Dow Roofing Systems, LLC v. Great Commission Baptist Church and Chamberlin Dallas, LLC F/K/A Chamberlin Dallas, Ltd. D/B/A Chamberlin Roofing and Waterproofing F/K/A Chamberlin Roofing & Waterproofing, Ltd.

                         COURT OF APPEALS
                          SECOND DISTRICT OF TEXAS
                               FORT WORTH

                              NO. 02-16-00395-CV


DOW ROOFING SYSTEMS, LLC                             APPELLANT

                                       V.

GREAT COMMISSION BAPTIST                             APPELLEES
CHURCH AND CHAMBERLIN
DALLAS, LLC F/K/A CHAMBERLIN
DALLAS, LTD. D/B/A CHAMBERLIN
ROOFING AND WATERPROOFING
F/K/A CHAMBERLIN ROOFING &
WATERPROOFING, LTD.

                                    ----------

         FROM THE 236TH DISTRICT COURT OF TARRANT COUNTY
                   TRIAL COURT NO. 236-269529-13



                                    ----------

                         MEMORANDUM OPINION1

                                    ----------




    1
        See Tex. R. App. P. 47.4.
      In two issues, Appellant Dow Roofing Systems, LLC appeals from the trial

court’s denial of its motion to compel arbitration against Appellee Great

Commission Baptist Church (the Church) and Appellee Chamberlin Dallas, LLC

f/k/a Chamberlin Dallas, Ltd. d/b/a Chamberlin Roofing And Waterproofing f/k/a

Chamberlin Roofing & Waterproofing, Ltd. Although the Court is sympathetic to

the arguments presented—particularly by the Church—that militate against

arbitration, we are bound by precedent and must reverse under the

circumstances presented.

                              I.    Background

      The parties’ dispute arose from the construction of a building for the

Church in Fort Worth. Construction began in early 2005 and was substantially

completed by March 2006.

      The architect’s project manual for the construction required the roof to be

covered with a thermoplastic polyolefin elastomeric membrane (TPO membrane).

Chamberlin installed the building’s roof using a TPO membrane manufactured

and supplied by Dow Roofing’s predecessor, Stevens Roofing Systems, Inc.

Several years before, Chamberlin had executed an applicator agreement with

Stevens Roofing (the Applicator Agreement), which authorized Chamberlin to

install Stevens Roofing products.    The Applicator Agreement contained an

arbitration provision.

      At the time of construction, Stevens Roofing was a division of JPS

Elastomerics Corporation.   JPS provided the Church with a limited warranty


                                       2
against leaks in the installed roofing system (the Limited Warranty). The Limited

Warranty had a ten-year term starting with the date of substantial completion and

the Church’s acceptance of the roofing system.         It included an arbitration

provision covering “[a]ny controversy or claim arising out of or relating to this

document, or the breach thereof.” In December 2006, the facilities manager for

the Church signed the Limited Warranty. After JPS issued the Limited Warranty,

Dow Roofing bought Stevens Roofing from JPS.

      After the building’s substantial completion, the roof consistently leaked

during and after periods of rainfall, and over time the leaks became more

frequent. Indeed, on at least five occasions, the Church requested repairs from

Dow Roofing under the Limited Warranty.        Dow Roofing responded to each

request and each time assured the Church that the TPO membrane was in good

condition. Eventually, after its insurer denied a claim for roof repair because of

an alleged manufacturing deficiency in the TPO membrane, the Church was

forced to sue Chamberlin, Dow Roofing, and the builder (not a party to this

appeal).

      In response to the Church’s lawsuit, Chamberlin filed cross-claims against

Dow Roofing for contribution, indemnity, and fraud.     In support of its claims,

Chamberlin alleged that Stevens Roofing inspected and warranted the roofing

system, that Dow Roofing made warranty repairs to the roof, and that any leaks

resulted from a defect in the roofing system. Also, Chamberlin pointed out that in

the Applicator Agreement, Stevens Roofing had provided a warranty against


                                        3
defects and had required Chamberlin to allow it to inspect and approve the

installation of its roofing system.

       Dow Roofing moved to compel arbitration of the Church’s and

Chamberlin’s claims based on the arbitration provisions in the Limited Warranty

and the Applicator Agreement, respectively. Neither the Church nor Chamberlin

filed a response to the motions.

       On March 16, 2015, the trial court granted the motions to compel

arbitration.   The parties took no action for a year.     On March 16, 2016, the

Church, having obtained new counsel, moved to set aside the trial court’s

arbitration order and to allow it to present arguments against arbitration. The trial

court granted the motion and set aside its March 16, 2015 order compelling

arbitration.

       The Church then filed a response to Dow Roofing’s motion to compel

arbitration. In its response, the Church asserted that Dow Roofing had recently

declared the warranty to be “null and void,” and as a result, the warranty never

came into existence—and, thus, neither did the arbitration provision. The Church

further argued that:    (1) the Limited Warranty was illusory; (2) the Church’s

claims arose before execution of the Limited Warranty, and the arbitration

provision thus had no application; and (3) the arbitration provision was

unconscionable.

       Dow Roofing then filed a consolidated amended motion to compel

arbitration of the Church’s and Chamberlin’s claims against it, addressing the


                                         4
Church’s contentions. Again, Chamberlin did not file a response to the renewed

motion to compel arbitration.

      The trial court denied Dow Roofing’s motion to compel arbitration. Dow

Roofing now appeals.

                            II.    Standard of Review

      We review a trial court’s denial of a motion to compel arbitration for an

abuse of discretion, but we review whether there is a valid and enforceable

arbitration agreement de novo.       Brand FX, LLC v. Rhine, 458 S.W.3d 195,

203 (Tex. App.—Fort Worth 2015, no pet.).           If the party seeking to compel

arbitration proves that a valid arbitration agreement exists, “a strong presumption

in favor of arbitration arises and the burden shifts to the party resisting arbitration

to establish a defense to enforcing arbitration.” Id. at 203–04.

      We review the question of whether the party resisting arbitration has

established a defense to arbitration de novo. Id. at 204. However, we give

deference to the trial court’s determination of any facts relevant to a defense, if

those determinations are supported by the record.             Id.   “If an arbitration

agreement is present, the claims are encompassed by the agreement, and the

party opposing arbitration failed to prove any defense to enforcement, the trial

court has no discretion but to compel arbitration,” and in that case, the trial

court’s denial of a motion to compel arbitration is an abuse of discretion. Id.




                                          5
                                 III.    Analysis

      Dow Roofing challenges the trial court’s denial of its motion to compel

arbitration as to both Chamberlin and the Church.

A.    The Trial Court Abused Its Discretion by Denying Arbitration of
      Chamberlin’s Claims.

      In its first issue, Dow Roofing argues that the arbitration provision in the

Applicator Agreement is enforceable and that Chamberlin’s claims fall within the

arbitration provision’s scope.

      Chamberlin does not dispute that it executed an agreement containing an

arbitration provision. Rather, Chamberlin first argues that Dow Roofing failed to

prove that Chamberlin’s claims fell within the scope of a valid arbitration

agreement because although the arbitration provision calls for application of the

American Arbitration Association (AAA) construction rules, it prohibits the

arbitrator from following those rules.        See American Arbitration Association,

Construction Industry Arbitration Rules and Mediation Procedures, Rule 9(b)

(effective July 1, 2015) (AAA construction rules), https://www.adr.org/sites/

default/files/Construction%20Rules.pdf.       Chamberlin points out that the AAA

construction rules give the arbitrator the power to determine the validity of a

contract of which an arbitration provision forms a part, and it contends that these

rules conflict with the arbitration provision, which prohibits the arbitrator from

modifying the Applicator Agreement. See id.




                                          6
      Chamberlin further argues that because the arbitration provision provides

that the arbitrator has no power to modify the Applicator Agreement or render an

award that effects or creates a modification, the arbitration provision is

unconscionable.     Chamberlin contends that the arbitration provision is

unconscionable because even if the arbitrator determines that terms of the

Applicator Agreement are unenforceable, the arbitrator may not modify the

agreement to omit those terms, and the arbitration provision prevents the

arbitrator from interpreting the agreement in any way contrary to Dow Roofing’s

interests.

      As for Chamberlin’s argument relating to the scope of the arbitration

provision, we may not consider it. The arbitration provision requires arbitration

“in accordance with” the AAA construction rules. This language makes the AAA

construction rules part of the arbitration provision.   See Schlumberger Tech.

Corp. v. Baker Hughes Inc., 355 S.W.3d 791, 803 (Tex. App.—Houston [1st

Dist.] 2011, no pet.) (holding that such language incorporates the cited AAA rules

into the arbitration agreement); AAA construction rules, Rule 1(a) (providing that

the parties shall be deemed to have made the AAA construction rules part of

their arbitration agreement if they have provided for arbitration under the rules).

The AAA construction rules give the arbitrator the authority to decide questions

about the scope of the arbitration provision. AAA construction rules, Rule 9(a).

Accordingly, Chamberlin must raise any challenges to the scope of the

agreement in arbitration. See Douglas v. Regions Bank, 757 F.3d 460, 462 (5th


                                        7
Cir. 2014) (“Parties may agree to arbitrate whether a particular claim is subject to

arbitration,” and “[d]elegation provisions thus normally require an arbitrator to

decide in the first instance whether a dispute falls within the scope of the

arbitration provision”).

      As for Chamberlin’s unconscionability argument, it is well-settled that

“parties can agree to arbitrate ‘gateway’ questions of ‘arbitrability,’ such as

whether the parties have agreed to arbitrate or whether their agreement covers a

particular controversy.” Rent-A-Ctr., W., Inc. v. Jackson, 561 U.S. 63, 68–69,

130 S. Ct. 2772, 2777 (2010). In fact, under the AAA construction rules, the

arbitrator has the power to rule on the validity of the arbitration provision. See

AAA construction rules, Rule 9(a). When an arbitration provision incorporates

such a rule and also provides for arbitration of all claims between the parties, the

arbitration provision evidences a clear and unmistakable delegation of

arbitrability. Burlington Res. Oil & Gas Co. LP v. San Juan Basin Royalty Tr.,

249 S.W.3d 34, 41 (Tex. App.—Houston [1st Dist.] 2007, pet. denied).           The

language of the arbitration provision in the Applicator Agreement evidences such

a delegation.    Accordingly, it is the arbitrator that must decide Chamberlin’s

unconscionability defense.

      In summary, because the parties agreed to the arbitration provision, the

arbitrator must decide the scope of that provision, and the arbitrator must

address Chamberlin’s unconscionability defense.        Accordingly, the trial court

abused its discretion by denying the motion to compel arbitration of Chamberlin’s


                                         8
claims. We sustain Dow Roofing’s first issue. Accordingly, we do not address

Dow Roofing’s remaining arguments under this issue. See Tex. R. App. P. 47.1.

B.    The Trial Court Abused its Discretion by Denying Arbitration of the
      Church’s Claims.

      Dow Roofing argues in its second issue that the trial court erred by

declining to compel arbitration of the Church’s claims against Dow Roofing, given

that the mandatory arbitration provision in the Limited Warranty: (1) is a valid

and enforceable agreement to arbitrate subject to the Federal Arbitration Act

(FAA);2 (2) applies to the Church’s claims against Dow Roofing; and (3) is subject

to no valid defenses or, at least no defenses that should be addressed anywhere

but arbitration.

      A party resisting arbitration may raise three types of challenges to an

arbitration provision in a contract. In re Morgan Stanley & Co., Inc., 293 S.W.3d

182, 185–87 (Tex. 2009).         First, a party may challenge the validity or

enforceability of a contract containing the arbitration provision. Id. An arbitrator

must decide the question of whether a contract that meets the requirements for

contract formation is nevertheless unenforceable. Id. at 185. Second, a party

may challenge the arbitration provision itself.    Id. at 187.    A court, not the


      2
        The Church does not dispute that the FAA applies. See Rapid
Settlements, Ltd. v. Green, 294 S.W.3d 701, 705 (Tex. App.—Houston [1st Dist.]
2009, no pet.) (citation and internal quotation marks omitted) (explaining that the
FAA applies when the dispute concerns a “contract evidencing a transaction
involving commerce,” which includes a contract “relating to” interstate
commerce).


                                         9
arbitrator, hears such challenges unless the parties have expressly delegated

that issue to the arbitrator. Id. Third, a party may raise the question of whether

any contract was ever concluded.         Id.    A court decides challenges to the

requirements for contract formation.      Id.   Here, the Church raised all three

challenges in resisting arbitration.

      The arbitration provision in the Limited Warranty expresses the parties’

intent to arbitrate claims covered by the agreement, and the Church’s building

manager acknowledged execution of this agreement.              The Church argued,

however, that despite the parties’ execution of the Limited Warranty, and despite

Dow Roofing’s performance under the Limited Warranty, no contract between the

parties ever existed or, alternatively, that any such contract is unenforceable.

      1.     The Arbitrator Must Decide the Effect of the “Null and Void”
             Provision.

      The Church first posits that because Dow Roofing nullified the Limited

Warranty, no contract containing an arbitration agreement exists. The Church

contends that “a contract declared ‘null and void’ legally ‘never came into

existence.’” The Church argues that, consequently, because Dow Roofing has

declared the Limited Warranty “null and void,” the Limited Warranty never

existed, and thus neither did the arbitration provision contained in it. We note

that while the timing and circumstances surrounding Dow Roofing’s actions with

regard to the Limited Warranty are certainly troubling, it is not for the trial court,




                                         10
but for the arbitrator to decide what effect, if any, Dow Roofing’s declaring the

Limited Warranty null and void has on the Limited Warranty’s validity.

      Under the Limited Warranty’s specific terms, Dow Roofing could declare

the Limited Warranty “null and void” if, in its discretion, it determined that one of

three specific events had occurred: (1) the Church had alterations or repairs

made on the roof without Dow Roofing’s authorization; (2) the Church failed to

use reasonable care in maintaining the roof; or (3) the Church failed to comply

with the Limited Warranty’s terms. But an argument relying on this termination

provision is not a challenge to the contract’s formation because the termination

provision, on its face, is not a condition precedent to formation. See Sharifi v.

Steen Auto., LLC, 370 S.W.3d 126, 143–44 (Tex. App.—Dallas 2012, no pet.) (“If

there is a condition precedent to the formation of a contract, then no binding

contract will arise until the specified condition has occurred or been performed.”);

Bans Props., L.L.C. v. Hous. Auth. of City of Odessa, 327 S.W.3d 310, 313 (Tex.

App.—Eastland 2010, no pet.) (“[C]onditions precedent are events that must be

performed before a right accrues to enforce a contract.”). This provision allows

Dow Roofing to cancel the Limited Warranty in certain limited circumstances after

the agreement was entered, but it does not prevent the formation of the

agreement in the first place. In fact, that Dow Roofing could cancel the Limited

Warranty presupposes that a valid contract existed that could be cancelled.

      The Church cites two cases that used “null and void” language to describe

disputed contracts, and the Church relies on them to support its point that the


                                         11
Limited Warranty—and thus its arbitration provision—never came into existence.

Unfortunately, these cases are of no assistance to the Church. In both cases,

the contract at issue contained conditions precedent to the formation of the

contract.     See,   e.g.,   Bannum,    Inc.   v.   Mees,   No.   07-12-00458-CV,

2014 WL 2918436, at *1 (Tex. App.—Amarillo June 24, 2014, no pet.) (mem. op.)

(reviewing contract with a provision rendering the contract “null and void” if the

appellant was not awarded a particular government contract or if it could not

begin performance); Elijah Ragira/VIP Lodging Grp., Inc. v. VIP Lodging Grp.,

Inc., 301 S.W.3d 747, 754 (Tex. App.—El Paso 2009, pet. denied) (reviewing

enforceability of a contract with unsatisfied conditions precedent). Here, unlike in

Bannum and Elijah Ragira, the “null and void” provision of the Limited Warranty

named no events that had to occur before the contract became binding and could

be enforced. See Cal-Tex Lumber Co. v. Owens Handle Co., 989 S.W.2d 802,

809 (Tex. App.—Tyler 1999, no pet.) (“Courts will not construe a contract

provision as a condition precedent unless they are compelled to do so by

language that may be construed in no other way.”). In point of fact, until the filing

of this lawsuit, both parties acted in conformance with the existence of the

Limited Warranty—the Church by requesting repairs under the Limited Warranty

and Dow Roofing by responding to the repair requests.

      The Church also cites Shri Lakshmi Cotsyn Ltd. v. HN Intern. Grp. Inc., No.

2:12-CV-01614, 2013 WL 1222718, at *3 (D.N.J. Mar. 25, 2013) (unpublished), in

support of its argument. The Church is correct that the federal district court


                                         12
explained in that case that a “voidable contract is one in which a party has the

power . . . to disaffirm the agreement,” while “a declaration that a contract is void

nullifies all aspects of the agreement . . . giving neither party the power to ratify or

disaffirm its provisions.” Id. (emphasis added). However, the New Jersey federal

court’s holding is inapplicable to the Church’s defense. That case involved a

challenge to the formation of the contract on the basis that the plaintiff had never

signed the contract. Id. at *4. In other words, the allegation there challenged the

basic requirements for contract formation, rendering the facts and circumstances

of Shri Lakshmi wholly distinguishable from this case.           See Harding Co. v.

Sendero Res., Inc., 365 S.W.3d 732, 740 (Tex. App.—Texarkana 2012, pet.

denied) (noting general rule that a person is not a party to a contract the person

did not sign).

       Because the Church’s defense challenges the continuing validity of the

Limited Warranty but does not challenge the requirements for formation of a

contract, it is the arbitrator that must decide the consequences of Dow Roofing’s

decision to declare the Limited Warranty “null and void.” See Morgan Stanley,

293 S.W.3d at 185.

       2.    The Limited Warranty is Not Illusory.

       The Church’s second defense to arbitration is that the Limited Warranty is

illusory.   The Church argues that because the Limited Warranty gave Dow

Roofing the ability to unilaterally nullify that agreement in its entirety, the Limited




                                          13
Warranty is illusory and, by extension, so is the arbitration provision.3 See J.M.

Davidson, Inc. v. Webster, 128 S.W.3d 223, 230 n.2 (Tex. 2003) (noting that

courts generally hold that “if a party retains the unilateral, unrestricted right to

terminate the . . . agreement, it is illusory”). The Church’s argument challenges

the formation of the Limited Warranty. See In re 24R, Inc., 324 S.W.3d 564,

567 (Tex. 2010) (stating that when illusory promises are all that support a

purported bilateral contract, there is no contract). Consequently, as explained

herein, we address the Church’s argument.4 See Morgan Stanley, 293 S.W.3d at

188.

       We determine that the Limited Warranty is not illusory simply because Dow

Roofing could terminate it. Dow Roofing did not have an unrestricted right to

cancel the Limited Warranty to avoid performance. To the contrary, the Limited

Warranty specified limited grounds upon which Dow Roofing could, in its

discretion, cancel it. Further, the parties do not dispute that Dow Roofing made

repairs to the roof when requested under the Limited Warranty. See Cherokee

Commc’ns, Inc. v. Skinny’s, Inc., 893 S.W.2d 313, 316 (Tex. App.—Eastland


       3
       The Church assumes in its brief that the Limited Warranty is a bilateral
contract. For purposes of addressing its argument, we assume the same.
       4
        The San Antonio Court of Appeals considers illusoriness to be a contract-
validity defense rather than a contract-formation defense. See Amateur Athletic
Union of the U.S., Inc. v. Bray, 499 S.W.3d 96, 103 (Tex. App.—San Antonio
2016, no pet.). In light of the Church’s position that mutual promises are the only
consideration supporting the Limited Warranty, we consider its argument to be a
contract-formation defense. See 24R, 324 S.W.3d at 567


                                        14
1994, writ denied) (“A contract which provides for its termination at the option of

one or either of the parties will be enforced if not contrary to equity and good

conscience” and citing established rule that a party’s performance may constitute

consideration even if the contract was void when made for lack of mutuality). We

therefore reject the Church’s argument that the cancellation provision in the

Limited Warranty rendered it illusory.5

      3.     The Arbitrator Decides Whether the Arbitration Provision Is
             Unconscionable.

      The Church next asserts as it did in the trial court that the arbitration

provision is both procedurally and substantively unconscionable. This defense is

a challenge to the arbitration provision itself, which is ordinarily a question for the

court rather than the arbitrator. See Morgan Stanley, 293 S.W.3d at 185. But

Dow Roofing maintains that in this case, the arbitration provision delegates this

issue to the arbitrator. We agree.

      As with the Applicator Agreement, the arbitration provision in the Limited

Warranty requires arbitration in accordance with the AAA construction rules.

This language makes the AAA construction rules part of the arbitration provision.

See Schlumberger Tech., 355 S.W.3d at 803; AAA construction rules, Rule 1(a).

Under both the AAA construction rules currently in effect and those in effect at

the time the parties executed the Limited Warranty, the arbitrator has “the power

      5
         The Church did not raise a separate argument specifically challenging the
illusoriness of the arbitration provision itself, so we do not address whether the
parties delegated that issue to the arbitrator or whether they could have done so.


                                          15
to rule on his or her own jurisdiction, including any objections with respect to the

existence, scope, or validity of the arbitration agreement” (the delegation rule).

AAA construction rules, Rule 9(a); American Arbitration Association, Construction

Industry Arbitration Rules and Mediation Procedures, Rule 9(a) (effective

October 1, 2009–July 1, 2015), https://www.adr.org/ArchiveRules. And like the

Applicator Agreement, the Limited Warranty’s arbitration provision calls for

arbitration of any controversy or claim arising out of or relating to the Limited

Warranty. It does not carve out any category of claims, and it does not include

only specific categories of claims that the arbitrator must decide. That language,

combined with the language incorporated from the AAA construction rules

assigning arbitrability questions to the arbitrator, is a clear and unmistakable

delegation of arbitrability to the arbitrator. See Burlington, 249 S.W.3d at 41.

      The Church relies on Haddock v. Quinn to argue that because the

arbitration provision does not specify what version of the AAA construction rules

apply, Dow Roofing has not proven that the parties agreed to submit questions of

arbitrability to an arbitrator. See 287 S.W.3d 158, 175 (Tex. App.—Fort Worth

2009, pet. denied). That case is distinguishable because there, the version of

the AAA rules in effect at the time the parties executed the arbitration agreement

differed from the version in effect at the time of the dispute, and the earlier

version did not contain the delegation rule. Id. The arbitration agreement at

issue in Haddock had been modified several times over the years with no change

to its language to specify which version of the AAA construction rules applied. Id.


                                         16
This court concluded that we could not tell which version the parties intended to

apply, and we consequently held that “we cannot assume from silence in the

agreement as to the issue of arbitrability or as to which version of the AAA rules

is to apply, that the parties intended to incorporate [the delegation rule], which did

not exist when the arbitration agreement was added.” Id.

      Here, unlike in Haddock, at the time the parties executed the Limited

Warranty, the AAA construction rules contained the delegation rule, and the

parties never amended the Limited Warranty after its execution. Further, the

current AAA construction rules retain the delegation rule. The parties clearly and

unmistakably intended to incorporate the delegation rule.

      Because the parties delegated arbitrability to the arbitrator, we do not

decide the Church’s unconscionability argument.

      4.     The Arbitrator Decides the Scope of the Arbitration Provision.

      As a final defense, the Church argues that the Limited Warranty does not

apply to claims arising before the Limited Warranty’s execution, such as its

claims for fraud and breach of the implied warranty of merchantability.          The

Church bases its argument on the arbitration provision’s language requiring

arbitration of “[a]ny controversy or claim arising out of or relating to this

document, or breach thereof.” [Emphasis added.] Again, our review is limited

because the arbitration provision delegates to the arbitrator the determination of

the arbitration provision’s scope. See Douglas, 757 F.3d at 462 (noting that

delegation provisions can require an arbitrator to decide the scope of the


                                         17
arbitration provision); AAA construction rules, Rule 9(a).       Accordingly, the

arbitrator must decide whether any of the Church’s claims do not fall within the

scope of the arbitration provision.

      Because Dow Roofing established the existence of a valid arbitration

provision, the Church failed to establish a defense to arbitration, and the

arbitrator must decide the scope of the arbitration provision and whether the

arbitration provision is unconscionable, we are compelled to hold, despite our

strong concerns about Dow Roofing’s action in canceling the Limited Warranty,

that the trial court abused its discretion by denying Dow Roofing’s motion to

compel arbitration. Accordingly, we sustain Dow Roofing’s second issue.

                                 IV.   Conclusion

      Having sustained Dow Roofing’s two issues, we reverse the trial court’s

order denying arbitration, and we remand this case to the trial court with

instructions to grant the motion to compel arbitration.




                                                    /s/ Mark T. Pittman
                                                    MARK T. PITTMAN
                                                    JUSTICE

PANEL: MEIER, SUDDERTH, and PITTMAN, JJ.

DELIVERED: August 3, 2017




                                         18