breach of contract.

          Both parties acknowledge that the negotiations were drawn

out and involved a series of offers and counteroffers.      Seating

argues that this is all it was, and that no offer was ever

accepted, because each response was only a counteroffer.    The May

21 draft contract was an offer, and Seating's return of it on July

5 with excisions was a counteroffer.   This was followed by the July

21 draft contract from TLT, which, since it embodied different

terms from the edited July 5 draft, was yet another counteroffer.

          TLT argues that the July 5 edited draft that Seating

returned actually embodied terms already agreed to in faxes and


                               -12-
discussions, and the draft was thus an acceptance of TLT's offer.

But we do not see from the record how this could be, since there is

no record evidence that any of the five issues raised by the July

5 edits had previously been agreed upon.             Seating had raised the

issues of permits and fees, bonding, union labor, and timing of

shop drawings prior to returning the draft contract on July 5, but

the record shows no response from TLT on these issues before July

5.   Furthermore, the issue of insurance limits had not been raised

previously at all.        The issues of permits and fees, insurance

limits, and timing of shop drawings went completely unaddressed

between July 5 and July 21, and the original terms remained in the

supposedly "clean" July 21 draft contract that TLT sent to Seating,

despite Seating's excision of those terms on July 5.

            On the issue of bonding, TLT itself argues (contrary to

its assertion that the July 5 agreement is binding), that the

bonding issue was not agreed upon until July 12.            In a letter sent

by   fax   on   that   day,   Seating,   according    to   TLT,   dropped   its

insistence on having progress payments with 10% retainage in lieu




                                     -13-
of bonding, and instead agreed to bond the project.7               We see it

differently.

           It   is   a   reasonable   inference   --   and    we   take   all

reasonable inferences in favor of Seating -- that this was still

just a step in the negotiation, rather than a final acquiescence.

Seating notes that it understood that "it was agreed that 10%

retainage would be held in [lieu] of bonding," thus acknowledging

a continuing dispute on the issue.        Furthermore, the letter also

states that "[w]hen bonding is required we reserve the right . . .

to have our factory supply the required bonds."              With this last

sentence Seating seems to acknowledge that bonding may or may not

be required.    The letter also brings up, for the first time in the

record, a request that the bonding be done through Seating's

factory.   Given the importance of bonding in the construction

industry, such a request could be a material change in terms,

making the July 12 letter just another counteroffer.            There is no


     7
      The district court viewed the July 12 letter as consistent
with the July 5 excisions.     The court stated that "in lieu of
bonding, TLT would hold 10% retainage, which Seating would then
bond through its factory, Outdoor Aluminum." First, we note that
this is not consistent with the fact that the bonding language
remained in the July 21 draft contract; either the language is in,
or it is out -- it cannot be both. Second, we believe that the
district court's finding is internally inconsistent. One cannot
say that there is both bonding, and retainage "in lieu of bonding."
It does not make sense to say that a party will bond a retainage.
Therefore, we believe that the most that can be said of the July 12
letter is that it represented Seating's acquiescence on the issue
of retainage and agreement to bond the project instead. TLT takes
essentially this position, in contrast to the district court's
finding.

                                  -14-
evidence of this issue being discussed further between the parties

until August 18.

            TLT claims that "it is [the July 5] contract[] which TLT

seeks to enforce.        All of the Parties' subsequent communications

merely entailed hammering out minor details."               While "[a] written

contract, signed by only one party, may be binding and enforceable

even   without    the    other    party's    signature     if   the   other   party

manifests acceptance," Haufler v. Zotos, 446 Mass. 489, 845 N.E.2d

322, 331 (2006), we see no manifestation of acceptance here.                   The

only communication in the record from TLT following the receipt of

the July 5 draft contract is the July 21 draft contract, which on

its face does not accept all of the terms of the July 5 draft

contract.   In addition, there is no evidence in the record that TLT

took any actions that could be construed as manifesting acceptance.

Furthermore, TLT's position that the July 5 draft contract should

be binding is contrary to TLT's assertion that the inclusion of the

bonding language in the July 21 agreement reflected the agreement

of the parties, an agreement purportedly made after July 5.                     The

position that the July 5 draft was binding and the position that

bonding was required cannot be reconciled.

            The   only    issue    that     appears   to   have   actually     been

resolved during this period was the issue of union labor.                 Seating

said that its bid was calculated using non-union wages, and that a

union requirement would raise the price of the project.                         TLT


                                      -15-
removed the union labor requirement from the July 21 draft contract

-- the only one of Seating's five requested changes that TLT made.

But because there is nothing in the record showing an agreement on

this issue prior to July 5, it is a reasonable inference that the

July 5 excision of union terms was an offer, with the July 21 draft

being TLT's acceptance (of that term alone).8

          Thus, summary judgment in favor of TLT should not have

been granted.   Furthermore, even taking all reasonable inferences

in favor of TLT, we hold that no contract was formed.9       As we

discussed above, there is no evidence in the record that the

parties came to an agreement prior to July 5 on any of the issues

raised by Seating in the July 5 draft contract.   The later removal

of the union language may lead to an inference that an agreement on

that issue had been reached earlier, but there was still no

agreement on bonding until July 12 at the earliest. Therefore, the

July 5 draft cannot be viewed as an acceptance of an offer.

Furthermore, by July 12, the issues of insurance limits, permits

and fees, and timing of shop drawings were still unresolved.

Indeed, their inclusion in the July 21 draft can only lead to the



     8
      The affidavit of Thomas V. Kostinden, the president of TLT,
does not indicate when TLT agreed not to require union labor.
     9
      The parties agree that there are no material facts in
dispute. Seating moved for summary judgment below and argued on
appeal that it was entitled to an entry of judgment because the
evidence could only lead to the conclusion that there was no
contract. We agree.

                               -16-
conclusion that the issues had not been agreed upon.   While we do

not hold that each of these terms individually was necessarily

material, the fact that four out of five requested changes to the

contract were not made, coupled with the fact that having a signed,

written contract was clearly important to both parties, leads us to

hold that there was no meeting of the minds before Seating changed

its offer price on August 13.

           Our decision today is in part a result of the complexity

of the negotiations, which is reflected in some inconsistencies in

the district court's opinion. For example, the district court said

at various points that: there was "an agreement in principle" on

May 17, 2004; that the parties were beyond "imperfect negotiation"

and that "[t]he essential terms of the agreement had been reached"

as of July 5; and that the parties agreed to bonding terms on July

12.   These three findings show the confusion of the process and in

a sense are contradictory.    Because the district court does not

pinpoint with precision the point at which the contract was formed,

we are inclined to view with some skepticism its conclusion.

           Furthermore, the district court found that the insurance

issue had been agreed to prior to July 5.     But the evidence for

this, a June 28 letter, does not deal with insurance limits at all.

The parties only discuss the language in the certificates and the

necessity of umbrella insurance.       Finally, the district court

explains the non-inclusion in the July 21 draft of Seating's


                                -17-
requested language on permits and fees, insurance limits, and

timing of shop drawings as "apparent mistakes in editing."          This

despite the fact that, on the record before us, none of these three

issues was ever discussed.

                           III. Conclusion

          For   the   foregoing   reasons,   we   reverse   the   summary

judgment order of the district court and remand with instructions

that summary judgment be entered in favor of Seating.

          Reversed and remanded.     Each side to bear its own costs.




                                  -18-