[PUBLISH]
IN THE UNITED STATES COURT OF APPEALS
FOR THE ELEVENTH CIRCUIT FILED
________________________ U.S. COURT OF APPEALS
ELEVENTH CIRCUIT
JUNE 24, 2009
No. 08-12308
THOMAS K. KAHN
________________________ CLERK
D. C. Docket No. 07-00113-CV-WLS-7
JULIE W. BRINSON,
Individually as Surviving Spouse of
Judson Byron Brinson, Deceased,
JULIE W. BRINSON,
Executrix and Personal Representative of
the Estate of Judson Byron Brinson, Deceased,
Plaintiff-Appellant,
versus
RAYTHEON COMPANY,
a Delaware corporation doing business in Georgia,
et al.,
Defendants,
RAYTHEON AIRCRAFT COMPANY,
a Kansas corporation doing business in Georgia,
Defendant-Appellee.
________________________
Appeal from the United States District Court
for the Middle District of Georgia
_________________________
(June 24, 2009)
Before TJOFLAT, ANDERSON and STAPLETON,* Circuit Judges.
ANDERSON, Circuit Judge:
Plaintiff-Appellant Julie W. Brinson appeals the district court’s order
granting summary judgment in favor of Defendant-Appellee Raytheon Aircraft
Company n/k/a Hawker Beechcraft Corporation (“RAC”). The district court
concluded that RAC was shielded from state law tort liability by application of the
military contractor defense. For the reasons set forth below, we affirm.
I. FACTS
On April 3, 2004, Judson B. Brinson, a Captain in the United States Air
Force (“USAF”) Reserves, died when the aircraft he was co-piloting, the T-6A
Texan II (“T-6A”), crashed near Savannah, Georgia. Appellant asserts that the T-
6A was defectively designed by RAC.
Brinson was an instructor in the Joint Primary Aircraft Training System
program (“JPATS”). JPATS was established to develop a unified system to train
flight personnel from all branches of the military. In 1992, JPATS issued a request
for design proposals for a new aircraft suitable for training military personnel to fly
*
Honorable Walter K. Stapleton, United States Circuit Judge for the Third Circuit,
sitting by designation.
2
jets. Although several competitors submitted designs for jet aircraft, RAC’s
prototype was a standard single-propeller aircraft called the Pilatus PC9. Propeller
driven aircraft have the attraction of being less expensive than jet aircraft.
However, there are key differences between single-propeller and jet aircraft
– among them the P Factor. The P Factor is a natural aerodynamic property of
single propeller-driven planes, which causes the aircraft to yaw and roll to the left.
Normally, pilots of propeller driven aircraft manually adjust the plane’s rudder to
compensate for the P Factor. However, jet aircraft are unaffected by the P Factor.
Therefore, in order to make its prototype emulate a jet, RAC designed and
developed a trim aid device (“TAD”). The TAD uses a computer and data input
sensors to automatically adjust the plane’s rudder through a series of pushrods and
bell cranks.
Plaintiff argues that the T-6A was defectively designed in two ways. First,
Plaintiff argues that the various components of the trim system represent “single
point failure opportunities” – when one component of the system breaks, the entire
TAD system fails. Plaintiff alleges that RAC should have included redundancies in
the rudder trim system to prevent the failure of the entire system in the event of a
single point failure. Second, Plaintiff alleges that the rudder trim system was
defectively designed using Teflon-lined pushrods. RAC selected the Teflon-lined
3
rods because they are self-lubricating and require less maintenance. However,
according to Plaintiff, Teflon tightens up with use and exposure to humidity. The
tighter the bearing on the end of the pushrod, the higher the bending stress and the
greater likelihood a rod will fracture and fail.
Plaintiff’s theory of the crash is as follows. Due to the heightened bending
stress caused by the use of Teflon-lined end bearings on the pushrods, one of the
pushrods fractured during takeoff – when the P factor is most pronounced. This
caused the entire TAD system to suddenly and unexpectedly fail. It sent the
aircraft into a severe, uncommanded left roll, causing the aircraft to crash.
Resolution of RAC’s motion for summary judgment requires an in-depth
examination of the process by which RAC and the USAF worked together to
produce the T-6A. The relevant evidence in this case is undisputed.1 However, its
significance is hotly contested. We will analyze the critical facts in the following
section. To set the stage, we note that the TAD was initially designed and patented
without any input from the government. However, military representatives and
RAC employees worked closely together during the development of all aspects of
1
Brinson did not expressly refute the numbered facts in RAC’s motion for
summary judgment. As a result, the district court deemed admitted RAC’s statement of material
facts. Brinson does not challenge that finding on appeal or assert that any of those factual
allegations are false. Accordingly, we accept RAC’s undisputed statement of material facts as
true.
4
the aircraft. The military was also involved in testing and certification of the T-6A.
Furthermore, in January of 2004, four months before the accident at issue, the
USAF issued a Technical Compliance/Technical Order (“TCTO”) requiring
inspection and replacement of the T-6A’s rudder trim pushrods. The TCTO
ordered that the rods be replaced by new, but otherwise identical, Teflon-lined
rods. The aircraft piloted by Captain Brinson on April 3, 2004 had been subjected
to the remedy ordered by the TCTO; its rods had been replaced. In 2006, well after
the accident at issue, the military ordered that the Teflon-lined rod ends be replaced
with a greased metal alternative.
RAC filed a motion for summary judgment asserting that it was shielded
from liability by application of the military contractor defense. The district court
agreed and entered summary judgment in favor of RAC. Brinson filed the instant
appeal.
II. STANDARD OF REVIEW
We review a district court’s grant of summary judgment de novo. Holloman
v. Mail-Well Corp., 443 F.3d 1199, 1204 (11th Cir. 2006). Summary judgment is
appropriate “if the pleadings, the discovery and disclosure materials on file, and
any affidavits show that there is no genuine issue as to any material fact and that
the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(c).
5
“When a motion for summary judgment is properly made and supported, an
opposing party may not rely merely on allegations or denials in its own pleading;
rather, its response must—by affidavits or as otherwise provided in this rule—set
out specific facts showing a genuine issue for trial.” Fed. R. Civ. P. 56(e)(2); see
also Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586-87, 106
S. Ct. 1348, 1356 (1986).
III. DISCUSSION
“[A] few areas, involving ‘uniquely federal interests,’ are so committed by
the Constitution and laws of the United States to federal control that state law is
pre-empted and replaced, where necessary, by federal law of a content prescribed
(absent explicit statutory directive) by the courts.” Boyle v. United Tech. Corp.,
487 U.S. 500, 504, 108 S. Ct. 2510, 2514 (1988) (internal citation omitted). “[T]he
procurement of equipment by the United States is an area of uniquely federal
interest . . . .” Boyle, 487 U.S. at 505-07, 108 S. Ct. at 2515-16. This, however,
merely establishes a necessary, not a sufficient, condition for the
displacement of state law. Displacement will occur only where . . . a
“significant conflict” exists between an identifiable federal policy or
interest and the operation of state law, or the application of state law
would frustrate specific objectives of federal legislation.
Boyle, 487 U.S. at 507, 108 S. Ct. at 2516 (internal quotations and citations
omitted).
6
The “scope of displacement” is determined by a three-part test. Boyle, 487
U.S. at 512, 108 S. Ct. at 2518.
Liability for design defects in military equipment cannot be imposed,
pursuant to state law, when (1) the United States approved reasonably
precise specifications; (2) the equipment conformed to those
specifications; and (3) the supplier warned the United States about the
dangers in the use of the equipment that were known to the supplier
but not to the United States.
Id. This doctrine is referred to as the “military contractor defense.” See Gray v.
Lockheed Aeronautical Sys. Co., 125 F.3d 1371, 1373 (11th Cir. 1997), abrogated
on other grounds by Gray v. Lockheed Aeronautical Sys. Co., 155 F.3d 1343 (11th
Cir. 1998). “Stripped to its essentials, the military contractor defense is available
only when the defendant demonstrates with respect to its design and manufacturing
decisions that the government made me do it.” Gray, 125 F.3d at 1377.
On appeal, Brinson argues that RAC has not presented sufficient evidence to
establish, as a matter of law, that the first two prongs of the Boyle test are
satisfied.2 We note that Brinson has not argued that RAC failed to prove the third
prong. Accordingly, we address the first two prongs in turn.
A. Approval of reasonably precise specifications
2
RAC argues that Brinson’s brief relies on evidence which is both inadmissible and
was not properly before the district court on summary judgment. We need not and do not address
this issue. We have reviewed all the evidence submitted to this Court by the parties. None of the
evidence in dispute affects our resolution of the merits of this appeal.
7
“This condition requires the existence of two factors: reasonably precise
specifications and government approval of them.” Gray, 125 F.3d at 1377. It is
meant to ensure that a government officer considered and approved “the design
feature in question.” Boyle, 487 U.S. at 512, 108 S. Ct. at 2518. Here, the design
feature in question is the rudder trim system, including specifically the TAD.
“Where the government merely approves imprecise or general guidelines, the
contractor retains the discretion over the important design decision and enjoys no
immunity against liability based on the Boyle defense.” Gray, 125 F.3d at 1377.
“[M]ilitary hardware does not suddenly spring into being from initial design and
procurement specifications, but evolves through drawings, blueprints and mockups
agreed upon by the parties.” Id. at 1378 (quoting Kleemann v. McDonnell
Douglas Corp., 890 F.2d 698, 702 (4th Cir. 1989)). “The ultimate design of the
product is determined not only by the original procurement and contract
specifications, but also by specific, quantitative engineering analysis developed
during the actual production process.” Id.
Two of our prior precedents illustrate these boundaries. In Gray, the Navy
contracted with Lockheed to develop a new antisubmarine warfare aircraft. Id. at
1374. The Navy worked closely with Lockheed to develop many aspects of the
aircraft and participated in a series of design reviews. Id. Nonetheless, Lockheed
8
failed to carry its burden on summary judgment under the military contractor
defense. The design feature in question was the aircraft’s aileron servo.3 Id.
Rather than producing copies of engineering drawings, Lockheed submitted a
document containing a narrative description of the general requirements the servo
was designed to meet. Id. at 1378. This Court held that general narrative
requirements can not rise to the level of “reasonably precise specifications.” Id.
By contrast, in Harduvel v. General Dynamics Corp., 878 F.2d 1311, 1320
(11th Cir. 1989), the defendant successfully carried its burden on summary
judgment under the military contractor defense. The USAF contracted with
General Dynamics to produce the military’s first “fly-by-wire” fighter, operated
completely by electric controls. Id. at 1313. Following a fatal crash, plaintiffs
theorized that the aircraft suffered from a massive electrical failure caused by
“‘wire chafing’ – the rubbing of wires in the electrical system against other wires,
fasteners, or structural parts of the plane.” Id. at 1314. General Dynamics
presented evidence that a group of USAF engineers was specifically assigned to
review the design of the aircraft’s electrical system including specifications,
3
“Part of the S-3’s flight control system, the servo is contained in the S-3’s
fuselage and it links the pilot with the ailerons. An aileron is a movable part of an airplane wing
or a movable airfoil external to the wing at the trailing edge for imparting a rolling motion and
thus providing lateral control.” Gray, 125 F.3d at 1374 (internal citations omitted).
9
drawings and blueprints. Id. at 1320. The USAF and General Dynamics engaged
in “continuous back and forth” discussions during the review and approval process.
Id. This evidence properly supported application of the military contractor defense
at summary judgment.
However, despite the guidance these cases provide, our inquiry cannot end
here. The instant case presents an issue of first impression in our Circuit. In
January of 2004, the USAF issued a TCTO requiring inspection and replacement of
the T-6A’s rudder trim pushrods. As a threshold matter, we must determine
whether RAC may rely on this post-design, post-production evidence as additional
evidence to satisfy the first prong of the Boyle test. We join several of our sister
circuits in concluding that it may.
First, we will return to the Supreme Court’s decision in Boyle to re-examine
the rationale behind the development of the military contractor defense. The Boyle
test is designed to identify those situations where there is a “significant conflict
between federal interests and state law in the context of Government procurement.”
Boyle, 487 U.S. at 511, 108 S. Ct. at 2518. To outline those situations presenting a
“significant conflict,” the Court relied on § 2680(a) of the Federal Tort Claims Act
(“FTCA”).
In the FTCA, Congress authorized damages to be recovered against
10
the United States for harm caused by the negligent or wrongful
conduct of Government employees, to the extent that a private person
would be liable under the law of the place where the conduct occurred.
28 U.S.C. § 1346(b). It excepted from this consent to suit, however,
“[a]ny claim . . . based upon the exercise or performance or the failure
to exercise or perform a discretionary function or duty on the part of a
federal agency or an employee of the Government, whether or not the
discretion involved be abused.” 28 U.S.C. § 2680(a).
Boyle, 487 U.S. at 511, 108 S. Ct. at 2518. The Court went on to reason:
We think that the selection of the appropriate design for military
equipment to be used by our Armed Forces is assuredly a discretionary
function within the meaning of this provision. It often involves not
merely engineering analysis but judgment as to the balancing of many
technical, military, and even social considerations, including
specifically the trade-off between greater safety and greater combat
effectiveness. And we are further of the view that permitting
“second-guessing” of these judgments through state tort suits against
contractors would produce the same effect sought to be avoided by the
FTCA exemption. The financial burden of judgments against the
contractors would ultimately be passed through, substantially if not
totally, to the United States itself, since defense contractors will
predictably raise their prices to cover, or to insure against, contingent
liability for the Government-ordered designs.
Boyle, 487 U.S. at 511-12, 108 S. Ct. at 2518. In light of this rationale, we
conclude that post-design, post-production evidence may fit within the Boyle
rationale. When faced with a potentially failing or defective part, the military may
make a discretionary decision concerning how to address the problem. We do not
want to “second-guess” that judgment through a state law tort suit. Just as in the
original design process, defense contractors may “predictably raise their prices to
11
cover, or to insure against” the possibility that the government will dictate how to
address a potential defect.
Review of cases outside this Circuit supports this conclusion. The Fourth
Circuit addressed this issue first. In Dowd v. Textron, Inc., 792 F.2d 409, 410 (4th
Cir. 1986),4 the Army contracted with the defendant, Bell, to design a helicopter.
Subsequently, during a flight at a Naval pilot school, the rotor system on one of the
Bell helicopters struck and severed its mast causing a fatal crash. Id. This
phenomenon is known as “mast bumping.” Id. The plaintiff alleged that the rotor
system was defectively designed. Bell moved for summary judgment on the basis of
the military contractor defense. Id. Bell presented evidence that the Army had
investigated the problem of mast bumping several years after the rotor system was
originally designed. Id. at 410-11. Bell and the Army exchanged information on
the design of the rotor system and Bell proposed three design modifications aimed
at preventing mast bumping. Id. at 411. The Army rejected Bell’s proposals. Id.
The Fourth Circuit concluded that “the Army’s experience with the 540 rotor system
4
Dowd was decided before the Supreme Court issued its decision in Boyle in 1989.
However, the Fourth Circuit’s decision was reaffirmed in Ramey v. Martin-Baker Aircraft Co.,
874 F.2d 946, 950 (4th Cir. 1989) (“There are two routes by which Martin-Baker may satisfy the
first prong of the Boyle test. In Dowd, we indicated that even though the military had not
developed or approved the specifications for the component at issue, ‘[t]he length and breadth of
the [military’s] experience with the [component] – and its decision to continue using it – amply
establish government approval of the alleged design defects.’ 792 F.2d at 412.”).
12
– and its decision to continue using it – amply establish government approval of the
alleged design defects.” Id. at 412.
Then, in 1993, the Second Circuit, citing and discussing Dowd, reached the
same conclusion. See Lewis v. Babcock Indus., Inc., 985 F.2d 83, 87-89 (2d Cir.
1993). In Lewis, the military contracted with General Dynamics to design its F-111
jet fighter. Id. at 84. After General Dynamics delivered the F-111 to the military,
the USAF became aware of corrosion on certain cables produced by Babcock
Industries. Id. at 85. The USAF completed an investigation of the problem and
decided to reorder new Babcock cables to replace the existing ones. Id.
Subsequently, the plaintiff suffered spinal injuries when one of the Babcock cables
connecting the parachute system to his crew ejection module severed. Id. at 84.
The Second Circuit held that “when the Government reordered the specific Babcock
cable, with knowledge of its alleged design defect, the Government approved
reasonably precise specifications for that product such that the manufacturer
qualifies for the military contractor defense for any defects in the design of that
product.” Id. at 89. The court noted that if liability were imposed the contractor
might
seek to raise the price of the replacement cables to cover its anticipated
liability from the damage that might be caused by their failure. Such
reaction would frustrate the policy underlying the FTCA’s
13
discretionary function exception by placing the cost of the
Government’s discretionary decisions on the Government itself when it
contracts for a product.
Id.
In sum, we join the Second and Fourth Circuits in concluding that post-design
evidence is relevant under the Boyle analysis.5 Whether or not the evidence in this
case represents meaningful acceptance of the rudder trim system and specifically the
TAD is a question we will explore in greater depth below.
We now apply the foregoing principles to the facts of this case. For the
reasons that follow, we conclude that RAC has presented sufficient evidence to
establish, as a matter of law, that the USAF approved reasonably precise
specifications of the rudder trim system, including the TAD in particular. First,
throughout 1998 and 1999, USAF engineers signed off on documents demonstrating
that they reviewed drawings of T-6A components, including the rudder trim system.
RAC’s undisputed statement of material facts asserts that these documents verify
“that the government approved and accepted the [TAD] as meeting the Contractual
5
See also Kerstetter v. Pacific Scientific Co., 210 F.3d 431, 434, 438 (5th Cir.
2000) (apparently also considering as relevant evidence the fact that the Navy continued to order
and use a potentially defective “crotch strap” notwithstanding the Navy’s knowledge of and
previous evaluation of potential deficiencies).
14
requirements.”6 Second, RAC presented evidence that, in February of 2000,
engineers representing the USAF reviewed engineering drawings and work
instructions for the T-6A rudder assembly, of which the TAD is a component.
RAC’s undisputed statement of material facts states that this review was conducted
to ensure that the “as-built” configuration of the aircraft complied with the
requirements in the design documentation; it also affirmatively states that the
government reviewed RAC’s design drawings to ensure that the aircraft complied
with those requirements. The cited report states that government representatives
“reviewed many engineering documents as a normal course of doing business while
performing contractor surveillance,” and notes that “[v]irtually all assembly
6
This crucial statement of material fact (as well as the others) is of course deemed
admitted. See supra note 1. Moreover, there is substantial evidence supporting the fact that the
government always had the design drawings and approved the design drawings of the several
systems, including the TAD. See, e.g., Larison Aff. ¶ 28 (“The government always had access to
drawings of the TAD and all other systems . . . . [A]ll design changes . . . were approved by the
government, regardless of whether they were initially conceived by the government or by
RAC.”); id. ¶ 22 (“The government was fully involved with the productionization design of the
TAD . . . [and] had the final say over the design’s suitability . . . .”); id. ¶ 5 n.1, ¶ 20
(Productionization means that the TAD system was not fully designed or fully qualified, but
necessary adjustments to the design had to be made with close government involvement in order
to fully qualify the design for government requirements); Hybl Aff. ¶ 7 (“The Trim Aid Device
(“TAD”), which is at issue in this lawsuit, was unique to the T-6A and instrumental to RAC’s bid
because it allowed the aircraft to fly like a jet and yet maintain the fuel efficiency of a propeller
driven aircraft. The government participated in numerous meetings with RAC concerning the
TAD . . . commented on its design . . . [and the] TAD was subjected to close governmental
involvement even before the contract was awarded.”); id. ¶ 26 (“[T]he government had its
‘fingerprints’ on every aspect of the T-6A, including the TAD system, approving the design,
testing procedures and results, production and certification of each part and system of the
T-6A.”).
15
drawings have been reviewed,” inter alia, “through day to day operations.”7 Finally,
the TCTO demonstrates that, as of January of 2004, the military was specifically
aware of the design defect at issue – i.e. that some of the rudder trim pushrods
showed evidence of bending. With this knowledge, the government issued a
specific order mandating the remedy it deemed appropriate with respect to the
known defect – i.e. the TCTO ordered that the pushrods be replaced with new but
identical Teflon-lined pushrods.
Appellant responds to this evidence, in part, by accurately noting that
“approval must be meaningful, not a mere formality.” Gray, 125 F.3d at 1377. A
defendant cannot prevail on summary judgment simply by showing that a
government representative signed a design drawing or ordered a replacement part.
Cf. Gray, 125 F.3d at 1379 (“The fact that the Navy . . . actually replaced the servo
in the crashed S-3 does not prove that the servo conformed to precise, Navy-
approved specifications”); see also Trevino v. Gen. Dynamics Corp., 865 F.2d 1474,
1477, 1486-87 (5th Cir. 1989) (concluding that the signatures of military
representatives on seventy-one detailed drawings of a Navy diving chamber were
not sufficient to satisfy the first prong of the military contractor defense if the
7
We also note that the TAD is one of the critical components of the T-6A. The
military selected RAC’s cost-efficient, single propeller proposal in part because design features
such as the TAD allowed the T-6A to emulate jet flight.
16
approval was nothing more than a rubber stamp).
The first prong of the Boyle test is designed to ensure that “the design feature
in question was considered by a Government officer.” Boyle, 487 U.S. at 512, 108
S. Ct. at 2518 (emphasis added). Here, that criterion is met. There is ample
undisputed evidence of a “continuous back and forth” between RAC and
governmental representatives during the development of the T-6A, involving review
and approval of design drawings of all systems, including the TAD.8 Harduvel, 878
F.2d at 1320. Evidence of exhaustive communication between a contractor and the
8
RAC’s undisputed statement of material facts demonstrates the extensive level of
interaction between RAC and the military. “RAC and the government operated on an ‘open
kimono’ basis, meaning that RAC and the government discussed all problems and issues . . . as
soon as these issues came up.” Specifically, RAC and USAF personnel interacted regularly
during daily status meetings, weekly conferences, monthly technical reviews and quarterly
program reviews. The technical reviews included government representatives from the Systems
Program Office, “an autonomous group tasked with making decisions regarding potential trade-
offs between safety and efficiency requirements of Air Force Aircraft.” “Engineers and others in
parallel professional disciplines from both RAC and the government worked closely together to
design, analyze, test, and improve the producibility of the T-6A.”
RAC also expressly addressed the rudder trim system and TAD. “The government
participated in numerous meetings with RAC concerning the TAD . . . prior to award of the
Contract.” “The government remained intimately involved in the T-6[A] program after award of
the Contract, when RAC and the government entered the manufacturing and development phase
of the project.” The Procurement Contract required RAC and USAF engineers to work together
as part of an “integrated product development” team. The integrated team concept “required
direct, hands on participation by both RAC and government representatives.” Clifton Larison
was the integrated products team leader for the mechanical, electrical and avionics sub-systems
on the T-6A. His USAF counterpart was civilian engineer Bob Fitzharris. Fitzharris was
involved in the “installation and interfacing” of the TAD into the T-6A. He ensured that the T-
6A trim system was properly certified by FAA standards and actively participated with RAC to
resolve problems. Larison estimated that he spoke with his government counterparts “an
average of two or three times per day throughout the certification process.”
17
military is a persuasive indication that the military’s approval, if given, was
meaningful. Id. Accordingly, on the facts before us, RAC has established that the
military’s review of rudder trim system drawings, including the TAD, was
meaningful. Furthermore, in light of both the military’s considered review of
engineering drawings and its extensive involvement (“continuous back and forth”)
in the development and production of the T-6A, RAC has presented sufficient
evidence from which we may conclude that the military’s January 2004 TCTO
(ordering immediate replacement of new but identical pushrods) reflects an
informed, discretionary decision on how to address a known problem.9
Accordingly, considering these three categories of evidence together, we conclude
that RAC has carried its burden on summary judgment to show that the government
approved reasonably precise specifications of the rudder trim system and its critical
component – the TAD.
RAC having properly supported its summary judgment and established as a
matter of law that the government approved reasonably precise specifications,
9
In considering the TCTO, along with the other evidence that the government
reviewed and approved reasonably precise specifications with respect to the TAD, we note that
the TCTO represents more than the mere unadorned fact of the government’s continued use in
the face of knowledge of the potential design defect. Rather, the TCTO represents a formal order
of the relevant government agency mandating specific action to remedy a known problem.
Accordingly, we need not express an opinion with respect to the significance of mere continued
use in the face of such knowledge. See Lewis, 985 F.2d at 89 n.3.
18
Brinson must set out specific facts showing there is a genuine issue for trial. See
Fed. R. Civ. P. 56(e)(2). Brinson has failed to do so. On appeal, Brinson asserts:
(1) RAC independently designed the TAD; (2) the USAF did not sign off on the
TAD’s source control drawings before they were sent to the subcontractor for
production; and (3) the Teflon-lined rod was an “off the shelf part.” We could
accept arguendo the first two factual assertions in Brinson’s favor; however, neither
raises a genuine issue for trial. Under the Boyle test, it is enough that the military
meaningfully approved reasonably precise drawings of the TAD at some point
during the design and production process. The third argument we find
unpersuasive. Although the TAD was originally designed and patented by RAC, we
have seen that RAC produced evidence that the design was considered, reviewed
and approved by the government in an extensive and “continuous back and forth”
process. Government engineers approved the inclusion of the pushrod into a unique
and critical component of a complex piece of equipment. See In re “Agent Orange”
Prod. Liab. Litig., 517 F.3d 76, 90 (2d Cir. 2007) (“All products can eventually be
broken down into various off-the-shelf components.” (quoting Miller v. Diamond
Shamrock Co., 275 F.3d 414, 420 (5th Cir. 2001))).
We believe that this case is very similar to our prior decision in Harduvel. In
both cases, government representatives reviewed and approved the design feature at
19
issue, including drawings, as part of a “continuous back and forth” process. Indeed,
in the instant case, we have the additional evidence (in the January 2004 TCTO) that
the government was aware of the specific design defect at issue and mandated
appropriate remedial action. With respect to this first Boyle factor, the instant case
is readily distinguished from Gray. There, the military contractor could prove only
that the Navy had approved a general narrative description. Gray, 125 F.3d at 378.
By contrast, in the instant case, RAC has proved that the government meaningfully
reviewed and approved reasonably precise specifications – i.e. the actual drawings
for the TAD.
In summary, RAC has sufficiently established that the military approved
reasonably precise specifications of the rudder trim system, including the TAD.
None of Brinson’s arguments raise a genuine issue of fact material to this
conclusion. Accordingly, we conclude that RAC has satisfied the first prong of the
Boyle test on summary judgment.
B. Conformity to Reasonably Precise Specifications
“To demonstrate the second Boyle condition, a contractor must show that the
equipment at issue conformed to precise, government-approved specifications.”
Gray, 125 F.3d at 1378. We conclude that RAC has carried its burden on summary
judgment. RAC presented evidence that engineers representing the government
20
reviewed drawings to ensure that the “as-built” configuration of the T-6A complied
with its design documentation. Furthermore, RAC attached a DD Form 250 to its
motion for summary judgment. The DD Form 250 is a “Material Inspection and
Receiving Report.” It is signed by a government representative and states that the
specific aircraft piloted by Captain Brinson on April 3, 2004 was accepted by the
military and conformed to the contract. See Miller v. Diamond Shamrock Co., 275
F.3d 414, 420 (5th Cir. 2001) (“[T]he government’s issuance of a DD Form 250,
Material Inspection and Receiving Report, further establishes the item’s
conformity.”). Finally, “where the procurement process involves [a] continuous
exchange between the contractor and the government, the process itself becomes
persuasive evidence of the product conformity to precise specifications.” Gray, 125
F.3d at 1378 (internal citations omitted). We have already established that RAC
presented ample evidence of a “continuous exchange” with the military. See supra
note 8.
Accordingly, RAC has properly supported its motion for summary judgment
and established that the equipment at issue conformed to government-approved
specifications. Thus, Brinson must to point to specific facts showing there is a
genuine issue for trial. See Fed. R. Civ. P. 56(e)(2).
Brinson argues that the TAD did not meet all of the Airworthiness Standards
21
for Acrobatic Category Airplanes contained in title 14, part 23 of the Code of
Federal Regulations.10 This argument in Brinson’s initial brief is far too sparse and
vague to warrant our review; the argument points to no lack of conformity with the
reasonably precise specifications that the government approved. Moreover,
Brinson’s argument misperceives our inquiry. At this stage, we ask only if the
rudder trim system, and the TAD in particular, conformed to the military’s
reasonably precise specifications.11 Brinson points to no facts suggesting that the
10
Brinson also asserts that the T-6A was not properly tested or FAA certified
because RAC personnel (as opposed to FAA or military representatives) were responsible for
testing and inspecting the TAD. However, RAC’s undisputed statement of material facts asserts:
(1) “RAC submitted a Quality Test Procedure to the government which was a proposal to test the
TAD and a rationale for how the proposed test would demonstrate that the TAD complied with
the government’s specifications and requirements for the system; the government reviewed and
approved the Quality Test Procedure; the testing was then performed on the TAD; a Quality Test
Report was prepared and presented to the government; and the government reviewed and
approved the test results in a document called a Compliance Report;” (2) “A government
engineer monitored the rudder and trim tab tests on the T-6[A] and had designated office space at
RAC for years;” and (3) “Contract compliance officers representing the government were on site
at RAC each and every day during design and certification of the aircraft. Government
representatives continue to be on site to this day, monitoring production and acceptance test
procedures.” Accordingly, Brinson fails to raise a genuine issue of fact as to the second prong of
the Boyle test.
11
The Fourth Circuit in Kleemann v. McDonnell Douglas Corp., 890 F.2d 698, 702-
03 (4th Cir. 1989), rejected a similar argument. There, the plaintiff relied on general
requirements that aircraft landing gear be strong enough to withstand normal landing loads. Id.
at 702. The Fourth Circuit held that these general requirements were used to develop detailed
structural load parameters and detailed design drawings, which the Navy approved. Id. The
Fourth Circuit held: “These working drawings, and not simply the general qualitative
specifications from the procurement stage, comprise ‘the reasonably precise specifications’
contemplated by [the second Boyle factor].” Id. Kleemann explains:
In essence, plaintiffs’ argument is that the ultimate design of the landing gear
failed to produce an aircraft that performed perfectly. Plaintiffs’ view would
render the government contractor defense illusory. Nonconformance to precise
22
TAD or any other component of the rudder trim system was not built exactly as it
was designed. We have already concluded that the military approved that design.
Accordingly, we conclude, as a matter of law, that RAC has met the second prong
of the Boyle test.12
IV. CONCLUSION
For the foregoing reasons, we affirm the district court’s grant of summary
judgment in favor of RAC on the military contractor defense.
AFFIRMED.
specifications must mean more than that the design does not work in compliance
with some “general admonition against an unwanted condition.” Harduvel, 878
F.2d at 1319 n.3. A product involved in a design-induced accident would, as a
definitional matter, always be deemed not to comply with such generalities since
no performance specifications approved by the government would purposely
allow a design that would result in an accident.
Id. at 703.
12
Again, with respect to the second Boyle factor, Gray is readily distinguished. In
Gray, the second Boyle factor was not satisfied because the product at issue did not conform to
the specifications – e.g., the latch did not conform to its specified dimension of 0.3750 plus or
minus 0.0001, and the shut-off valve triggered at 1400 psi instead of the specified 800 psi. As
noted, Brinson in this case points to no such nonconformity with the precise specifications.
23