1 IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO
2 Opinion Number: __________
3 Filing Date: November 22, 2016
4 NO. 34,226 (consolidated with No. 34,461)
5 DARREL ALLRED, ROBERT ALLRED,
6 JOHN ALLRED, BRUCE ALLRED, and
7 DWAYNE ALLRED,
8 Plaintiffs-Appellees,
9 v.
10 NEW MEXICO DEPARTMENT
11 OF TRANSPORTATION,
12 Defendant-Appellant.
13 APPEAL FROM THE DISTRICT COURT OF CATRON COUNTY
14 Kevin R. Sweazea, District Judge
15 Domenici Law Firm, P.C.
16 Pete V. Domenici, Jr.
17 Albuquerque, NM
18 for Appellees
19 Miller Stratvert P.A.
20 Cody R. Rogers
21 Luke A. Salganek
22 Las Cruces, NM
23 for Appellant
1 OPINION
2 WECHSLER, Judge.
3 {1} Appellant New Mexico Department of Transportation appeals the district
4 court’s finding of contempt and award of judicial sanctions in the amount of
5 $408,764. Appellant also appeals the district court’s award of attorney fees and costs
6 in the amount of $54,301.41. With respect to the district court’s finding of contempt,
7 Appellant argues that the district court lacked subject matter jurisdiction or, in the
8 alternative, erroneously interpreted a “settlement agreement” between the parties.
9 Because we conclude that a portion of the “settlement agreement” was an enforceable
10 injunctive order, which was appropriately interpreted by the district court, these
11 arguments lack merit. Appellant additionally argues that the district court’s (1)
12 finding of contempt was not supported by substantial evidence or was invalidated by
13 evidentiary error, (2) award of judicial sanctions was not supported by substantial
14 evidence or resulted from an abuse of discretion, and (3) calculation of damages was
15 erroneous. We decline to accept these arguments except with respect to the district
16 court’s calculation of damages, to which we apply a $15,000 reduction.
17 {2} As to Appellant’s appeal of the district court’s award of attorney fees and
18 costs, our review of Appellant’s brief in chief and reply brief reveals insufficient
1 discussion and legal analysis from which to formulate an opinion. As such, we
2 consider these issues to be abandoned.
3 BACKGROUND
4 {3} Appellees Darrel, Robert, John, Bruce, and Dwayne Allred own and operate
5 a farming and livestock operation on lands adjacent to Whitewater Creek in
6 Glenwood, New Mexico. The Whitewater Creek Bridge (the Bridge) spans U.S.
7 Highway 180. Appellant constructed and maintains the Bridge. Since its
8 reconstruction in 1981, sediment aggradation has occurred at and about the Bridge.
9 This sediment aggradation resulted in an increased risk of flooding over time.
10 Because of this increased risk, on June 17, 2011 Appellees filed this action for
11 negligence, inverse condemnation, injunctive relief, and damages.
12 {4} During the pendency of the litigation, Appellees requested and were granted
13 a preliminary injunction related to the maintenance of the Whitewater Creek bed (the
14 Creek bed). The preliminary injunction required that Appellant (1) update its pre-
15 construction notice (PCN); (2) provide the updated biological assessment and
16 environmental analysis as required by the United States Army Corps of Engineers
17 (ACE) or the United States Fish and Wildlife Service; (3) submit a construction plan
18 to ACE, including a subsequent maintenance plan sufficient to put the Creek bed and
19 the Bridge in compliance with the 1981 design standards; and (4) undertake the
2
1 maintenance operation and promptly prosecute the maintenance to completion within
2 thirty days of ACE approval of the updated PCN. The preliminary injunction further
3 required that Appellant regularly maintain the Creek bed in accordance with the PCN.
4 {5} ACE approved the updated PCN, and Appellant began maintenance on the
5 Creek bed on March 14, 2012. This maintenance progressed until a dispute related
6 to the construction specifications halted progress. On April 12, 2012, the parties
7 entered court-ordered mediation. This mediation resulted in an agreement in principle
8 as to the terms of a permanent maintenance plan, which the parties referred to as a
9 permanent injunction.
10 {6} On December 10-11, 2012, the parties signed a Settlement Agreement and
11 Mutual Release (Settlement Agreement). The Settlement Agreement outlined the
12 Terms of Settlement as (1) the entry of a Stipulated Permanent Injunction Order
13 (Permanent Injunction) and (2) dismissal of the lawsuit by “execut[ion of] the
14 attached Stipulated Motion of Voluntary Dismissal With Prejudice.” The Settlement
15 Agreement additionally contained an arbitration provision triggered by the failure of
16 “any party . . . to perform any of the promises made in this [a]greement[.]”
17 {7} On January 18, 2013, the district court ordered entry of the Permanent
18 Injunction, which detailed the parties’ rights and obligations with respect to the
19 maintenance plan. The Permanent Injunction contained a “maintenance trigger” that
3
1 required Appellant to undertake maintenance efforts “when the average distance
2 between sediment accumulations to the low chord of the [B]ridge is [seven] feet.”
3 Additionally, the Permanent Injunction detailed the scope of Appellant’s maintenance
4 obligation and described circumstances under which the Permanent Injunction could
5 require amendment and protocol for such amendment. Finally, the Permanent
6 Injunction provided that “[t]he terms set forth herein resolve all pending issues related
7 to the injunctive relief requested by the [Appellees]. Title and compensation issues
8 between the [p]arties shall be disposed of and resolved through a separate
9 simultaneously executed settlement agreement and release.”
10 {8} On February 25, 2013, the parties jointly filed a Motion for Entry of Stipulated
11 Permanent Injunction and Voluntary Dismissal With Prejudice of All Remaining
12 Claims and Counterclaims (Motion for Entry and Voluntary Dismissal). The motion
13 stated, in pertinent part,
14 The Parties notify this [c]ourt that they have entered a Stipulated
15 Permanent Injunction that details a maintenance plan for [Whitewater]
16 Creek, above, below and under the U.S. 180 bridge in Glenwood, New
17 Mexico, Catron County as detailed therein.
18 The Parties further notify this [c]ourt that they have settled the
19 remaining disputes between them in the underlying lawsuit and pursuant
20 to Rule 1-041(A)(1)(b) [NMRA], hereby stipulate to the voluntary
21 dismissal with prejudice of all claims and counterclaims, known or
22 unknown, raised in this lawsuit or that could have been raised, against
23 the Parties.
4
1 {9} On February 27, 2013, the district court entered its Order of Dismissal With
2 Prejudice of All Remaining Claims (Order of Dismissal), which stated, in pertinent
3 part,
4 THIS MATTER having come before the [c]ourt upon the Parties’
5 notice of entry of Stipulated Permanent Injunction detailing a
6 maintenance plan on Whitewater Creek as detailed therein, and further
7 notice of settlement of the remaining disputes between them in the
8 underlying lawsuit, and stipulation to the voluntary dismissal with
9 prejudice of all claims and counterclaims, known or unknown, raised in
10 this lawsuit or that could have been raised by the Parties;
11 The [c]ourt being otherwise fully advised in the premises FINDS
12 that the stipulation is well-taken and is hereby GRANTED. All claims
13 and counterclaims raised or that could have been raised by the Parties in
14 this lawsuit are dismissed with prejudice upon the entry of this [c]ourt’s
15 Order, and each party shall bear its own fees and costs.
16 {10} On July 28, 2013, Appellees notified Appellant that sediment levels in the
17 Creek bed required maintenance. Beginning on August 2, 2013, Appellant dispatched
18 employees to remove sediment from the Creek bed in accordance with the Permanent
19 Injunction. For the majority of the time between August 2, 2013 and approximately
20 August 26, 2013, Appellant assigned two employees to the project. Appellee Darrel
21 Allred used his bulldozer to assist these employees for approximately one hundred
22 fifty hours during the month of August. On approximately August 26, 2013,
23 Appellant determined that a heavy equipment crew was required to complete the
24 project and ordered its employees to discontinue their maintenance efforts. This
5
1 discontinuation was premature and left the Creek bed out of compliance with the
2 terms of the Permanent Injunction. The heavy equipment crew was scheduled to
3 arrive at Whitewater Creek on September 16, 2013. During the intervening weeks,
4 several rain events deposited additional sediment in the Creek bed.
5 {11} On the night of September 14, 2013, a substantial rain event occurred, causing
6 storm water to flow down Whitewater Creek and, ultimately, to overtop the Bridge
7 and flow through Appellees’ property downstream from the Bridge. Additionally,
8 storm water backed up at the Bridge and overtopped the upstream dikes on both sides
9 of Whitewater Creek, causing damage to the dikes themselves, as well as irrigated
10 fields, irrigation systems, and crops.
11 {12} On September 17, 2013, Appellees filed a Verified Motion to Enforce
12 Permanent Injunction For Relief for Violation of Permanent Injunction (Verified
13 Motion to Enforce). This motion requested an emergency hearing “to determine and
14 order appropriate remedial actions [Appellant] must take, and grant any further relief
15 the [c]ourt deems justice requires.” In the weeks between the filing of the motion and
16 the emergency hearing on October 9, 2013, Appellant reentered the Creek bed and
17 removed sediment in accordance with the Permanent Injunction.
18 {13} At the October 9, 2013 hearing, Appellees clarified that they were no longer
19 seeking emergency relief but hoped to “move[] this matter forward in the direction
6
1 of some appropriate sanction for violation of the [Permanent Injunction] order.” After
2 attorney argument and testimony, the district court ruled that Appellant “violated the
3 stipulated [Permanent Injunction] order by failing to diligently pursue maintenance
4 until completion[.]” Appellees were given leave to petition the district court for
5 damages and sanctions—the appropriateness of which was to be determined at a
6 subsequent hearing on the issues of liability, causation, and damages. Neither of the
7 parties raised the issue of subject matter jurisdiction in the pre-hearing briefing or at
8 the hearing. On November 8, 2013, Appellant filed a motion to reconsider, which
9 argued, generally, that its conduct did not violate the Permanent Injunction. This
10 motion was denied.
11 {14} On November 21, 2013, Appellees filed a petition for sanctions and damages
12 for Appellant’s violation of the Permanent Injunction. The petition alleged that
13 Appellant was liable for damages to Appellees’ property. The district court scheduled
14 a motion hearing on June 25-26, 2014 and set a June 1, 2014 discovery deadline.
15 {15} During discovery, the pending hearing was rescheduled for July 24-25, 2014.
16 On July 21, 2014, counsel for Appellant sent a letter to the district court and counsel
17 for Appellees asserting that, effective February 27, 2013, the district court lacked
18 subject matter jurisdiction over the case. This letter posited that an entry of voluntary
19 dismissal “terminates a case, leaving the district court without jurisdiction to take[]
7
1 any further action in the case.” The letter additionally posited that, per the Settlement
2 Agreement, arbitration was the appropriate forum for resolving Appellees’ claims.
3 Following a telephonic hearing related to the letter, Appellant filed motions (1) to
4 enforce the Settlement Agreement and dismissal (Motion to Enforce) and (2) to
5 vacate (Motion to Vacate) the pending hearing for lack of subject matter jurisdiction.
6 The Motion to Enforce focused on the interplay between the Settlement Agreement,
7 its arbitration provision, and the Permanent Injunction. The Motion to Vacate
8 expressly asserted that the district court lacked subject matter jurisdiction over
9 Appellees’ claims following the parties’ voluntary dismissal.
10 {16} At the outset of the July 24, 2014 hearing, the district court considered the
11 merits of the Motion to Enforce and the Motion to Vacate. The central issues were (1)
12 whether the Settlement Agreement incorporated the Permanent Injunction such that
13 Appellees’ claims were subject to arbitration and (2) if the Permanent Injunction was
14 incorporated, did Appellant’s failure to timely assert its right to arbitrate constitute
15 a waiver. The district court ruled in favor of Appellees, specifically concluding that
16 “it does not appear that the provisions of the injunction are subsumed within the
17 requirement of arbitration.” The district court did not rule, nor did Appellant orally
18 raise, the effect of the stipulated voluntary dismissal on the district court’s subject
19 matter jurisdiction.
8
1 {17} During the hearing, Appellees presented testimony and evidence on topics
2 including: (1) the September 14, 2013 flood event; (2) damage to personal property;
3 and (3) the cost to repair such damage. Appellees offered expert witness testimony
4 by Walter L. Niccoli, which described the likely sequence of events on September 14,
5 2013 and the causal relationship between Appellant’s violation of the Permanent
6 Injunction and damages suffered by Appellees. As a counterpoint to Niccoli’s
7 testimony, Appellant intended to introduce expert witness testimony by John Wallace.
8 However, the district court excluded Wallace’s testimony as a sanction for discovery
9 violations. After this ruling, Appellant moved to strike Niccoli’s testimony. This
10 motion was granted in part with respect to testimony related to sediment aggradation
11 in the Creek bed.
12 {18} The district court concluded that it had jurisdiction over the motions before it,
13 including Appellees’ Petition for Sanctions, under Article VI, Section 13 of the New
14 Mexico Constitution. The district court ruled that (1) Appellant’s violation of the
15 Permanent Injunction constituted contempt, (2) a causal relationship existed between
16 Appellant’s violation of the Permanent Injunction and Appellees’ damages, and (3)
17 Appellees suffered damages in the amount of $408,764. The district court ordered
18 sanctions in the form of compensatory damages in the amount of $408,764. The
9
1 parties also litigated attorney fees and costs, which resulted in an award to Appellees
2 in the amount of $54,301.41.
3 {19} Appellant timely filed notice of appeal of the district court’s ruling on the
4 merits and its award of attorney fees and costs. These appeals were consolidated by
5 order of this Court.
6 SUBJECT MATTER JURISDICTION
7 {20} “Subject matter jurisdiction is the power to adjudicate the general questions
8 involved in the claim[.]” Gonzales v. Surgidev Corp., 1995-NMSC-036, ¶ 12, 120
9 N.M. 133, 899 P.2d 576. As a general rule, a court has subject matter jurisdiction over
10 claims that “fall[] within the general scope of authority conferred upon such court by
11 the constitution or statute.” Id. (internal quotation marks and citation omitted). A
12 judgment entered by a court lacking subject matter jurisdiction has no legal effect.
13 See State v. Patten, 1937-NMSC-034, ¶ 11, 41 N.M. 395, 69 P.2d 931 (“There are
14 three jurisdictional essentials necessary to the validity of every judgment, to wit,
15 jurisdiction of parties, jurisdiction of the subject matter, and power or authority to
16 decide the particular matters presented, and the lack of [any] is fatal to the
17 judgment[.]” (emphasis, internal quotation marks, and citations omitted)). The issue
18 of subject matter jurisdiction cannot be waived and may be raised at any time,
19 including on appeal to this Court. Becenti v. Becenti, 2004-NMCA-091, ¶ 13, 136
10
1 N.M. 124, 94 P.3d 867. We review claims related to subject matter jurisdiction de
2 novo. Murken v. Solv-Ex Corp., 2006-NMCA-064, ¶ 8, 139 N.M. 625, 136 P.3d 1035.
3 {21} Rule 1-041(A) NMRA provides for the voluntary dismissal of a claim brought
4 in a New Mexico district court. The rule states, in pertinent part, “an action may be
5 dismissed by the plaintiff . . . by filing a stipulation of dismissal signed by all parties
6 who have appeared generally in the action.” Rule 1-041(A)(1)(b). The effect of such
7 a dismissal “leaves a situation, so far as procedures therein are concerned, the same
8 as though the suit had never been brought; and upon such voluntary dismissal, all
9 prior proceedings and orders in the case are vitiated and annulled, and jurisdiction of
10 the court is immediately terminated.” McCuistion v. McCuistion, 1963-NMSC-144,
11 ¶ 9, 73 N.M. 27, 385 P.2d 357.
12 {22} Appellant’s central argument on appeal is that the Permanent Injunction was
13 subject to the parties’ Rule 1-041 voluntary dismissal and, therefore, was
14 unenforceable by the district court. Under McCuistion, Appellant’s argument would
15 prevail if the Permanent Injunction was subject to the Order of Dismissal entered by
16 the district court. For the reasons discussed below, however, we conclude that it was
17 not.
11
1 The District Court’s Order of Dismissal
2 {23} A judgment “must be certain and unequivocal” such that it “dispose[s] of the
3 matters at issue between the parties that they . . . will be able to determine with
4 reasonable certainty the extent to which their rights and obligations have been
5 determined[.]” Hollingsworth v. Hicks, 1953-NMSC-045, ¶ 26, 57 N.M. 336, 258
6 P.2d 724 (internal quotation marks and citation omitted). While appellate courts draw
7 certain distinctions between stipulated judgments and judgments on the merits, no
8 such distinctions apply when construing a judgment’s intended effect. Compare id.
9 ¶ 30 (construing a judgment on the merits), with Mundy & Mundy, Inc. v. Adams,
10 1979-NMSC-084, ¶ 20, 93 N.M. 534, 602 P.2d 1021 (construing a stipulated
11 judgment). When a judgment is “clear and unambiguous . . . [i]t must stand and be
12 enforced as it speaks.” Parks v. Parks, 1978-NMSC-008, ¶ 20, 91 N.M. 369, 574 P.2d
13 588. However, if “the meaning is obscure, doubtful, or ambiguous, the judgment,
14 pleadings, and entire record may always be resorted to for the purpose of aiding in the
15 construction thereof.” Hollingsworth, 1953-NMSC-045, ¶ 30. Our goal in construing
16 an ambiguous judgment is “to determine the intention and meaning of the author[.]”
17 Id. ¶ 31. Stipulations incorporated into a court’s judgment are “construed liberally to
18 give effect to the intent of the parties.” Parks, 1978-NMSC-008, ¶¶ 15-16.
12
1 {24} As discussed above, the Order of Dismissal resulted from the parties’ Motion
2 for Entry and Voluntary Dismissal. The Order of Dismissal separately detailed the
3 parties’ agreement as to (1) a maintenance plan for Whitewater Creek, by way of the
4 Permanent Injunction; (2) settlement of the remaining disputes in the underlying
5 lawsuit; and (3) “voluntary dismissal with prejudice of all claims and
6 counterclaims . . . raised in th[e] lawsuit[.]” The Order of Dismissal did not expressly
7 reserve authority to the district court to enforce the Permanent Injunction. However,
8 the Permanent Injunction itself implies ongoing enforcement authority, stating,
9 The Parties recognize that if regulatory changes or conditions are
10 unilaterally implemented by any controlling state or federal agency that
11 impacts the ability of [Appellant] to comply with the terms of this Order,
12 the Parties recognize [Appellant] will need to comply with those
13 regulatory requirements[.] . . . In the event there is not agreement
14 between the Parties that regulatory changes or conditions were
15 unilaterally implemented by any controlling state or federal agency that
16 impacts the ability of [Appellant] to comply with the terms of this Order,
17 [Appellant] must request and obtain modification to the permanent
18 injunction.
19 The Parties recognize that if site conditions change such that
20 [Appellant’s] ability to comply with the terms of this Order is impacted,
21 [Appellant] will advise the principal [Appellee] Darrel Allred of such
22 changes. In the event there is not agreement between the Parties that site
23 conditions change such that [Appellant’s] ability to comply with the
24 terms of this Order is impacted, [Appellant] must request and obtain
25 modification to the permanent injunction.
13
1 {25} Appellees argue that the parties did not, in dismissing all remaining claims,
2 intend to limit the district court’s enforcement power with respect to the Permanent
3 Injunction. Appellant argues that the Motion for Entry and Voluntary Dismissal
4 indicated the parties’ intent to terminate the district court’s jurisdiction over the
5 Permanent Injunction. The Order of Dismissal does not clearly indicate which of
6 these positions was intended by the parties’ stipulated dismissal of “all remaining
7 claims.” This ambiguity requires that we look to the entire record to construe the
8 judgment. Parks, 1978-NMSC-008, ¶ 16; Hollingsworth, 1953-NMSC-045, ¶ 30.
9 {26} The Permanent Injunction itself is particularly illuminating as to the intent of
10 the parties. First, the district court entered the Permanent Injunction on January 18,
11 2013—more than six weeks before its entry of the Order of Dismissal, which
12 dismissed “all remaining claims.” Additionally, the Permanent Injunction
13 contemplated the possibility that regulatory or site condition changes could impact
14 Appellant’s ability to comply with its maintenance obligations. It also contemplated
15 disagreement between the parties, such that Appellant “must request and obtain
16 modification to the [Permanent Injunction].” The Permanent Injunction did not
17 expressly indicate to which entity such a request was to be made. However, because
18 the district court entered the Permanent Injunction on January 18, 2013 and no
19 alternate forum was indicated on that date, the obvious implication is that any request
14
1 for modification would be made to the district court. The power to modify the
2 Permanent Injunction implies ongoing enforcement authority.
3 {27} Generally speaking, the inclusion of an express reservation or repudiation of
4 ongoing judicial enforcement authority within an order of dismissal limits the need
5 for such analysis. See, e.g., Kokkonen v. Guardian Life Ins. Co. of Am., 511 U.S. 375,
6 381-82 (1994) (discussing the retention of judicial authority by the consent of the
7 parties over settlement agreements that result in voluntary dismissal). However,
8 having conducted the analysis, we conclude that the Permanent Injunction was not
9 subject to the Order of Dismissal. Therefore, the district court retained authority to
10 enforce the Permanent Injunction and had subject matter jurisdiction over Appellees’
11 Verified Motion to Enforce.
12 THE PERMANENT INJUNCTION
13 {28} In the alternative, Appellant asserts numerous errors by the district court in
14 interpreting or construing the Permanent Injunction, including: (1) that the Settlement
15 Agreement and the Permanent Injunction functioned as a contract between the parties,
16 such that claims arising from a violation of the Permanent Injunction were subject to
17 arbitration; (2) that the district court improperly reformed the Permanent Injunction
18 by adding and omitting terms; and (3) that the district court erroneously concluded
19 that Appellant violated the Permanent Injunction. To the extent that our analysis
15
1 requires, we review questions of contractual interpretation de novo. Thompson v.
2 Potter, 2012-NMCA-014, ¶ 12, 268 P.3d 57.
3 The Nature of the Permanent Injunction
4 {29} As a general rule, a stipulated judgment “is not considered to be a judicial
5 determination, but a contract between the parties[.]” Williams v. Crutcher, 2013-
6 NMCA-044, ¶ 8, 298 P.3d 1184. However, discussing this general rule in Pope v.
7 Gap, Inc., this Court clarified that stipulated judgments have characteristics of both
8 judgments and contracts. See 1998-NMCA-103, ¶ 22, 125 N.M. 376, 961 P.2d 1283
9 (“[A consent judgment] is similar to a judgment because it is entered and enforceable
10 as a judgment; however, it is like a contract because its terms and conditions are
11 reached by the mutual agreement of the parties.”). Inasmuch as Williams’ statement
12 of our general rule would subject the Permanent Injunction to a pure contract law
13 analysis, the injunctive relief granted in this particular case is distinguishable from
14 the general rule.
15 {30} United States v. City of Miami, 664 F.2d 435 (5th Cir. 1981) (per curiam), cited
16 by this Court in Pope, is instructive. In that case, the attorney general filed a
17 complaint against the city of Miami (the City) and the Fraternal Order of Police
18 (FOP) for discriminating against certain protected classes of individuals in violation
19 of the Fourteenth Amendment and federal law. City of Miami, 664 F.2d at 436. The
16
1 complaint sought both temporary and permanent injunctive relief. Id. Post-complaint
2 negotiations resulted in a proposed consent decree that was signed by both the United
3 States and the City. Id. at 438. The district court approved and entered the consent
4 decree over objections by the FOP. Id. Shortly thereafter, the FOP filed a motion to
5 vacate the consent decree, which the district court granted. Id. After a hearing, the
6 United States and the City submitted a modified consent decree. Id. at 439. The
7 district court entered the modified consent decree over continued objection by the
8 FOP, finding that “the decree does not violate the contractual relationship between
9 [the parties and] . . . [t]he consent reached is constitutionally valid.” Id. (internal
10 quotation marks omitted). The modified consent decree included language stating that
11 the defendants “are permanently enjoined and restrained from engaging in any act or
12 practice which has the purpose or effect of unlawfully discriminating against [the
13 protected classes.]” Id. (internal quotation marks omitted). The FOP appealed the
14 entry of the consent decree. Id.
15 {31} In discussing the principles underlying consent decrees, the Fifth Circuit stated,
16 When presented with a proposed consent decree, the court’s duty
17 is akin, but not identical to its responsibility in approving settlements of
18 class actions, stockholders’ derivative suits, and proposed compromises
19 of claims in bankruptcy. In these situations, the requisite court approval
20 is merely the ratification of a compromise. The court must ascertain only
21 that the settlement is “fair, adequate and reasonable.”
17
1 Because th[is] consent decree does not merely validate a
2 compromise but, by virtue of its injunctive provisions, reaches into the
3 future and has continuing effect, its terms require more careful scrutiny.
4 Even when it affects only the parties, the court should, therefore,
5 examine it carefully to ascertain not only that it is a fair settlement but
6 also that it does not put the court’s sanction on and power behind a
7 decree that violates Constitution, statute, or jurisprudence.
8 Id. at 441 (emphasis added) (footnotes omitted).
9 {32} The judicial process outlined in City of Miami is more analogous to the current
10 case than Williams or other New Mexico appellate cases that define stipulated or
11 consent judgments as contractual in nature. See, e.g., Owen v. Burn Constr. Co.,
12 1977-NMSC-029, 90 N.M. 297, 563 P.2d 91 (discussing a stipulated judgment arising
13 from the settlement of claims for property damage); State ex rel. State Highway
14 Comm’n v. Clark, 1968-NMSC-057, 79 N.M. 29, 439 P.2d 547 (discussing a
15 stipulated judgment arising from the settlement of eminent domain proceedings); La
16 Luz Cmty. Ditch Co. v. Town of Alamogordo, 1929-NMSC-044, 34 N.M. 127, 279 P.
17 72 (discussing a stipulated judgment arising from the settlement of claims related to
18 water rights); Williams, 2013-NMCA-044 (discussing a stipulated judgment arising
19 from the settlement of claims related to trust distributions).
20 {33} In Owen, for example, the defendant was employed by a municipal
21 redevelopment agency to demolish a hotel adjacent to the plaintiffs’ restaurant. 1977-
22 NMSC-029, ¶ 2. During the demolition, the defendant’s negligence caused the hotel
18
1 to fall onto and destroy the restaurant. Id. The plaintiffs reached a settlement with the
2 agency to compensate them for the value of the lot. Id. ¶ 3. The terms of the
3 settlement were entered as a judgment by the district court. Id. The plaintiffs then
4 filed a lawsuit against the defendant for damages to the physical structure. Id. ¶ 4.
5 {34} In this context, the stipulated judgment, which memorialized the settlement
6 agreement between the plaintiffs and the agency, was more like a contract than a
7 judgment. The plaintiffs and the agency determined, among themselves, the value of
8 the lot. After payment of the stipulated amount, the plaintiffs and the agency had no
9 additional rights or obligations with respect to the other. The district court
10 unquestionably had no ongoing enforcement obligations. As such, the district court’s
11 role was, as described in Appellant’s brief in chief, “ministerial.”
12 {35} The stipulated judgment in Owen is simply not analogous to that in the current
13 case. On June 17, 2011, Appellees filed a complaint alleging negligence and
14 requesting injunctive relief related to Appellant’s maintenance obligation at the
15 Bridge. Appellees’ request for injunctive relief specifically requested that the district
16 court “requir[e Appellant] to immediately begin restoring the Whitewater Creek
17 Bridge to 1981 design standards[.]” After an evidentiary hearing, the district court
18 issued a preliminary injunction, ordering Appellant to “submit to the ACE a
19 construction notice with a specific plan for immediate maintenance of the Whitewater
19
1 Creek and the Bridge” including “a subsequent maintenance plan that is sufficient to
2 put the [C]reek bed and [the] Bridge in compliance with the 1981 design standards
3 of the Bridge.” The preliminary injunction additionally provided that regular creek
4 bed maintenance “shall be undertaken” until further order of the court.
5 {36} Appellant argues on appeal that the Permanent Injunction is contractual in
6 nature because it resulted from negotiations between the parties. However, the
7 preliminary injunction proceedings demonstrate that the district court contemplated
8 the equities involved with granting injunctive relief long before entering the
9 Permanent Injunction. Additionally, the terms of the Permanent
10 Injunction—particularly those related to ongoing maintenance requirements placed
11 on Appellant—comport with the legal rationale supporting injunctive relief. See
12 Insure N.M., LLC v. McGonigle, 2000-NMCA-018, ¶ 6, 128 N.M. 611, 995 P.2d 1053
13 (“In determining whether to grant injunctive relief, a [district] court must consider a
14 number of factors and balance the equities and hardships. Some of these factors
15 include: (1) the character of the interest to be protected; (2) the relative adequacy to
16 the plaintiff of an injunction, when compared to other remedies; (3) the interests of
17 third parties; (4) the practicability of granting and enforcing the order; and (5) the
18 relative hardship likely to result to the defendant if granted and to the plaintiff if
19 denied.” (internal quotation marks and citations omitted)). Given this procedural
20
1 history, the district court’s role in entering the Permanent Injunction was more than
2 ministerial.
3 {37} Despite being the product of a stipulation between the parties, the Permanent
4 Injunction is a judgment of the district court and not merely a memorialization of a
5 contractual agreement. Because the Permanent Injunction is a judgment, it is
6 enforceable by the district court and not subject to the arbitration clause contained
7 within the Settlement Agreement. See NMSA 1978, § 39-1-5 (1850-1851) (“It shall
8 be the duty of the judge of any court to cause judgment, sentence or decree of the
9 court to be carried into effect, according to law.”).
10 Interpretation of the Permanent Injunction
11 A. Terms
12 {38} Appellant additionally argues that the district court erroneously interpreted the
13 Permanent Injunction by “adding terms not agreed upon by the parties, and omitting
14 terms specifically agreed to by the parties.” Because Appellant’s argument is
15 premised upon its claim that the Permanent Injunction is a contract, it is, to a degree,
16 inapplicable. However, we apply similar principles in construing contracts and
17 judgments. See Owen, 1977-NMSC-029, ¶ 14 (“The rules to be followed in arriving
18 at the meaning of judgments and decrees are not dissimilar to those relating to other
19 written documents. Where the decree is clear and unambiguous, neither pleadings,
21
1 findings nor matters dehors the record may be used to change or even to construe its
2 meaning.”). We therefore review de novo whether the district court’s interpretation
3 of the Permanent Injunction resulted in a reformation of the judgment.
4 {39} On October 9, 2013, the district court held a hearing on Appellees’ Verified
5 Motion to Enforce. After taking testimony related to Appellant’s maintenance efforts
6 between August 2, 2013 and approximately August 28, 2013, the district court ruled
7 that Appellant “violated the stipulated permanent injunction order by failing to
8 diligently pursue maintenance until completion[.]”
9 {40} The Permanent Injunction states, in pertinent part, that “[c]ontinuing
10 maintenance required under the PCN shall be performed in conformance with the
11 maintenance plan . . . and shall be diligently pursued until completion recognizing
12 that, force majeure, regulatory restrictions, and conditions provided for upon
13 approval of [Appellant’s] PCN, or otherwise, will ultimately dictate [Appellant’s]
14 maintenance time frames.” Appellant argues that the district court’s interpretation (1)
15 erroneously established timeliness and resource allocation requirements for the
16 project and (2) ignored provisions that provided Appellant with discretion over
17 maintenance time frames.
18 {41} Appellant’s timeliness and resource allocation argument is predicated on its
19 claim that “[t]he unambiguous language of the [Permanent Injunction] requires only
22
1 that [Appellant] ‘diligently pursue maintenance until completion.’” Appellant asserts
2 that the district court’s interpretation reformed the Permanent Injunction to “include
3 specific requirements . . . such as ‘continuous’ pursuit of maintenance, time frames
4 for completion, prioritization of maintenance, size of crew, or equipment used[.]” We
5 disagree. Our review of the record indicates that the district court simply emphasized
6 that the “judgment requires prosecution diligently to completion.” (Emphasis added.)
7 Appellant never completed the required maintenance prior to discontinuing its efforts
8 on or about August 28, 2013. “[W]here the language of a judgment or decree is clear
9 and unambiguous, . . . [i]t must stand and be enforced as it speaks.” Hollingsworth,
10 1953-NMSC-045, ¶ 30. The district court’s ruling that Appellant violated the
11 Permanent Injunction by failing to complete its maintenance obligation did not
12 constitute a reformation of the Permanent Injunction by the district court.
13 {42} Appellant’s second argument—that it had broad discretion over maintenance
14 time frames—is in two parts and is predicated upon acknowledgment in the
15 Permanent Injunction that certain conditions will “dictate [Appellant’s] maintenance
16 time frames.” These conditions are “force majeure, regulatory restrictions, and
17 conditions provided for upon approval of [Appellant’s] PCN, or otherwise[.]”
18 {43} Appellant argues that the “or otherwise” clause is an “important area[] of
19 discretion given to [Appellant] by the [Permanent Injunction]” and that the district
23
1 court’s interpretation of the “or otherwise” clause rendered it “mere surplusage[.]”
2 We disagree. Our reading of the “or otherwise” clause in the context of the entire
3 document indicates that it does not stand alone, but that it instead modifies the
4 immediately preceding phrase, which itself refers back to an earlier provision related
5 to pending regulatory approval.1 Given this conclusion, it is Appellant’s
6 reading—that the “or otherwise” clause provided seemingly unlimited discretion over
7 maintenance time frames and resource allocation—that renders certain preceding
8 language meaningless. Cf. Bank of N.M. v. Sholer, 1984-NMSC-118, ¶ 6, 102 N.M.
9 78, 691 P.2d 465 (“A contract must be construed as a harmonious whole, and every
10 word or phrase must be given meaning and significance according to its importance
11 in the context of the whole contract.”).
12 {44} Appellant additionally argues that monsoonal rains and increased sediment
13 accumulation related to the Whitewater-Baldy Complex fire constituted a force
14 majeure excusing compliance with the Permanent Injunction. After taking testimony
1
15 Paragraph two of the Permanent Injunction states, in pertinent part,
16 “[Appellant] will submit to the [ACE] a [PCN] addressing its subsequent maintenance
17 and re-vegetation plan, the scope of which is to read, as much as practicable, as
18 consistent with Exhibit B, as attached, and shall be made pursuant to the terms and
19 conditions set forth below, subject to approval of the [ACE], or as otherwise directed
20 by regulatory agencies thereto.” (Emphasis added). We read this sentence to
21 contemplate additional regulatory action, potentially affecting Appellant’s ability to
22 comply with its maintenance obligation under the Permanent Injunction.
24
1 and evidence, the district court ruled that the physical conditions at and around the
2 Bridge did not constitute a force majeure such that Appellant’s duty to perform was
3 excused. This conclusion, however unsatisfactory to Appellant, resulted from the
4 district court’s analysis of the force majeure clause and does not constitute a
5 reformation of the Permanent Injunction by the district court.
6 B. Causation
7 {45} Appellant’s final argument in this regard asserts that the district court’s
8 conclusion that a causal relationship exists between Appellant’s violation of the
9 Permanent Injunction and damages suffered by Appellees is not supported by
10 substantial evidence. In conducting such review, “[w]e are deferential to facts found
11 by the district court, but we review conclusions of law de novo.” Benavidez v.
12 Benavidez, 2006-NMCA-138, ¶ 21, 140 N.M. 637, 145 P.3d 117. As part of its
13 argument, Appellant claims that the district court erroneously excluded its expert
14 witness. We review the admission of expert testimony for an abuse of discretion.
15 Leithead v. City of Santa Fe, 1997-NMCA-041, ¶ 27, 123 N.M. 353, 940 P.2d 459.
16 1. Admission of Expert Testimony
17 {46} Appellant, citing various case law, asserts that the district court improperly
18 struck its expert witness, John Wallace. Our review of the record does not support
19 Appellant’s position.
25
1 {47} Rule 1-026 NMRA governs civil discovery, including the admission of expert
2 witness testimony. With respect to expert witness disclosures, the rule provides, in
3 pertinent part,
4 A party may through interrogatories and requests for production
5 discover the identity of each person the other party may call as an expert
6 witness at trial, the subject matter on which the expert is expected to
7 testify, and the substance of the facts and opinions to which the expert
8 is expected to testify and a summary of the grounds for each opinion.
9 Rule 1-026(B)(6)(a). A failure to make such disclosures is sufficient grounds to
10 exclude expert witness testimony. See Rule 1-037(B)(2)(b) NMRA (providing “if a
11 party fails to obey an order under Rule 1-026 . . . , the court in which the action is
12 pending may . . . prohibit[] that party from introducing designated matters in
13 evidence”); Lewis ex rel. Lewis v. Samson, 2001-NMSC-035, ¶¶ 13, 16, 131 N.M.
14 317, 35 P.3d 972 (holding that “lesser sanctions,” including the exclusion of
15 witnesses, “may be applied to any failure to comply with discovery orders” (internal
16 quotation marks and citation omitted)).
17 {48} During discovery, Appellees propounded interrogatories and requests for
18 production on Appellant, including at least one related to expert witnesses. In
19 response, Appellant named Wallace as its expert witness. Appellant’s answer to the
20 interrogatory did not provide information concerning Wallace’s opinions, the grounds
21 for those opinions, or the facts, documents, and other information upon which
26
1 Wallace relied in forming his opinions. Appellant did not provide Appellees with
2 Wallace’s expert report.
3 {49} Appellees requested supplementation of Appellant’s response to its
4 interrogatories, including “review [of] the opinions and materials Mr. Wallace relied
5 upon in making any expert opinions he intends to offer at [the scheduled] hearing[.]”
6 In the absence of written discovery, Appellees noticed a deposition for Wallace on
7 July 2, 2014. This notice was accompanied by a letter requesting alternate dates if the
8 noticed date presented a scheduling conflict. On June 29, 2014, Appellant notified
9 Appellees of a conflict with the noticed deposition. Appellees indicated availability
10 on July 3, 2014, but they also indicated that additional delays were unacceptable
11 given the proximity to trial. In their response, Appellees reiterated their request for
12 supplementation of discovery materials. Appellant failed to supplement and instead
13 filed a motion for a protective order related to Wallace’s noticed deposition and a
14 motion to stay proceedings. Both parties subsequently filed motions in limine to
15 exclude the other’s expert witness. The district court declined to address Appellant’s
16 motion to stay proceedings due to its untimeliness and reserved its ruling on the
17 motions in limine until the witnesses were called at trial.
18 {50} Appellant called Wallace to testify and elicited his expert qualifications on
19 direct examination. At the outset of Wallace’s substantive testimony, Appellees
27
1 objected and moved to exclude Wallace due to alleged discovery violations. After
2 oral argument by the parties, the district court sustained Appellees’ objection, ruling
3 that the “Rule [1-0]26 disclosure was inadequate” because it included “no facts and
4 no opinions . . . in [the] disclosure and there is no report that can be referred to
5 instead.” Appellant filed a Motion to Reconsider and Offer of Proof (Motion to
6 Reconsider), which the district court denied.
7 {51} Rule 1-037(B) bestows authority on the district court to grant and enforce
8 sanctions for discovery violations. Given Appellant’s conduct during the discovery
9 process, the district court did not abuse its discretion by excluding Wallace’s expert
10 testimony. Applying the same rationale, the district court also did not abuse its
11 discretion by denying Appellant’s Motion to Reconsider.
12 2. Substantial Evidence of Causation
13 {52} The district court ruled that Appellant’s failure to comply with the Permanent
14 Injunction resulted in storm water overtopping both the Bridge and the upstream
15 dikes, “caus[ing] serious damage to [Appellees’] property.” Causation is a
16 prerequisite for an award of civil damages, including damages predicated upon a
17 finding of civil contempt. See El Paso Prod. Co. v. PWG P’ship, 1993-NMSC-075,
18 ¶ 31, 116 N.M. 583, 866 P.2d 311 (“We hold that once a plaintiff satisfies his [or her]
19 burden of proving violation of a court order, proximate cause, and damages, he or she
28
1 is entitled to judgment for recovery of those damages.”). Appellant argues that this
2 ruling was not supported by substantial evidence or, in the alternative, that lay
3 witness testimony is insufficient to support a finding of causation in the context of
4 flooding. But see Moore v. Associated Material & Supply Co., 948 P.2d 652, 662
5 (Kan. 1997) (“[W]itnesses who have long been familiar with the flooding patterns of
6 an area are competent to form an opinion as to the cause of flooding.”). Appellant’s
7 secondary argument was not preserved and is, therefore, not considered by this Court.
8 See Wolfley v. Real Estate Comm’n, 1983-NMSC-064, ¶ 5, 100 N.M. 187, 668 P.2d
9 303 (“[T]heories, defenses, or other objections will not be considered when raised for
10 the first time on appeal.”).
11 {53} In support of their claims, Appellees offered expert witness testimony by
12 Niccoli. During discovery, Appellees disclosed Niccoli’s expert report, which stated,
13 in pertinent part,
14 [M]y opinion is that the Bridge did not have adequate capacity to pass
15 the flow from the Event. Because the Bridge did not have the capacity,
16 it resulted in the flood waters backing up behind the Bridge, damaging
17 or destroying upstream flood containment structures (e.g., dikes), and
18 the flood waters jumping the channel. Had [Appellant] completed [its]
19 maintenance duties on September 5[], 2013, the Event would have
20 passed beneath the Bridge and [would] not have caused the damage[.]
21 After Niccoli’s testimony, Appellant argued that his expert report and answers to
22 interrogatories failed to adequately disclose his theory as to causation. The district
29
1 court struck certain portions of Niccoli’s testimony related to sediment aggradation,
2 but the extent to which this ruling limited Niccoli’s testimony is unclear to this Court.
3 Despite passing reference to the district court’s ruling in its appellate briefing,
4 Appellant does not provide record citation to the portions of Niccoli’s testimony that
5 were struck by the district court or comprehensive analysis of the effect of this
6 evidentiary ruling on our substantial evidence review. See Rule 12-213(A)(4) NMRA
7 (requiring the appellant to provide citations to the record proper in support of each
8 argument); Fenner v. Fenner, 1987-NMCA-066, ¶ 28, 106 N.M. 36, 738 P.2d 908
9 (holding that this Court need not consider arguments raised on appeal that are
10 unsupported by citation to the record and transcript).
11 {54} We view Niccoli’s expert witness report, quoted above and properly disclosed
12 pursuant to Rule 1-026(B)(6)(a), to provide sufficient notice as to the substance of
13 Niccoli’s opinion testimony—that Appellant’s failure to complete its maintenance
14 obligation caused (1) a backup of water at the Bridge, (2) storm water to jump the
15 channel upstream and downstream from the Bridge, and (3) damage to Appellees’
16 property. Inasmuch as Niccoli offered testimony consistent with this disclosed theory,
17 it was not subject to the district court’s order to strike. An example of such testimony
18 includes:
30
1 Appellees’ Counsel: So, do you have an opinion as to how that
2 stream was reacting upstream when the water
3 began topping the Bridge and then topped it a
4 little more and then the tree actually impacted
5 the Bridge? What was going on back
6 upstream?
7 Niccoli: Back upstream, because again the
8 maintenance hadn’t occurred, the stream
9 channel was raised, five thousand CFS
10 coming through here. I think Mr. Allred keeps
11 his dikes at about six to nine feet deep, again
12 matching the part down here. So, this only
13 had about two or three feet of clearance that
14 night. There’s probably only about three feet
15 of clearance upstream also and there wouldn’t
16 be enough capacity in the channel and it
17 probably came up to the level of the dike. As
18 soon as it got to the level of the dike, it started
19 overtopping and the erosive forces would
20 have moved the dike away and caused
21 flooding of the field.
22 Appellees’ Counsel: What about flooding of the pond?
23 Niccoli: The pond also. . . . There’s two things that
24 probably happened at the pond. One which
25 could have been the backup of the water from
26 the plugging of the Bridge loosening the dikes
27 toward the center and into that. And then also
28 this pond here is also on the bend in the river,
29 so the maximum forces are going to be on that
30 outside. So with the stream level raised up
31 due to the lack of maintenance, that water
32 would have wanted to force its way around
33 this corner to the northeast of the upper pond
34 and would have again loosened the dike. And
31
1 it did obviously loosen it up and water flowed
2 into there.
3 Appellees’ Counsel: And then what happened below the Bridge to
4 what we call the lower pond or the fencing
5 around the lower pond?
6 Niccoli: Sure. . . . When the water flowed over the top
7 of the [Bridge] and spread out along the
8 road . . . the stream . . . flowed through the
9 property.
10 {55} Comments by the district court indicate that its ruling as to causation was
11 informed by both lay and expert witness testimony. With respect to Niccoli’s
12 testimony, it stated that
13 [the] expert testimony from [Appellees’] expert is, unequivocally, had
14 the cleaning been done . . . the waters would have stayed in the bounds
15 of the creek . . . and would not have overtopped the levees[.] . . . There
16 was also testimony that when the water overtopped the Bridge, it started
17 going on the northwest side of the road, and that that is what caused
18 damage in that area[.]
19 {56} Based on Niccoli’s testimony alone, substantial evidence supported the
20 existence of a causal relationship between Appellant’s violation of the Permanent
21 Injunction and damages suffered by Appellees. Appellant’s argument in this regard
22 is not well-taken.
32
1 CIVIL CONTEMPT SANCTIONS
2 {57} Appellant’s final substantive arguments relate to the district court’s award of
3 civil contempt sanctions. Appellant first argues that substantial evidence did not
4 support this award. As noted above, in reviewing whether substantial evidence exists
5 to support a district court’s ruling, we defer to the factual findings of the district court
6 but review the application of those facts to the law de novo. Benavidez, 2006-NMCA-
7 138, ¶ 21. Additionally, our appellate courts view the evidence and draw all
8 reasonable inferences in the light most favorable to the findings of the district court.
9 Cave v. Cave, 1970-NMSC-113, ¶ 4, 81 N.M. 797, 474 P.2d 480. Second, Appellant
10 argues that compensatory sanctions were not an appropriate remedy because neither
11 party prevailed in the underlying litigation. This Court reviews a district court’s
12 determination that a party prevailed at trial for an abuse of discretion. Mayeux v.
13 Winder, 2006-NMCA-028, ¶ 41, 139 N.M. 235, 131 P.3d 85. We address Appellant’s
14 arguments in turn.
15 {58} “The elements necessary for a finding of civil contempt are: (1) knowledge of
16 the court’s order, and (2) an ability to comply.” In re Hooker, 1980-NMSC-109, ¶ 4,
17 94 N.M. 798, 617 P.2d 1313. Although periodically discussed in our appellate
18 opinions, neither willfulness nor intent is an element of civil contempt. Spear v.
19 McDermott, 1996-NMCA-048, ¶ 41, 121 N.M. 609, 916 P.2d 228. As such,
33
1 Appellant’s argument that the district court’s characterization of Appellant’s conduct
2 as a “willful decision” requires that we consider “willfulness” as an element of civil
3 contempt is misplaced.
4 {59} Appellant does not contest that it had knowledge of the Permanent Injunction.
5 Appellant does, however, argue that “[t]here was no evidence presented to the district
6 court to suggest that . . . [Appellant] ever had the ability to comply with the
7 [Permanent Injunction.]” In support of this argument, Appellant states, without
8 citation to the record, that “[a]ll the evidence presented to [the] district
9 court . . . demonstrated that although [Appellant] was attempting to comply with the
10 [Permanent Injunction], continuing issues regarding the availability of manpower and
11 equipment, coupled with weather, delayed compliance.” See Rule 12-213(A)(4)
12 (requiring the appellant to provide citations to the record proper in support of each
13 argument).
14 {60} This argument, which advances Appellant’s theory that it was unable to comply
15 with the Permanent Injunction, improperly shifts the burden of proof from Appellant
16 to Appellees. See Spear, 1996-NMCA-048, ¶ 31 (“[T]he contemnor has the burden
17 of proof concerning inability to comply with a court order. . . . [T]his burden extends
18 to the self-inducement issue; that is, the contemnor has the burden of proving not only
19 that it [was] impossible for him to comply, but that he did not create the
34
1 impossibility.” (citation omitted)). Whatever the evidence was at trial, it clearly did
2 not impress upon the district court that circumstances related to weather and resource
3 allocation created a situation in which Appellant was unable to comply. Additionally,
4 Appellant did not request that the district court make such a finding in its proposed
5 findings of fact and conclusions of law. The district court expressly concluded that
6 “[Appellant’s] decision not to allocate sufficient resources . . . and [its] decision to
7 not continuously prosecute the maintenance . . . was a deliberate, conscious
8 decision[.]” This factual finding indicates that neither weather nor a lack of available
9 resources created a situation in which Appellant was unable to comply with the
10 Permanent Injunction. We defer to the factual findings of the district court.
11 {61} Appellant had the burden of proving that it was unable to comply with the
12 Permanent Injunction. Its attempt to shift that burden of proof to Appellees,
13 necessitating that Appellees prove that Appellant was able to comply, is misplaced
14 and constitutes a mischaracterization of our civil contempt jurisprudence.
15 {62} Appellant’s “prevailing party” argument correctly articulates our general rule
16 that “compensatory sanctions [are] only available if petitioner wins the action in the
17 original [law]suit.” Rhinehart v. Nowlin, 1990-NMCA-136, ¶ 28, 111 N.M. 319, 805
18 P.2d 88. However, its claim that the parties’ entry into the Settlement Agreement and
35
1 voluntary dismissal of the underlying case resulted in a circumstance in which neither
2 party “won” in the underlying case is not compelling.
3 {63} The prevailing party in litigation is “[t]he party to a suit who successfully
4 prosecutes the action or successfully defends against it, prevailing on the main issue,
5 even though not necessarily to the extent of his original contention.” Mayeux, 2006-
6 NMCA-028, ¶ 41 (internal quotation marks and citation omitted). As discussed
7 above, the district court entered an enforceable judgment, in the form of the
8 Permanent Injunction, on January 18, 2013. The Permanent Injunction imposed
9 mandatory maintenance obligations on Appellant, as requested in the initial complaint
10 and granted in the district court’s preliminary injunction. The entry of the Permanent
11 Injunction was “the main issue” in the underlying lawsuit. Id. Because Appellees’
12 claims arose from a violation of the Permanent Injunction, the district court did not
13 abuse its discretion in concluding that compensatory sanctions were an appropriate
14 remedy for contempt.
15 CALCULATION OF DAMAGES
16 {64} Finally, Appellant claims that the district court erred in its calculation of
17 damages. The district court ruled that Appellees were entitled to recover actual losses
18 in the amount of $408,764. Appellant argues on appeal that the appropriate method
19 to calculate damages to real property “is the difference between the value of the
36
1 property immediately before the occurrence and immediately after.” See UJI 13-1819
2 NMRA (“You shall determine what was the value of the property immediately before
3 the occurrence and immediately after the occurrence. The difference between these
4 two figures is the legal measure of damages to real property.”). We believe that
5 Appellant’s argument is largely misplaced.
6 {65} As a general rule, the remedy for civil contempt is “[j]udicial sanctions . . . to
7 compensate the complainant for losses sustained.” State ex rel. Apodaca v. Our
8 Chapel of Memories of N.M., Inc., 1964-NMSC-068, ¶ 10, 74 N.M. 201, 392 P.2d
9 347. The losses sustained by Appellees, as indicated by the district court’s findings
10 of fact and conclusions of law, were to personal property and improvements,
11 including crops, livestock, irrigation systems, flood control structures, and fences. See
12 Branch v. Walker, 1952-NMSC-080, ¶ 7, 56 N.M. 594, 247 P.2d 172 (describing
13 “farming implements, livestock and . . . crops” as personal property). The appropriate
14 method for calculating damages to personal property is the cost of repair. See UJI 13-
15 1813 NMRA (“In determining [personal] property damages, if any, you may award
16 the reasonable expense of necessary repairs to the property which was damaged.”).2
2
17 UJI 13-1817 NMRA articulates an alternative method for calculating damages
18 to personal property. However, neither party offered any testimony or evidence as to
19 the diminution of value to Appellees’ personal property. Therefore, we utilize UJI 13-
20 1813 in our analysis.
37
1 {66} However, the district court also awarded compensatory sanctions in the amount
2 of $15,000 for work performed by Appellees prior to September 14, 2013. Work
3 performed by Appellees prior to the date on which they suffered damages ca
4 nnot be included as part of “the reasonable expense of necessary repairs to the
5 property which was damaged.” Id. While Appellees may be entitled to reimbursement
6 or payment for this work, they must attempt such recovery under an alternate legal
7 theory.
8 {67} Appellees suffered damages to personal property in the amount of $393,764.
9 As such, we affirm this portion of the award in Appellees’ favor. We reverse the
10 district court’s award of $15,000 for work performed by Appellees prior to September
11 14, 2013. To the extent that Appellant offered additional arguments related to
12 statutory limitations on damages in its docketing statement, these arguments are not
13 developed on appeal and are not considered by this Court. See State v. White, 1994-
14 NMCA-084, ¶ 1, 118 N.M. 225, 880 P.2d 322 (“Issues raised at earlier stages of the
15 appeal but not briefed are deemed abandoned.”).
16 ATTORNEY FEES AND COSTS
17 {68} Appellant filed a separate notice of appeal related to the district court’s order
18 denying its objection to Appellees’ attorney fees affidavit and cost bill. Appellant
19 filed a docketing statement addressing these issues. The background section of
38
1 Appellant’s brief in chief includes discussion of the district court’s award of attorney
2 fees and costs. This section generally asserts Appellant’s claims that the district court
3 erred by (1) awarding costs designated as non-recoverable by Rule 1-054(D)(3)
4 NMRA, (2) awarding attorney fees for clerical work, and (3) failing to reduce expert
5 witness fees. However, neither the brief in chief nor the reply brief offers any legal
6 argument on these topics. Given the filing of a separate notice of appeal and
7 docketing statement, and discussion in the background section of the brief in chief,
8 we are unclear whether this omission was intentional or inadvertent. Regardless,
9 Appellant has abandoned these issues on appeal. See White, 1994-NMCA-084, ¶ 1.
10 CONCLUSION
11 {69} For the foregoing reasons, we affirm in part but reduce the award of civil
12 contempt damages in favor of Appellees to $393,764.
13 {70} IT IS SO ORDERED.
14 ________________________________
15 JAMES J. WECHSLER, Judge
39
1 WE CONCUR:
2 ________________________________
3 MICHAEL E. VIGIL, Chief Judge
4 ________________________________
5 JONATHAN B. SUTIN, Judge
40