MPACT Construction Group, LLC v. Superior Concrete Constructors, Inc.

Attorneys for Appellant                                  Attorneys for
Appellees
Steven S. Hoar                                           Angela L. Freel
Evansville, Indiana                                      James D. Johnson
                                                   R. Steven Krohn
Don L. Smith                                             James E. Stoltz
Nashville, Tennessee                                     Robert F. Stayman
                                                   Evansville, Indiana

                                                   Jerry D. Stilwell
                                                   Princeton, Indiana
____________________________________________________________________________
__

                                   In the
                            Indiana Supreme Court
                      _________________________________

                            No. 26S01-0307-CV-349

Mpact Construction Group, LLC,
                                               Appellant (Defendant below),

                                     v.

Superior Concrete Constructors, Inc.,
                                                   Appellee (Plaintiff
below),

and

Flying J, Inc., FJI Plaza Company III, LLC,
Lehman Brothers Holdings, Inc. d/b/a
Lehman Capital, a Division of Lehman
Brothers Holdings, Inc., Gary’s Plumbing
Service, Inc., Koberstein Trucking, Inc.,
Combs Landscape & Nursery, Inc, B & B
Electric Co., Inc., June Rinsch, in her
capacity as the Gibson County Treasurer,
                                                  Appellees (Defendants
below),

and

J.D. Music Tile Company, Inc., and
E & B Paving, Inc.
                                              Appellees (Intervenors below).



                       _______________________________

         Appeal from the Gibson Circuit Court, No. 26C01-0111-CP-142
                 The Honorable Keith A. Meier, Special Judge
                      _________________________________

 On Petition To Transfer from the Indiana Court of Appeals, No. 26A01-0209-
                                   CV-345
                      _________________________________

                              February 4, 2004

Sullivan, Justice.

      When the owner failed to pay for  work  and  supplies  on  its  travel
plaza, a subcontractor foreclosed  on  its  mechanic’s  lien.   The  general
contractor sought to compel arbitration among the owner,  general,  and  all
subcontractors.  While we acknowledge arbitration’s utility in this kind  of
multiparty dispute, our inspection of the contract documents indicates  that
the subcontractors did not agree to arbitrate the issues in dispute here.

                                 Background

      MPACT Construction Group, LLC, a general contractor,  entered  into  a
contract with Flying J, Inc. to construct a travel plaza in  Gibson  County,
Indiana.[1]  Flying J was the owner of the construction plaza at  the  time,
and it is now owned by FJI Plaza  III,  LLC.   MPACT  entered  into  several
contracts with subcontractors[2] (“Subcontractors”) to do the project  work.
 Flying J failed to pay for all of the work and supplies, and so  MPACT  and
some of the Subcontractors recorded mechanic’s liens against Flying J.   One
of the  Subcontractors,  Superior  Concrete  Constructors,  Inc.,  filed  an
action to foreclose its mechanic’s lien.  Several counterclaims  and  cross-
claims for the foreclosure of mechanic’s liens and for  breach  of  contract
were filed among the various parties.

      The contract between MPACT and Flying J is an  American  Institute  of
Architects (“AIA”) Standard Form  Agreement  Between  Owner  and  Contractor
(“General Contract”).  Articles 1 and 9 of the General Contract  incorporate
by reference the AIA General Conditions of  the  Contract  for  Construction
(“General Conditions”), and the General Conditions  contain  an  arbitration
clause.  However, the subcontracts were not AIA standard form contracts  but
instead were contracts prepared by MPACT.  After  approximately  six  months
of preparing for litigation, MPACT filed a motion  to  stay  litigation  and
compel arbitration.  The trial  court  summarily  denied  its  motion.   The
Court of Appeals reversed in part, granting the motion as to Flying  J,  and
affirmed in part, denying  the  motion  as  to  the  Subcontractors.   MPACT
Constr. Group, LLC v. Superior Concrete Constructors, Inc., 785 N.E.2d  632,
639, 640.  We reach the same result as the Court of Appeals.

                                 Discussion

      The main issue is whether  MPACT  and  the  Subcontractors  agreed  to
arbitrate disputes arising out  of  their  business  dealings.   Because  no
explicit arbitration provision is contained in  the  subcontracts,  we  must
determine if  the  arbitration  provision  in  the  General  Conditions  was
incorporated by reference into the subcontracts.

                                      I

      The Federal Arbitration Act (“FAA”)  applies  to  written  arbitration
provisions contained in contracts involving interstate commerce.   9  U.S.C.
§§ 1, 2 (2000).  MPACT, Flying J, FJI  Plaza  III,  LLC,  and  many  of  the
Subcontractors are from different states, and so  this  project  constitutes
interstate commerce.  See Prima Paint Corp. v. Flood  &  Conklin  Mfg.  Co.,
388 U.S. 395, 400-01 (1967); Univ. Casework Sys., Inc. v.  Bahre,  172  Ind.
App. 624, 634-35, 362 N.E.2d 155, 162 (1977); Pathman Constr.  Co.  v.  Knox
County Hosp. Ass’n, 164 Ind.  App.  121,  133-34,  326  N.E.2d  844,  852-53
(1975).

      The FAA applies only if  parties  agree  to  arbitrate.   The  Supreme
Court has stated  that  both  state  law  contract  principles  and  federal
substantive law of arbitration apply  to  answering  this  question.   First
Options of Chicago, Inc. v. Kaplan, 514 U.S. 938, 944  (1995)  (state  law);
Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S.  1,  24  (1983)
(federal law).  In dicta, the Court has said:

      [T]he text of § 2 [of the FAA] provides the  touchstone  for  choosing
      between state-law principles and the principles of federal common  law
      envisioned by the passage of that statute: An agreement  to  arbitrate
      is valid, irrevocable, and enforceable, as a matter  of  federal  law,
      ‘save upon such  grounds  as  exist  at  law  or  in  equity  for  the
      revocation of any contract.’  Thus state law . . .  is  applicable  if
      that law arose to govern issues concerning the validity, revocability,
      or enforceability of contracts generally.

Perry v. Thomas, 482 U.S. 483, 492  n.9  (1987)  (quoting  9  U.S.C.  §  2).
Recently, the Court clarified this statement, declaring that laws  generally
applicable to contracts  may  be  applied  to  arbitration  agreements,  but
“[c]ourts may not . . . invalidate arbitration agreements under  state  laws
applicable only to  arbitration  provisions.”   Doctor’s  Assocs.,  Inc.  v.
Casarotto, 517 U.S. 681, 686-87 (1996); see also PaineWebber Inc. v.  Elahi,
87 F.3d 589, 593 (1st Cir. 1996)  (referring  to  Doctor’s  Associates,  the
court stated “the Supreme Court explained that if a state law is  applicable
to contracts generally, it may be applied to arbitration agreements,  but  a
state  law  that  is  specifically  and  solely  applicable  to  arbitration
agreements is displaced by the FAA”).

      The Court of Appeals, the Seventh Circuit, a  federal  district  court
applying Indiana law, and most other federal circuit courts of  appeal  have
concluded that state law contract  principles  apply  to  determine  whether
parties have agreed to arbitrate.   St.  John  Sanitary  Dist.  v.  Town  of
Schererville, 621  N.E.2d  1160,  1162  (Ind.  Ct.  App.  1993);  Gibson  v.
Neighborhood Health Clinics, Inc., 121 F.3d  1126,  1130  (7th  Cir.  1997);
Ziegler v. Whale Sec. Co., L.P., 786 F. Supp. 739,  741  (N.D.  Ind.  1992);
Fazio v. Lehman Bros., 340 F.3d 386, 393 (6th Cir. 2003); Bank One, N.A.  v.
Shumake, 281 F.3d 507, 513 (5th Cir.  2002),  cert.  denied,  537  U.S.  818
(2002); Mirra Co. v. Sch. Admin. Dist. #35, 251  F.3d  301,  304  (1st  Cir.
2001); Int’l Paper Co. v. Schwabedissen Maschinen & Anlagen GMBH,  206  F.3d
411, 417 n.4 (4th Cir. 2000); Schooley v. Merrill Lynch,  Pierce,  Fenner  &
Smith, Inc., 133 Lab. Cas. (CCH) ¶ 58,234, 1997 U.S. App. LEXIS 1884, at  *5
(10th Cir. Feb. 5, 1997); PaineWebber Inc. v.  Bybyk,  81  F.3d  1193,  1198
(2nd Cir. 1996).

      MPACT contends, however, that whenever state law presents an  obstacle
to arbitration, federal law preempts  the  application  of  state  law.   It
argues that the Court of Appeals, in  finding  no  agreement  to  arbitrate,
either misconstrued Indiana  law  or  properly  construed  Indiana  law  but
should have applied federal law instead.  The  Subcontractors  respond  that
the “FAA only pre-empts state law which  requires  the  parties  to  resolve
their disputes in a judicial forum when the contracting parties have  agreed
to resolve their disputes through arbitration.”   (Joint  Br.  in  Resp.  to
Pet. for Transfer at 6.)  That is not the case  here,  they  argue,  because
there was no agreement to arbitrate.

      “The FAA contains  no  express  pre-emptive  provision,  nor  does  it
reflect a congressional intent to occupy the entire field  of  arbitration.”
Volt Info. Scis., Inc. v. Bd. of Trs. of  Leland  Stanford  Jr.  Univ.,  489
U.S. 468, 477 (1989).  Nevertheless, “state law may . . . be  pre-empted  to
the extent that it actually conflicts with federal law –  that  is,  to  the
extent that it ‘stands as an obstacle to the  accomplishment  and  execution
of the full purposes and objectives of Congress.’”  Id.  (quoting  Hines  v.
Davidowitz, 312 U.S. 52, 67 (1941)).  Preemption has  been  found  in  cases
where  state  statutes   explicitly   made   certain   arbitration   clauses
unenforceable  or  placed  serious  burdens   on   the   enforceability   of
arbitration provisions.  See, e.g., Doctor’s Assocs., 517 U.S. at  683,  688
(finding   preemption   where   Montana   law   made   arbitration   clauses
unenforceable unless the first page of the contract contained in  underlined
capital letters a statement that the contract was subject  to  arbitration);
Allied-Bruce Terminix Cos. v. Dobson, 513 U.S. 265, 269, 272-73, 282  (1995)
(reversing Alabama Supreme Court’s denial of arbitration based  on  a  state
statute   rendering   predispute   arbitration   agreements   invalid    and
unenforceable); Southland  Corp.  v.  Keating,  465  U.S.  1,  10-16  (1984)
(holding invalid on preemption grounds state statute  making  agreements  to
arbitrate franchise claims unenforceable).  But no such statute is  involved
here.  Nor is it  the  case  that  state  law  is  hostile  to  arbitration.
Indeed, Indiana policy favors arbitration.  PSI Energy, Inc. v. AMAX,  Inc.,
644 N.E.2d 96, 98 (Ind. 1994) (stating that “Indiana was  surely  among  the
first  jurisdictions  to  sanction  arbitration  as  a  means   of   dispute
resolution” as it had a law allowing arbitration  before  Indiana  became  a
state in 1816); Ind. CPA Soc’y v.  GoMembers,  Inc.,  777  N.E.2d  747,  750
(Ind.  Ct.  App.  2002)  (“Indiana  recognizes  a  strong  policy   favoring
enforcement of arbitration agreements.”); see also Uniform Arbitration  Act,
Ind. Code § 34-57-2-1 (1998).


      MPACT focuses solely on the result.  It is  just  not  true,  however,
that preemption occurs every time a court finds that  the  parties  did  not
agree to arbitrate.  If a court, fairly applying generally applicable  state
law contract principles and not  singling  out  arbitration  agreements  for
hostile treatment, finds that the parties did not agree to  arbitrate,  then
federal law does not preempt.  See Perry, 482 U.S. at 492 n.9 (“A court  may
not, in  assessing  the  rights  of  litigants  to  enforce  an  arbitration
agreement, construe that agreement in a manner different from that in  which
it otherwise construes nonarbitration agreements under state law.”);  Scherk
v. Alberto-Culver Co., 417 U.S. 506, 511 (1974) (the intention  of  the  FAA
was  to  put  arbitration  agreements  “upon  the  same  footing  as   other
contracts”) (quoting H.R. Rep. No. 96, 68th Cong., 1st Sess., 1, 2 (1924)).


      For these reasons, we will apply Indiana law to determine whether  the
Subcontractors agreed to arbitrate.[3]

      MPACT further argues that even if Indiana  law  applies,  the  federal
policy favoring  arbitration  should  influence  the  question  whether  the
parties agreed to arbitrate.  The Subcontractors respond that a court  “must
first  determine  whether  the  parties  generally   agreed   to   arbitrate
disputes.”  (Joint Br. in Resp. to Pet. for Transfer at 2.)  We  agree  with
the Subcontractors.

      Whether the parties agreed to arbitrate any disputes is  a  matter  of
contract interpretation, and most importantly,  a  matter  of  the  parties’
intent.  AGCO Corp. v. Anglin, 216 F.3d 589, 593 (7th Cir. 2000)  (“As  with
any contract, the touchstone for interpreting an arbitration clause must  be
the intention of the parties.”).  “Courts in Indiana  have  long  recognized
the freedom of parties to  enter  into  contracts  and  have  presumed  that
contracts  represent  the  freely  bargained  agreement  of  the   parties.”
Trimble v. Ameritech Publ'g,  Inc.,  700  N.E.2d  1128,  1129  (Ind.  1998);
Cont’l Basketball Ass’n v. Ellenstein Enters., 669  N.E.2d  134,  140  (Ind.
1996).  Consequently, imposing on  parties  a  policy  favoring  arbitration
before determining whether they agreed  to  arbitrate  could  frustrate  the
parties’ intent and their freedom to contract.  The Supreme Court  has  made
this clear – “arbitration is a matter of contract  and  a  party  cannot  be
required to submit to arbitration any dispute which he has not agreed so  to
submit.”  AT&T Techs., Inc. v. Communications Workers of Am., 475 U.S.  643,
648 (1986) (quotations and citations omitted); accord Homes  by  Pate,  Inc.
v. DeHaan, 713 N.E.2d 303, 306 (Ind. Ct. App. 1999).

      Additionally, courts have regularly distinguished the treatment  given
questions of the existence of an agreement to  arbitrate  and  questions  of
the scope of an agreed-to arbitration clause.  In determining the  scope  of
an arbitration agreement, “due regard must be given to  the  federal  policy
favoring arbitration, and ambiguities as to the  scope  of  the  arbitration
clause itself resolved in favor of arbitration.”  Volt,  489  U.S.  at  476;
accord Moses H. Cone, 460 U.S. at  24-25;  Bank  One,  281  F.3d  at  513-14
n.24.[4]  Because there was  already  an  agreed-to  arbitration  clause  in
these cases, applying federal policy in construing  the  arbitration  clause
would not have frustrated the parties’ intent.  Using  the  policy  favoring
arbitration to decide whether the parties did in  fact  agree  to  arbitrate
does not answer the question but rather avoids having to  decide  it.   Only
after it has been determined that the  parties  agreed  to  arbitrate  their
disputes does the policy favoring arbitration play an  important  role.   We
must determine, therefore, whether MPACT and the  Subcontractors  agreed  to
arbitrate without resort to the federal policy favoring arbitration.

                                     II

      Whether  MPACT  and  the  Subcontractors  agreed  to  arbitrate  their
disputes  depends  on  whether  the  arbitration  clause  in   the   General
Conditions of the General Contract was incorporated by  reference  into  the
subcontracts.  “It is well settled that, under the Federal Arbitration  Act,
an agreement to arbitrate may be validly incorporated into a subcontract  by
reference to  an  arbitration  provision  in  a  general  contract.”   Maxum
Founds., Inc. v. Salus Corp., 779  F.2d  974,  978  (4th  Cir.  1985);  R.J.
O’Brien & Assocs. v. Pipkin, 64 F.3d 257, 260 (7th Cir.  1995);  cf.  Wilson
Fertilizer & Grain, Inc. v. ADM Milling Co., 654 N.E.2d  848,  854-55  (Ind.
Ct. App. 1995) (finding that under the Uniform Commercial Code  §  2-207,  a
party cannot  claim  surprise  to  an  arbitration  clause  incorporated  by
reference into the  contract),  trans.  denied.   In  deciding  whether  the
subcontracts incorporated by reference the arbitration  provision,  we  must
look to the language of the contract documents.

      MPACT points to  two  clauses  in  the  subcontracts  to  support  its
contention that the arbitration  provision  was  incorporated  by  reference
into the subcontracts.  The first reads:

      [Article VI(b)] The Sub-contractor acknowledges that he has  read  the
      General contract and all plans and specifications, together  with  all
      amendments and addenda thereto, and is familiar therewith  and  agrees
      to comply with and perform all provisions thereof  applicable  to  the
      Sub-Contractor.  The intent of the Contract documents  is  to  include
      all items necessary for the proper execution  and  completion  of  the
      work.  The contract documents are complementary and what  is  required
      by any one shall be as binding  as  if  required  by  all.   Work  not
      covered in the Contract documents will not be required, unless  it  is
      consistent therewith and is reasonable [sic]  inferable  therefrom  as
      being necessary to produce the intended results.

The second reads:

      Contractor has heretofore entered into a General Contract with [Flying
      J], hereinafter called the Owner, to furnish and pay for all necessary
      and required labor, materials . . . to perform all work required . . .
      inclusive of, but not limited to the project plans and  specifications
      . . . schedules, drawings and amendments by addenda, as prepared by  .
      . . the Architect, and known as Flying “J”  Travel  Plaza,  which  are
      hereby made a part of the General Contract between the Owner  and  the
      Contractor and are  hereby,  made  a  part  of  this  subcontract,  as
      applicable  to  the  work  stated  therein  and   pursuant   to   this
      subcontractor’s intent to enter into this  sub-contractual  agreement,
      with reference to any and all of said work.


      MPACT argues that these provisions,  and  particularly  the  sentence,
“The contract documents are complementary and what is required  by  any  one
shall be  as  binding  as  if  required  by  all,”  show  that  the  General
Conditions, which were incorporated into the General Contract between  MPACT
and Flying J, were incorporated into the subcontracts.   The  Subcontractors
respond, and the Court of Appeals agreed, that  provisions  of  the  General
Contract were incorporated for the limited purpose of governing the work  to
be performed.  They emphasize that the sentence MPACT relies on is  preceded
and followed by sentences pertaining specifically to  work,  and  that  this
limits the effect of that sentence.

      While the cited provisions support both arguments, the larger  context
suggests  that  the  Subcontractors’  construction   is   correct.    Allied
Structural Steel Co. v. State, 148 Ind. App. 283, 288,  265  N.E.2d  49,  52
(1970) (“The true meaning  of  a  contract  is  to  be  ascertained  from  a
consideration  of  all  its  provisions,  and   a   liberal   or   technical
construction of an isolated clause should not  be  indulged  to  defeat  the
true meaning.”); Gen. Ins. Co. of Am. v. Hutchison, 143 Ind. App. 250,  254,
239 N.E.2d 596, 598-99 (1968) (“It is the general rule of law in  our  State
that words, phrases,  sentences,  paragraphs  and  sections  of  a  contract
cannot  be  read  alone.”).   Of  particular  importance  is  the   language
surrounding Article VI(b).  Not only do the sentences within that  provision
specifically discuss the work to be performed, but all other  provisions  in
the article of which it is a part  relate  to  the  work  to  be  performed.
Clause (a) of Article VI requires that the  Subcontractor  “supply  adequate
tools, appliances, and equipment, [and]  a  sufficient  number  of  properly
skilled workmen”  to  ensure  that  the  work  gets  done  “efficiently  and
promptly.”  Clause (c) discusses the Architect’s control over  the  work  to
be performed.  Clause (d) addresses the Subcontractors need to  get  permits
and licenses.  Taken as a whole, this  article  is  about  the  work  to  be
performed  and  nothing  more.   If  the  parties  intended  to   bind   the
Subcontractors to arbitration,  logic  dictates  that  an  incorporation  by
reference clause clearly apply to the entire contract – or be in a  separate
section on rights and remedies or  at  least  with  contract  provisions  on
liability and indemnification – rather than with provisions relating to  the
work.

      Other provisions are telling as well, though not conclusive.   Article
5.3.1 of the General Conditions states:

      By appropriate agreement, written where legally required for validity,
      the Contractor shall require each Subcontractor, to the extent of  the
      Work to be  performed  by  the  Subcontractor,  to  be  bound  to  the
      Contractor by terms of the Contract Documents, and  to  assume  toward
      the Contractor all the  obligations  and  responsibilities  which  the
      Contractor,  by  these  Documents,  assumes  toward  the   Owner   and
      Architect.  Each subcontract . . . shall allow to  the  Subcontractor,
      unless specifically provided otherwise in the  subcontract  agreement,
      the benefit of all rights, remedies and redress against the Contractor
      that the Contractor, by the Contract Documents, has against the Owner.



Viewing this provision with the language of  the  subcontract  that,  “[t]he
Sub-contractor acknowledges that he has read the General contract . . .  and
is familiar therewith and agrees to comply with and perform  all  provisions
thereof applicable to the Sub-Contractor,” suggests that the  Subcontractors
are required to submit to arbitration.  The Subcontractors agreed to  comply
with provisions of the General Contract  applicable  to  them,  and  Article
5.3.1 of the General  Conditions,  as  part  of  the  General  Contract,  is
applicable to subcontractors.  Although Article 5.3.1 was probably  intended
to bind subcontractors directly, the language itself puts the burden on  the
contractor to obtain an agreement from subcontractors  to  assume  the  same
responsibilities as the contractor assumes  toward  the  owner.   A  comment
from  the  American  Institute  of  Architects,  drafters  of  the   General
Conditions, provides some guidance.  It first states, “A  basic  requirement
of the contract is  that  subcontractors  be  bound  by  the  terms  of  the
contract documents.  AIA  Document  A401  Standard  Form  Agreement  Between
Contractor and Subcontractor, so provides.”  Am. Inst. of  Architects,  A201
Commentary (1997).  But the  next  sentence  reads,  “If  other  subcontract
forms are utilized, care must be taken to coordinate them with  Subparagraph
5.3.1.”   Id.   This  indicates  that  if  the   general   contractor   uses
subcontract forms other than those provided by the AIA – which MPACT did  in
this case – it must in its own contract include a  provision  requiring  the
subcontractors to assume the same responsibilities that  it  assumes  toward
the owner.

      MPACT may well have believed the language it used  was  sufficient  to
bind the Subcontractors to arbitration.  It cites several cases  to  support
its contention that the language in its  subcontracts  validly  incorporated
the arbitration clause by reference.  The Subcontractors  respond  that  all
of those cases can be distinguished from this one.   Uniroyal,  Inc.  v.  A.
Esptein & Sons, Inc., 428 F.2d 523, 524  (7th  Cir.  1970)  (in  section  of
contract discussing general obligations, the  subcontract  stated  that  the
subcontractor agrees “to assume toward [the contractor] all the  obligations
and responsibilities that [the  contractor],  by  those  documents,  assumes
toward the Owner,” and that “[i]n the matter of  arbitration,  their  rights
and obligations and all procedure shall be analogous to those set  forth  in
this Contract”); Kvaerner ASA v. Bank of Tokyo – Mitsubishi Ltd.,  210  F.3d
262, 265 (4th Cir. 2000) (subcontract used the phrase the “the  same  rights
and remedies” and in a provision concerning default);  Maxum,  779  F.2d  at
979 (subcontract stated that “the  Subcontractor  shall  be  bound  by,  and
expressly assumes for the benefit of the  Contractor,  all  obligations  and
liabilities which the  Contract  Documents  impose  upon  the  Contractor”);
Exch. Mut. Ins. Co. v. Haskell Co.,  742  F.2d  274,  275  (6th  Cir.  1984)
(“Subcontractor hereby assumes the  same  obligations  and  responsibilities
with respect to his performance  under  this  Subcontract,  that  Contractor
assumes towards Owner . . . .”); J.S. & H. Constr. Co.  v.  Richmond  County
Hosp. Auth., 473 F.2d  212,  213-14  n.3  (5th  Cir.  1973)  (“Subcontractor
agrees to be bound to the Contractor by all of the terms  of  the  agreement
between the Contractor and the Owner and by the Contract  Documents  and  to
assume  toward   the   Contractor   all   of   the   obligations   and   the
responsibilities that the Contractor by  those  instruments  assumes  toward
the Owner.”); Vespe Contracting Co. v. Anvan Corp., 399 F.  Supp.  516,  520
n.4 (E.D. Pa. 1975) (“Subcontractor . . . shall  assume  towards  Contractor
all the obligations and responsibilities that the Contractor . .  .  assumes
towards Owner.”).  We agree that these cases  are  distinct  from  the  case
here.   In  all  of  the  other  cases,  the  language   incorporating   the
arbitration provision is more clear and explicit than  in  the  subcontracts
here.[5]

      Courts are required to give effect to parties’  contracts  and  to  do
so, courts look to the words of a  contract.   In  contracting,  clarity  of
language is key.  Here, however,  provisions  in  the  subcontracts  support
both arguments, at least in part.  When there is ambiguity  in  a  contract,
it is construed against its drafter.  Philco Corp.  v.  Automatic  Sprinkler
Corp. of Am., 337 F.2d 405, 408 (7th Cir. 1964);  Smith  v.  Sparks  Milling
Co., 219 Ind. 576, 603, 39 N.E.2d 125, 135 (1942); Bicknell  Minerals,  Inc.
v. Tilly, 570 N.E.2d 1307, 1313 (Ind. Ct. App.  1991),  trans.  denied.   In
this instance, the AIA Standard Form of  Agreement  Between  Contractor  and
Subcontractor was not used.  MPACT instead  drafted  its  own  subcontracts.
It was therefore MPACT’s responsibility  to  ensure  that  its  subcontracts
conformed to the requirements of the  General  Conditions  and  incorporated
the arbitration clause.  MPACT did not do so.

      The problem in this case seems to have  resulted  from  poor  contract
drafting and inadequate contract negotiations.  Each side  believed  at  the
time of contract execution that the contract provided for what it  wanted  –
in MPACT’s case, for arbitration, and in the Subcontractors’ case,  not  for
arbitration.  Regardless, it is clear that arbitration was not  sufficiently
discussed by the parties.  This leads to one conclusion, that there  was  no
meeting of the minds between  the  parties  on  the  issue  of  arbitration.
Consequently, we find that there  was  no  agreement  to  arbitrate  between
MPACT and the Subcontractors and the  Subcontractors  are  not  required  to
arbitrate their disputes with MPACT.

      MPACT also sought arbitration of its  disputes  with  Flying  J.   The
Court of Appeals found that the disputes were governed  by  the  arbitration
provision in the General Conditions of the General Contract, and  held  that
MPACT was entitled to arbitration with Flying J.  We  summarily  affirm  the
Court of Appeals on this point.  Ind. Appellate Rule 58(A)(2).

                                     III

      The Subcontractors additionally argue that MPACT waived its  right  to
arbitrate, if such a right actually exists.  Whether a party has waived  the
right to arbitration depends primarily upon whether  that  party  has  acted
inconsistently with its right to arbitrate.   Welborn  Clinic  v.  Medquist,
Inc.,  301  F.3d  634,  637  (7th  Cir.  2002);  St.  Mary’s  Med.  Ctr.  of
Evansville, Inc. v. Disco Aluminum Prods. Co., 969 F.2d 585, 588  (7th  Cir.
1992); Kilkenny v. Mitchell Hurst Jacobs & Dick, 733 N.E.2d 984,  986  (Ind.
Ct. App. 2000), trans. denied, 753 N.E.2d 8 (Ind. 2001).  This  requires  an
analysis of the specific facts in each case.  Ernst &  Young  LLP  v.  Baker
O’Neal Holdings, Inc., 304 F.3d 753, 756 (7th Cir. 2002);  St.  Mary’s  Med.
Ctr., 969 F.2d at 588; Kilkenny, 733 N.E.2d at 986.

      Some facts suggest that MPACT may have waived its right  to  arbitrate
by actively participating in the litigation.  Ernst & Young  LLP,  304  F.3d
at 757-58; St. Mary’s Med. Ctr., 969 F.2d at  589.   MPACT  filed  a  cross-
claim against  Flying  J  for  breach  of  contract  and  filed  cross-  and
counterclaims against Flying J and the Subcontractors to foreclose  its  own
mechanic’s lien.  MPACT also participated in  telephone  conferences  and  a
scheduling conference where summary judgment  deadlines  and  a  trial  date
were set.

      The filing of counterclaims and cross-claims does not always  indicate
active participation in litigation.  While all cross-claims are  permissive,
some counterclaims are compulsory, that is,  a  party  must  bring  them  or
waive them.  Ind. Trial Rule 13.  A party should not be held to have  waived
its right to arbitrate when, in response to a complaint  filed  against  it,
it raises  counterclaims  in  order  to  preserve  them.   Cf.  Underwriting
Members of Lloyds of London v. United Home Life Ins. Co., 549 N.E.2d 67,  71
(Ind. Ct. App. 1990)  (stating  that  participation  in  discovery  did  not
result in a waiver of arbitration because defendant was  required  by  court
order  to  do  so),  adopted  by,  563  N.E.2d  609  (Ind.  1990).   MPACT’s
counterclaims in this case are compulsory.  The cross-claims  are  not,  and
to that extent, MPACT  could  be  seen  as  actively  participating  in  the
litigation.  But that  alone  is  not  sufficient  to  establish  a  waiver,
particularly in light of the other facts.

      In its answer filed March 29, 2002,  MPACT  stated  that  it  was  not
waiving its right to arbitration and in its affirmative defenses,  requested
that the claims be submitted to arbitration.   St.  Mary’s  Med.  Ctr.,  969
F.2d at 589 (finding that defendant waived the right  to  arbitrate  because
in the ten months that passed since being sued, defendant filed a motion  to
dismiss or for summary judgment and then did  not  raise  arbitration  until
losing its motion); Kilkenny, 733 N.E.2d at 987  (“This  is  clearly  not  a
case where a request for arbitration was plead in the initial complaint  and
then not again asserted until  discovery  was  complete  or  an  unfavorable
result on the individual claims was imminent.”); Lloyds, 549  N.E.2d  at  71
(finding no waiver  because  defendant  “asserted  its  right  to  arbitrate
throughout the proceedings”).  MPACT also did not file  motions  to  dismiss
or for summary judgment before asserting  its  right  to  arbitrate.   These
facts show that MPACT acted consistently with its right to arbitrate, if  it
had one, and so its actions would not have  constituted  a  waiver  of  that
right.
                                 Conclusion

      We grant transfer, summarily affirm  the  decision  of  the  Court  of
Appeals reversing the  trial  court’s  denial  of  MPACT’s  motion  to  stay
proceedings and compel arbitration as to Flying  J,  and  affirm  the  trial
court’s denial of MPACT’s motion as to the  Subcontractors.   This  case  is
remanded to the trial court for further  proceedings  consistent  with  this
opinion.

Dickson and Rucker, JJ., concur.
Boehm, J., dissents with a separate opinion in which Shepard, C.J., joins.









































Boehm, J., dissenting.


      I respectfully dissent.  This is  a  typical  multiparty  construction
litigation,  where  various  parties  are  pointing   fingers   in   various
directions and claiming  that  whatever  went  wrong  with  the  project  is
somebody else’s—anybody else’s—problem.  I agree that state law governs  the
formation of the contract and that nothing in the  Federal  Arbitration  Act
requires  that  these  disputes  between  subcontractors  and  the   general
contractor be arbitrated  unless  the  parties  agreed  to  that  method  of
dispute resolution.  I believe, however, that these agreements do  call  for
arbitration of the entire multiparty dispute among the  owner,  the  general
contractor, and these several subcontractors.


      The agreement between the  general  contractor  and  the  owner  is  a
standard printed form AIA  construction  agreement.   All  agree  that  that
contract includes an enforceable arbitration clause, and an  undertaking  to
bind subcontractors to the  same  terms  that  obligate  the  general.   The
general’s agreements with the subs provide that each  sub  acknowledges  the
principal agreement and agrees to be bound by it.  The  principal  agreement
provides, inter alia, that the general will impose conforming conditions  on
all subs.  These agreements are among businesses fully  familiar  with  this
sort of arrangement, and fully cognizant that  the  last  thing  either  the
general or the owner wants is  piecemeal  litigation  with  different  subs.
The result the majority reaches produces an arbitration  between  the  owner
and the general and litigation with one or more subs in  a  separate  forum.
The majority concedes  that  the  general  intended  to  bind  the  subs  to
arbitration, but points to imprecision in the language  used  to  accomplish
that.  It seems to me that the subs did understand,  or  should  have,  that
arbitration was intended.  They should be held to have accepted  arbitration
when  they  accepted  these  agreements.   Accordingly,  I   would   require
arbitration of this entire dispute in one proceeding.


      The majority points to what I agree is less than elegant  phrasing  of
the agreement, and what it describes as “inadequate contract  negotiations.”
 I think these agreements, given the context, were sufficient to make  clear
to the subs that they were expected to arbitrate  their  disputes  with  the
general or the owner.  Particularly in  an  industry  where  arbitration  is
widely used, ambiguity does not necessarily lead to the conclusion  that  no
meeting of the minds occurred.  Rather,  I  would  conclude  that  ambiguity
should be construed in favor of finding  an  agreement  to  arbitrate  where
that  is  commonplace  in  the  industry.   We  have  on  several  occasions
expressed support for the policy under  Indiana  law  favoring  arbitration.
PSI Energy, Inc. v. AMAX, Inc., 644 N.E.2d 96, 99 (Ind. 1994); Sch. City  v.
East Chicago Fed’n of Teachers, Local No. 511, 622  N.E.2d  166,  169  (Ind.
1993).  These rulings also support finding an agreement to  arbitrate  where
the documents support that conclusion, albeit with less than precision.


      Shepard, C.J., joins.



-----------------------
[1] MPACT and Flying J also entered into a contract to  construct  a  travel
plaza in Oklahoma.  The Court  of  Appeals  stated:  “Because  the  Oklahoma
contract does not appear to have bearing on the present  appeal,  and  based
upon counsel’s statements at oral argument, we do not expressly  address  it
herein.”  MPACT Constr. Group, LLC v. Superior Concrete Constructors,  Inc.,
785 N.E.2d 632, 635 n.3 (Ind. Ct. App. 2003).  Similarly, we do not  address
that contract here.

[2] The subcontractors are  Superior  Concrete  Constructors,  Inc.,  Gary’s
Plumbing  Service,  Inc.,  Koberstein  Trucking,  Inc.,  Combs  Landscape  &
Nursery, Inc., B & B Electric Co., Inc., J.D. Music Tile Company, Inc.,  and
E & B Paving, Inc.
[3] Some of the subcontracts included a choice of law  clause  stating  that
Indiana law would apply and others stating that Tennessee law  would  apply.
Ind. Code § 32-28-3-17 (Supp. 2002), however, makes void  any  provision  in
“a contract for the improvement of real estate in Indiana” that  “makes  the
contract subject to the laws of another state.”  Therefore,  we  will  apply
only Indiana law.

[4]  Cf.  First  Options,  514  U.S.  at  944-45   (requiring   “clear   and
unmistakable” evidence that parties agreed to submit to  an  arbitrator  the
question who should decide whether the parties agreed to arbitrate,  because
it is different from the question involving  the  scope  of  an  arbitration
provision, in which “the parties [already] have  a  contract  that  provides
for arbitration of some issues”).

[5] MPACT also cited U.S. Fid. & Guar. Co. v. West Point  Constr.  Co.,  837
F.2d 1507 (11th Cir. 1988), but the language in that case is conclusory  and
as such, does not aid MPACT’s argument.  Additionally, MPACT  cited  J  &  S
Constr. Co. v. Travelers Indem. Co., 520 F.2d 809 (1st Cir.  1975),  but  it
is not on point.