Notice: This opinion is subject to correction before publication in the PACIFIC REPORTER.
Readers are requested to bring errors to the attention of the Clerk of the Appellate Courts,
303 K Street, Anchorage, Alaska 99501, phone (907) 264-0608, fax (907) 264-0878, email
corrections@akcourts.us.
THE SUPREME COURT OF THE STATE OF ALASKA
JAMES WILLIAM DAGGETT and )
NADIA TORA DAGGETT, )
) Supreme Court Nos. S-15799/15819
Appellants and )
Cross-Appellees, )
) Superior Court No. 3HO-11-00359 CI
v. )
) OPINION
RICHARD L. FEENEY, )
) No. 7179 – June 16, 2017
Appellee and )
Cross-Appellant. )
)
Appeal from the Superior Court of the State of Alaska, Third
Judicial District, Homer, Charles T. Huguelet, Judge.
Appearances: James William Daggett and Nadia Tora
Daggett, pro se, Anchorage, Appellants. Lindsay Wolter,
Homer, for Appellee.
Before: Stowers, Chief Justice, Winfree, Maassen, Bolger,
and Carney, Justices.
CARNEY, Justice.
I. INTRODUCTION
A property owner cancelled a contract to install a wind turbine on his
property and sued the contractor to recover his down payment. The contractor filed a
counterclaim for breach of contract. The superior court concluded that the contractor
was required to be licensed by the State and had misrepresented its licensing status. It
also concluded that the contractor could not maintain the counterclaim because the
contractor was unregistered. The court ordered the contract rescinded and the contractor
to return the down payment less a setoff covering costs incurred in the transaction. The
contractor failed to pay and the court amended the judgment to include the contractor’s
individual owners and a successor company. The contractor’s individual owners appeal
the licensing determination and the amended judgment. The property owner cross-
appeals the setoff calculation. We conclude that the court erred only in its setoff
calculation.
II. FACTS AND PROCEEDINGS
A. Facts
This case involves a cancelled contract between Richard Feeney and
Alaskan Wind Industries (AWI), a renewable energy contractor, for the sale and
installation of a wind turbine on Feeney’s property in Homer. AWI was the trade name
for Daggett LLC, owned by James and Nadia Daggett. The Daggetts owned several
similarly named organizations, as well as Standard Steel, Inc.
Feeney and his wife, Elizabeth Bashaw, began discussing the purchase of
a wind turbine with AWI representatives in the summer of 2009. In these discussions
AWI was often represented by sales representative Erik Schreier and occasionally by
Nadia Daggett. The parties dispute whether Schreier told Feeney and Bashaw that AWI
was licensed1 and bonded as a steel erection contractor and whether Schreier promised
to make sure neighboring landowners would not oppose the turbine’s installation. But
the parties agree that they discussed AWI’s successful installation of another turbine in
the same area without opposition from neighboring landowners.
1
The parties and the superior court frequently used the term “license” to refer
to registration under AS 08.18.011-.061.
-2- 7179
The parties ultimately signed a contract in October 2010, with Schreier
signing on behalf of AWI. The contract was on AWI letterhead and did not mention
Daggett LLC. It required AWI to provide and install a wind turbine, a 49-foot tower,
and an inverter. The contract expressly affirmed that AWI was “qualified by law as a
licensed steel erector in the state of Alaska” and allocated to Feeney the responsibility
for “meet[ing] all builders[’] permit requirements, variances, [and] height restriction
waivers.”
Bashaw paid the 60% down payment of $32,880 immediately after the
contract was signed. AWI then ordered the wind turbine from a California-based
supplier and had it shipped to Alaska. AWI began digging the turbine’s foundation in
November 2010. The work was soon stopped by Bashaw because a neighbor was
concerned that the 49-foot turbine would violate a subdivision land-use covenant. AWI
agreed that Feeney and Bashaw could take a few months to resolve the conflict with their
neighbor.
In late November the neighbor formally notified Feeney and Bashaw of a
land-use covenant that prohibited structures over 35 feet tall in the subdivision and
threatened legal action if the project moved forward. In December Bashaw emailed
Nadia Daggett saying, “We need to get this contract cancelled as soon as possible,
especially since it is illegal and you were aware that was so when it was signed.” Despite
discussions during the first half of 2011 to try to reach a mutually agreeable solution
regarding contract cancellation and refund, the parties were unable to reach an
agreement.
B. Proceedings
Feeney filed suit in early December 2011, naming AWI, James Daggett,
and Nadia Daggett as the defendants. Feeney alleged that AWI and its representatives
had “assured” him that they were familiar with the subdivision covenants, that the wind
-3- 7179
turbine would not violate them, and that AWI would check with Feeney’s neighbors to
make sure they did not object to the turbine. Feeney asked the court to rescind the
contract and order the return of his down payment, “less any offset which the court
deems appropriate”; he also requested an accounting to determine the offset amount.
AWI’s answer admitted that it had entered into a contract with Feeney and
asserted wrongful rejection of the turbine delivery as an affirmative defense. AWI also
filed a counterclaim, alleging that Feeney had materially breached the contract by
refusing to accept full performance and pay the full price for the turbine. James and
Nadia Daggett filed separate answers raising affirmative defenses that they were not
party to the contract between Feeney and AWI and were not liable to Feeney under
AS 10.50.265, which limits LLC members’ liability to third parties.2
Feeney replied to AWI’s counterclaim and amended his complaint seeking
to pierce the corporate veil and reach the Daggetts personally because of some confusion
about the Daggetts’ various corporate entities.3 Feeney expanded his claim for contract
rescission, alleging that rescission was justified because “AWI was not registered as a
general or specialty contractor with the State of Alaska” when it entered the contract, as
required by state law. Having discovered that AWI was no longer a registered business
and that the Daggetts had set up a new entity under the name Standard Steel, Inc., Feeney
also sought to add Standard Steel as a defendant.
2
AS 10.50.265 provides that “[a] person who is a member of a limited
liability company or a foreign limited liability company is not liable, solely by reason of
being a member, under a judgment, decree, or order of a court, or in another manner, for
a liability of the company to a third party.”
3
Because the superior court ultimately concluded that the correct entity was
Daggett LLC d/b/a Alaskan Wind Industries, we use that name throughout.
-4- 7179
A two-day bench trial took place in Homer in November 2012. Feeney
testified that he had specifically asked Schreier whether AWI was a licensed and bonded
contractor and that Schreier had affirmed AWI was licensed and bonded. Feeney
explained that this information was important to him in deciding to purchase the wind
turbine. Schreier testified that Feeney had never asked about AWI’s licensing status.
Nadia Daggett testified that she and James had believed wind energy
installers were not required to be licensed as construction contractors at the time of the
contract with Feeney. She stated that “[i]t was industry standard” not to carry a license
at the time and claimed that none of AWI’s competitors had done so. Nadia also testified
that she had contacted the State and had been told there was no North American Industry
Classification System (NAICS)4 code for renewable energy installers. She further
testified that in late 2010 a state licensing inspector had told them that renewable energy
contractors would be required to be licensed beginning in 2011.
The superior court issued a written opinion in favor of Feeney in July 2013.
The court decided that Feeney was entitled to rescission on the ground of
misrepresentation5 because AWI had misrepresented its licensing status, noting that “the
4
AS 43.70.020(a)(2) requires business licenses to include the lines of
business to be conducted, and the State uses some NAICS codes to determine lines of
business for this purpose. What is “Line of Business” or “LOB”? and “What is
“NAICS”?, in Line of Business/Alaska NAICS Code, DEP’T OF COMMERCE, CMTY., AND
ECON. DEV., DIV. OF CORPS., BUS. & PROF’L LICENSING,
https://www.commerce.alaska.gov/web/cbpl/BusinessLicensing/AKLOBandNAICS.aspx
(last visited Apr. 7, 2017).
5
See Foster v. Cross, 650 P.2d 406, 409 (Alaska 1982) (first citing
Cousineau v. Walker, 613 P.2d 608, 612 (Alaska 1980); then citing Halpert v. Rosenthal,
267 A.2d 730, 733 (1970); then citing RESTATEMENT (SECOND) OF CONTRACTS § 164(1)
(1981)) (holding that, to void a contract, a party must show that the other party “made
a false representation of material fact which was actually and justifiably relied upon”).
-5- 7179
[c]ontract itself expressly establishe[d] that ‘[AWI was] qualified by law as a licensed
steel erector in the State of Alaska.’ ” The court concluded that wind energy installers
were required to be licensed as steel erection contractors because tower-mounted wind
turbines qualify as “steel towers and pylons” under regulations6 adopted pursuant to
AS 08.18.0137 and AS 08.18.024.8 And the court found that AWI had been “neither
licensed nor bonded as a ‘steel erection contractor’ ” when the contract was executed.
The superior court noted that there was “evidence to suggest” that AWI had
known it needed to be licensed because it had previously held a specialty contractor
license which expired in 2009, before execution of the contract. The court found AWI’s
representation of its licensing status to be a misrepresentation of a material fact, and it
pointed to Feeney’s testimony that he would not have entered into the contract without
it. The court therefore concluded that Feeney was entitled to rescission of the contract
based on AWI’s misrepresentation of its non-licensed status because he “ ‘actually and
justifiably relied upon’ a ‘false representation of a material fact.’ ”9 The court
accordingly ruled that Feeney was entitled to reimbursement of his down payment.
But the superior court noted that Feeney’s position on the issue of licensing
appeared “pretextual.” It believed Feeney had “unilaterally cancelled” the contract to
avoid the threatened suit from his neighbor and doubted he would have objected to
6
See 12 Alaska Administrative Code (AAC) 21.510(a)(3) (2012).
7
AS 08.18.013 authorizes regulations that categorize and require the
registration of contractors.
8
AS 08.18.024 describes specialty contractors.
9
See Foster, 650 P.2d at 409 (citing Cousineau, 613 P.2d at 612; Halpert,
267 A.2d at 733; RESTATEMENT (SECOND) OF CONTRACTS § 164(1)).
-6- 7179
AWI’s non-licensed status without that threat. The court suggested it would take this
into account as an equitable consideration in determining AWI’s recovery amount.
The superior court also addressed AWI’s counterclaim for breach of
contract. Although it was “inclined to entertain the merits” of AWI’s counterclaim
because Feeney’s termination of the contract was “suspect,” the court concluded that the
counterclaim was barred by AS 08.18.151, which provides that a contractor “may not
bring an action . . . for breach of a contract for which registration is required” unless the
contractor can show it “was a registered contractor . . . at the time of contracting.”
Having already decided AWI was required to be licensed as a steel erection contractor
and was not licensed at the time of the contract, the superior court concluded AWI was
barred from bringing the counterclaim. The court rejected the Daggetts’ argument that
AWI was exempt from AS 08.18.151 under the “finished products” exemption expressed
in AS 08.18.161(5), because the wind turbine “bec[a]me a permanent, fixed part of a
structure” and was not a finished product as contemplated in the exemption.
Nonetheless the superior court explained that even an unlicensed contractor
may recover “any sums which may be equitably due [it]” through a setoff against the
damages to be paid. It relied on Sumner Development Corp. v. Shivers, in which we held
that a setoff against the plaintiff’s recovery is appropriate if a contract has been partially
performed and the plaintiff would receive a windfall from retaining the benefit of the
partially performed work in addition to receiving contract damages.10 Here the court
allowed a setoff because Feeney was “not without unclean hands” and “AWI suffered
substantial financial loss as a result of” Feeney’s cancelling the contract.
10
517 P.2d 757, 765-66 (Alaska 1974) (quoting S & Q Constr. Co. v. Palma
Ceia Dev. Org., 3 Cal. Rptr. 690, 692 (Cal. Dist. Ct. App. 1960)).
-7- 7179
The superior court determined that AWI was entitled to a setoff for any
resale costs, out-of-pocket costs, and incidental costs it had incurred in partially
performing the contract. It did not award a setoff for resale costs because it calculated
that AWI had not lost money on resale but instead made a small profit. The court
awarded out-of-pocket expenses that were incurred following execution of the contract,
which included commissions, the cost of shipping the turbine to Alaska, and the
materials, equipment, and labor used to begin creating the foundation. The court also
awarded certain incidental expenses mainly related to moving the turbine to its new
purchaser. The total setoff was $9,609.06.
The superior court expressly withheld judgment on the question whether
Feeney could seek recovery of his down payment from anyone other than AWI. But the
court concluded that if Feeney was not able to recover his reimbursement from AWI, it
would “consider whether Defendants James and Nadia Daggett, or any entity registered
to them or otherwise owned by them, should be held liable.”
In December 2013 the superior court issued a final judgment awarding
Feeney $23,270.94 in damages (the amount of the down payment minus AWI’s equitable
setoff), plus pre- and post-judgment interest, attorney’s fees, and court costs, for a total
of $36,010.15. The court authorized Feeney to seek to amend the judgment to permit
recovery from the other defendants if AWI failed to satisfy the judgment within 90 days,
suspending the ordinary timeline established by Civil Rule 59(f) and allowing Feeney
to file within 120 days of the entry of judgment.
When AWI did not satisfy the judgment within 90 days, Feeney filed a
motion to amend the final judgment, naming James Daggett, Nadia Daggett, and
Standard Steel as additional defendants. The Daggetts objected to both their individual
liability and that of Standard Steel. They also opposed the superior court’s decision to
allow Feeney to move to amend after the Alaska Civil Rule 59(f) time limit had expired.
-8- 7179
The superior court issued an amended final judgment in December 2014.
The court found that the “primary contractor entity” Feeney had contracted with was
Daggett LLC d/b/a AWI, but that Feeney had not had notice that Daggett LLC was the
principal because the contract named only AWI and “did not disclose the existence of”
Daggett LLC. And the court explained that because the contract only used the AWI
trade name, Feeney was not given notice that he was contracting with a limited-liability
entity. The court therefore concluded that James and Nadia Daggett were personally
liable to Feeney as agents of an undisclosed principal on the contract, with Erik Schreier
acting as their subagent.11
The superior court also concluded that Standard Steel was liable to Feeney
as AWI’s successor under the “mere continuation” and “continuity of enterprise”
exceptions to the general rule that a corporation is not liable for its predecessor’s acts.12
The court found that Standard Steel was “simply a change in name and corporate form”
from Daggett LLC, noting that Standard Steel continued the LLC’s renewable energy
and wind turbine installation business at the same address and website; that “[t]he
Daggetts remained the sole stockholders and officers of the new entity”; and that the new
entity did business as “Alaska’s Wind Industries,” a “negligible change” from its
previous name. The court thus concluded that Standard Steel was liable to Feeney as the
successor to AWI.
11
See Jensen v. Alaska Valuation Serv., Inc., 688 P.2d 161, 163 (Alaska
1984) (citing RESTATEMENT (SECOND) OF AGENCY, §§ 321, 322 (1958)) (“An agent who
makes a contract for an undisclosed or partially disclosed principal will be liable as a
party to the contract.”).
12
Savage Arms, Inc. v. W. Auto Supply Co., 18 P.3d 49, 55-56 (Alaska 2001)
(explaining doctrine of successor liability).
-9- 7179
James and Nadia Daggett represent themselves in this appeal of the superior
court’s initial decision issued in July 2013, the final judgment issued in December 2013,
and the amended final judgment issued in December 2014. They contest multiple
elements of these rulings. Feeney cross-appeals the court’s determination of AWI’s
setoff amount.
III. STANDARD OF REVIEW
“Interpretation of a statute is a question of law to which we apply our
independent judgment; we interpret the statute according to reason, practicality, and
common sense, considering the meaning of the statute’s language, its legislative history,
and its purpose.”13 For mixed questions of law and fact, including applications of agency
law,14 we review legal questions de novo and review factual findings for clear error.15
“A fact finding is not clearly erroneous unless the reviewing court has a definite and firm
conviction that a mistake has been made.”16
“We review the grant of an equitable remedy . . . for abuse of discretion,
but we review de novo any underlying questions of law and the application of law to
facts.”17
13
Adamson v. Municipality of Anchorage, 333 P.3d 5, 11 (Alaska 2014)
(citing Grimm v. Wagoner, 77 P.3d 423, 427 (Alaska 2003)).
14
See Foster v. Cross, 650 P.2d 406, 408 (Alaska 1982).
15
Diblik v. Marcy, 166 P.3d 23, 25 (Alaska 2007) (first citing Forshee v.
Forshee, 145 P.3d 492, 497 (Alaska 2006); then citing Keturi v. Keturi, 84 P.3d 408, 412
(Alaska 2004)).
16
Id. at 25-26 (citing Keturi, 84 P.3d at 412).
17
In re Estate of Fields, 219 P.3d 995, 1002 (Alaska 2009), as modified on
denial of reh’g (Dec. 16, 2009) (citing Riddell v. Edwards, 76 P.3d 847, 852 (Alaska
(continued...)
-10- 7179
Whether a party has standing to assert a given claim is a question of law
that we review de novo.18
IV. DISCUSSION
A. The Superior Court Did Not Err In Concluding That AWI Was
Required To Be Registered As A Specialty Contractor.
The Daggetts argue that the superior court was wrong to conclude AWI was
required to be registered as a specialty steel erection contractor, asserting that AWI was
exempted by an express exception covering contractors who install “finished products.”
Feeney counters that wind turbine installation does not fall under the finished products
exemption. We conclude that the superior court correctly interpreted the statute and
regulations.19
17
(...continued)
2003)).
18
Keller v. French, 205 P.3d 299, 302 (Alaska 2009) (citing St. Paul Church,
Inc. v. Bd. of Trs. of the Alaska Missionary Conference of the United Methodist Church,
Inc., 145 P.3d 541, 549-50 (Alaska 2006)).
19
In their statement of points on appeal, the Daggetts also challenge the
superior court’s finding that AWI misrepresented its licensing status and the court’s
subsequent conclusion that this misrepresentation was grounds for rescission. But they
do not explicitly contest these issues in their appellate briefing. In general, “issues not
briefed or only cursorily briefed are considered waived.” Shearer v. Mundt, 36 P.3d
1196, 1199 (Alaska 2001) (citing Adamson v. Univ. of Alaska, 819 P.2d 886, 889 n.3
(Alaska 1991)). Because self-represented litigants are held to a less demanding
procedural standard, we will consider a self-represented litigant’s argument if his or her
“briefing was such that [the court] could discern [the party’s] legal arguments and [the
opposing party] could reply to them.” Mitchell v. Mitchell, 370 P.3d 1070, 1083 (Alaska
2016) (alterations in original) (quoting Peterson v. Ek, 93 P.3d 458, 464 n.9 (Alaska
2004)). Feeney’s brief does not discuss the issues. Even under the more lenient standard
for self-represented litigants, the Daggetts have waived this issue on appeal.
-11- 7179
1. The statute requires registration.
Alaska Statute 08.18.171(4) defines a contractor as “a person who, in the
pursuit of an independent business, undertakes or offers to perform . . . or submits a bid
for a project to construct, alter, repair, move, or demolish a building . . . or any type of
fixed structure, including excavation and site development and erection of scaffolding.”
It further provides that “ ‘contractor’ includes a general contractor, builder, mechanical
contractor, specialty contractor, and subcontractor.” Alaska Statute 08.18.011 requires
all contractors to be registered with the Alaska Department of Commerce, Community,
and Economic Development.20 Alaska Statutes 08.18.013 and .024 authorize the
Department to register and issue licenses to contractors and specialty contractors. The
Department has adopted regulations defining 37 categories of specialty contractor.21 A
contractor who installs steel towers or pylons is considered a steel erection contractor.22
The superior court concluded that the 49-foot tower for the wind turbine qualifies as a
steel tower or pylon under this statutory framework and that AWI was therefore required
to be registered as a steel erection contractor.
The Daggetts do not contest that the wind turbine tower falls within this
category or that an installer of steel towers generally is required to register as a steel
erection contractor. Instead they argue that AWI was exempt from registration under
20
“A person may not submit a bid or work as a contractor until that person
has been issued a certificate of registration as a contractor by the department.”
AS 08.18.011(a). “Department” is defined as “the Department of Commerce,
Community, and Economic Development, unless the context indicates otherwise.”
AS 08.18.171(5).
21
See 12 AAC 21.200 (2010).
22
12 AAC 21.510. See 12 AAC 21.200 (31) (listing “Steel Erection
Contractor” as a type of specialty contractor).
-12- 7179
AS 08.18.161(5), which provides that the chapter governing contractor registration “does
not apply to . . . the sale or installation of finished products, materials, or articles of
merchandise that are not actually fabricated into and do not become a permanent, fixed
part of a structure.” The Daggetts argue that the wind turbine kit was a finished product
and AWI “would simply have been putting the pieces together and installing [the
turbine] on Feeney’s property.”
We have discussed this exemption only once before, in Industrial Power
&Lighting Corp. v. Western Modular Corp.23 Western Modular supplied pre-fabricated
homes that Industrial Power assembled on-site.24 We decided that AS 08.18.161(5) did
not apply to Western Modular because the section was “aimed at a supplier who actually
installs his [or her] products,” whereas “Western Modular had no installation
responsibilities” because the homes were installed by Industrial Power.25 Instead we
concluded that Western Modular was exempt under a different section of AS 08.18.161
that covered suppliers who “only furnished materials” without installing them.26
The Daggetts read Industrial Power to support their contention that AWI’s
wind turbine installation falls under the finished products exemption. But the Daggetts’
focus on this language is misplaced. In Industrial Power we inquired whether the
supplier installed the product in order to distinguish between two exemptions with
otherwise similar language.27 We did not suggest that any supplier who installed a
23
623 P.2d 291, 294-95 (Alaska 1981).
24
Id. at 292-93.
25
Id. at 295.
26
Id. at 294; see AS 08.18.161(7).
27
Indus. Power, 623 P.2d at 295.
-13- 7179
product would be exempt under AS 08.18.161(5); to do so would let the exception
swallow the rule.
Instead, as Feeney suggests, we must evaluate the provision’s full language,
which exempts “the sale or installation of finished products . . . that are not actually
fabricated into and do not become a permanent, fixed part of a structure.”28 Thus the
question is not only whether the turbine was to be installed but whether a turbine kit is
a “finished product[]” that “become[s] a permanent, fixed part of a structure.” This
language and related elements of the statutory structure indicate that a turbine becomes
a permanent, fixed structure within the meaning of this provision.
Alaska Statute 08.18.171(4) defines “contractor” to include someone who
constructs or alters “any type of fixed structure, including . . . erection of scaffolding.”
A wind turbine affixed to a 49-foot tower is clearly a fixed structure in the plain sense
of the phrase, and towers have been recognized as “structures” in other statutory contexts
such as zoning codes.29 Moreover, when scaffolding, which is inherently temporary, is
considered a fixed structure under AS 08.18.171(4), a more permanent structure such as
a wind turbine must also be considered a fixed structure. As a fixed structure, the pole
and turbine would not fall under AS 08.18.161(5)’s exemption for finished products that
are not part of a fixed structure when installed.
The Daggetts point out that the turbine system is “a free[-]standing, finished
product that [is] not ‘fabricated’ into another structure,” perhaps implying that a fixed
structure product like a wind turbine is exempt because it is not made part of another
28
AS 08.18.161(5).
29
See Pruitt v. City of Seward, 152 P.3d 1130, 1133 (Alaska 2007) (citing
Seward City Code § 15.10.140, which defines “structure” as “[a]nything constructed or
erected on the ground or attached to something having location on the ground, including,
but not limited to, buildings, towers, and sheds,” but excluding short walls).
-14- 7179
structure.30 But this interpretation is unsustainable. The provision must be read as
exempting the installation of finished products that do not become a permanent, fixed
part of a structure or do not become permanent, fixed structures themselves. Feeney
notes that the construction of an entire house would be exempted from all contractor
regulations under the Daggetts’ interpretation because the house does not become part
of another fixed structure. Such a result would be nonsensical and would undermine
much of the chapter governing contractors, which was clearly intended to apply to the
construction of new houses and other structures in addition to modification of existing
structures.31 Alaska Statute 08.18.161(5)’s finished products exemption does not apply
to the Daggetts because we have already determined that the turbine becomes a fixed
structure.
Our decision in Industrial Power confirms this interpretation of the finished
products exemption. There we held that Industrial Power, the contractor that assembled
and installed the prefabricated houses on-site, was required to register as a contractor.32
The wind turbine kit that would have been assembled and installed by AWI to become
30
At oral argument James Daggett argued that among steel professionals,
“fabricate” has a specialized meaning: “to construct from raw materials” by cutting,
welding, and drilling them to build a structure. He considered AWI’s work to be simple
“assembly,” using hand tools, of components fabricated by the manufacturer. But
AS 08.18.161(5) applies to all kinds of finished products, so a specialized meaning, even
if proven, would not apply. See N. Alaska Envtl. Ctr. v. State, Dep’t of Nat. Res., 2 P.3d
629, 634 (Alaska 2000) (“[W]e construe terms according to their common usage, unless
a term has acquired a peculiar meaning due to statutory definition or judicial
construction.”). Although it does not affect our decision, it is understandable that, based
on his experience, James was familiar with a more specialized definition.
31
See AS 08.18.171(13) (defining “new home” for purposes of title 8, chapter
18).
32
Indus. Power, 623 P.2d at 295-97.
-15- 7179
a free-standing, fixed structure is analogous to the prefabricated houses in that case,
which were similarly assembled and installed by Industrial Power to become individual,
free-standing structures.
For these reasons we agree with the superior court that the finished products
exemption does not apply and that AWI was required to register as a steel erection
contractor.
2. Assuming it is relevant to our statutory interpretation, the
superior court did not clearly err in rejecting the Daggetts’
claim that renewable energy contractors were, in practice,
exempted by the State.
The Daggetts maintain that a state official told them renewable energy
installers did not need to be registered as contractors, impliedly arguing that the State had
interpreted the finished products exemption to include renewable energy installation.
They argue that the superior court erred in discounting Nadia’s testimony on this point
and dispute the court’s finding that they knew AWI needed to be licensed.
Assuming it is relevant to our interpretation, whether the State interpreted
contractor registration requirements to exclude renewable energy contractors at the time
of the contract is a question of fact; we therefore review the superior court’s findings for
clear error.33 Nadia testified at trial that it was industry standard for renewable energy
contractors not to carry a license and that AWI’s competitors who also installed wind
turbines were not licensed at the time. She also testified that a state employee in Juneau
told her there was no NAICS code for renewable energy, and that in late 2010 a state
licensing inspector told her that renewable energy contractors would need to be licensed
beginning in 2011.
33
Diblik v. Marcy, 166 P.3d 23, 25 (Alaska 2007) (citing Keturi v. Keturi, 84
P.3d 408, 412 (Alaska 2004)).
-16- 7179
It was the superior court’s task to determine the credibility of these
statements and weigh them against other evidence.34 The court heard no testimony by
representatives of the State, nor does the record reveal any other evidence of the State’s
position at the time. On the other hand, evidence suggesting the Daggetts knew AWI
needed to be registered included the contract’s affirmation that AWI was licensed and
Daggett LLC’s previous specialty contractor registration.
The superior court evidently found the written contract and the Daggetts’
actions more persuasive than Nadia’s testimony about AWI’s need to be registered. We
have explained that “[t]he superior court’s ‘factual findings enjoy particular deference
when they are based “primarily on oral testimony, because the trial court, not this court,
performs the function of judging the credibility of witnesses and weighing conflicting
evidence.” ’ ”35 The court did not clearly err in discounting testimony that renewable
energy installers were not required to be registered or in concluding that there was no in-
practice exemption from the registration requirement.
B. AWI’s Counterclaim For Breach Is Barred By Statute.
The superior court held that AWI was barred by statute from bringing a
counterclaim against Feeney for breach of contract. Under AS 08.18.151 an unregistered
contractor who was required to be registered may not bring a breach-of-contract claim:
A person acting in the capacity of a contractor . . . may not
bring an action in a court of this state . . . for breach of a
contract for which registration is required under this chapter
without alleging and proving that the contractor . . . was a
34
William P. v. Taunya P., 258 P.3d 812, 814 (Alaska 2011) (citing Misyura
v. Misyura, 242 P.3d 1037, 1039 (Alaska 2010)).
35
In re Adoption of S.F., 340 P.3d 1045, 1047 (Alaska 2014) (quoting
William P., 258 P.3d at 814).
-17- 7179
registered contractor . . . at the time of contracting for the
performance of the work.
Because AWI did not fall under the finished products exemption of AS 08.18.161(5), it
was required to register as a specialty steel contractor in order to install wind turbines.
The plain language of AS 08.18.151 therefore prohibits AWI’s counterclaim.
The Daggetts contend that, because it involves the forfeiture of a claim,
AS 08.18.151 should be construed narrowly so that it would not apply here. They point
to Industrial Power, where we “decline[d] to give the statute an expansive reading”
because “AS 08.18.151 causes the forfeiture of an otherwise valid claim.”36 But even
under this narrow reading of section .151, we concluded that Industrial Power, because
it was assembling and installing prefabricated homes, was required to be registered and
thus was barred from bringing a breach of contract claim.37 As we discussed above in
Section A.1, AWI is in a position analogous to that of Industrial Power, not Western
Modular, the supplier of the prefabricated homes. We therefore conclude that AS
08.18.151 bars AWI’s counterclaim.
C. The Superior Court Did Not Err In Declining To Address AWI’s
Claim For Wrongful Rejection Under The UCC.
The Daggetts argue that the superior court erred by declining to address
AWI’s potential remedies for wrongful rejection under the Uniform Commercial Code
(UCC) when AWI raised wrongful rejection as an affirmative defense.38 They point to
36
623 P.2d at 294.
37
Id. at 295-97.
38
Although the Daggetts did not raise this issue in their statement of points
on appeal, they did raise it before the superior court and discussed it adequately in their
appellate briefing; Feeney also briefed the issue. We therefore consider the merits of the
argument. See Bylers Alaska Wilderness Adventures Inc. v. City of Kodiak, 197 P.3d
(continued...)
-18- 7179
provisions of the UCC incorporated into AS 45.02.703, .706, and .708, which provide
a seller with specific remedies in the case of wrongful rejection by the buyer. They argue
that these remedies are separate from the breach-of-contract counterclaim and are not
barred by AS 08.18.151 even if AWI unlawfully failed to register as a specialty
contractor.
But Feeney correctly notes that the Daggetts have failed to cite any legal
authority for their proposition that AS 08.18.151 does not bar claims for these remedies
under the UCC. In fact, AS 08.18.151 bars an unregistered contractor from “bring[ing]
an action . . . for the collection of compensation for the performance of work or for
breach of a contract.” An action for remedies under the UCC qualifies as “an action . . .
for the collection of compensation” within the meaning of this statute, and there is no
indication that the UCC remedies were intended to displace the barrier to suit created by
AS 08.18.151.39 Accordingly AS 08.18.151 bars the Daggetts’ claim for UCC remedies,
and the superior court did not err in failing to consider this defense.
D. The Setoff Calculation Is Clearly Erroneous.
After concluding that Feeney was entitled to the return of his down
payment, the superior court concluded that AWI was entitled to an equitable setoff
compensating it for out-of-pocket and incidental expenses. Although the court did not
abuse its discretion by awarding a setoff based on the costs incurred by AWI, the setoff
calculation was clearly erroneous.
38
(...continued)
199, 205 n.10 (Alaska 2008) (citing Native Vill. of Eklutna v. Bd. of Adjustment for the
Municipality of Anchorage, 995 P.2d 641, 646 (Alaska 2000)) (considering claims that
were raised below and briefed by both parties).
39
See AS 45.01.113(b) (providing that relevant provisions of Alaska law
supplement the UCC “[u]nless displaced by the particular provisions of the code”).
-19- 7179
1. It was not an abuse of discretion to base the setoff on costs
incurred by AWI instead of on benefits received by Feeney.
Feeney successfully voided the contract on the ground of misrepresentation.
His complaint correctly noted that AWI would be entitled to an equitable setoff. The
superior court determined AWI’s setoff based on the costs incurred by AWI. As we
have explained, actions for compensation by an unregistered contractor are normally
barred by AS 08.18.151. But in Sumner Development Corp. v. Shivers, we held that in
the interests of equity, an unregistered contractor may “offset[] as a defense sums which
would otherwise be due him [or her] under the illegal contract.”40 We adopted this
principle because awarding the return of the property owner’s full payment would create
a “windfall” if the owner also retained the benefit of the work completed prior to
rescission.41 “Allowing setoff achieves an equitable result of compensating the owner
only if the damages caused are greater than the benefit received.”42
Because “rescission involves restoring the parties to their ‘pre-contract
position[s], at least as far as [it is] possible to do so,’ ”43 Feeney argues that any setoff
under this principle is limited to the benefit the owner received — i.e., the amount of
“windfall” that the owner would receive if allowed to retain the completed work in
addition to receiving full reimbursement. He argues that he received no benefit from the
work completed before the contract was cancelled. But our decision in
40
517 P.2d 757, 764-65 (Alaska 1974) (quoting S & Q Construction Co. v.
Palma Ceia Dev. Org., 3 Cal. Rptr. 690, 692 (Cal. Dist. App. 1960)).
41
Id. at 765-66.
42
Id. at 766.
43
Watega v. Watega, 143 P.3d 658, 666 (Alaska 2006) (alterations in original)
(citing 1 DAN B. DOBBS, LAW OF REMEDIES § 4.8, at 676 (2d ed.1993)).
-20- 7179
Sumner emphasizes that the setoff is intended to “achieve[] an equitable result” and
compensate the contractor for “any sums which may be equitably due [it].”44
Because the award of a setoff is an equitable remedy,45 we review the
superior court’s decision for abuse of discretion.46 The court weighed the equitable
considerations in the case, including its view that Feeney’s pursuit of the licensing issue
was “pretextual” and that he had “unilaterally ‘cancelled’ the [c]ontract” for other
reasons and then sought “to justify this termination based on . . . AWI’s non-licensed
status.” We defer to the court’s factual determinations about Feeney’s true reason for
cancelling the contract, which do not appear clearly erroneous from the record.47 Based
on this factual determination, the superior court did not abuse its discretion in awarding
an equitable setoff that compensated AWI for costs it incurred.
2. The setoff amount was based in part on an erroneous
calculation.
The calculated setoff amount did not consider the profit actually made by
AWI on resale. After the contract plans fell apart, AWI was able to resell the parts for
a total of $37,054.52: the turbine and inverter were sold for $25,100.72 and the tower
44
Id. at 765-66.
45
Id. at 766.
46
In re Estate of Fields, 219 P.3d 995, 1002 (Alaska 2009), as modified on
denial of reh’g (Dec. 16, 2009) (citing Riddell v. Edwards, 76 P.3d 847, 852 (Alaska
2003)).
47
See Diblik v. Marcy, 166 P.3d 23, 25 (Alaska 2007) (citing Keturi v. Keturi,
84 P.3d 408, 412 (Alaska 2004)). Indeed, the record supports the finding that Feeney
cancelled the contract based on his neighbor’s contention that the turbine violated local
land-use covenants. Under the terms of the contract, Feeney expressly assumed the
responsibility of ensuring that the installation complied with the covenants. As the
superior court stated, Feeney “is not without unclean hands.”
-21- 7179
for $11,953.80. The court only briefly looked at profit to determine whether AWI was
entitled to any setoff based on resale at a loss. Because the court calculated that AWI
made a slight profit, it concluded that AWI was not entitled to resale damages. Under
the superior court’s calculation, where AWI supposedly paid $37,000 and received
$37,054.52 for the parts, AWI’s profit would have been $54.52. But this was incorrect:
the supplier’s invoice shows that AWI paid the wholesale price of $30,950 for the Wind
Turbine Package, not the retail price of $37,000. AWI therefore made a profit of
$6,104.52 when it sold the parts. Because the contract is rescinded, AWI is entitled to
offset its costs, as the court concluded, but only to the extent that their costs are greater
than the profit they gained. We therefore remand this case to the court to recalculate the
setoff amount based on AWI’s actual profit.48
E. The Superior Court Did Not Err In Amending The Final Judgment To
Assign Liability To The Daggetts And Standard Steel.
The Daggetts argue that it was procedurally improper to delay judgment on
the question of liability and that the amended judgment is substantively incorrect.
1. It was not an abuse of discretion to allow Feeney to move to
amend the judgment after the Civil Rule 59(f) deadline.
The superior court’s July 2013 opinion reserved judgment on whether
Feeney could seek recovery of his down payment from anyone other than AWI,
indicating that it would consider the question if AWI did not satisfy the judgment against
it. The December 2013 final judgment expressly stated that, “[n]otwithstanding the
requirements of Civil Rule 59(f),” Feeney could “seek to amend the judgment to include
the remaining defendants” within 120 days if AWI failed to satisfy the judgment within
48
We also note that the court’s calculated total for out-of-pocket expenses
appears to be $65 short.
-22- 7179
90 days. The Daggetts argue that Rule 59(f) sets a “strict deadline” for motions to amend
a judgment that the court was wrong to ignore.
Feeney counters that the Daggetts waived any objection to the timeline
because they did not object to this amendment mechanism when he proposed it. An
issue not timely raised below cannot be raised on appeal.49 Feeney submitted the
proposed final judgment suspending Rule 59(f) on October 29, 2013, and the court
signed it on December 15, 2013. The Daggetts did not object to the amendment
mechanism until May 6, 2014. Because the Daggetts did not timely raise their objection,
it is waived. But even if the issue were properly before us, we would not disturb the
superior court’s decision.
Rule 59(f) requires a motion to amend a judgment to be served “not later
than 10 days after the entry of the judgment,” far sooner than the 120-day deadline here.
But Civil Rule 94 states that the Civil Rules “are designed to facilitate business and
advance justice” and allows the court to “relax[] or dispense[] with” any of the rules
when it is “manifest to the court that a strict adherence to them will work injustice.” The
court’s December 2013 final judgment stated that Rule 59(f) would not apply, and Rule
94 leaves such decisions to the superior court’s discretion.50
The superior court chose to give AWI an opportunity to satisfy the
judgment before considering whether the Daggetts or an entity owned by them could also
be held liable for it. The court’s decision did not deny the Daggetts due process. The
49
See Stephanie W. v. Maxwell V., 319 P.3d 219, 225-26 (Alaska 1995)
(“ ‘[A]n issue raised for the first time in a motion for reconsideration is not timely’ and
is therefore not preserved for appeal.” (quoting Stadnicky v. Southpark Terrace
Homeowner’s Ass’n, 939 P.2d 403, 405 (Alaska 1997))).
50
See ConocoPhillips Alaska, Inc. v. Williams Alaska Petroleum, Inc., 322
P.3d 114, 134 (Alaska 2014) (reviewing a decision to enlarge time to file for attorney’s
fees under Rule 94 for abuse of discretion).
-23- 7179
Daggetts were named as defendants in the original judgment; the delay did nothing to
change their position in the case. The Daggetts had an opportunity to be heard on the
issue of their personal liability, and they took that opportunity. Nor were the Daggetts
prejudiced by the delay; if anything, the delay could have benefitted them by allowing
AWI to satisfy the judgment before the court issued a judgment against the Daggetts in
their personal capacity. Because the delay was reasonable and there was no prejudice
to the Daggetts, the court’s decision to relax the Rule 59(f) deadline was not an abuse of
discretion.
2. It was not error to decide that the Daggetts and Standard Steel
were liable to Feeney.
The superior court concluded that the Daggetts were personally liable to
Feeney under the contract because they signed it as agents of an undisclosed principal,
Daggett LLC. The Daggetts do not contest the court’s factual finding that they acted as
agents of an undisclosed principal,51 nor do they contest the legal conclusion that agents
of an undisclosed principal are generally liable on a contract with a third party.52 Rather
they argue that the court erred in applying these principles of agency law in this case
because AS 10.50.265 protects members of an LLC from the liabilities of their LLC.
Alaska Statute 10.50.265 gives some protection to LLC members by
providing:
51
The Daggetts briefly challenge the superior court’s finding that they entered
into a contract with Feeney, arguing that Schreier was the relevant actor. But this
argument does not affect our analysis because the superior court found that Schreier
acted as a subagent of the Daggetts and, as such, that they were liable for his actions
regardless of who actually signed the contract. To the extent that the argument is
relevant, the superior court’s findings on this point are not clearly erroneous.
52
See Jensen v. Alaska Valuation Serv., Inc., 688 P.2d 161, 163 (Alaska
1984) (citing RESTATEMENT (SECOND) OF AGENCY, §§ 321, 322 (AM. LAW INST. 1958)).
See also 3A FLETCHER CYCLOPEDIA OF THE LAW OF CORPORATIONS § 1120 (2016).
-24- 7179
A person who is a member of a limited liability company . . .
is not liable, solely by reason of being a member, under a
judgment, decree, or order of a court . . . for a liability of the
company to a third party, whether the liability arises in
contract, tort, or another form, or for the acts or omissions of
another member, manager, agent, or employee of the
company to a third party.
The Daggetts mistakenly read this statute to provide “complete protection” against
personal liability for members of an LLC. Based on the statute’s language protecting
against liability arising “in contract . . . or another form,” the Daggetts argue that
AS 10.50.265 protects them against liability both on the contract and in restitution under
the rescinded contract. And they contend that the provision protecting against liability
“for the acts or omissions of another member, manager, agent, or employee”
encompasses all the actions and relationships in this case.
Although AS 10.50.265 does provide some protection for limited liability
company members, it is not a blanket ban on all possible liability for members. The
plain language of the statute protects members only against liability to which they are
subject “solely by reason of being a member.”53 Where a limited liability company
member’s liability arises from the member’s own actions, the statute provides no
protection.54 Here the superior court found that the Daggetts were liable to Feeney not
in their capacity as members of Daggett LLC but instead because they acted as agents
53
AS 10.50.265. (Emphasis added.)
54
AS 10.50.265 protects a member from liability that arises from “the acts or
omissions of another member,” not of the member personally. (Emphasis added.) Cf.
Weber v. U.S. Sterling Securities, Inc., 924 A.2d 816, 823-24 (Conn. 2007) (holding that
a similar statute did not bar personal liability of limited liability company members for
their own acts).
-25- 7179
of Daggett LLC in executing a contract for an undisclosed principal. Therefore
AS 10.50.265 does not preclude their liability.
Turning to Standard Steel’s liability as the successor to AWI, we decline
to consider the merits of this question because the Daggetts do not have standing to
contest it. Alaska Statute 22.20.040(a)(2) mandates that “a corporation, either public or
private, shall appear by an attorney in all cases unless an exception to the corporation’s
appearance by an attorney has been explicitly made by law.” In Pister v. State,
Department of Revenue we applied this statutory restriction, explaining that when Pister
filed a pro se appeal on behalf of himself and two corporations, the corporate entities
“were . . . dismissed as appellants [until] an attorney filed an entry of appearance on
behalf of all appellants.”55 The Daggetts represent themselves in this appeal and
therefore cannot represent Standard Steel or, for that matter, AWI. Because the Daggetts
may not represent Standard Steel in litigation under AS 22.20.040, the procedural
leniency otherwise afforded to self-represented litigants is not available here,56 and the
Daggetts’ appeal may not be construed as an appeal on behalf of Standard Steel.57
55
354 P.3d 357, 361 n.9 (Alaska 2015) (citing AS 22.20.040(a)(2)).
56
See Lawson v. Helmer, 77 P.3d 724, 729 (Alaska 2003) (citing Kaiser v.
Sakata, 40 P.3d 800, 803 (Alaska 2002)) (explaining that “we relax some procedural
requirements for a pro se litigant where the litigant has made a good faith attempt to
comply with judicial procedures”).
57
The Daggetts may of course defend and raise claims in their individual
capacity. See St. Paul Church, Inc. v. Bd. of Trs. of Alaska Missionary Conference of the
United Methodist Church, Inc., 145 P.3d 541, 559-60 (Alaska 2006). And in their
capacity as agents of AWI, they may defend themselves against personal liability using
the same defenses that would be available to Daggett LLC d/b/a AWI. RESTATEMENT
(SECOND) OF AGENCY § 334. But this does not allow them to raise any defense that
would be available only to Standard Steel.
-26- 7179
V. CONCLUSION
For the reasons explained above, we AFFIRM in part, REVERSE in part,
and REMAND to the superior court to redetermine the setoff amount.
-27- 7179