Gulf States Utilities Co. v. Public Utility Commission

841 S.W.2d 459 (1992)

GULF STATES UTILITIES COMPANY, Appellant,
v.
PUBLIC UTILITY COMMISSION OF TEXAS, et al., Appellees.

No. 3-90-173-CV.

Court of Appeals of Texas, Austin.

October 21, 1992. Rehearing Overruled December 23, 1992.

*460 Cecil L. Johnson, Beaumont, Patrick R. Cowlishaw, Cohan, Simpson, Cowlishaw, Aranza & Wolff, Dallas, for appellant.

Dan Morales, Atty. Gen., Norma K. Scogin, Asst. Atty. Gen, Austin, for Public Utility Com'n of Texas.

Barbara Day, Butler, Porter & Gay, Austin, for intervenor cities of China, Groves, Nederland, Port Arthur, Port Neches and Vidor.

Jim Boyle, Boyle & Freeman, Austin, for intervenor North Star Steel Texas, Inc.

John L. Laakso, Office of Public Utility Counsel, Austin, for intervenor Public Utility Counsel.

Before POWERS, JONES and B.A. SMITH, JJ.

BEA ANN SMITH, Justice.

Gulf States Utilities Company ("Gulf States") appeals a district court judgment affirming a decision of the Public Utility Commission (the "Commission") disallowing Gulf States' recovery of energy capacity costs arising under a series of energy contracts with the Southern Company ("Southern"), a utility holding company. The Commission disallowed Gulf States' capacity *461 costs after determining that they had been imprudently incurred. The district court affirmed the Commission's order; we will affirm the district court's judgment.

THE CONTROVERSY

A Summary of the Dispute.

This dispute arises from Gulf States' decision to contract with Southern for the long-term supply of energy and energy capacity. In exchange for this long-term supply, Gulf States agreed to multi-billion dollar payments over an eight-year period. After entering into these contracts, Gulf States petitioned the Commission for a retail-rate increase, hoping to pass through to its retail customers the contracts' energy and capacity costs. The Commission allowed Gulf States to recover its energy costs but denied the recovery of its capacity costs, ruling that Gulf States had not acted prudently in incurring them. The Commission based its ruling on findings that Gulf States knew or should have known at the time it entered the contracts that it did not need the Southern capacity in order to meet its future requirements and that the utility failed to explore alternative sources of energy. Gulf States sued in district court for judicial review of the Commission's order, which the court affirmed. In this appeal, Gulf States contends the Commission (1) lacked jurisdiction to pass upon the "prudence" of the company's decision to purchase the Southern power; (2) violated the Commerce Clause in arriving at its final order; (3) arbitrarily and capriciously ignored key evidence; (4) failed to apply res judicata to earlier Commission orders; (5) applied an incorrect legal standard of "prudence"; and (6) erroneously shifted the parties' burdens of proof when determining the prudence of the Southern purchases.

The Relevant Details.

Gulf States is an investor-owned utility engaged in generating, transmitting, distributing, and retailing electric energy throughout southeast Texas and south-central Louisiana. Before 1982, Gulf States primarily used natural gas to fuel its generators. However, in the late 1970s and early 1980s, the company began to construct coal-fired and nuclear-fired power plants in an effort to decrease its reliance on natural gas in generating electric power. Gulf States also determined that it would not be able to generate sufficient energy to meet its customers' demands during the 1980s and decided to purchase additional power on the open market.

In February 1982, Gulf States contracted with Southern[1] to purchase coal-fired energy and capacity, agreeing to pay both energy charges and capacity charges in exchange for access to large quantities of energy. Because this dispute centers on capacity charges, we pause to explain how these differ from the energy charges that the Commission allowed Gulf States to recover.

The price of any purchase of electric power is made up of an energy component, the variable costs associated with the production of electric energy (primarily the cost of fuel and some operating and maintenance expenses), and a capacity component, costs associated with providing the capability to deliver energy (primarily the capital costs of facilities).

Pennsylvania Power Co. v. Pennsylvania Pub. Serv. Comm'n, 127 Pa.Cmwlth. 97, 561 A.2d 43, 46 n. 4 (1989), affd, 526 Pa. 453, 587 A.2d 312 (1991).

The capacity charges were calculated as a percentage of Southern's fixed investment for plant construction costs, corresponding to the portion of the facilities dedicated to producing Gulf States' purchase *462 of the plant's generating potential. The energy charges reflected the cost of fuel and other variables associated with producing the energy. These contracts covered the period from 1984 to 1992 and required Gulf States to purchase 500 megawatts of capacity. In May 1982, Gulf States contracted with Southern for an additional 500 megawatts of capacity. Gulf States agreed to a 100% take-or-pay commitment for this capacity and a 50% takeor-pay commitment for purchased energy.

In August 1982, the Commission issued Gulf States a certificate of convenience and necessity to construct a transmission line to deliver the Southern energy to Gulf States' facilities.[2] In October 1985, Gulf States filed with the Commission a statement of intent to increase its retail rates in order to pass through to its consumers the costs of the Southern purchase. See Public Utility Regulatory Act, Tex.Rev.Civ.Stat. Ann. art. 1446c, § 43(a) (West Supp.1992) ("PURA"). The Commission assigned this request Docket No. 6525 and scheduled a hearing for March 17, 1986.

The opponents[3] to the rate increase claimed that Gulf States failed to bargain for advantageous terms. They complained specifically of the contracts' take-or-pay clauses, which had no "market out" exceptions, and of the more expensive energy rates predicated upon Southern's use of newer, more costly generators. These opponents argued that the Southern contracts were so unfavorable that Gulf States never should have entered into the agreements. After seven weeks of hearings, the parties recessed for settlement negotiations and eventually entered into a stipulation that resolved most of the disputed issues.

In June 1986, the Commission reconvened to deal with the unresolved issues, specifically whether Gulf States could pass through the capacity charges to its retail customers. The hearing examiner ruled that Gulf States had failed to demonstrate prudent decision-making in entering into the contracts to purchase large quantities of energy capacity and therefore should not be allowed to recoup its capacity charges as part of the requested rate-increase. The Commission, with one dissent, accepted this recommendation, found that Gulf States had acted imprudently, and disallowed the capacity charges. The district court affirmed the Commission's order.

JURISDICTIONAL CHALLENGES

In three points of error, Gulf States has challenged the Commission's jurisdiction to disallow recovery of the Southern capacity charges in the utility's rate increase. In these points, Gulf States makes five distinct claims:

• FERC[4] previously determined the prudence of Gulf States' decision to purchase the Southern capacity;

• FERC exercises exclusive jurisdiction to review the prudence of purchases of wholesale electric power;

• Disallowance of Gulf States' capacity costs constitutes impermissible "trapping" and violates the "filed rate" doctrine;

• The Commission lacks jurisdiction to review the particular terms of these contracts; and

• The Commission's order impermissibly burdens interstate commerce.

The first four claims implicate federal preemption principles arising under the Supremacy Clause;[5] the remaining claim implicates *463 the Commerce Clause.[6]

Gulf States' jurisdictional challenge requires us to examine the evolving "jurisdictional tug-of-war" between state and federal regulation of the electric utility industry. See Clinton A. Vince & John S. Moot, Federal Preemption versus State Utility Regulation in a Post-Mississippi Era, 10 Energy L.J. 1, 3 (1989). We are asked to determine if the growing federal preemption of energy regulation precludes a state regulatory commission, in its traditional role of setting retail energy rates, from reviewing the prudence of a utility's purchase of capacity at FERC-approved rates. This is an issue of first impression in Texas that requires us to review the historical development of state and federal regulation of the electric utility industry.

The Historical Context.

Before 1935, no federal agency existed to regulate the electric utility industry; instead, various state public service commissions performed this function. See Vince & Moot, supra, at 9. In 1927, the Supreme Court invalidated a state commission's attempt to regulate a utility's interstate sales and transmissions of electricity. See Public Utils. Comm'n v. Attleboro Steam & Elec. Co., 273 U.S. 83, 88-90, 47 S. Ct. 294, 296, 71 L. Ed. 54 (1927). The Court reasoned that, under the Commerce Clause, Congress alone possessed the authority to regulate interstate transmissions of electricity. Id. at 90, 47 S. Ct. at 296. After Attleboro, states could continue to regulate retail electric-power sales and rates, but could not regulate wholesale transmissions of electric energy in interstate commerce. See Federal Power Comm'n v. Southern Cal. Edison Co., 376 U.S. 205, 213 n. 8, 84 S. Ct. 644, 650 n. 8, 11 L. Ed. 2d 638 (1964).

Attleboro revealed a "gap" in the regulatory oversight of electric utilities: although Congress retained the exclusive authority to regulate interstate transmissions of power, no federal agency had been given these responsibilities. In 1935, Congress enacted the Federal Power Act, 16 U.S.C.A. §§ 791a-828c (West 1985 & Supp.1992) ("Federal Power Act" or "FPA"), to fill this regulatory void. Its intent was

to "fill the gap"—the phrase is repeated many times in the hearings, congressional debates and contemporary literature— left by Attleboro in utility regulation. Congress interpreted that case as prohibiting state control of wholesale rates in interstate commerce for resale, and so armed the Federal Power Commission with precisely that power.

United States v. Public Utils. Comm'n, 345 U.S. 295, 307-08, 73 S. Ct. 706, 714, 97 L. Ed. 1020 (1953); see also Frank R. Lindh, Federal Preemption of State Regulation in the Field of Electricity and Natural Gas: A Supreme Court Chronicle, 10 Energy L.J. 277, 285-86 (1989). The FPA created the Federal Power Commission (now FERC) to regulate wholesale transmissions and sales of energy in interstate commerce. FPA §§ 792, 824(a).

The "Bright Line": Federal versus State Regulation.

The Supreme Court has characterized the Federal Power Act as a Congressional attempt to establish a "bright line" between state and federal jurisdiction over utility regulation. See Southern Cal. Edison Co., 376 U.S. at 215-16, 84 S. Ct. at 651. This bright-line analysis has proved useful in challenges to state jurisdiction brought under both the Commerce and Supremacy Clauses;[7] it permits courts to focus upon *464 the interstate distinction as well as the wholesale or retail nature of the transactions involved.

The "Filed Rate" Doctrine.

In their regulation of retail rates, states may not challenge federally approved wholesale rates as unreasonable. In Montana-Dakota Utilities Co. v. Northwestern Public Service Co., 341 U.S. 246, 251-52, 71 S. Ct. 692, 695, 95 L. Ed. 912 (1951), the Court pronounced the "filed rate" doctrine: the utility rate filed with and approved by FERC is the only reasonable wholesale rate. One federal circuit court has elaborated on the doctrine:

The purchaser's right to a reasonable wholesale rate is the right to the rate which the Commission [FERC] files or fixes. Except for a narrow review of the Commission's orders, the court can assure no right to a different rate on the ground that, in its opinion, another rate is the only or more reasonable one.

Kentucky W. Va. Gas Co. v. Pennsylvania Pub. Util. Comm'n, 837 F.2d 600, 606 (3rd Cir.), cert, denied, 488 U.S. 941, 109 S. Ct. 365, 102 L. Ed. 2d 355 (1988) (discussing Montana-Dakota Utilities).

The Narragansett and Pike County Doctrines.

The filed rate doctrine restricts state regulation of the electric utility industry. The Rhode Island Supreme Court examined the interplay between this doctrine and state regulatory practices in Narragansett Electric Co. v. Burke, 119 R.I. 559, 381 A.2d 1358 (1977), cert, denied, 435 U.S. 972, 98 S. Ct. 1614, 56 L. Ed. 2d 63 (1978). That court held that the state regulatory commission could not review the reasonableness of FERC-approved wholesale rates and must treat the FERC rates as reasonable operating expenses when establishing a utility's costs of retail service. See id. 381 A.2d at 1363. Because FERC exercises exclusive jurisdiction to determine "just and reasonable" rates for wholesale sales of electric power in interstate commerce, see FPA § 824d(a), federal preemption principles preclude state regulatory practices that effectively challenge the reasonableness of FERC-set rates. See Narragansett, 381 A.2d at 1361; see also Northern States Power Co. v. Minnesota Pub. Utils. Comm'n, 344 N.W.2d 374 (Minn.), cert, denied, 467 U.S. 1256, 104 S. Ct. 3546, 82 L. Ed. 2d 850 (1984); Eastern Edison Co. v. Department of Pub. Utils., 388 Mass. 292, 446 N.E.2d 684 (1983); Northern States Power Co. v. Hagen, 314 N.W.2d 32 (N.D. 1981).

A Pennsylvania decision crafted an exception to the preemption doctrine of Narragansett. In Pike County Light and Power Co. v. Pennsylvania Public Utility Commission, 77 Pa.Cmwlth. 268, 465 A.2d 735 (1983), the court noted that although FERC exercises exclusive jurisdiction to set just and reasonable rates, FERC "makes no determination of whether it is just and reasonable for Pike [the utility company] to incur such a rate as an expense." Id. 465 A.2d at 738 (emphasis in original).

According to Pike County, FERC has statutory jurisdiction under the Federal Power Act to determine whether the seller's rates are just and reasonable and in the public interest in considering the seller's costs. See id; see also FPA § 824d(a). But the Act does not charge FERC with examining the prudence of the purchaser's decision to obtain power from this source. Therefore, the preemption doctrine of Narragansett does not deprive a state commission of jurisdiction to review a utility's decision to purchase power from a particular source at a particular price in light of alternative sources. See Pike County, 465 A.2d at 738. While Narragansett would foreclose a state's review of the reasonableness of FERC-approved wholesale rates, Pike County permits "state commissions [to] inquire into the prudence of the retail utility's purchasing decisions in determining whether to allow the utility full recovery of its purchase power costs in its *465 retail costs of service." See Vince & Moot, supra, at 22.

The Present Controversy.

Gulf States claims that federal preemption principles deprive the Commission of jurisdiction to review the prudence of Gulf States' capacity costs after FERC approved the rates governing the wholesale transaction between Southern and Gulf States. Gulf States also relies on the Supreme Court's holding in Mississippi Power & Light Co. v. Mississippi ex rel. Moore, 487 U.S. 354, 108 S. Ct. 2428, 101 L. Ed. 2d 322 (1988), to argue that FERC exercises exclusive jurisdiction to review a purchaser's prudence and to maintain that Pike County and its progeny enjoy no continuing vitality.

The Commission relies on Pike County to exercise its review of Gulf States' prudence in incurring the capacity charges at issue here. It argues that Mississippi Power & Light does not foreclose the Pike County doctrine and does not divest the Commission of jurisdiction to review the prudence of Gulf States' purchase of capacity.

• Did FERC determine that Gulf States was prudent in purchasing the Southern capacity?

In Southern Company Services, Inc., 26 FERC ¶ 61,360, at 61,796 (1984), FERC described the rates at which Southern sold capacity to Gulf States as "just and reasonable and in the public interest." Gulf States argues that this characterization of the wholesale rates constitutes a finding that Gulf States prudently incurred the capacity costs and preempts the Commission's prudence inquiry during subsequent retail-rate hearings. We disagree.

Section 824 of the FPA expressly grants FERC jurisdiction to regulate sales of wholesale power in interstate commerce; FERC's inquiry focuses on the rate at which sellers market their power. FERC does not review the market conditions or other factors that govern the prudence of the purchaser's decision to buy power in the wholesale transaction. FERC specifically deferred consideration of Gulf States' prudence to a future rate hearing:

[T]he question of the prudence of a utility's power purchases is properly an issue in the buying utility's rate case where it seeks to pass the costs of its purchased power on to its ratepayers. If and when Gulf States makes a rate filing reflecting its costs under these contracts, any interested party may intervene and challenge those costs.

Southern Co. Servs., Inc., 26 FERC ¶ 61,360, at 61,795. By approving Southern's wholesale rates as just and reasonable, FERC did not implicitly find that Gulf States was prudent in purchasing the Southern capacity.

• Does FERC exercise exclusive jurisdiction to review the prudence of purchases of wholesale electric power?

Whether or not FERC actually examined the prudence of Gulf States' purchases of capacity from Southern, Gulf States claims that FERC has exclusive jurisdiction to do so and consequently, the Commission may not exercise this jurisdiction.[8] This preemption argument goes to the heart of the jurisdictional tug-of-war between the federal and state regulation of electric utilities.

"[T]he regulation of utilities is one of the most important of the functions traditionally associated with the police power of the States." Arkansas Elec. Coop. Corp. v. Arkansas Pub. Serv. Comm'n, *466 461 U.S. 375, 377, 103 S. Ct. 1905, 1908, 76 L. Ed. 2d 1 (1983). PURA empowers the Commission to set just and reasonable retail rates. See PURA § 38. A rate cannot be deemed just and reasonable unless the utility was prudent in incurring the operating expenses it seeks to pass through to consumers.[9] Our state regulatory scheme grants the Commission jurisdiction to review the prudence of Gulf States' operating expenses when the utility seeks a rate increase.

Congress created a federal regulatory scheme to fill the void that Attleboro identified in the regulation of the electric utility industry's interstate transactions. The Act provides for federal regulation of transmissions and wholesale sales of electric power in interstate commerce. See FPA § 824(a). Its declaration of policy states that "such Federal Regulation, however, [is] to extend only to those matters which are not subject to regulation by the States." Id. The federal government's jurisdiction "was to complement that of the state regulatory bodies." Federal Power Comm'n v. Panhandle E. Pipe Line Co., 337 U.S. 498, 503, 69 S. Ct. 1251, 1255, 93 L. Ed. 1499 (1949).

But Gulf States asserts that federal jurisdiction now preempts the states' traditional authority to review a utility's prudence in incurring the operating expenses it seeks to include in retail rates. Preemption is a disfavored doctrine. See Chicago & N. W. Trans. Co. v. Kalo Brick & Tile Co., 450 U.S. 311, 317, 101 S. Ct. 1124, 1130, 67 L. Ed. 2d 258 (1981). Generally speaking, federal law may preempt state law in three ways: (1) Congress may express its intent to preempt state law; (2) Congress may merely signal an intent to occupy an area; and (3) a state law may be automatically preempted because it conflicts with a federal law. New Orleans Pub. Serv. Inc. v. Council of New Orleans, 911 F.2d 993, 998 (5th Cir. 1990), cert, dismissed,___ U.S. ___, 112 S. Ct. 411, 116 L. Ed. 2d 357 (1991) (citing Michigan Canners & Freezers Ass'n, Inc. v. Agricultural Mktg. & Bargaining Bd., 467 U.S. 461, 469, 104 S. Ct. 2518, 2523, 81 L. Ed. 2d 399 (1984)). We detect nothing in the Federal Power Act that would foreclose the state's jurisdiction to review a utility's prudence in incurring operating expenses when the utility seeks a rate increase.

Gulf States argues, however, that in Mississippi Power & Light the Supreme Court has "laid to rest any doubt that FERC's authority extends to the purchaser's side of wholesale electric transactions," and that "FERC cannot tenably disclaim jurisdiction over purchaser prudence after Mississippi Power & Light." We disagree. While Mississippi Power & Light does recognize FERC's jurisdiction to review a purchaser's prudence in certain situations, it does not hold that all wholesale purchases are subject to FERC's exclusive jurisdiction, and it does not govern the issue presented in this case.

Mississippi Power & Light involved Mississippi's attempts to circumvent FERC's allocation of construction costs for the Grand Gulf nuclear power plant. Middle South Utilities (Middle South), a public utility holding company, began construction of Grand Gulf, a plant designed to provide power for each of Middle South's four operating subsidiaries, which had formed a FERC-approved integrated pooling arrangement. By virtue of this power pool, the subsidiaries sold wholesale power to each other and to other outside companies for resale and also engaged in retail sales of power throughout Louisiana, Arkansas, Missouri, and Mississippi.

*467 Grand Gulf's construction costs exceeded the initial estimate six-fold, dramatically increasing Middle South's completion costs. FERC revised, and ultimately approved, Middle South's operating agreement allocating Grand Gulf's capacity costs to the four subsidiaries in varying percentages. The operating agreement served to distribute the pain of Grand Gulf's increased construction costs among the affiliated poolmembers. Because Grand Gulf had been constructed to serve the collective needs of all the pool participants, FERC allocated the plant's construction costs among the pool members in accordance with their share of the plant's generating capacity.

Some of the individual affiliates then attempted to pass through these allocated capacity costs to their respective retail customers. Mississippi Power & Light ("MP & L") successfully obtained a retail rate increase that allowed it to recoup its share of Grand Gulf's capacity charges, as determined by FERC. The Mississippi Supreme Court overturned the state commission's order, holding that the commission erred in approving a rate increase without first determining that MP & L's capacity expenses were prudently incurred. State ex rel. Pittman v. Mississippi Pub. Serv. Comm'n, 506 So. 2d 978, 986-87 (Miss. 1987). The Mississippi court noted that FERC had not addressed the prudence of MP & L's participation in the Grand Gulf project, and consequently, Mississippi was not precluded from reviewing this issue.

The United States Supreme Court reversed, holding that the state commission was preempted from reviewing the prudence issue:

The [commission] cannot evaluate either the prudence of MSU's decision to invest in Grand Gulf and bring it on line or the prudence of MP & L's decision to be a party to agreements to construct and operate Grand Gulf without traversing matters squarely within FERC's jurisdiction.

Mississippi Power & Light, 487 U.S. at 376, 108 S. Ct. at 2441.

It is critical to our inquiry today to understand why the Supreme Court determined that FERC had jurisdiction to determine the purchaser-prudence issue, an inquiry traditionally performed by the states in their rate-making process. Mississippi Power & Light suggests that FERC's jurisdiction to review particular purchaser-prudence issues arose from its exclusive jurisdiction to review the operating agreements governing an integrated power pool.

MP & L was a participant in a power pool consisting of all of Middle South's operating affiliates. Each affiliate member purchased and sold wholesale electric power. See Mississippi Power & Light, 487 U.S. at 357, 108 S. Ct. at 2431. Middle South's operating agreement was subject to FERC's review because it involved the sale of wholesale power among the affiliate members. See FPA § 824. Applying federal preemption principles, FERC exercised exclusive jurisdiction to review the reasonableness of the wholesale rates. Id. at § 824d.

The Mississippi court's order to review all transactions between MP & L and the holding company to determine their effect on operating expenses was invalid because the transactions to be reviewed

comprise the very Systems Agreements between MSU and the operating companies and UPSA [Unit Power Sales Agreement] evaluated by FERC in the exercise of its jurisdiction over wholesale rates. The MPSC [commission] lacks jurisdiction to reevaluate the reasonableness of those transactions.

Id. (emphasis added). Only FERC may evaluate the agreements governing members of an integrated power pool; the state may not reevaluate the reasonableness of those wholesale transactions. Id. Therefore, a state regulatory commission may not review the prudence of a purchaser's participation in an integrated operating arrangement involving wholesale and retail transmissions between pool members.

In American Electric Power Service Corp., 32 FERC ¶ 61,363 (1985), a municipality and a state agency intervened to ask FERC to refrain from considering whether pool members were wise or prudent in entering *468 into the pooling agreement. Id. at 61,814. FERC declined to limit its review:

Transmission and allocation of the costs of the AEP [pool] transmission network are integral parts of the operation of the AEP pool. Therefore, the prudence of being a party to the ... transmission agreement cannot be considered separately from the prudence of being a party to the entire AEP pool relationship. A challenge to the membership in a public utility holding company power pool of a member of the holding company is a federal matter....

Moreover, a state commission could not review the prudence of an AEP operating company in entering into the ... transmission agreement without invading our jurisdiction by ruling to some extent on the merits of the agreement itself.... For a state commission to decide such questions for itself would be an invasion of our exclusive jurisdiction over the ... transmission agreement. Commission [FERC] precedent leaving to the state commissions the question of the prudence of an operating company in making a particular purchase is not applicable under the facts of this case.

Id. at 61,818 (emphasis added). See also American Elec. Power Serv. Corp., 37 FERC ¶ 61,001 (1986); AEP Generating Co., 36 FERC ¶ 61,226 (1986). This decision illustrates the rationale announced later in Mississippi Power & Light that FERC has exclusive jurisdiction to review the prudence of a pool member's participation in a pooling arrangement that involves buying and selling energy at wholesale rates.

Although Mississippi Power & Light recognizes FERC's exclusive jurisdiction to review the prudence of entering into certain transmission agreements, it does not establish FERC's exclusive jurisdiction to determine the prudence of every wholesale purchase of electric power. Here, Gulf States is not a participant in an integrated pooling arrangement which might invoke FERC's exclusive jurisdiction. Nor is Gulf States transmitting or selling wholesale electric power in exchange for the Southern capacity, conditions which would subject it as a seller to FERC's exclusive jurisdiction. Unless the purchaser is also a seller of wholesale power or a member of an operating arrangement subject to FERC regulation, FERC has no statutory authority to review the prudence of the purchaser's expenses or the reasonableness of the purchaser's decision to participate in the project. See Mississippi Power & Light, 487 U.S. at 376, 108 S. Ct. at 2441.

FERC has noted this limitation on its jurisdiction. In Monongahela Power Co., et al, 39 FERC 1161,350, at 62,094-95 (1987), FERC was asked to review the Potomac Electric Power Company's ("PECO's") purchase of 450 megawatts of energy and related capacity from the Allegheny Power System ("APS"). PEPCO was under no preexisting obligation to purchase this capacity due to a pooling arrangement or integrated corporate structure. Interveners challenged FERC's jurisdiction to review the prudence of an unaffiliated operating utility's purchase from a holding company. FERC recognized its lack of jurisdiction to evaluate an unaffiliated purchaser's prudence under these circumstances:

Given PEPCO's status as a purchaser not affiliated with ... APS and not under any preexisting obligation under the terms of any interconnection agreement, power pool, or other highly integrated contractual or corporate arrangement to make this purchase, we do not have jurisdiction in this proceeding over the question of whether PEPCO was prudent in entering into this transaction.

Id. at 62,095 (citing Pike County). See also Southern Co. Servs., Inc., 26 FERC ¶ 61,360; PSI Energy, Inc., 55 FERC ¶ 61,254, at p. 61,810-11 n. 18 (1991); Palisades Generating Co., 48 FERC ¶ 61,144, AT P. 61,574-75 (1990).

Even after Mississippi Power & Light, FERC will probably continue to disclaim jurisdiction to inquire into a purchaser's prudence in entering into an agreement not dictated by pooling arrangements or corporate integration. FERC's recognition that it lacked jurisdiction in this case *469 to review Gulf States' prudence[10] is entirely consistent with the Federal Power Act and Mississippi Power & Light. Under the circumstances of this case, federal preemption does not preclude the Commission's review of Gulf States' prudence in contracting to purchase this quantity of energy capacity from Southern in light of its projected needs and considering its alternative sources of power.

• Did the Commission's disallowance of Gulf States' capacity costs constitute impermissible "trapping"?

Gulf States argues that the Commission violated the filed rate doctrine by failing to allow as a reasonable operating expense recovery of the costs incurred in paying a FERC-determined wholesale price. See Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953, 964-65, 106 S. Ct. 2349, 2356, 90 L. Ed. 2d 943 (1986);[11]Narragansett, 381 A.2d at 1363. The utility characterizes the disallowance of this operating expense as "trapping," an impermissible state regulatory action. See Mississippi Power & Light, 487 U.S. at 372, 108 S. Ct. at 2439; see also Nantahala, 476 U.S. at 970-71, 106 S. Ct. at 2359. The Commission responds that Pike County and its progeny permit the Commission to review the wisdom of Gulf States' initial decision to purchase Southern capacity.

In its findings of fact, the Commission determined that "Gulf States did not need any of the capacity it obtained under the Southern contracts and did not appropriately evaluate the desirability of entering into such contractual commitments versus other alternatives...." Finding of Fact No. 67. This finding focuses solely on purchaser prudence, as Pike County permits a state regulatory commission to do. The Commission did not challenge FERC's wholesale rates by manipulating FERC-ordered allocations or second-guessing the reasonableness of other factors previously approved by FERC.

Mississippi Power & Light and Nantahala indicate that impermissible trapping occurs when FERC mandates a particular rate or quantity of power and the state commission refuses to allow the utility to recoup that mandated expense in its retail rates. See Mississippi Power & Light, 487 U.S. at 372, 108 S. Ct. at 2439; Nantahala, 476 U.S. at 971-72, 106 S. Ct. at 2359. Both decisions involved FERC-mandated allocations of power; the utility companies had no choice but to purchase the quantities that they were allocated. Mississippi Power & Light, 487 U.S. at 374, 108 S. Ct. at 2440; Nantahala, 476 U.S. at 970-71, 106 S. Ct. at 2359. In our present situation, FERC made no allocations; Gulf States was under no obligation to purchase any quantity of power from Southern.

If a utility has a choice to purchase a particular quantity of power at a particular price, the state may properly review the utility's prudence in incurring that expense. *470 Compare Kentucky W. Va. Gas Co., 837 F.2d at 609 (FERC approval does not mandate pass-through of actual costs where utility had option to purchase wholesale gas at lower rate) with Kentucky W. Va. Gas Co. v. Pennsylvania Pub. Util. Comm'n, 862 F.2d 69, 74 (3d Cir.1988) (state commission's disallowance of costs improper where costs are FERC-mandated). A state's refusal to pass through to consumers unreasonable capacity costs voluntarily incurred by a utility is not impermissible trapping; it is the exercise of a discretion necessary and proper to meaningful retail rate-making. To hold otherwise would effectively end state regulation of retail sales that involve any wholesale purchases of power at FERC-set rates. If FERC declined to review the purchaser's prudence, as it has in some circumstances, we would be creating another regulatory void. Federal preemption principles do not require total emasuclation of the states' traditional role in setting reasonable retail rates to protect the ultimate consumers of electric power.

In a case decided after Mississippi Power & Light and Nantahala, the Supreme Court has signalled that preemption principles do not always preclude state or local jurisdiction to conduct prudence reviews in situations involving FERC-mandated allocations and FERC-set rates. In New Orleans Public Service, Inc. v. Council of the City of New Orleans, 491 U.S. 350, 109 S. Ct. 2506, 105 L. Ed. 2d 298 (1989), the Court reviewed a federal-abstention issue within the context of a utility's attempts to pass through its FERC-mandated allocation of a nuclear plant's costs. The City Council of New Orleans (the "Council") had challenged New Orleans Public Service, Inc.'s ("NOPSI's") request for an immediate rate increase. NOPSI sought to pass through to consumers its FERC-allocated share of costs involving the same Grand Gulf power plant at issue in Mississippi Power & Light. The Council disallowed an immediate pass through of NOPSI's capacity costs and announced that it would review the wisdom of NOPSI's failure to diversify its portfolio after the risk of nuclear power became apparent. The Council specifically provided, however, that in determining appropriate retail rates, it would not invalidate any of the Grand Gulf agreements nor would it order NOPSI to pay any wholesale rates other than those approved by FERC. Id. 491 U.S. at 356, 109 S. Ct. at 2511.

Though its holding was tied to the abstention issue, the Court noted that

[t]he Council has not sought directly to regulate interstate wholesale rates; nor has it questioned the validity of the FERC-prescribed allocation of power within the Grand Gulf System, or the FERC-prescribed wholesale rates; nor has it reexamined the prudence of NOPSI's agreement to participate in Grand Gulf 1 in the first place. Rather, the Council maintains that it has examined the prudence of NOPSI's failure, after the risk of nuclear power became apparent, to diversify its supply portfolio and that finding that failure negligent, it has taken the normal ratemaking step of making NOPSI's shareholders rather than the ratepayers bear the consequences. Nothing in this is directly or even indirectly foreclosed by the federal statute, the regulations implementing it, or the caselaw applying it. There may well be reason to doubt the Council's necessary factual finding that NOPSI would have saved money had it diversified. But we cannot conclusively say it is wrong without further factual inquiry....

Id. at 367, 109 S. Ct. at 2517. On remand, the Fifth Circuit ruled that federal law did not preempt the Council's prudence review and its resulting order. See New Orleans Pub. Serv. Inc., 911 F.2d at 1002.

The NOPSI decisions validate state review of costs that a purchaser voluntarily but imprudently incurs in a wholesale transaction involving FERC-set rates. The decisions support a state or local regulatory agency's refusal to pass through to consumers certain imprudently incurred operating expenses. Such a rate-making decision will not be labelled an impermissible trapping. Although the disallowed costs will be trapped, the trapping is not impermissible unless FERC mandated the utility's *471 decision to incur the costs. By disallowing Gulf States' voluntarily incurred capacity costs, the Commission has not impermissibly trapped the capacity costs.

• Did the Commission impermissibly review the particular terms contained in the Southern contracts?

Gulf States claims that the Commission's order is based upon an impermissible review of the specific terms of its contracts with Southern. The utility argues that by disallowing the capacity costs, the Commission has effectively ruled that the terms of the purchase were unreasonable. This, says the utility, constitutes an infringement of FERC's exclusive jurisdiction to review the terms of agreements governing wholesale transmissions of energy. Gulf States mischaracterizes the scope of the Commission's review, and we reject its claim that the Commission encroached upon FERC's jurisdiction.

FERC's jurisdiction encompasses wholesale rates and power allocations affecting those rates, as well as purchaser-prudence issues arising in the context of integrated pooling agreements or sales between corporate affiliates. See FPA §§ 824, 824d; Mississippi Power Nantahala. We have already determined that FERC did not review Gulf States' prudence in buying energy from Southern and that FERC did not require Gulf States to purchase any particular quantity of energy. The remaining question is whether the Commission's disallowance of Gulf States' capacity costs directly or indirectly challenged FERC's exclusive jurisdiction over wholesale rates.

We conclude that the Commission's order does not challenge FERC's determination that Southern's wholesale rates were just and reasonable. The Commission found that "Gulf States did not need any of the capacity it obtained under the Southern contracts...." Finding of Fact No. 67 (emphasis added). To argue that the Commission impermissibly challenged FERC-set rates, Gulf States must add several words to this finding that are not there: "Gulf States did not need any of the capacity it obtained under the Southern contracts at the rate specified." But the Commission's factfinding does not challenge the reasonableness of FERC's wholesale rates; it challenges Gulf States' reasonableness in analyzing its energy needs.

Gulf States points to the Commission's finding that the utility "was imprudent in its failure to seek more favorable terms when it was negotiating with Southern to purchase the 1,000 MW of Southern power." Finding of Fact No. 76. But this finding does not, in itself, illustrate any jurisdictional infringement. The Federal Power Act does not grant FERC exclusive jurisdiction over the reasonableness of all contract provisions submitted for FERC review. FERC acknowledged this when it stated:

We do not view our responsibilities under the Federal Power Act as including a determination that the purchaser has purchased wisely or has made the best deal available. However, these are legitimate concerns of the state commissions and this Commission as well in determining whether purchases reflect prudently incurred expenses for purposes of determining the purchaser's rates of sales to others.

Pennsylvania Power & Light, 23 FERC fl 61,325 at 61,716 (1983). See also Southern Co. Servs., Inc., 39 FERC ¶ 63,026 at 65,147 (1987). FERC reviews the rates at which interstate transmissions of wholesale power for resale are made; it does not preempt the states' jurisdiction to review the reasonableness of all operating expenses that the utility wants to include in the retail rate base.

Even when FERC finds wholesale transmission rates are just and reasonable, a purchaser who wishes to pass those costs on to consumers may still be required to. show a need for the power it has purchased. The Commission may properly evaluate the prudence of Gulf States' purchase in view of the utility's long-term capacity requirements and its alternative sources of power. The Commission's prudence inquiry was a proper function of its retail ratemaking authority, and it did not directly or indirectly challenge the reasonableness of the FERC-approved rates.

*472 • Did the Commission's order impermissibly burden interstate commerce?

In its final jurisdictional challenge, Gulf States claims, that the Commission's order disallowing recovery of the capacity costs impermissibly burdens interstate commerce. To prevail, Gulf States must establish that the claimed burden on interstate commerce outweighs any "putative local effects of the prudence review conducted as part of the Commission's ratemaking process." See Arkansas Elec. Coop. Corp., 461 U.S. at 393-94, 103 S. Ct. at 1917; Pike v. Bruce Church, Inc., 397 U.S. 137, 90 S. Ct. 844, 25 L. Ed. 2d 174 (1970).

"Need for new power facilities, their economic feasibility, and rates and services, are areas that have been characteristically governed by the States." Pacific Gas & Elec. Co. v. State Energy Resources Conservation & Dev. Comm'n, 461 U.S. 190, 205, 103 S. Ct. 1713, 1723, 75 L. Ed. 2d 752 (1983). Gulf States has not demonstrated how the Commission's exercise of its traditional regulatory authority violates the Commerce Clause.

Where [a] statute regulates evenhandedly to effectuate a legitimate local public interest, and its effects on interstate commerce are only incidental, it will be upheld unless the burden imposed on such commerce is clearly excessive in relation to local putative benefits. If a legitimate local purpose is found, then the question becomes one of degree. And the extent of the burden that will be tolerated will of course depend on the nature of the local interest involved, and on whether it could be promoted as well with a lesser impact on interstate activities.

Arkansas Elec. Coop. Corp., 461 U.S. at 393-94, 103 S. Ct. at 1917 (citing Pike v. Bruce Church, Inc., 397 U.S. at 142, 90 S. Ct. at 847). The regulation of retail rates is a legitimate public interest. In performing this traditional state function, the Commission followed its statutory mandate to inquire if Gulf States had prudently analyzed its needs for energy capacity and the other sources available to meet those needs. By disallowing imprudently incurred capacity costs, the Commission has imposed a burden on Gulf States' shareholders rather than impose that burden on the utility's ratepayers. But the Commission has not imposed an excessive burden on interstate commerce that violates the Commerce Clause.

We hold that the Commission's actions violated neither the Supremacy Clause nor the Commerce Clause. In so holding, we specifically conclude that (1) FERC did not review Gulf States' prudence in contracting for the Southern capacity; (2) the Commission retained jurisdiction to review the prudence of Gulf States' capacity purchases; (3) the Commission's disallowance of the Southern capacity costs did not constitute impermissible trapping; (4) the Commission's finding that Gulf States did not need the capacity it purchased from Southern did not constitute an impermissible review of FERC-set rates; and (5) the Commission's disallowance of the capacity costs did not excessively burden interstate commerce. We overrule Gulf States' first three points of error.

PRECLUSION ISSUES

In its fourth point of error, Gulf States claims that the Commission arbitrarily ignored its earlier order in Docket No. 4501 that Gulf States needed the Southern power to ensure adequate reserve requirements. In that earlier order, the Commission approved Gulf States' application to amend its certificate of convenience and necessity ("CCN") to allow the utility to build a transmission line linking Gulf States' facilities with Southern's. The Commission found that such a transmission line "is needed in order to enable GSU [Gulf States] to import from Southern power which is necessary to ensure adequate reserve margins and to help reduce dependence on oil and gas based energy." Finding of Fact No. 2. Gulf States argues that this order precludes any subsequent finding that the Southern capacity was not needed. We disagree.

Courts do apply collateral estoppel principles to administrative proceedings, see generally *473 Kenneth C. Davis, Administrative Law Treatise, § 21:2-11 (2d ed. 1983 & Supp.1989), and Texas courts have made limited use of preclusion principles in cases involving orders of administrative agencies. See, e.g., Coalition of Cities for Affordable Util. Rates v. Public TJtil. Comm'n, 798 S.W.2d 560 (Tex. 1990), cert, denied, ___ U.S.___, 111 S. Ct. 1641, 113 L. Ed. 2d 736 (1991); Al-Jazrawi v. Texas Bd. of Land Surveying, 719 S.W.2d 670 (Tex.App.—Austin 1986, writ refd n.r.e.). As Professor Davis explains, "[Res judicata ] is at its best as it applies to an adjudication of past facts, where the second proceeding involves the same claim or transaction as the first." Kenneth C. Davis, Administrative Law Text (1972).

Coalition of Cities presented such an instance. There the Commission sought to conduct a second prudence review of a utility's expenditures, even though this matter had already been litigated before the agency and the utility had failed to meet its burden. Coalition of Cities, 798 S.W.2d at 563. The Court determined that the second review would only embrace the same historical investment facts scrutinized in the first prudence review. Id. Because the second review would address subject matter identical to the first, the Court found the application of res judicata appropriate.

By contrast with Coalition of Cities, application of preclusion principles in this case is unwarranted. The Commission's order in Docket No. 4501 granted Gulf States a CCN authorizing the construction of a power line to transport Southern power from Mississippi to Louisiana. Under PURA section 54(b), the Commission may grant a CCN only on finding that the certificate is "necessary for the service, accommodation, convenience, or safety of the public." Section 54(c) further requires the Commission to consider the adequacy of existing service, the need for additional service, the effect of the granting of a certificate on the recipient and on any public utility of the same kind already serving the proximate area, and on such factors as community values, recreational and park areas, historical and aesthetic values, environmental integrity, and the probable improvement of service or lowering of cost to consumers in such area.

While PURA requires the Commission to consider a broad range of factors before issuing a CCN, we do not understand the statute to require the Commission to find that the utility has prudently selected the method by which to meet its service needs.[12] Nor did the Commission make any such finding in Docket No. 4501. Consequently, we conclude that Docket No. 4501 did not address the subject matter of the cause currently under review, namely Gulf States' prudence in purchasing the Southern capacity. We overrule Gulf States' fourth point of error.

EVIDENTIARY ISSUES

In its fifth point of error, Gulf States asserts that the Commission failed to consider certain evidence in arriving at its findings and conclusions. The utility characterizes this action as a "discovery sanction" and complains that it was unlawful. In addition, Gulf States complains that the Commission's declaration that its findings on the prudence issue were res judicata will compound the harm caused by the alleged discovery sanction.

The Alleged "Discovery Sanction".

Gulf States asserts that the Commission ignored key evidence when making critical findings of fact. The utility argues that the Commission acted arbitrarily and capriciously *474 in not considering (1) Gulf States' Form 10-K; (2) a Board of Directors' Study; and (3) a report entitled "Exxon Task-Force Studies."

Gulf States characterizes the Commission's action as an unlawful sanction but has not identified in the record where the hearing examiner levied any actual "discovery sanction." Nor has Gulf States illustrated how the hearing examiner erred when treating these particular items.[13] Rather, Gulf States complains that the Commission failed to base its findings on this evidence.

Gulf States proffered the "sanctioned" evidence to support its claim that it had prudently considered alternative fuel sources when deciding to purchase the Southern capacity.[14] But at least two witnesses suggested that Gulf States deferred the Nelson-5 project after it purchased Southern capacity.[15] The resolution of conflicting evidence goes to the credibility of the witnesses and to the weight of the evidence. Similarly, the hearing examiner's determination that the Exxon Task-Force Studies did not support Gulf States' earlier deferral also goes to the weight of the evidence.

An agency may or may not accept the testimony of witnesses and the agency is the judge of the weight accorded that testimony. Southern Union Gas Co. v. Railroad Comm'n, 692 S.W.2d 137, 141 (Tex.App.—Austin 1985, writ refd n.r.e.). A reviewing court is prohibited from substituting its judgment as to the weight of the evidence on questions committed to agency discretion. Texas Health Facilities Comm `n v. Charter Medical-Dallas, Inc., 665 S.W.2d 446, 452 (Tex. 1984). Presumably, the hearing examiner and the Commission attached greater weight to the testimony suggesting that Gulf States' decision to defer the Nelson-5 project was made after contracting with Southern.

Gulf States suggests that the Commission acted arbitrarily and capriciously in reaching this conclusion. To determine if an agency acted arbitrarily and capriciously, even though substantial evidence supports its order or action, we look to see if the order was based on a consideration of all relevant factors. See Starr County v. Starr Indus. Servs., Inc., 584 S.W.2d 352, 355 (Tex.Civ.App—Austin 1979, writ refd n.r.e.) (citing Lewis v. Metropolitan Sav. *475 and Loan Ass'n, 550 S.W.2d 11, 16 (Tex. 1977)). A rational connection must exist between the facts and the decision of the agency. Id. at 356. Here, such a connection exists: Gulf States' failure to consider alternative sources of power before incurring long-term capacity charges led to the Commission's finding that the capacity costs were imprudently incurred, and thus to the order disallowing recovery of the capacity expenses. The Commission's failure to base its findings solely upon evidence favorable to Gulf States was not arbitrary or capricious and does not constitute a discovery sanction.

Res Judicata Application to the Commission `s Factfindings.

In this same point of error, Gulf States next argues that by attaching a res judicata effect to its findings,[16] the Commission "greatly compounded the punitive aspect of the discovery sanction" by preventing Gulf States from relitigating the prudence issues.

Gulf States' complaint is premature at best. The Commission levied no discovery sanction and no one has yet attempted to relitigate the issue of the utility's prudence. The doctrine of res judicata relies on a previous determination of issues or claims to preclude their subsequent relitigation. Res judicata, if pleaded, would by its very nature arise in a subsequent attempt to relitigate already-resolved issues or claims. See, e.g., Coalition of Cities, 798 S.W.2d at 562, 565.

The Commission's declaration that its findings are res judicata may be premature; from Gulf States' viewpoint, the declaration may be inaccurate. But this issue does not concern this appeal, which involves no attempt to relitigate issues previously decided by the Commission.[17]

Finding no merit in either of these contentions, we overrule the fifth point of error.

GULF STATES' PRUDENCE

In its sixth point of error, Gulf States asserts that the Commission applied a legally incorrect standard of prudence in evaluating the purchases of Southern capacity. Gulf States agrees with the Commission's definition of prudence, but complains that the Commission's application of that standard allowed the company insufficient latitude in its decision-making.

The burden of proof to show that a proposed change in rates is just and reasonable is on the public utility. PURA § 40. "A utility has the burden to prove the prudence and reasonableness of its expenditures before a rate increase can be approved." Coalition of Cities, 798 S.W.2d at 563. In order to include capacity charges in its rates, Gulf States had to demonstrate the prudence of its decision to purchase the Southern capacity.

In determining whether Gulf States met its burden, the Commission employed the following definition of prudence:

The exercise of that judgment and the choosing of that select range of options which a reasonable utility manager would exercise or choose in the same or similar circumstances given the information or alternatives at the point in time such judgment is exercised or option is chosen.

Conclusion of Law No. 25. Gulf States does not challenge this definition. Instead, it contends that the Commission misapplied the definition.

The examiner's report indicates that prudent decision-making may be demonstrated in one of two ways: "[T]o recover costs in rates, a utility may show either that its decisionmaking process was prudent, *476 or that the same decision is in the select range of options that would have resulted had prudent decisionmaking been employed." See Examiner's Report at 59; cf. Houston Lighting & Power Co., Docket No. 5779, 12 Tex.Pub.Util.Comm'n Bull. 261, 313 (1985); El Paso Elec. Co., Docket No. 6350, 13 Tex.Pub.Util.Comm'n Bull. 1091, 1119-1122 (1986).

Under the first method, a utility presents contemporaneous documentation of its decision-making process, thereby enabling the Commission to review the actual investigations and analyses leading to the utility's decision. When there is no evidence of contemporaneous investigation and analysis, a utility may employ the second method, analyzing the prudence of the decision after-the-fact. Id. at 58-59, 173.

We note that an attempt to demonstrate prudent decision-making by retrospective analyses is inherently defensive and hence more suspect:

First, after-the-fact analyses are not created for the purpose of helping corporate management reach the best decision, which would have tended to encourage frankness about problems with different courses of conduct. Rather, they are produced for the purpose of defending conduct already engaged in, which might have the opposite effect. Second, such analyses might describe events, available information, alternatives and decisions less accurately and completely than contemporaneous documents, due to such problems as imperfect recollection, changes in personnel or corporate philosophies and the influence of hindsight. For these reasons, utilities are well advised to keep appropriate documentation.

Examiner's Report at 58.

The utility without contemporaneous evidence to support its decision-making process faces a heavy burden; the Commission will subject its after-the-fact justifications to rigorous review. The lack of documentation impedes the Commission's ability to determine whether the utility conducted a reasoned investigation of all relevant factors and alternatives before reaching its decision. Thus, through independent retrospective analyses, the utility must demonstrate that a reasonable utility manager, having investigated all relevant factors and alternatives as they existed at the time the decision was made, would have found the utility's actual decision a reasonably prudent course.

Gulf States resorted to independent retrospective analyses to demonstrate the prudence of its Southern capacity purchases. In its appellate brief, Gulf States fixates on the language that a prudent decision must fall within "the select range of options that would have resulted had prudent decisionmaking been employed." Gulf States claims that the Southern purchase effectively saved its ratepayers approximately $500 million[18] and that such a benefit placed the Southern purchase in the select range of options unless distinctly superior alternatives were available.

We understand Gulf States to mean that once it offered evidence that its decision would benefit its ratepayers, it had satisfied its burden of proof, which then shifted to either the Commission or the interveners to show the availability of a "distinctly superior alternative" to the decision taken. We find no basis in either PURA § 40 or the caselaw construing it for such burdenshifting.

Furthermore, even firm evidence that benefits flow from a particular decision would not prove that a reasonable utility manager who had investigated all the relevant factors available at the time Gulf States decided to purchase Southern capacity would have found that decision reasonably prudent. An examination of such relevant factors might have indicated that the purchase of excess capacity, despite possible attendant benefits, would be imprudent when compared with alternative courses.

Indeed, the Commission's findings of fact show this to be the case. Based on *477 its study of the record evidence, the Commission found that Gulf States

(1) knew or should have known at the time it committed to the capacity purchases that such capacity was unnecessary to meet its needs. Finding of Fact No. 52;

(2) failed to consider or properly analyze alternatives to the purchases of Southern capacity and such failure constitutes imprudent action. Finding of Fact No. 53;

(3) failed to consider or properly analyze evidence indicating that load management techniques or cogeneration, in combination with other alternatives, might have substituted for the Southern contracts at less cost or risk. Finding of Fact No. 54;

(4) should have considered, but failed to consider, sensitivity or risk analyses reflecting the effect of variations in fuel prices from those forecasted on the advisability of purchasing Southern power. Finding of Fact No. 60;

(5) failed to analyze its most recent load forecast and to consider up-to-date information concerning the possibility that its load would be significantly lower than forecasted. Finding of Fact No. 50;

(6) failed to appropriately evaluate the alternative of not deferring Nelson 5. Finding of Fact No. 65;

(7) failed to show that the Southern purchases were needed for capacity reasons as a result of the deferral of River Bend plant. Finding of Fact No. 61;

(8) could not rely on the two-year deferral of the River Bend plant to justify entering into the long-term Southern contracts. Finding of Fact No. 62; and

(9) failed to make reasonable efforts to identify and negotiate with suppliers of purchased power other than Southern. Finding of Fact No. 66.

These findings of fact indicate that at the time it made its decision to purchase the Southern capacity, Gulf States failed to analyze data suggesting that its capacity needs might be diminishing and could be met by instituting internal efficiencies and combining smaller, short-term purchases.

We believe the Commission could reasonably conclude from the indicated findings that Gulf States failed to discharge its heavy burden of showing through independent retrospective analysis that a reasonable utility manager who had investigated the data available at the time of the decision would have found the purchases of Southern capacity a reasonably prudent course. We overrule appellant's sixth point of error.

RECOVERY OF ATTENDANT COSTS

In its seventh point of error, Gulf States makes two distinct arguments: (1) that the Commission erroneously required the utility to demonstrate the prudence of its purchases; and (2) that the Commission's disallowance of Gulf States' capacity charges contradicts its finding that the energy purchases were prudent.

We have already established that Gulf States had the burden to demonstrate the prudence of its energy purchases. PURA §§ 40, 41(c)(3)(D); see supra note 9. Gulf States' argument in support of this point contains scant discussion of the Commission's alleged error and provides nothing for review.[19]

Gulf States' second argument is an attempt to "piggy-back" the recovery of the capacity charges on the recovery of the energy charges. The utility insists that it *478 would have been impossible to procure Southern energy without paying the capacity charges. Therefore, if the energy charges were prudently incurred, then the capacity charges must have been prudently incurred as well.

The question is not whether Gulf States could obtain energy from Southern without paying the capacity charges; the question is whether Gulf States needed the Southern capacity it contracted to purchase. The Commission's order recites that "[t]he decision to make the capacity payments in question was imprudent." Finding of Fact No. 71. Underlying this finding was Gulf States' miscalculation of its need for future capacity and its inadequate examination of alternative sources of long-term power. A review of the alternatives might have shown that Gulf States could have secured the energy it needed from other sources without incurring the high Southern capacity costs. Consequently, the Commission disallowed recovery of those charges from consumers.

We detect no error in the Commission's finding that Gulf States' energy costs were reasonable while failing to find that its capacity costs were reasonable. As Gulf States argued before the Commission, the utility would have incurred energy charges even if it had purchased its power from alternative sources. To the extent that the energy costs were reasonable, they were correctly recoverable in the rate increase; to the extent that the capacity charges were imprudently incurred, they were properly disallowed. We overrule appellant's seventh point of error. Because Gulf States' eighth point of error complains of the cumulative effect of any previous error, and because we have found no such error, we overrule the eighth point of error as well.

CONCLUSION

Finding no error in the Commission's order, we afirm the judgment of the district court.

NOTES

[1] "The Southern Company is a holding company registered under the provisions of the Public Utility Holding Company Act of 1935. Four wholly owned subsidiaries—Alabama Power Company, Georgia Power Company, Gulf Power Company, and Mississippi Power Company— operate electric utility facilities on an integrated basis. Southern Company Services Inc. provides engineering, accounting, and other services on behalf of the operating utilities. The four operating utilities and Southern Company Services Inc. are signatories to the contracts with GSU [Gulf States]." Southern Company Services, Inc., 43 FERC 61,003, at 61,010 (1988) (citations omitted).

[2] See Tex.Public Util. Comm'n, Gulf States Utils. Co., Docket No. 4501, 8 Tex.P.U.C.Bull. 509 (August 24, 1982) (CCN amendment granted for transmission agreement) (Memorandum Decision) ("Docket No. 4501").

[3] Numerous parties have contested Gulf States' requested rate increase. North Star Steel Texas, Inc., Office of Public Utility Counsel, the cities of China, Groves, Nederland, Port Arthur, Port Neches, and Vidor have all intervened in these proceedings.

[4] The Federal Energy Regulatory Commission ("FERC"), the successor to the Federal Power Commission, is the federal agency charged with regulating transmission and sale at wholesale of electric energy in interstate commerce.

[5] "This Constitution, and the Laws of the United States which shall be made in pursuance thereof... shall be the Supreme Law of the Land..." U.S. Const, art. VI, cl. 2.

[6] "The Congress shall have Power ... To regulate Commerce ... among the several States." U.S. Const, art. I, § 8, cl. 3.

[7] In Arkansas Electric Cooperative Corp. v. Arkansas Public Service Commission, 461 U.S. 375, 393, 103 S. Ct. 1905, 1917, 76 L. Ed. 2d 1 (1983), the Court abandoned the bright-line test for deciding the jurisdictional boundaries separating state and federal regulation of electric utilities under the Commerce Clause. Instead, the Court adopted the more current Commerce Clause analysis, balancing state interests against federal interests to determine whether interstate commerce has been unduly burdened. Id. at 391, 103 S. Ct. at 1916. However, bright-line analysis continues to determine challenges to state regulation brought under the Supremacy Clause. See Vince & Moot, supra, at 11-12 (citing Illinois Natural Gas Co. v. Centra! III. Pub. Serv. Co., 314 U.S. 498, 504, 62 S. Ct. 384, 386, 86 L. Ed. 371 (1942). See also Arkansas Elec. Coop., 461 U.S. at 379, 103 S. Ct. at 1910 (Congressional enactment of the Federal Power Act "shifted this Court's main focus—in determining the permissible scope of state regulation of public utilities—from the constitutional issues that concerned us in Attleboro to analyses of legislative intent.").

[8] The utility maintains that FERC's statements concerning its jurisdiction are not dispositive and cites to General Motors Corp. v. Illinois Commerce Commission, 143 Ill. 2d 407, 158 Ill. Dec. 537, 543, 574 N.E.2d 650, 656 (1991), cert. denied,___ U.S.___, 112 S. Ct. 1936, 118 L. Ed. 2d 542 (1992), in support. We agree with Gulf States that FERC's pronouncements of its jurisdictional limits are not controlling; those limits are found in the Federal Power Act and in the caselaw interpreting that Act.

But this is not to say that FERC's jurisdictional views are of no effect. FERC's interpretation of its jurisdiction is persuasive and worthy of deference. See Mississippi Power & Light, 487 U.S. at 380-82, 108 S. Ct. at 2443-45 (Scalia, J. concurring). Thus we cite to FERC orders and opinions where we find them illustrative of a given legal principle.

[9] "Purchased power costs constitute an operating expense, which may be allowed in rates only to the extent `reasonable and necessary to provide service to the public' PURA section 39(a), P.U.C. SUBST.R. 23.21(b). Any expenditure found by the Commission to be `unreasonable, unnecessary, or not in the public interest' is to be disallowed. PURA section 41(c)(3)(D), P.U.C. SUBST.R. 23.21(b)(2)(J)." Examiner's Report at p. 44.

All parties advocated a review under a "reasonable and necessary" standard analogous to the standard governing construction-work-inprogress (CWIP), presumably because CWIP and long-term purchase costs each involve costly, long-term expenditures. PURA § 41(a) provides that CWIP shall not be included in the rate base if the projects have been "inefficiently or imprudently planned or managed."

[10] See 26 FERC 1161,360, at 61,795.

[11] Nantahala involved a state commission's attempt to adjust a FERC-ordered allocation of low-cost entitlement power. Nantahala Power & Light was a participant in the Tennessee Valley Authority ("TVA") power grid. The utility would supply TVA with power in return for TVA's supply of low cost "entitlement" power. In addition, however, Nantahala also purchased more expensive power from TVA; the utility sold the purchased power to its retail customers.

Because Nantahala and TVA's operating agreement involved interstate transmissions and sales of wholesale electric power, FERC exercised jurisdiction over the wholesale rates. FERC allocated to Nantahala a 22.5% share of low cost; the North Carolina Utilities Commission later recalculated this percentage upwards to 24.5% and used this higher percentage when setting Nantahala's retail rates (by characterizing a larger percentage of Nantahala's power as low-cost power, the commission effectively reduced the costs which Nantahala would recover through its retail rates).

Nantahala argued that recalculating this percentage ran afoul of the filed rate doctrine. Because the state commission did not give effect to the FERC allocation, Nantahala was unable to recover the actual costs incurred in providing power to its retail customers.

The Supreme Court agreed with the utility and held that FERC's exclusive jurisdiction under the FPA extended not only to the establishment of rates, but to allocations which affected those rates. Nantahala, 476 U.S. at 972-73, 106 S. Ct. at 2360. The Court reasoned that the state commission impermissibly trapped costs at the utility, costs which otherwise would be recouped through its retail rates. See id. at 971, 106 S. Ct. at 2359.

[12] The Commission itself has explained:

[T]he granting of a CCN does not bind the Commission in any manner with regards to subsequent ratemaking treatment to be afforded the certificated facilities.

. . . . .

A CCN ... is essentially a license which indicates that a need for additional capacity has been demonstrated and at the time of certification the proposed/certificated facilities appeared to be a reasonable means of meeting the additional capacity needs. However, the CCN is not a guarantee that the facilities will be included in rate base.

El Paso Electric Co., Docket No. 5700, 10 Tex. Pub.Util.Comm'n Bull. 1071, 1099-1101 (1984) (emphasis added).

[13] The hearing examiner allowed the Form 10-K to be admitted into evidence, but did not allow Gulf States to introduce the Board of Directors Study because it concerned Gulf States' River Bend project and not the Nelson-5 expansion plant. Implicitly, then, the hearing examiner made a ruling on the basis of relevancy.

We note that "[i]n contested cases, irrelevant... evidence shall be excluded." Administrative Procedure and Texas Register Act, Tex.Rev.Civ. Stat.Ann. art. 6252-13a, § 14(a) (West Supp. 1992) (APTRA). "Administrative proceedings are subject to certain rules of procedure, and to the rules of civil evidence." Smith Motor Sales, Inc. v. Texas Motor Vehicle Comm'n, 809 S.W.2d 268, 272 (Tex.App.—Austin 1992, writ denied) (citing APTRA §§ 14, 20). Gulf States has not challenged the hearing examiner's determination that the Study was irrelevant, arguing instead that the Commission's failure to consider the Study was arbitrary and capricious.

[14] The Form 10-K and the Board presentation were allegedly relevant to Gulf States' decision to defer the construction of its Nelson-5 generating plant. In order to demonstrate the underlying prudence of the Southern purchases, Gulf States wished to show the imprudence associated with completing the Nelson-5 unit, an alternative source of long-term power. Opponents to the rate increase had argued that completion of Nelson-5 was preferable to the Southern purchases.

Similarly, Gulf States introduced the Exxon Task-Force Study as support for its claim that it had adequately analyzed gas generation under alternative price scenarios. Because Gulf States' long-term gas contracts with Exxon were set to expire soon, the utility was faced with the option of securing an alternative long-term gas supplier. Gulf States maintained that the Exxon Task-Force Study demonstrated a consideration of alternative sources of fuel and the subsequent impact that these sources would have on Gulf States' operating costs.

[15] The timing of the decision was critical to the prudence inquiry: a decision to defer construction made before the contract negotiations with Southern would tend to support Gulf States' claim that it had examined the Nelson-5 alternative. On the other hand, if the deferral decision was made after the Southern contracts were signed, it might support the opponents' claim that the decision to contract with Southern was made without examining the Nelson-5 alternative.

[16] The Commission's order stated that "[tjhe Commission's findings concerning GSU's [Gulf States'] imprudence with respect to the Southern contracts shall be res judicata with respect to the matters addressed by such findings." Application of Gulf States Utilities Co. for Authority to Change Rates, Tex.Pub.Util.Comm'n., Consolidated Docket Nos. 6477, 6525, 6660, 6748, 6842, Order No. 7 (October 15, 1986).

[17] Thus we take no position as to whether the Commission's findings concerning Gulf States' imprudence are res judicata in any subsequent proceedings.

[18] The Commission found that Gulf States' fuelprice forecasts in 1982 were reasonable, see Finding of Fact No. 52, but this claim does not establish that the Southern contracts saved ratepayers one-half billion dollars. The Office of Public Utility Counsel argues that the Commission never found that the Southern purchases would save one-half billion dollars.

[19] In a single footnote, Gulf States complains that it should not have been required to "prove prudence and quantify imprudence" because the other parties offered no evidence of damages and because to do so would be contrary to the Commission's statutory duty to fix just and reasonable rates. Gulf States analogized its position to that of a defendant in a civil trial, noting that a defendant is not burdened to prove liability or damages.

We find this analogy lacking. If anything, Gulf States more appropriately resembles a plaintiff in a civil action. The utility has approached the Commission in search of relief—in this case, a rate increase. Continuing the analogy, Gulf States, as the party seeking relief, carries the burden of proof. In any event, PURA clearly places the burden of proof upon Gulf States. See PURA §§ 40, 41(c)(3)(D).