PS Commercial Play, L.L.C. v. Harp Contrs., Inc.

[Cite as PS Commercial Play, L.L.C. v. Harp Contrs., Inc., 2017-Ohio-4011.]




                             IN THE COURT OF APPEALS OF OHIO
                                SECOND APPELLATE DISTRICT
                                    MONTGOMERY COUNTY

 PS COMMERCIAL PLAY, LLC                              :
                                                      :
         Plaintiff-Appellee                           :     C.A. CASE NO. 27253
                                                      :
 v.                                                   :     T.C. NO. 16-CV-2584
                                                      :
 HARP CONTRACTORS, INC., et al.                       :     (Civil Appeal from
                                                      :      Common Pleas Court)
         Defendants-Appellants                        :
                                                      :

                                              ...........

                                              OPINION

                 Rendered on the ___26th ___ day of _____May_____, 2017.

                                              ...........

DANIEL A. BROWN, Atty. Reg. No. 0044132, 204 S. Ludlow Street, Suite 300, Dayton,
Ohio 45402
      Attorney for Plaintiff-Appellee

ANDREW J. NATALE, Atty. Reg. No. 0042110 and NORA E. LOFTUS, Atty. Reg. No.
0079985, 200 Public Square, Suite 3000, Cleveland, Ohio 44114
     Attorneys for Defendant-Appellant Harp Contractors, Inc.

                                             .............

DONOVAN, J.

                This matter is before the Court on the Notice of Appeal of Harp Contractors,

Inc. (“Harp”), filed September 6, 2016. Harp appeals from the trial court’s August 9, 2016

decision overruling “Defendant’s Motion to Stay Pending Arbitration.” We hereby affirm
                                                                                         -2-


the judgment of the trial court.

              On May 23, 2016, PS Commercial Play, LLC, DBA Play & Park Structures

(“Play & Park”), filed a Complaint against Harp and Ohio Farmers Insurance Co. (“Ohio

Farmers”). The Complaint provides that “Harp was the prime contractor on a public

works project undertaken by Harp with the Ohio Facilities Commission (‘OSFC’) and the

Northmont City School District Board of Education (‘Northmont’) commonly known as

Northmont City Schools – Kleptz Early Learning Center (‘the Project’) on the real property

located at 1100 National Road, Clayton, OH 45315.” According to the Complaint, “Play

& Park was the subcontractor of Harp on the Project,” and a copy of the March 10, 2014

Subcontractor Agreement is attached to the complaint. The Complaint alleges that in “its

contract with the OSFC and Northmont, and pursuant to Ohio Revised Code Section

153.54, Harp was required to provide a Payment Bond for the Project,” and a copy of the

Payment Bond is also attached to the complaint.         Play & Park asserted that Ohio

Farmers was the surety on the Payment Bond.

             The Complaint alleges that Play & Park “has provided materials for the

Project for which it has not been paid,” and that it “is owed the entire amount of the

Subcontract Agreement, the principal sum of $117,285.96.” According to the complaint,

Play & Park “has demanded payment from Harp and Harp has failed or otherwise refused

to pay the sums due and owing.” The complaint provides that Play & Park also “notified

Ohio Farmers of the amount due in accordance with” R.C. 153.56(A), and that Ohio

Farmers has refused to pay the amount due. In Count I of its Complaint, Play & Park

asserts that “Harp’s failure to pay Play & Park for labor performed and/or material supplied

on the Project constitutes a breach of contract.” In Count II, Play & Park asserts that
                                                                                        -3-


“Ohio Farmers owes Play & Park the principal sum of $117,285.96 under the Payment

Bond.” In Count III, Play & Park asserts that Harp has been unjustly enriched to Play &

Park’s detriment.

            The attached Subcontract Agreement identifies Harp as the Contractor and

Play & Park as the Subcontractor. Article 4, paragraph 4.1 provides in part: “Payments

generally will be made within 45 days of Contractors billing to Owner for Subcontractor’s

work * * *.” Article 10, paragraph 10.7 thereof provides in part as follows:

              In Contractor’s sole discretion, any and all claims or disputes

       between the Contractor and the Subcontractor arising out or relating to the

       Agreement or the Contract Documents, or the breach thereof, shall be

       decided by in accordance with the Construction Industry Arbitration Rules

       of the American Arbitration Association currently in effect unless the parties

       mutually agree otherwise. Notice of the demand for arbitration shall be

       filed in writing with the other party to this Agreement and with the American

       Arbitration Association and shall be made within a reasonable time after the

       dispute has arisen. * * *

            On June 23, 2016, a “Stipulated Leave to Plead” was filed which provides:

“We, the attorneys for the respective parties, do hereby stipulate that Defendants [Harp]

and [Ohio Farmers] shall have an additional thirty (30) days, until July 25, 2016 to move,

plead or otherwise answer Plaintiff’s Complaint.”

            On July 25, 2016, “Defendants’ Joint Answer to Complaint and Harp

Contractors, Inc.’s Statement regarding Counterclaims” (“Answer”) was filed, along with

“Defendants’ Motion to Stay Pending Arbitration” (“Motion”). The Answer provides in part
                                                                                           -4-


that “Defendants state that Play & Park’s work was untimely and defective, and Harp has

not received payments from the owners for Play & Park’s work.” The Answer asserts the

following defense: “Play & Park’s claims are subject to mandatory and binding arbitration

per the express written subcontract between the parties.” The Answer further contains

the following statement: “Harp has claims against Play & Park that are covered by the

arbitration provision in the Subcontract, and Harp reasserts its right to pursue those

claims through arbitration as set forth in Harp’s Motion to Stay * * *. In the event that this

Court denies the Motion to Stay, Harp requests fourteen (14) days leave following the

entry of the Order denying the Motion to assert its counterclaims against Play & Park.”

             The Motion provides that “Harp must be permitted to exercise its contractual

right to have Play & Park’[s] claims decided through mandatory and binding arbitration,

as required by the arbitration agreement Play & Park agreed to in writing.” According to

the Motion, “[i]n addition to the arbitration provision, the Subcontract also includes a ‘pay

if paid’ provision that states that Harp is not required to pay Play & Park for any work

unless and until Harp receives payment from the owner.” The Motion further provides

that the “Project owner has made claims against Harp relating to deficiencies in Play &

Park’s work and has withheld payment from Harp as a result of those alleged deficiencies,

which form the basis of Harp’s counterclaims against Play & Park.” The Motion provides

that Harp is not in default in proceeding with arbitration. The Motion provides as follows:



              For over a year, Harp has taken every effort to get the owner to

       release funds to Harp, including the mandatory and lengthy administrative

       claims process.     In an effort to mitigate its damages, including those
                                                                                             -5-


       against Play & Park, as alleged by the owner, Harp has continuously been

       investigating and working to try to resolve claims upstream with the owner

       so that it could then try to resolve claims downstream with the

       subcontractors.       For these reasons, Harp had not previously filed

       arbitration. However, since it does not appear that Harp will be able to

       resolve its claims with Play & Park at this time, it will be filing an arbitration

       demand.

                It is worthy to note that prior to filing its lawsuit, Play & Park did not

       request from Harp confirmation as to whether Harp would select arbitration

       to resolve the dispute, as customarily happens in the construction industry

       when arbitration is at one party’s election.        Typically, when a contract

       includes an arbitration provision that one party can elect at its sole

       discretion, or both parties must mutually agree upon, there is a pre-suit

       request from one party to the other to confirm whether the dispute will

       proceed to arbitration. That did not happen here.

Finally, the motion provides that Play & Park’s bond claim must also be stayed pending

arbitration.

               On July 26, 2016, the trial court issued a default notice which provides that

Harp and Ohio Farmers are in default for answer or appearance.

               On August 4, 2016, “Plaintiff’s Response to Defendant’s Motion to Stay

Pending Arbitration” was filed. Play & Park asserted that Harp’s motion should be denied

because Harp “waited far too long to initiate an arbitration proceeding, and that delay

must be considered a waiver of Defendant’s right to pursue a resolution of Plaintiff’s
                                                                                          -6-


claims through arbitration.” Play & Park asserted that it “provided labor and materials for

the Project during the time period of July 2014 through November 2014 for which it has

not been paid.    It is Play & Park’s understanding that the Project was considered

substantially complete in March 2015.” Play & Park asserted that it then “made several

demands for payment to Harp that were ignored. After waiting several months for a

potential resolution of the matter with Harp, Play & Park provided a written notice dated

October 16, 2015 to Ohio Farmers of its claim in the amount of $117, 285.96 against the

Bond,” which Ohio Farmers denied in correspondence dated October 21, 2015. Play &

Park asserted that the arbitration clause at issue “cannot be considered a mandatory

arbitration clause because its invocation is based on the contractor’s discretion and that

the parties have not otherwise agreed. Only Harp has discretion to have the dispute

referred to arbitration. Until Harp initiates the process, Play & Park, as the subcontractor,

has no notice that it should not file suit.” Play & Park asserted that “Harp’s stated

‘intention’ to file for arbitration is not enough to justify its Motion to Stay.” Play & Park

further argued that “[b]ecause the failure to provide a demand for arbitration within a

reasonable time after the dispute arose is contrary to the requirements of the [arbitration]

clause, such delay is properly construed as a default in its exercise of discretion to

demand binding arbitration of the dispute with Play & Park * * *.”

              In overruling Harp’s motion, the trial court determined as follows:

              Upon review, the Court finds Plaintiff’s arguments to be persuasive.

       Specifically, the Court notes that, pursuant to R.C. 2711.02(B), a stay

       pending arbitration is appropriate when “the applicant for the stay is not in

       default in proceeding with arbitration.” However, here, Defendant did not
                                                                                              -7-


       demonstrate any intention to proceed with arbitration until more than a year

       after the project at issue had been substantially completed, and it was

       aware that Plaintiff was not satisfied with Defendant’s performance under

       the contract. Accordingly, the Court finds that Defendant did not pursue

       arbitration within a “reasonable time,” as required by the parties’ contractual

       agreement.

              The docket reflects that on August 22, 2016, the trial court referred the

matter to mediation, and on October 27, 2016, a “Termination of Mediation – Transfer of

Case from Mediation; Mediation Conference Date Vacated” was filed. The Termination

provides: “As there are many appeals pending, parties want to wait until they hear the

outcome of said appeals before coming to mediation.”

              Harp asserts the following assignment of error:

              THE TRIAL COURT ERRED AS A MATTER OF LAW IN DENYING

       APPELLANT HARP CONTRACTORS, INC.’S (“HARP”) MOTION TO

       STAY PENDING ARBITRATION BECAUSE THE CONTRACT BETWEEN

       HARP AND APPELLEE PS COMMERCIAL PLAY LLC dba PLAY & PARK

       STRUCTURES (“PLAY & PARK”) CONTAINS A MANDATORY AND

       BINDING ARBITRATION PROVISION, AND HARP NEITHER WAIVED ITS

       RIGHT TO ARBITRATE NOR WAS IN DEFAULT IN PROCEEDING WITH

       ARBITRATION.

               Harp asserts that it “asserted its right to arbitrate by filing its Motion to Stay

simultaneously with its Answer,” and that it “has not participated in litigation.” Harp

asserts that it is not required to “initiate a dispute with Play & Park by filing a demand for
                                                                                              -8-


arbitration.” According to Harp, if “Park & Play had decided to file suit earlier than May

2016, Harp would have asserted its right to arbitration earlier as well.” Harp argues that

the “Subcontract does not require Harp to file a demand for arbitration in order to enforce

its right to arbitrate the dispute.”

               Play & Park responds that “the trial court properly concludes that Harp did

not promptly assert its right to arbitration when Play & Park demanded payment of the

Subcontract amount after the Project was substantially completed in March 2015.”

               As this Court has previously noted, “ ‘Ohio has a strong public policy

favoring arbitration.’ * * *. Arbitration is favored because it allows parties to bypass

expensive and time-consuming litigation and ‘provides the parties thereto with a relatively

expeditious and economical means of resolving a dispute.’ * * *.” Westerfield v. Three

Rivers Nursing & Rehab. Ctr., 2d Dist. Montgomery No. 25347, 2013-Ohio-512, ¶ 16.

“Indeed, the Ohio courts recognize a ‘presumption favoring arbitration’ that arises ‘when

the claim in dispute falls within the scope of the arbitration provision.’ * * *.” Taylor Bldg.

Corp. of Am. v. Benfield, 117 Ohio St.3d 352, 2008-Ohio-938, 884 N.E.2d 12, ¶ 27.

               “The Ohio Arbitration Act sets forth a trial court's role in construing and

enforcing arbitration agreements.” Lindsey v. Sinclair Broadcast Group, Inc., 2d Dist.

Montgomery No. 19903, 2003-Ohio-6898, ¶ 15. R.C. 2711.02(B) provides:

               If any action is brought upon any issue referable to arbitration under

       an agreement in writing for arbitration, the court in which the action is

       pending, upon being satisfied that the issue involved in the action is

       referable to arbitration under an agreement in writing for arbitration, shall on

       application of one of the parties stay the trial of the action until the arbitration
                                                                                           -9-


       of the issue has been had in accordance with the agreement, provided the

       applicant for the stay is not in default in proceeding with arbitration.

               “Default” is “the omission or failure to perform a legal or contractual duty.”

Black’s Law Dictionary 376 (5th Ed. 1979).

              “In determining whether a trial court has properly ruled upon a motion to

stay the proceedings and compel arbitration, the standard of review is whether the order

constitutes an abuse of discretion. Zachary v. Crocket Homes, Inc., 2003-Ohio-5237, ¶

15.” Lindsey, ¶ 19. As this Court has previously noted:

              “Abuse of discretion” has been defined as an attitude that is

       unreasonable, arbitrary, or unconscionable.        Huffman v. Hair Surgeon,

       Inc., 19 Ohio St.3d 83, 482 N.E.2d 1248 (1985).                 A decision is

       unreasonable if there is no sound reasoning process that would support that

       decision.    AAAA Enterprises, Inc. v. River Place Community Urban

       Redevelopment Corp., 50 Ohio St.3d 157, 553 N.E.2d 597 (1990);

       Feldmiller v. Feldmiller, 2d Dist. Montgomery No. 24989, 2012-Ohio-4621,

       ¶ 7.

Routson-Gim-Belluardo, v. Jefferson Twp. Local School Dist. Bd. of Educ., 2016-Ohio-

1265, 61 N.E.3d 914, ¶ 27 (2d Dist.)

               Paragraph 10.7 of the Subcontract Agreement does not contain a

mandatory and binding arbitration provision but rather granted Harp the discretion to

arbitrate any and all claims or disputes between it and Play and Park relating to the

Subcontract Agreement. If Harp chose to do so, Paragraph 10.7 set forth a contractual

duty that “Notice of the demand for arbitration shall be filed in writing with the other party
                                                                                             -10-

to this Agreement and with the American Arbitration Association and shall be made within

a reasonable time after the dispute has arisen.” Harp does not dispute Play & Park’s

assertion that the work herein was substantially completed by March of 2015. In its reply

brief, Harp asserts that if “the trial court’s decision is upheld, it would essentially allow all

claimants to wait ‘more than a year after the project at issue had been substantially

completed’ before filing litigation in order to avoid an arbitration provision to which that

claimant agreed to be bound by the clear and unambiguous terms of a written contract.”

It was up to Harp to pursue arbitration by filing a demand for arbitration within a

reasonable time after the dispute arose, namely after Play & Park submitted requests for

payment for materials and labor that remained unpaid. Harp does not assert that it filed

a notice of demand for arbitration, and there is no evidence that Harp initiated the

arbitration process as required by Paragraph 10.7.

              We conclude that Harp is in default in proceeding with arbitration for its

failure to file a demand for arbitration within a reasonable time after its dispute with Play

& Park arose. In other words, an abuse of discretion is not demonstrated, and Harp’s

sole assignment of error is overruled. The judgment of the trial court is affirmed.

                                           .............

HALL, P.J. and WELBAUM, J., concur.

Copies mailed to:

Daniel A. Brown
Andrew J. Natale
Nora E. Loftus
Hon. Dennis J. Adkins