J D Fields & Co, Inc v. Gottfried Corp

                     Revised November 26, 2001

                  UNITED STATES COURT OF APPEALS
                       For the Fifth Circuit



                             No. 00-60668



      J. D. FIELDS & COMPANY, INC., United States of America
                          for the use of,

                                                      Plaintiff-Appellant,


                                VERSUS


                  GOTTFRIED CORPORATION, ET AL.,

                                                                Defendants,

       GOTTFRIED CORPORATION; CONTINENTAL CASUALTY COMPANY,

                                                     Defendants-Appellees.




           Appeal from the United States District Court
             for the Southern District of Mississippi


                         November 6, 2001
Before JONES and DeMOSS, Circuit Judges, and FELDMAN, District
Judge.1

DeMOSS, Circuit Judge:

      Plaintiff-Appellant,   J.D.       Fields   &   Company,   Inc.   (J.D.


  1
   District Judge for the Eastern District of Louisiana, sitting
by designation.

                                    1
Fields), appeals the district court's final judgment following a

bench trial dismissing Fields’ claims under the Miller Act, 40

U.S.C. §§ 270a-270d, against Defendants-Appellees, The Gottfried

Corporation      (Gottfried)         and        Continental         Casualty      Company

(Continental Casualty), because of Fields’ failure to give adequate

notice within the 90-day period prescribed by section 270b(a). The

district court's decision is vacated and remanded for further

proceedings.

                                I.    BACKGROUND

     In 1997, Gottfried, as general contractor, contracted with the

United States Government, Department of Veterans Affairs (VA), to

perform    construction       work     at       the    VA        Hospital    in   Biloxi,

Mississippi.        Continental       Casualty         supplied        a    payment    bond

guaranteeing Gottfried's payment of labor and materials supplied to

the job.      Cherokee Towing & Construction Co., Inc. (Cherokee)

entered into a subcontract with Gottfried wherein it agreed to

provide the labor, material, equipment, and supervision required to

complete   two    steel   sheet-pile            cofferdams        on   the    project    in

conjunction      with   the   construction            of    an    elevator     shaft    and

stairwell.

     Cherokee executed a rental agreement with J.D. Fields for the

pilings it used in making the cofferdams, which it began driving on

May 19, 1997. The rental agreement required the payment of monthly

rental by Cherokee to J.D. Fields.                    The rental agreement was to



                                            2
terminate when Cherokee notified J.D. Fields that the pilings were

ready for inspection and return shipment, after which J.D. Fields

would be given the opportunity to inspect the pilings at the job

site.   Pursuant to the rental agreement, Cherokee was to pay final

liquidation and reconditioning charges and pay attorneys' fees in

the event of its default.

       Brian McHale, Sales Manager for J.D. Fields, testified that

Cherokee's rental payments were untimely throughout the rental

period immediately prior to halting altogether in October 1997.

McHale also testified that in late December 1997, or early January

1998, he called Karl Gottfried, of The Gottfried Corporation,

regarding the failure of Cherokee to meet its obligation to pay the

rental payments for the months of October, November, and December

1997.    McHale further testified during his telephone conversation

that    he   informed        Gottfried     that   his     corporation        would   be

responsible for any lien required to secure payment, as well as any

attorneys' fees, if the rental payments remained outstanding.

       According        to   McHale,     Gottfried     told    him    that    he   would

investigate       the    matter    and    get   back    in    touch    with    McHale.

Gottfried's testimony did not conflict with McHale's testimony on

this fact. However, the district court found that both documentary

evidence and witness testimony revealed that on December 22, 1997,

Gottfried required Cherokee to execute a release certifying that

all    invoices    for       materials,    payrolls,     and    other    obligations

incurred by Cherokee in connection with the VA project had been

                                            3
paid in full and that there were no outstanding obligations against

Cherokee applicable to the project.         Nevertheless, the district

court concluded that it was unclear from the testimony whether

Gottfried was aware of Cherokee's outstanding obligations at the

time it required Cherokee to sign the release.

     The district court found that Gottfried issued a check on

January 7, 1998, made payable jointly to Cherokee and J.D. Fields

for rental payments due in October, November, and December 1997,

bringing   Cherokee’s   account   current   through     January   9,   1998.

Gottfried testified that at the time the check was issued, Cherokee

had completed driving the pilings and he believed the pilings had

been returned to J.D. Fields.     Gottfried expected that no further

rental fees would be owed and was unaware that the pilings had not

been returned to J.D. Fields.

     The district court noted that there was conflicting testimony

regarding when the pilings left the job site.         Louis Evans, a truck

driver for Cherokee, testified that he observed the pilings in the

lay-down yard on the VA premises approximately one month after the

pilings were removed from the ground.             Notably, Doug Ladner,

President of Cherokee, testified that the pilings were stored for

at least two weeks, and perhaps until late January or early

February, on the VA premises in an area where daily logs and

reports were   not   required.     Jane   Page,   a   Cherokee    employee,

testified that the pilings remained in the “lay down” area for

about one week after they were removed from the ground.                George

                                   4
Malcolm Brooks, Jr., Project Supervisor for Gottfried, testified

that the pilings were removed and taken from the site on December

18, 1997, and that he did not see them on the “lay down” site after

that date.    James Levens, President of Levins Builders, Inc.,

another subcontractor, stated that his firm began constructing

stairs for the VA project on December 19, 1997, and that the

pilings would have had to have been removed from the site by that

date in order for his company to begin work.   Levin also testified

that he never saw the pilings at the lay-down yard.   David Boggs,

Project Manager for the VA, recalled that the pilings remained for

a few days near the loading dock after being removed from the

ground, but he did not recall seeing them in the “lay down” yard.

On redirect, Boggs testified that the pilings may have remained on

site for two to three days after having been removed from the

ground.

     In view of the conflicting testimony, the district court

concluded that the written records before it were the most reliable

evidence.    Those documents included Cherokee’s Daily Manpower

Reports and Gottfried’s Daily Logs. The court noted that the Daily

Logs showed that as of December 15, 1997, Cherokee had “finished

pulling piling.”    On December 17, Cherokee was “hauling sheet

piling from job site.”     On December 18, Cherokee had “finished

removing piling.”    The court found that there was no further

mention of the pilings and no Daily Log was admitted into evidence

on or after December 19.     Although there was a Daily Manpower

                                 5
Report    completed    by   Cherokee   on    December   19,   indicating   its

presence    on   the   site,   there   was   no   description   of   the   work

completed for the day.         As a result, the court concluded that the

last day the pilings were supplied to the job site was December 18,

1997.     Based on this factual finding, the court found that the

statutory period for notice under the Miller Act began to run on

December 19, 1997, and expired 90 days later on March 18, 1998.

     There is no dispute that the material rented by Cherokee was

returned to J.D. Fields on February 27, 1998.           On March 2, 10, and

12, J.D. Fields sent letters to Cherokee regarding the charges for

reconditioning and liquidation of the pilings used in the VA

project.    The letters do not indicate that they were copied to

Gottfried; however, Gottfried does not deny that it received

copies.    On March 20, 1998, J.D. Fields mailed written notice to

Cherokee and Gottfried of its Miller Act claim.           The notice was not

received by Gottfried until March 23, 1998.

     The court found that prior to the notice of claim mailed on

March 20, 1998, and received on March 23, 1998, Gottfried received

no notice of a demand upon it for payment of Cherokee’s account.

The court found that the correspondence of March 2, 10, and 12,

1997, was inadequate as notice under the Miller Act.                 The court

also found that demands for rental payments due for the months of

October, November, and December 1997, could not be construed as

notice of demand for the January and February rental amounts and

the reconditioning and liquidation charges that Cherokee owed J.D.

                                       6
Fields.   Based on the lack of an adequate and timely notice of

claim, the district court entered final judgment dismissing J.D.

Fields’ claims against Gottfried and Continental Casualty.

                        II.    STANDARD OF REVIEW

     This court reviews the district court's conclusions of law de

novo.   Reich v. Lancaster, 55 F.3d 1034, 1045 (5th Cir. 1995).           The

factual   components   of     the    district   court's   determination   are

reviewed for clear error.       Id.    The district court's findings will

be considered clearly erroneous only if we have a “definite and

firm conviction that a mistake has been committed.”           B.H. Bunn Co.

v. AAA Replacement Parts Co., 451 F.2d 1254, 1260 (5th Cir. 1971).

                              III.    DISCUSSION

     The Miller Act requires general contractors on most federal

construction projects to furnish a bond for performance and to

secure payment to all suppliers of labor and materials.           40 U.S.C.

§ 270a(a)(2). The Act also provides that suppliers of materials to

subcontractors on federal construction projects may recover from

the general contractor's payment bond any unpaid amount due from

the subcontractor.     40 U.S.C. § 270b(a).        To establish a right of

action against the general contractor's payment bond, the supplier

must give the contractor sufficient written notice “within ninety

days from the date on which such person did or performed the last

of the labor or furnished or supplied the last of the material for

which such claim is made.”      Id.    A notice to the general contractor


                                        7
will be sufficient only if “it plainly appears that the nature and

state   of   the   indebtedness    was     brought   home     to   the   general

contractor.”    Houston Fire & Cas. Ins. Co. v. United States ex rel.

Trane Co., 217 F.2d 727, 730 (5th Cir. 1954).              The required 90-day

notice is designed to protect the general contractor by fixing a

date beyond which it will not be held liable for subcontractors'

debts, absent proper notification from the supplier. United States

ex rel. Kinlau Sheet Metal Works v. Great Am. Ins. Co., 537 F.2d

222, 223-24 n.1 (5th Cir. 1976) (citing Nolan Co. v. Allied

Contractors, Inc., 273 F.2d 917, 920-21 (4th Cir. 1959)). Notably,

the Miller Act is highly remedial in nature and is entitled to a

liberal construction and application in order to effectuate the

Congressional      intent   to   protect    those    who    furnish   labor   or

materials for public works.           Glassell-Taylor Co. v. Magnolia

Petrolium Co., 153 F.2d 527, 529-30 (5th Cir. 1946).

     The issue before this court is whether the last day on which

J.D. Fields "furnished or supplied" the pilings to Cherokee was

when Cherokee returned them, or when they were removed from the

site of the VA construction project.           Resolving this issue will

allow us to determine the starting date of the required 90-day

period for notice under to the Miller Act.                 The district court

determined that the last day the pilings were supplied to the job

site was December 18, 1997.          The court reached this conclusion

primarily based on Gottfried's Daily Logs, which indicated that the

                                      8
pilings were no longer being used by Cherokee and that they had

been removed from the premises of the VA construction project by

that date.   As a result, the court concluded that the statutory

period for notice under the Miller Act began to run on December 19,

1997, and expired on March 18, 1998.

     We disagree with the district court's conclusion.   The rental

agreement entered into by J.D. Fields and Cherokee, called for the

rental period to end “on the date that written notice is received

by FIELDS stating that piling is ready for inspection and return

shipment as and when directed by FIELDS.”      Significantly, the

record shows that the first notice J.D. Fields received regarding

the fact that the pilings were no longer in use or on the premises

of the construction project was on February 27, 1998, when the

pilings were returned.   Before that date, J.D. Fields would have

had no way of knowing when the 90-day period for giving notice

would begin to run.   Therefore, we conclude that the pilings were

still being made available, that is "furnished or supplied," to

Cherokee until February 27, 1998, when they were returned.    This

was the date that the rental period ended according to the rental

agreement.   Until that date, the pilings were still in Cherokee's

possession and, therefore, still available to Cherokee for use on

the job if necessary.

     Our conclusion is not novel.    Other courts have reached the

same conclusion.   See, e.g., Interform Co. v. Mitchell, 575 F.2d



                                 9
1270, 1280 (9th Cir. 1978) (holding that “a furnisher of rental

equipment continues to ‘supply’ such equipment through the entire

rental period; the date of last supply occurs not at the beginning

of a job but at the end or at the time the equipment is last

available for use on the job”);       United States ex rel. Carter-

Schneider-Nelson, Inc. v. Campbell, 293 F.2d 816, 820 (9th Cir.

1961) (same); United States ex rel. Malpass Constr. Co. v. Scotland

Concrete Co., 294 F. Supp. 1299, 1302 (E.D.N.C. 1968) (same);

United States v. Continental Cas. Co., 230 F. Supp. 557, 559-60

(W.D. Pa.   1964)   (same).   Furthermore,   a   previous   Miller   Act

decision of this court, Mike Bradford & Co. v. F.A. Chastain

Constr., Inc., 387 F.2d 942 (5th Cir. 1968), lends considerable

support to our decision in the instant case.

     In Mike Bradford, this court was faced with the issue of

whether a Miller Act suit was commenced after the expiration of one

year from the last work performed under the contract, and hence

outside the Miller Act’s statute of limitations.        The governing

statute provided, as it does today, that “no such suit shall be

commenced after the expiration of one year after the day on which

the last of the labor was performed or material was supplied.”        40

U.S.C. § 270b(b).    This language is substantially similar to the

provision at issue in the instant case, which requires notice of

claim “within ninety days from the date on which such person did or

performed the last of the labor or furnished or supplied the last

                                 10
of    the   material    for    which      such    claim    is   made.”    40   U.S.C.

§ 270b(a).

       The plaintiff in Mike Bradford agreed to furnish machinery and

equipment, along with operators, to the defendant.                       387 F.2d at

942-43.        No operators for the equipment were furnished after

September 1, 1963, but the equipment was utilized by the defendant

until October 4, 1963.          Id. at 943.         The equipment may have been

idle in the interim.          Id. at 944.        Suit was filed on September 21,

1964, and the defendant averred that it was untimely.                    Id. at 943-

44.    This court disagreed, holding that under the plain meaning of

40 U.S.C. § 270b(b), the one-year period begins to run on the day

when the labor ceases or when the last material was supplied.                     Id.

at 944.      The court stated that it was “undisputed that the last

material was supplied as of October 4, 1963,” which was the date

the equipment was returned.            Id. at 944.        Thus, the court held the

action was timely filed.            Id.

       Thus,    the    last   day    on    which    J.D.    Fields   "furnished    or

supplied" the pilings to Cherokee was the date on which they were

returned, which was February 27, 1998.                    As a result, the 90-day

period for giving proper notice in the instant case began to run on

February 28, 1998, and expired on May 28, 1998.                    Any notice given

by J.D. Fields to Gottfried before that date would have been

premature and, therefore, insufficient.                    See Kinlau Sheet Metal,

537 F.2d at 224 (holding that monthly statements and summary sheets

                                           11
delivered by the supplier to the prime contractor's agent showing

for each job the amount that the subcontractor owed the supplier,

the amount paid to that date, and the balance due, were premature

and could not be considered as sufficient notice for that job);

National Union Indem. Co. v. R.O. Davis, Inc., 393 F.2d 897, 900

(5th Cir. 1968) (stating that premature notification of a claim

under the Miller Act could not be a proper notice).

                            CONCLUSION

     We hold that the last day on which J.D. Fields "furnished or

supplied" the pilings to Cherokee was February 27, 1998.   Thus, the

90-day period for giving proper notice under the Miller Act, 40

U.S.C. § 270b(a), began to run on February 28, 1998, and expired on

May 28, 1998.   We vacate the district court's decision and remand

for further proceedings consistent with this opinion.




                                12