ACCEPTED
14-15-00463-CV
FOURTEENTH COURT OF APPEALS
HOUSTON, TEXAS
11/18/2015 7:33:39 PM
CHRISTOPHER PRINE
CLERK
14-15-00463-CV
FILED IN
14th COURT OF APPEALS
COURT OF APPEALS FOR THE HOUSTON, TEXAS
FOURTEENTH DISTRICT OF TEXAS 11/18/2015 7:33:39 PM
Houston, Texas CHRISTOPHER A. PRINE
Clerk
CROSSLAND ACQUISITION, INC.,
Plaintiff - Appellant,
V.
HNTB CORPORATION,
Defendant - Appellee.
____________________________________________
APPELLANT’S BRIEF
____________________________________________
Bryant S. Banes Neel, Hooper & Banes, P.C.
State Bar No. 24035950 1800 West Loop South, Suite 1750
Sean D. Forbes Houston, Texas 77027
State Bar No. 24040916 713-629-1800
Stormy N. Mayfield 713-629-1812 (Fax)
State Bar No. 24067656 Email: bbanes@nhblaw.com
Email: sforbes@nhblaw.com
Email: smayfield@nhblaw.com
Attorneys for Crossland Acquisition, Inc.
ORAL ARGUMENT REQUESTED
IDENTITY OF COUNSEL
The following parties and counsel listed are involved in this matter. See TEX. R.
APP. P. 38.1(a).
Plaintiff/Appellant:
Crossland Acquisition, Inc.
Defendant/Appellee:
HNTB Corporation
Counsel for Plaintiff/Appellant:
Bryant S. Banes
Sean D. Forbes
Stormy N. Mayfield
Neel, Hooper & Banes, P.C.
1800 West Loop South, Suite 1750
Houston, Texas 77027
Counsel for Defendant/Appellee:
P. Randall Crump
Shook Hardy & Bacon, L.L.P.
600 Travis, Suite 3400
Houston, Texas 77002-2926
ii
TABLE OF CONTENTS
PAGE NO.
IDENTITY OF COUNSEL ...................................................................................... ii
TABLE OF CONTENTS ......................................................................................... iii
TABLE OF AUTHORITIES ..................................................................................... v
STATEMENT OF THE CASE ............................................................................... vii
STATEMENT REGARDING ORAL ARGUMENT ............................................ viii
ISSUES PRESENTED ..............................................................................................ix
STATEMENT OF THE FACTS................................................................................ 2
SUMMARY OF THE ARGUMENT......................................................................... 7
STANDARD OF REVIEW ....................................................................................... 8
ARGUMENT ........................................................................................................... 12
I. The trial court erred in ruling that the parties’ contract required
Crossland’s completion of all services for all land parcels for a
firm, fixed price, despite plain contract language to the contrary .................. 12
PRAYER .................................................................................................................. 17
CERTIFICATE OF SERVICE ................................................................................ 18
CERTIFICATE OF COMPLIANCE ....................................................................... 18
APPENDIX
Order on Defendant HNTB Corporation’s Traditional Motion for Summary Judgment
Signed on January 20, 2015 ...................................................................................... A
iii
Amended Order on Summary Judgment Signed on February 16, 2015.................... B
Final Judgment Signed on May 1, 2015 .................................................................... C
Master Agreement between HNTB Corporation and Consultation ......................... D
Task Order 3 .............................................................................................................. E
Supplemental Agreement 1 to Task Order 3 ............................................................. F
Supplemental Agreement 2 to Task Order 3 ............................................................. G
Supplemental Agreement 3 to Task Order 3 ............................................................. H
Task Order 4 ............................................................................................................... I
Supplemental Agreement 1 to Task Order 4 .............................................................. J
iv
TABLE OF AUTHORITIES
CASES: PAGE NO:
Beverick v. Koch Power, Inc., 186 S.W.3d 145 (Tex. App.—Houston [1st Dist.]
2005, pet. denied) .....................................................................................................12
Black Lake Pipe Line Co. v. Union Constr. Co., 538 S.W.2d 80 (Tex.1976),
overruled on other grounds by Sterner v. Marathon Oil Co., 767 S.W.2d 686
(Tex.1989) ................................................................................................................11
Bluelinx Corp. v. Texas Const. Sys., Inc., 363 S.W.3d 623 (Tex. App.—Houston
[14th Dist.] 2011, no pet.) ..................................................................................11, 12
City of Keller v. Wilson, 168 S.W.3d 802 (Tex.2005) ...............................................9
Forbes, Inc. v. Granada Biosciences, Inc., 124 S.W.3d 167 (Tex. 2003) ............8, 9
Frost Nat’l Bank v. L & F Distribs., Ltd., 165 S.W.3d 310 (Tex. 2005) .................11
Great Am. Reserve Ins. Co. v. San Antonio Plumbing Supply Co., 391 S.W.2d 41
(Tex.1965) ..................................................................................................................9
Gulbenkian v. Penn, 151 Tex. 412, 252 S.W.2d 929 (Tex.1952) ..............................9
Heritage Res., Inc. v. NationsBank, 939 S.W.2d 118 (Tex. 1996)...........................10
In Re Polybutelene Plumbing Litig. v. Hoechst Celanese Corp., 23 S.W.3d 428
(Tex.App.-Houston [1st Dist.] 2000, no pet.) ..........................................................12
Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding, 289 S.W.3d 844
(Tex.2009) ..................................................................................................................9
MMP, Ltd. v. Jones, 710 S.W.2d 59 (Tex.1986)........................................................9
Nat'l Union Fire Ins. Co. v. CBI Indus., Inc., 907 S.W.2d 517 (Tex. 1994)............11
Randall's Food Markets, Inc. v. Johnson, 891 S.W.2d 640 (Tex.1995) ....................9
v
S. Cnty. Mut. Ins. v. Sur. Bank, N.A., 270 S.W.3d 684 (Tex. App.—Fort Worth
2008, no pet.).....................................................................................................passim
Seagull Energy E & P, Inc. v. Eland Energy, Inc., 207 S.W.3d 342 (Tex. 2006)....10
Taylor–Made Hose, Inc. v. Wilkerson, 21 S.W.3d 484 (Tex.App.-San Antonio
2000, pet. denied) .......................................................................................................9
Valence Operating Co. v. Dorsett, 164 S.W.3d 656 (Tex.2005) ...............................9
STATUTES AND RULES: PAGE NO:
TEX. R. APP. P. 38.1 .................................................................................................. ii
TEX. R. APP. P. 39 .................................................................................................. viii
TEX. R. CIV. P. 166a ...................................................................................................9
vi
STATEMENT OF THE CASE
Nature of the Case: Breach of contract and quantum meruit arising
from HNTB Corporation’s (“HNTB”)
requiring Crossland Acquisition, Inc.
(“Crossland”) to continue providing right-of-
way acquisition and relocation services in
connection a State government contract
without payment. (CR 36-63) 1.
Style of the Case: Cause No. 2013-63341; Crossland
Acquisition, Inc. vs. HNTB Corporation.
Trial Court: The 190th District Court of Harris County,
Texas, the Honorable Patricia J. Kerrigan.
Trial Court’s Disposition: Both parties moved for summary judgment on
Crossland’s breach of contract claims. (CR
66-1095). Subsequently, HNTB also filed a
motion for summary judgment on Crossland’s
quantum meruit claims. (CR 1801-2048).
Ultimately, the trial court granted summary
judgment in HNTB’s favor as to Crossland’s
breach of contract and quantum meruit claims.
(CR 1790; CR 2737).
1 “CR __” refers to a page number from the Clerk’s Record in this case.
vii
STATEMENT REGARDING ORAL ARGUMENT
Appellant/Plaintiff does believe oral argument would be helpful to the Court.
The judgment appealed from is based on omissions of facts and legal matters in
connection with a complex commercial contract and, given such, the matters presented
herein require amplification for the court to understand the precise nature of the
dispute. See TEX. R. APP. P. 39.
viii
ISSUES PRESENTED
I. Whether the trial court erred in ruling that the parties’ contract required
Crossland Acquisition, Inc.’s completion of all services for all land parcels for a
firm fixed price, despite plain contract language to the contrary.
ix
14-15-00463-CV
COURT OF APPEALS FOR THE
FOURTEENTH DISTRICT OF TEXAS
Houston, Texas
CROSSLAND ACQUISITION, INC.,
Plaintiff - Appellant,
V.
HNTB CORPORATION,
Defendant - Appellee.
____________________________________________
APPELLANT’S BRIEF
____________________________________________
To The Honorable Fourteenth Court of Appeals:
Crossland requests that this Court reverse the trial court’s grant of summary
judgment on its breach of contract and quantum meruit claims and render judgment on
the contract interpretation issue presented herein. Alternatively, Crossland requests
reverse and remand for further proceedings. In support thereof, Crossland would show
the following:
1
STATEMENT OF THE FACTS
On June 12, 2006, HNTB entered into a contract with the Texas Department of
Transportation (“TxDOT”) in connection with the construction of transportation
improvements along the US 290/Hempstead corridor, which extends from IH 610 to
FM 2920. (CR 389-523). According to TxDOT, the construction of transportation
improvements along the US 290/Hempstead corridor was a high-profile project. (CR
646; CR 799 at 233:9-233:18; see also CR 1007 at 78:20-79:21 and 80:9-80:20). This
was also an extremely complex and unique project for TxDOT. (CR 653; CR 664 at
35:18-35:21; CR 710 at 218:19-220:24). Right-of-way acquisition and relocation
services were a key component of HNTB’s contract with TxDOT. (CR 390).
However, HNTB did not have the expertise in the State of Texas to handle those types
of services. (CR 799 at 233:9-233:18; CR 1007 at 78:20-79:21 and 80:9-80:20).
Consequently, and because Crossland had expertise in right-of-way acquisition and
relocation within the State of Texas, HNTB contracted with Crossland to provide those
services. (Id.).
HNTB’s contract with Crossland actually consisted of a master contract and
multiple supplemental agreements thereto. (See CR 381-616). The master contract is
the July 5, 2006 agreement between HNTB and Crossland (the “Master Agreement”),
which incorporated all portions of HNTB’s contract with TxDOT that were “pertinent
to [Crossland’s] responsibilities, compensation, and timing of Services and not in
2
conflict with any provision” of the Master Agreement. (CR 381-548). The
supplemental agreements referred to by the parties as “Task Orders” provided authority
for Crossland to perform right-of-way acquisition and relocation services along the US
290/Hempstead corridor. (CR 381 (“Task orders shall be used to describe the parties’
mutual agreement on the scope of the Services, schedule, compensation and other
particulars as stated therein.”); see also CR 550 and CR 595). While there were
several Task Orders, those at issue in this appeal are the ones referred to by the parties
as “Task Order 3” and “Task Order 4.” (See CR 550-616).
Task Orders 3 and 4 contained specific time limitations, i.e., they had
termination dates. (CR 553-54; CR 556-57; CR 559; CR 561-62; CR 564-65; CR 569;
CR 597; CR 600; CR 602; CR 605-06; CR 610; CR 613). The first line of Exhibit B to
Task Order 3 states: “This task order is for the initial period from execution through
September 30, 2011.” (CR 553). Exhibit B then repeats 11 times that the scope of
services applied during “the initial period of this Task Order.” (CR 553-54; CR 556-
57; CR 559; CR 561-62; CR 564-65; CR 569). Likewise, Task Order 4 was from
execution through June 30, 2012 (CR 613; see also CR 618), and Exhibit B thereto
repeats 7 times that the scope of services applied during the “initial period of this Task
Order.” (CR 597; CR 600; CR 602; CR 605-06; CR 610). Moreover, there was a
supplemental agreement executed solely for the purpose of extending Task Order 3’s
termination date. (CR 577).
3
During the time limitations of Task Orders 3 and 4, Crossland was contractually
obligated to provide “deliverables.” (CR 381 at “Article 4 – Scope of Services;” CR
550; CR 570; CR 595; CR 611; CR 851-52 at 48:6-48:21, 49:3-49:7 and 49:20-50:8).
A “deliverable” is “a unit or increment of work required by the contract, including such
items as goods, services, reports or documents.” (CR 1474). Crossland’s
“deliverables” were monthly status reports and “budget projections and anticipated
funding requirements every thirty (30) days and more frequently as requested by the
State during this Task Order.” (CR 570; CR 611) (emphasis added). 2 These
“deliverables” were the “foregoing obligations” Crossland had to perform in order to
get paid under the contract. (CR 550; CR 595; CR 851 at 49:3-49:7 (“Yeah. I’m not
sure. I know that the total – all the deliverables would have to be completed within that
total dollar amount, the total scope – the total fee. But I’m not sure if it was --”)).
With respect to payment, Crossland was to be paid an hourly rate for each hour
2
The exception to this lies in Supplement 1 to Task Order 4. (CR 618-26; see also CR 1444-46).
Supplement 1 to Task Order 4, which was the subject of the duress portion of Crossland’s claims
(CR 46 at ¶ 26; CR 57-58 at ¶ 57), contains different “deliverables” and a different method of
payment. (Compare CR 550, 570 and 575 with CR 618, 621, and 625; see also CR 1444-46). Due
to these different “deliverables’ and different method of payment, for work under Supplement 1 to
Task Order 4 (and only that supplement to that task order), Crossland was contractually required to
complete all listed services for all parcels listed therein for the maximum amount set forth therein.
(CR 509 at “Unit Cost;” CR 1510 at “Firm Fixed Price;” CR 618-26; see also CR 1444-46). While
HNTB may try to suggest otherwise, this supplement: does not apply to Task Order 3 (CR 618);
only applies to Task Order 4 after the date of its execution (id.); and its only relevance to this appeal
is to help illustrate that, for the relevant portions of Task Orders 3 and 4, the parties’ contract did not
require Crossland to complete all services for all parcels for the maximum amount set forth in the
task orders. (Compare CR 550, 570 and 575 with CR 618, 621, and 625; see also CR 1444-46).
4
worked. 3 (CR 511; CR 540; CR 550; CR 575; CR 587-88; CR 592-93; CR 595; CR
615-16). Task Order 3 stated:
In return for the performance of the foregoing obligations,
HNTB shall pay to [Crossland] the maximum amount of
$1,988,636.46, payable in accordance with Attachment E
and E-1 of the Master Agreement and the attachment
Exhibit D – Fee Schedule.
(CR 550). Task Order 4 was identical except for the amount of compensation. (CR
595). Exhibit D to the Task Orders and Attachment E to the Master Agreement each
identified “specified rate” as the method of payment. (CR 511; CR 540; CR 550; CR
575; CR 587-88; CR 592-93; CR 595; CR 615-16). “Specified Rate” was defined as
follows:
Payment shall be based on the actual hours worked
multiplied by the specified rate for each type of labor plus
other agreed to special direct cost items. The specified rate
includes direct labor and indirect cost and fixed fee.
(CR 509).
While the task orders set forth a “maximum amount” to be received by
Crossland in return for the “deliverables,” nothing contractually required Crossland to
complete all services for all land parcels for that “maximum amount.” (See CR 381-
3
As indicated in note 1, the exception to this is Supplement 1 to Task Order 4. (CR 618-26; see also
CR 1444-46). For work performed in connection with Supplement 1 to Task Order 4, Crossland was
to be paid a firm fixed price for each indicated milestone it reached (“unit cost”). (Id.; CR 509).
5
616). 4 Nowhere does the parties’ agreement state that Crossland had to complete all
services for all land parcels for the task orders’ “maximum amount.” (Id.). Rather, the
contract explicitly states and contemplates that Crossland need not complete all
services for all land parcels for the task orders’ “maximum amount.” (See CR 550; CR
554-55; CR 570; CR 595; CR 611; CR 851 at 49:3-49:7; see also CR 2453 at ¶¶ 6-7;
CR 2456-64).
As set forth above, completion of all services for all land parcels was not a
“deliverable.” (CR 550; CR 570; CR 595; CR 611; CR 851 at 49:3-49:7). In fact, there
were no specific parcels identified in the “deliverables” or the fee schedules for the
Task Orders. 5 (Id.; CR 575; CR 615-16; see also CR 2453 at ¶¶ 6-7; CR 2456-64).
Further, the contract’s express language stated that Crossland need not complete all
services for a task order within the specified time limits. (CR 554-55). For example,
Task Order 3 stated:
The Services on this Task Order are generally for major
elements during Preliminary and Final Design Development
and many of these services have started in the previous
Task Orders (Crossland Acquisition Task Order #1 and
4
Again, this is where Supplement 1 to Task Order 4 differs. Due to the changed language in
Supplement 1 to Task Order 4 regarding deliverables and payment method, Supplement 1 to Task
Order 4 set forth that, for the work performed under that supplement (and only that work), the
“maximum amount” was the total amount due Crossland for all services for all land parcels listed
therein. (CR 509 at “Unit Cost;” CR 618-26; CR 1510 at “Firm Fixed Price;” see also CR 1444-46).
5
By way of comparison, Supplement 1 to Task Order 4 did list specific land parcels in the
“deliverables” and fee schedule. (CR 621; CR 625).
6
Crossland Acquisition Task Order #2) and/or will be
completed or continued in subsequent Task Orders as
deemed necessary by the State.
(Id.) (emphasis added). This is consistent with Crossland’s method of payment under
the Task Orders. (CR 1511 at description of “Time and Material”). It is also
consistent with the parties’ course of dealing whereby supplements were executed
adding to the “maximum amount.” (CR 581; CR 590).
SUMMARY OF THE ARGUMENT
Did the parties’ contract require Crossland to complete all services for all land
parcels for a firm fixed price? That was the central question before the trial court on
HNTB’s motions for summary judgment, and it is the central question in this appeal.
(See CR 66-77; CR 1790; CR 1801-1811; CR 2737). If the answer to this question is
no, reversal and/or remand is required.
In its motion for summary judgment regarding Crossland’s breach of contract
claims, HNTB alleged that the language of the parties’ agreement required Crossland
to complete all services for all land parcels (i.e.¸ the alleged “foregoing obligations”)
for a fixed sum (i.e., the “maximum amount”) that could not be increased (i.e., the
changes clauses incorporated into the Master Agreement were not applicable to
Crossland). (CR 66-77). 6 In its motion for summary judgment regarding Crossland’s
6
Crossland also filed for summary judgment on its breach of contract claims. (CR 335-1095). In
that motion and its response to HNTB’s initial motion for summary judgment, Crossland argued that
(CONT.)
7
quantum meruit claims, HNTB alleged that quantum meruit was unavailable because
the services were covered by the parties’ contract (i.e., Crossland had to complete all
services for all land parcels for the “maximum amount”). (CR 1801-11). Thus, in
order to grant summary judgment as it did, the trial court’s answer to this central
question was in the affirmative. 7 However, as set forth in more detail below, this is
wholly based on an incomplete reading of the parties’ contract and renders multiple
provisions in same meaningless. It also constitutes a redrafting of the terms of the
parties’ agreement. This was improper.
STANDARD OF REVIEW
The appellate court must review the trial court's grant of summary judgment de
novo. Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding, 289 S.W.3d 844, 848
the sums claimed were within the scope of the contract because of the contract’s changes clauses.
(Id.; CR 1440-1709). In response, HNTB alleged that the changes clauses were not applicable to
Crossland’s contract despite same being incorporated therein and previously utilized by the parties.
(CR 66-323; CR 1162-1437). In order to grant summary judgment in HNTB’s favor on the contract
claims, the trial court had to incorrectly find the changes clauses inapplicable to Crossland’s contract.
(Id.; CR1790). Therefore, under the trial court’s ruling, once Crossland was outside of the
contract’s time limits or maximum amount, it was outside the scope of the contract. Hence,
Crossland’s quantum meruit claims. (See CR 2051-2661).
7
HNTB also brought a no evidence motion for summary judgment in response to Crossland’s
quantum meruit claims. However, despite Crossland’s production of significantly more than a
scintilla of evidence (see CR 2051-2661), HNTB did not provide a response that could overcome all
of that evidence in a way that would justify the grant of a no evidence summary judgment motion.
(See CR 2663-2729); accord Forbes, Inc. v. Granada Biosciences, Inc., 124 S.W.3d 167, 172 (Tex.
2003). Consequently, the trial court’s quantum meruit judgment was clearly based on HNTB’s claim
that the services were within the scope of the contract. To the extent it was not, as can be seen from
this brief and Crossland’s brief below, any grant of a no evidence summary judgment would have
been improper. See Taylor–Made Hose, Inc. v. Wilkerson, 21 S.W.3d 484, 488 (Tex.App.-San
(CONT.)
8
(Tex.2009); Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex.2005). To
prevail on a motion for summary judgment, a party must conclusively establish the
absence of any genuine question of material fact, and that he is entitled to judgment as
a matter of law. TEX. R. CIV. P. 166a. A movant must either negate at least one
essential element of the nonmovant's cause of action or prove all essential elements of
an affirmative defense. See Randall's Food Markets, Inc. v. Johnson, 891 S.W.2d 640,
644 (Tex.1995); see also MMP, Ltd. v. Jones, 710 S.W.2d 59, 60 (Tex.1986). Since the
burden of proof is on the movant, and all doubts about the existence of a genuine issue
of material fact are resolved against the movant, a court must view the evidence and its
reasonable inferences in the light most favorable to the nonmovant. See Great Am.
Reserve Ins. Co. v. San Antonio Plumbing Supply Co., 391 S.W.2d 41, 47 (Tex.1965);
see also Fielding, 289 S.W.3d at 848; see also City of Keller v. Wilson, 168 S.W.3d
802, 827 (Tex.2005). The court is not required to ascertain the credibility of affiants or
to determine the weight of evidence in the affidavits, depositions, exhibits, and other
summary judgment proof. See Gulbenkian v. Penn, 151 Tex. 412, 252 S.W.2d 929,
932 (Tex.1952). The only question is whether or not an issue of material fact is
presented. See TEX. R. CIV. P. 166a(c).
The court's primary concern when interpreting a contract is to ascertain and give
effect to the intent of the parties as expressed in the contract. Seagull Energy E & P,
Antonio 2000, pet. denied); accord Forbes, Inc., 124 S.W.3d at 172.
9
Inc. v. Eland Energy, Inc., 207 S.W.3d 342, 345 (Tex. 2006). When construing a
written contract, the court ascertains the true intentions of the parties as expressed in
the instrument. Coker v. Coker, 650 S.W.2d 391, 393 (Tex. 1983). The court presumes
that the parties intended for every clause to have some effect. Heritage Res., Inc. v.
NationsBank, 939 S.W.2d 118, 121 (Tex. 1996). Put another way, “[t]o achieve this
objective, courts should examine and consider the entire writing in an effort to
harmonize and give effect to all the provisions of the contract so that none will be
rendered meaningless.” Coker, 650 S.W.2d at 393 (emphasis in original). “No single
provision taken alone will be given controlling effect; rather, all the provisions must be
considered with reference to the whole instrument.” Id. And courts will not construe
contracts to produce an absurd result when a reasonable alternative construction exists.
S. Cnty. Mut. Ins. v. Sur. Bank, N.A., 270 S.W.3d 684, 689 (Tex. App.—Fort Worth
2008, no pet.).
Whether a contract is ambiguous is a question of law to be determined “by
looking at the contract as a whole in light of the circumstances present when the
contract was entered.” Coker, 650 S.W.2d at 394. If the written instrument is so
worded that it can be given a definite or certain legal meaning, then the contract may
be construed as a matter of law. Seagull Energy, 207 S.W.3d at 345.
A contract is ambiguous when its meaning is susceptible to more than one
reasonable interpretation. Frost Nat’l Bank v. L & F Distribs., Ltd., 165 S.W.3d 310,
10
312 (Tex. 2005). Only when a contract is first determined to be ambiguous may the
courts consider the parties’ interpretation and admit extraneous evidence to determine
the true meaning of the instrument. Nat'l Union Fire Ins. Co. v. CBI Indus., Inc., 907
S.W.2d 517, 520 (Tex. 1994). A patent ambiguity is evident on the face of the contract,
while a latent ambiguity arises when a contract, unambiguous on its face, is applied to
the subject matter with which it deals, and an ambiguity appears by reason of some
collateral matter. Id. When a contract is found to be ambiguous, the parties’ intent is a
determination for the fact finder. Coker, 650 S.W.2d at 395. “When a contract contains
an ambiguity, the granting of a motion for summary judgment is improper because the
interpretation of the instrument becomes a fact issue.” Id. at 394.
The right to recover in quantum meruit is based upon a promise implied by law
to pay for beneficial services rendered and knowingly accepted. Black Lake Pipe Line
Co. v. Union Constr. Co., 538 S.W.2d 80, 86 (Tex.1976), overruled on other grounds
by Sterner v. Marathon Oil Co., 767 S.W.2d 686 (Tex.1989). A party may recover in
quantum meruit when there is no express contract covering the services furnished. Id.;
Bluelinx Corp. v. Texas Const. Sys., Inc., 363 S.W.3d 623, 627 (Tex. App.—Houston
[14th Dist.] 2011, no pet.). However, the existence of an express contract does not
preclude recovery in quantum meruit for the reasonable value of services rendered and
accepted which are not covered by the contract. Black Lake, 538 S.W.2d at 86;
Beverick v. Koch Power, Inc., 186 S.W.3d 145, 154 (Tex. App.—Houston [1st Dist.]
11
2005, pet. denied); Bluelinx, 363 S.W.3d at 627.
ARGUMENT
I. The trial court erred in ruling that the parties’ contract required
Crossland’s completion of all services for all land parcels for a firm, fixed
price, despite plain contract language to the contrary.
As a reading of the entirety of Crossland’s contract with HNTB makes clear,
Crossland was not required to complete all services under Task Orders 3 and 4 for all
parcels for the “maximum amount.” (See CR 381-616). To find otherwise
impermissibly ignores multiple provisions in the parties’ agreement and renders them
meaningless. Coker, 650 S.W.2d at 393; S. Cnty. Mut. Ins., 270 S.W.3d at 689.
Moreover, finding otherwise constitutes an impermissible redrafting and/or variance of
the contract’s explicit terms. In Re Polybutelene Plumbing Litig. v. Hoechst Celanese
Corp., 23 S.W.3d 428, 437 (Tex.App.-Houston [1st Dist.] 2000, no pet.); American
Mfrs. Mut. Ins. Co. v. Schaefer, 124 S.W.3d 154, 162 (Tex. 2003).
As the contract makes clear, Crossland’s “deliverables” under Task Orders 3 and
4 consisted of monthly status reports and “budget projections and anticipated
funding requirements every thirty (30) days and more frequently as requested by the
State during this Task Order.” (CR 570; CR 611) (emphasis added). These
“deliverables” were Crossland’s “foregoing obligations” under the contract. (CR 381
at “Article 4 – Scope of Services;” CR 550; CR 570; CR 595; CR 611; CR 851-52 at
48:6-48:21, 49:3-49:7 and 49:20-50:8; see also CR 1474). HNTB’s own officers agree
12
with this fact. (CR 851-52 at 48:6-48:21, 49:3-49:7 and 49:20-50:8). Nothing herein
suggests that the completion of all services for all parcels within the “maximum
amount” was a requirement. (CR 570; CR 611). To the contrary, the primary
“deliverable” of delivering “budget projections and anticipated funding requirements”
counsels squarely against such a reading. Accord Coker, 650 S.W.2d at 393; S. Cnty.
Mut. Ins., 270 S.W.3d at 689.
If HNTB wanted to require the completion of all services for all parcels as the
“foregoing obligations,” it would have done so because that is what it did in instances
where such was required. (Compare CR 550, 570 and 575 with CR 618, 621, and 625;
see also CR 1444-46). More specifically, HNTB would have removed the references
to budget projections and anticipated funding requirements as a “deliverable.” (Id.).
HNTB would have also made specific reference to the land parcels at issue as part of
the “deliverables.” (Id.). As set forth below, other language in the contract similarly
(and explicitly) demonstrates this fact even further.
The task orders make clear that specific services and parcels would be assigned
at a later date and were subject to change. (See CR 550; CR 554-55; CR 570; CR 595;
CR 611; CR 851 at 49:3-49:7; see also CR 2453 at ¶¶ 6-7; CR 2456-64). For example,
they say that “[t]he State, at its option, may elect to expand, reduce or delete the extent
of each work element . . . .” (CR 554; CR 597) (emphasis added). Exhibit B to Task
Order 3 repeats 10 times that the services only apply to “select limited parcels as
13
assigned along US 290.” (CR 562-65; CR 567; CR 569) (emphasis added). It also says
that “[t]here is no guarantee that any or all of the services described in this Task Order
will be assigned by the State and/or HNTB during the term of this Task Order.” (CR
555) (emphasis added). Moreover, Task Order 3 specifically states that “many of
these services have started in previous Task Orders” and/or they “will be
completed or continued in subsequent Task Orders.” (CR 554-55) (emphasis
added). To hold that Crossland has to complete all services for all land parcels in
return for a fixed sum that cannot be increased, as the trial court did here, utterly
ignores these provisions and impermissibly renders them meaningless. Accord Coker,
650 S.W.2d at 393. It also leads to an absurd result. Accord S. Cnty. Mut. Ins., 270
S.W.3d at 689.
Again, the task orders did not specify the number or type (commercial,
residential, land-only, multi-family dwelling, etc.) of parcels on which Crossland was
required to perform right-of-way and relocation services. (CR 550; CR 570; CR 575;
CR 595; CR 611; CR 615-16; CR 851 at 49:3-49:7; see also CR 2453 at ¶¶ 6-7; CR
2456-64). Rather, they only say that parcels may be assigned by the State or HNTB at
their discretion, and the work may be expanded. (Id.). Indeed, HNTB did just this,
i.e., assigned parcels separate from, and after execution, of the task orders. (CR 2453
at ¶¶ 6-7; CR 2456-58). The task orders had set time limits, i.e., termination dates.
(CR 553-54; CR 556-57; CR 559; CR 561-62; CR 564-65; CR 569; CR 597; CR 600;
14
CR 602; CR 605-06; CR 610; CR 613). Further, HNTB alleged (and the trial court
presumably accepted) that, despite being incorporated into Crossland’s Master
Agreement and same having been utilized in other supplements, the changes clauses
were not applicable to Crossland’s contract. (See supra at n.6) Therefore, under the
trial court’s interpretation, HNTB could assign an indefinite number of parcels to
Crossland, and Crossland would have to complete the services for all of the parcels at
its own cost, and perhaps beyond the termination date. This is an absurd result. See S.
Cnty. Mut. Ins., 270 S.W.3d at 689.
Finally, the trial court’s interpretation renders the payment terms in Crossland’s
contract with HNTB meaningless. The task orders specifically provided that the
“maximum amount” was “payable in accordance with” Attachment E to the Master
Agreement Exhibit D to the task orders. (CR 550; CR 595). Attachment E to the
Master Agreement and Exhibit D to the task orders identified “specified rate” as the
method of payment. (CR 511; CR 540; CR 550; CR 575; CR 587-88; CR 592-93; CR
595; CR 615-16). “Specified Rate” was defined in Attachment E to the Master
Agreement as follows:
Payment shall be based on the actual hours worked
multiplied by the specified rate for each type of labor plus
other agreed to special direct cost items. The specified rate
includes direct labor and indirect cost and fixed fee.
(CR 509). It also provided that “Contract Rates are to be billed” and that the rates are
15
not subject to audit. (Id.). Yet, under the trial court’s interpretation, Crossland would
only be paid the contract rates up to the “maximum amount,” and, afterwards,
Crossland must complete the remaining services for all parcels for free.
Crossland cannot be paid “in accordance with” Attachment E or Exhibit D to the
task orders if it is to work for free after reaching the “maximum amount.” Thus, the
trial court’s interpretation also renders the “specified rate” provisions in Crossland’s
contract meaningless and, again, leads to an absurd result. Accord Coker, 650 S.W.2d
at 393; S. Cnty. Mut. Ins., 270 S.W.3d at 689. This is especially true given that, where
Crossland was required to complete all services for all parcels within the “maximum
amount,” the Master Agreement allowed for alternative payment methods meant to
achieve same, and the parties’ actually utilized them. (Compare CR 550, 570 and 575
with CR 618, 621, and 625; see also CR 1444-46).
In sum, all of the foregoing demonstrates that the trial court’s interpretation
impermissibly rendered numerous contractual provisions meaningless, rewrites the
parties’ agreement and produces absurd results. Alternatively, and at a minimum, the
foregoing demonstrates that Crossland’s interpretation of the agreement is reasonable.
This is especially true given that same is in line with the general interpretation of other
contracts containing similar “deliverables” and methods of payment. (CR 1511 at
description of “Time and Material”). Either way, it was improper for the trial court to
grant summary judgment. Accord Coker, 650 S.W.2d at 393-94; S. Cnty. Mut. Ins.,
16
270 S.W.3d at 689.
PRAYER
For the foregoing reasons, the Appellant respectfully requests that this Court
reverse the trial court’s judgment and render all questions of law in its favor and/or
remand this matter back to the trial court for further proceedings.
Respectfully submitted,
_____________________________________
Bryant S. Banes
State Bar No. 24035950
Sean D. Forbes
State Bar No. 24040916
Stormy N. Mayfield
State Bar No. 24067656
Neel, Hooper & Banes, P.C.
1800 West Loop South, Suite 1750
Houston, Texas 77027
713-629-1800
713-629-1812 (Fax)
Attorneys for Crossland Acquisition, Inc.
17
CERTIFICATE OF SERVICE
The undersigned certifies that a true and correct copy of Appellant’s Brief has
been forwarded to counsel of record for HNTB Corporation, Appellee/Defendant, via
email, on this 18th day of November, 2015.
P. Randall Crump
PCRUMP@shb.com
____________________________________
Bryant S. Banes
CERTIFICATE OF COMPLIANCE
This is to certify that Appellant’s Brief contains 4,313 words.
____________________________________
Bryant S. Banes
18
APPENDIX
Order on Defendant HNTB Corporation’s Traditional Motion for Summary
Judgment Signed on January 20, 2015 ..................................................................... A
Amended Order on Summary Judgment Signed on February 16, 2015................... B
Final Judgment Signed on May 1, 2015 ................................................................... C
Master Agreement between HNTB Corporation and Consultation ......................... D
Task Order 3.............................................................................................................. E
Supplemental Agreement 1 to Task Order 3 ............................................................ F
Supplemental Agreement 2 to Task Order 3 ............................................................ G
Supplemental Agreement 3 to Task Order 3 ............................................................ H
Task Order 4............................................................................................................... I
Supplemental Agreement 1 to Task Order 4 ............................................................. J
A
1769
B
1790
C
2737
D
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
516
517
518
519
520
521
522
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
538
539
540
541
542
543
544
545
546
547
548
E
550
551
552
553
554
555
556
557
558
559
560
561
562
563
564
565
566
567
568
569
570
571
572
573
574
575
F
577
578
579
G
581
582
583
584
585
586
587
588
H
590
591
592
593
I
595
596
597
598
599
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
J
618
619
620
621
622
623
624
625