In March, 1923, C.L. Graves entered into a contract with the county of Spokane for the construction of three bridges. The contract, in all respects necessary in our consideration of the case, was similar to the one involved and discussed in the case of Pacific Coast Steel Co. v. Old National Bank of Spokane,ante p. 457, 235 P. 947.
For the purpose of financing his undertaking, Graves assigned his rights to payments on the estimates to be made under the contract to the Old National Bank of Spokane, shortly after he entered into the contract. The bank gave the county auditor written notice of the assignment. In the course of the performance of the work, the county made several payments that were received by the bank without any notice on the part of the county that there were any outstanding claims for labor and material. The work was completed and accepted, and the county at that time having written notice of unpaid claims for service and material furnished *Page 675 on the work amounting to more than the fund of fifteen per cent provided for in the contract as required by statute for the protection of laborers and materialmen, claimed the right, under the terms of the contract, to withhold enough, in addition to the fifteen per cent to pay the excess. The Old National Bank of Spokane then brought this suit against the county to recover the balance due above the fifteen per cent. The Fidelity National Bank of Spokane intervened as assignee of a materialman. The judgment of the court was for the plaintiff. The county and the Fidelity National Bank have appealed.
As to the law relating to the right of the county to hold the funds until claims due for labor and material have been paid, under a contract like the one involved in this case, the case ofPacific Coast Steel Co. v. Old National Bank, supra, is decisive. That case reviewed all of our decisions, the ones relied on by respective counsel in this case, and formulated rules to ascertain the rights of an assignee of a contractor in the construction of public works. Under the doctrine of that case where, as here, the county specifically reserves by its contract the right to hold an amount necessary above the fifteen per cent to satisfy claims of laborers, mechanics and materialmen, about all that is necessary to further inquire into is the evidence on the question of the acceptance of the assignment made by the contractor in connection with the date of the county's knowledge of unpaid claims of laborers and materialmen. In the present case Graves, the contractor, made a formal written assignment of his rights to payments to the respondent on May 10, 1923. On the next day the respondent mailed the assignment to the county auditor.
On June 15, 1923, the clerk of the board of county commissioners wrote to the bank, "Please be advised *Page 676 that the county will forward the warrants covering the amounts of these estimates to the Old National Bank Yours truly, Board of County Commissioners Spokane County, Wn., by O.W. Young, clerk." However, the uncontradicted testimony of O.W. Young was that the matter of the assignment or the notice of it forwarded by the bank was not called to the attention of the board of county commissioners, and that he had no authority from them, or any of them, to write the letter of June 15. He further testified that the letter was never intended as an acceptance of the assignment, but only that the warrants would be forwarded to the bank as a means of paying the contractor, and therefore the form of the warrants that were issued, viz.: The first one to "Old National Bank for C.L. Graves"; the others to "Old National Bank, credit department, for C.L. Graves." As held in the Pacific Coast SteelCo., case, supra, the county auditor has no authority to accept an assignment. For that purpose the body having authority to make the contract should be the one which has exclusive authority to accept an assignment. In this case the board of county commissioners took no action with reference to the assignment, nor does it seem to have been called to their attention until the present situation arose, at which time they claimed the right, under the contract, to hold out enough to pay the excess over fifteen per cent due for labor and material furnished on the work. This they had the right to do.
The further contention of the respondent in support of the judgment is that it is entitled to recover under ch. 166, Laws of 1921, p. 657 [Rem. Comp. Stat., § 10320]. The same contention was made by the assignee in the Pacific Coast Steel Co., case,supra. It was there decided to the contrary. And upon the *Page 677 authority of that case it must be held in the present one that this contention of the respondent cannot prevail.
Judgment reversed.
TOLMAN, C.J., FULLERTON, MACKINTOSH and HOLCOMB, JJ., concur.