United States Court of Appeals
For the First Circuit
No. 08-2122
NULANKEYUTMONEN NKIHTAQMIKON; DAVID MOSES BRIDGES; VERA FRANCIS;
HILDA LEWIS; DEANNA FRANCIS; REGINALD JOSEPH STANLEY; and MARY
BASSETT,
Plaintiffs, Appellants,
v.
ROBERT K. IMPSON, Acting Regional Director, Eastern Region,
Bureau of Indian Affairs; and KEN SALAZAR,* Secretary, United
States Department of the Interior,
Defendants, Appellees.
APPEAL FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MAINE
[Hon. John A. Woodcock, Jr., U.S. District Judge]
Before
Torruella, Ripple,** and Boudin,
Circuit Judges.
Teresa B. Clemmer, Environmental and Natural Resources Law
Clinic, Vermont Law School, with whom David K. Mears, Environmental
and Natural Resources Law Clinic, Vermont Law School, was on brief
for appellants.
John L. Smeltzer, Department of Justice, Environment & Natural
Resources Division, with whom John C. Cruden, Acting Assistant
Attorney General, Sara E. Costello, M. Alice Thurston, Department
of Justice, Environment & Natural Resources Division, and John
Harrington, Assistant Regional Solicitor, Department of the
*
Pursuant to Fed. R. App. P 43(c)(2), Secretary of the
Department of the Interior Ken Salazar has been substituted for
former Secretary Gale Norton as defendant, appellee.
**
Of the Seventh Circuit, sitting by designation.
Interior, Office of the Solicitor, were on brief for appellees.
October 28, 2009
BOUDIN, Circuit Judge. This appeal is the second in
continuing litigation by a group of members of the Passamaquoddy
Tribe called Nulankeyutmonen Nkihtaqmikon--the phrase means "We
Protect the Homeland," and we refer to the group as NN--to
challenge a Bureau of Indian Affairs ("BIA") decision; the decision
approved a lease of a plot of Passamaquoddy land for the
construction and operation of a liquefied natural gas ("LNG")
facility, contingent on federal regulatory approval being obtained
from the Federal Energy Regulatory Commission ("FERC"). The
relevant facts, which have been discussed in previous decisions,1
are as follows.
In May 2005, the tribal authorities in charge of the
Pleasant Point reservation agreed to a lease with Quoddy Bay, LLC
("Quoddy Bay"), that would allow Quoddy Bay to construct a LNG
facility on a 3/4 acre portion of the tribe's land known as Split
Rock. The lease contemplates four phases: permitting,
construction, operations, and removal and remediation. In the
first "permitting" phase, Quoddy Bay is entitled to test and survey
the land as needed to obtain FERC approval for construction, and
the latter phases, if the project moves ahead, allow for
construction and operation of the LNG facility. Absent FERC
1
Nulankeyutmonen Nkihtaqmikon v. Impson ("NN I"), 462 F. Supp.
2d 86, 91-93 (D. Me. 2006); Nulankeyutmonen Nkihtaqmikon v. Impson
("NN II"), 503 F.3d 18, 23-25 (1st Cir. 2007); Nulankeyutmonen
Nkihtaqmikon v. Impson ("NN III"), 573 F. Supp. 2d 311, 314-15 (D.
Me. 2008).
-3-
approval, the project cannot proceed and the lease can be
terminated by the Tribe.
The lease was submitted to the BIA for approval in May
2005 under the Indian Long-Term Leasing Act ("Leasing Act"), 25
U.S.C. § 415 (2006), and the BIA approved it approximately one week
later, on June 1, 2005. The BIA did not prepare an environmental
impact statement, consult with other agencies or conduct other
inquiries before approving the lease. It said, however, that its
lease approval allowed only site investigation and that anything
more would require approval by FERC, see 15 U.S.C. § 717b(e)(1);
the more thorough analyses required by the National Environmental
Policy Act ("NEPA"), 42 U.S.C. § 4321 et seq., and other statutes
would be part of that approval process.2 The BIA stated that
lease approval is solely for the site
investigation required for the [FERC]
permitting process in the development of [the
required environmental assessment ("EIS")] . .
. . Continuing the lease beyond the
investigation period is contingent upon FERC
permit approval, acceptability of the EIS
2
NEPA requires federal agencies to assess the potential
environmental consequences of actions that might detrimentally
affect "the quality of the human environment." 42 U.S.C. §
4332(2)(C), but environmental impact statements are not required,
for "categor[ies] of actions which do not . . . have a significant
effect on the human environment and which have been found to have
no such effect in procedures adopted by a Federal agency in
implementation of these regulations." 40 C.F.R. § 1508.4 (2009).
The BIA adopted regulations implementing this exception in 1988,
see National Environmental Policy Act; Revised Implementing
Procedures, 53 Fed. Reg. 10439 (Mar. 31, 1988), and found that the
lease was exempted because it was, at least in its current stage,
intended primarily for data gathering.
-4-
analysis and insignificant impact on the
leased property.
Seeking to forestall the surveying and testing, NN filed
suit in November 2005: it alleged that the BIA approved the lease
in violation of NEPA, the National Historic Preservation Act, 16
U.S.C. § 470 et seq., the Leasing Act, and the Administrative
Procedure Act ("APA"), 5 U.S.C. §§ 701-706, by failing to conduct
environmental reviews; consider the historical, religious, and
cultural significance of the leased land; prepare a fair market
appraisal; and provide an opportunity for public comment. NN later
sued to enjoin the lease under a citizen-suit provision of the
Endangered Species Act, 16 U.S.C. § 1540(g), and the two actions
were consolidated.
The BIA moved to dismiss on multiple grounds: that what
it described as preliminary approval was not "final" agency action,
that NN lacked standing, and that the case was not yet ripe for
judicial review. The district court agreed, NN I, 462 F. Supp. 2d
at 112, but on appeal, the BIA conceded that its lease approval was
technically final, albeit no construction or operation could be
undertaken without FERC approval, NN II, 503 F.3d at 26. Still,
the BIA argued that the law suit was premature because NN had not
exhausted administrative review within the Interior Department
available under its regulations. See 25 C.F.R. §§ 2.4(e), 2.6; 43
C.F.R. § 4.331.
-5-
Rejecting other BIA objections (standing, ripeness), this
court held that exhaustion of agency remedies was "mandatory" under
governing precedent, subject only to the possibility that one of
the established exceptions to the exhaustion requirement applied.
NN II, 503 F.3d at 33-34. The court then remanded the case to the
district court with instructions to "consider whether [NN] merit[s]
an exception to the exhaustion requirement." Id. at 34. Back in
the district court, NN preserved its administrative remedies,3 and
then, instead of arguing any "exception" excused its failure to
exhaust, told the district court that this court had erred by
imposing the exhaustion requirement in the first place.
The district court replied that this court had declared
exhaustion "mandatory" unless an exception applied, and it found no
exception applicable: the exceptions mooted but rejected by the
district court were those based on exceptional circumstances, see
White Mountain Apache Tribe v. Hodel, 840 F.2d 675, 677 (9th Cir.
1988), and on equitable considerations like waiver or estoppel, see
Frederique-Alexandre v. Dep't of Natural and Envtl. Res., 478 F.3d
433, 440 (1st Cir. 2007). Accordingly, the district court
dismissed the case--leaving NN to pursue its internal Interior
Department appeals before resuming (if necessary) litigation in the
district court. NN III, 573 F. Supp. 2d at 314, 318.
3
NN filed a protective administrative appeal with the Interior
Board of Indian Appeals, which was stayed by stipulation during the
remand proceedings in the district court and in this court.
-6-
On this second appeal, NN does not argue that any
exception to the exhaustion requirement applies; instead it takes
issue, as it did in the district court, with our earlier decision
that exhaustion was mandatory unless an exception applied. Yet the
remand order was quite clear that exhaustion was required unless
excused, see NN II, 503 F.3d at 33-34, and any request that it be
reconsidered should have been made by a timely petition for
rehearing in this court, see United States v. DeJesus, 752 F.2d
640, 643 (1st Cir. 1985); when our mandate issued, it established
the law of the case. United States v. Moran, 393 F.3d 1, 7 (1st
Cir. 2004).
We could revisit our own earlier decision if NN could
"show that controlling legal authority has changed dramatically;"
"proffer significant new evidence, not earlier obtainable in the
exercise of due diligence;" or "convince the court that a blatant
error in the prior decision will, if uncorrected, result in a
serious injustice." United States v. Bell, 988 F.2d 247, 251 (1st
Cir. 1993); see also United States v. Rivera-Martinez, 931 F.2d
148, 151 (1st Cir. 1991), cert. denied 502 U.S. 862 (2006). Only
the third ground is even arguably relevant here: for the sake of
future litigation, we describe briefly NN's claim that error
occurred, but we resolve the appeal against NN solely on the ground
that no serious injustice is threatened by leaving the mandate
undisturbed.
-7-
NN's main argument against our prior decision is that
unless a statute requires exhaustion, judicial review of agency
action under the APA, applicable where no other statutory channel
of review is provided, does not require exhaustion unless there is
both internal agency review available and the final agency action
is rendered inoperative during such review. See 5 U.S.C. § 704;
Darby v. Cisneros, 509 U.S. 137, 154 (1993). Most of the statutes
invoked by NN in this case as the basis for attacking the BIA
decision are subject to APA review; the Endangered Species Act
alone provides its own statutory channel of review.
The BIA says that its decision was and is presently
inoperative. This assertion turns on the BIA's contention that its
earlier lease approval did not become operative under BIA
regulations, so requiring exhaustion accords with section 704's
conditions and with Darby. An agency decision can be completed but
ineffective pending further review at a higher agency level or in
court, cf. Idaho Watersheds Project v. Hahn, 307 F.3d 815, 825-27
(9th Cir. 2002); but to so describe the lease approval in this
case is admittedly at odds with the BIA's earlier claim, on the
first appeal to this court, that "the lease became effective and
binding on the date it was signed." The BIA admits this change of
position to be so but says that it previously overlooked a
peculiarity of this case.
-8-
The BIA now points to a regulation stating that a BIA
decision becomes "effective" only when (1) the time for filing a
notice of appeal has expired and no such appeal has been filed, (2)
the BIA specifically makes a decision effective immediately or (3)
the appellate agency review board renders a final decision. See 25
C.F.R. § 2.6; 43 C.F.R. § 4.337(a). The time for filing an appeal
is ordinarily 30 days, 25 C.F.R. § 2.7(c), but, says the BIA,
notice of the decision was not initially provided to NN (since it
was not a party to the lease), NN's appeal rights did not expire,
and the lease is now inoperative until the pending administrative
appeal is resolved. 25 C.F.R. § 2.7.4
NN objects to the agency's change of its position, but
the change of position is not automatically barred if it is made in
good faith and without causing unfair prejudice, see InterGen N.V.
v. Grina, 344 F.3d 134, 144-45 (1st Cir. 2003); Patriot Cinemas,
Inc. v. General Cinemas Corp., 834 F.2d 208, 212 (1st Cir. 1987),
and the BIA is now committed to affording NN internal agency
review. What is more arresting is NN's claim that despite the
supposedly ineffective lease, surveying is currently underway and
the tribe is collecting lease payments. But it is not certain that
4
The BIA regulation states that the agency's failure to
provide notice "shall not affect the validity of the [challenged]
decision or action but the time to file a notice of appeal
regarding such a decision shall not begin to run until notice has
been given." 25 C.F.R. § 2.7(b)(emphasis added). Asked what limit
applies absent agency notice, the BIA responded in oral argument
that laches is the only limit on delayed attacks.
-9-
any lease approval, effective or otherwise, is legally required for
either the surveying or the payments, see 25 C.F.R. § 162.103(b);
and as to these steps, the Tribe and the company may be proceeding
at their own risk
In all events, we need not decide the merits of these
arguments as to the need for exhaustion of administrative remedies.
NN could have presented its APA and Darby argument in its first
appeal; it did not do so, and its request for relief from the
mandate rule requires a showing of both blatant error and the
threat of serious injustice if we adhere to the mandate. Blatant
error has not been demonstrated and there is no showing that
exhaustion of the internal remedies will cause any significant
harm, let alone serious injustice; when pressed on the issue, NN
was unable to point to any concrete harm so long as no operation or
construction is allowed without FERC approval.
The same lack of blatant error or harm amounting to an
injustice is true as to NN's claim that exhaustion is not a
requirement for judicial review of claims under the Endangered
Species Act. NN has one circuit precedent on its side, Wash.
Toxics Coalition v. EPA, 413 F.3d 1024, 1033-34 (9th Cir. 2005),
cert. denied 546 U.S. 1090 (2006), and a few district court cases,
while the BIA has some policy arguments in its favor. But, once
again, this argument could have been made on the first appeal and
the attack is foreclosed by our mandate unless our earlier decision
-10-
was plainly wrong and following it would cause a serious injustice.
Neither condition has been satisfied.
NN has recently filed a document calling attention to new
developments with respect to the lease and its IBIA appeal. NN
advises that since the appeal was filed, Quoddy Bay's FERC permit
application has been delayed; the tribe has attempted to terminate
the lease--an action that Quoddy Bay contests; and the BIA proposes
to consider whether the lease may be cancelled if the IBIA agrees
to remand NN's administrative appeal. None of these developments
affects our analysis in the present appeal.
The district court's judgment is affirmed. Each side
will bear its own costs on the appeal.
It is so ordered.
-11-