Morgen & Oswood Construction Co. v. Big Sky of Montana, Inc.

                                   No. 12997

         I N THE SUPREME COURT O THE STATE O M N A A
                                F           F OTN

                                       1976



MORGEN & O W O CONSTRUCTION CO,
              S OD
I N C . , A M N A A CORPORATION,
             OTN

                           P l a i n t i f f and A p p e l l a n t ,



B I G SKY O MONTANA, I N C
           F
DELAIJAR E CORPORATION,
                                ., a
                           Defendant and Respondent.



Appeal from:     D i s t r i c t Court of t h e Eighteenth J u d i c i a l D i s t r i c t ,
                 Honorable W. Id. L e s s l e y , Judge p r e s i d i n g .

Counsel of Record:

     For Appellant :

           J a r d i n e , Stephenson, B l e w e t t & Weaver, G r e a t F a l l s ,
             Mon t a na
           J a c k L. Lewis a r g u e d , G r e a t F a l l s , Montana

     F o r Respondent :

           Landoe and Gary, Bozeman, Montana
           J o s e p h B. Gary a r g u e d and S t e p h e n B a r r e t t a p p e a r e d ,
             Bozeman, Montana
           David J. P e n w e l l , G a l l a t i n Gateway, Montana



                                                   Submitted:          September 3 , 1976

                                                      Decided :        NRVZ R ISif;
Filed:
            2 :' ;g$
~ r J:u s t i c e John Conway Harrison d e l i v e r e d t h e Opinion of t h e
Court.


          This i s an appeal from a judgment of t h e d i s t r i c t c o u r t ,

G a l l a t i n County, f o r defendant i n an a c t i o n t o f o r e c l o s e on a

mechanic's l i e n .

          P l a i n t i f f Morgen & Oswood Construction Co., I n c . (Morgen &

Oswood) brought t h i s a c t i o n t o f o r e c l o s e a mechanic's l i e n on

seventeen b u i l d i n g s containing f i f t y condominium u n i t s a t Big

Sky of Montana, Inc. (Big Sky) s i t e i n t h e G a l l a t i n Canyon, south

of Bozeman.         These were t h e f i r s t condominium u n i t s b u i l t a t Big

Sky and were b u i l t when t h e a r e a was s t i l l r e l a t i v e l y p r i m i t i v e .

          Big Sky sought b i d s on t h e p r o j e c t from s e v e r a l c o n t r a c t o r s

b u t d i d n o t request a b i d from Morgen & Oswood.                       Morgen & Oswood

approached Big Sky asking t o be allowed t o b i d .                          It was given t h e

s p e c i f i c a t i o n s f o r t h e job and informed t h e time allowed f o r t h e

completion of t h e p r o j e c t would be 114 days, which meant t h e

schedule was t i g h t .          The s p e c i f i c a t i o n s contained a c l a u s e

exacting a $500 per day deduction f o r each day t h e p r o j e c t was l a t e .

A t Big Sky's r e q u e s t an a l i t e r n a t i v e b i d was submitted on t h e

p r o j e c t i f t h e r e would be an e x t r a 46 days added t o t h e completion

time.     Morgen & Oswood submitted an a l t e r n a t i v e b i d $15,000 lower

than t h e 114 day b i d .         This a l t e r n a t i v e b i d was r e j e c t e d by Big

Sky.

          The c o n t r a c t was awarded t o Morgen & Oswood and Big Sky

allowed work on the p r o j e c t t o begin twelve days before t h e d a t e

c a l l e d f o r i n t h e c o n t r a c t , without s t a r t i n g t h e    114 day c l o c k

running.
          The questions presented f o r review a r e :

           1 ) Was t h e $500 per day deduction a penalty v i o l a t i v e of

s e c t i o n 13-804, R.C.M.       1947?

           2)    Did t h e d i s t r i c t c o u r t e r r i n f i n d i n g t h a t January 3,

1972, .was t h e d a t e upon which t o end t h e $500 per day deduction?

           3)    Did t h e d i s t r i c t c o u r t err i n f i n d i n g t h e r e was n o ,

proof t h a t Big Sky c o n t r i b u t e d s u b s t a n t i a l l y t o t h e delay i n t h e

completion of t h e p r o j e c t ?

          4)    Did t h e d i s t r i c t c o u r t e r r i n f i n d i n g t h a t Big Sky

made a v a l i d tender of t h e money due t o Morgen & Oswood?
                                                              I


          The f i r s t question involves c o n s t r u c t i o n of s e c t i o n s

13-804 and 13-805, R.C.M.               1947 which provide:

          ''13-804.  Contracts f i x i n g damages void. Every c o n t r a c t
          by which t h e amount of damage t o be paid, o r o t h e r com-
          pensation t o be made, f o r a breach of an o b l i g a t i o n ,
          i s determined i n a n t i c i p a t i o n t h e r e o f , i s t o t h a t e x t e n t
          void, except a s expressly provided i n t h e next section.''

          "13-805.        Exception. The p a r t i e s t o a c o n t r a c t may a g r e e
          t h e r e i n upon an amount which s h a l l be presumed t o be an
          amount of damage s u s t a i n e d by a breach t h e r e o f , when,
          from t h e n a t u r e of t h e case, i t would be impracticable
          o r extremely d i f f i c u l t t o f i x t h e a c t u a l damage.''

The Montana cases i n t e r p r e t i n g t h e s e s e c t i o n s e s t a b l i s h t h a t a

penalty c l a u s e i s prima f a c i e void and t o come w i t h i n t h e exception,

f a c t s must be a l l e g e d and proven from which t h e c o u r t can say

t h e l i q u i d a t e d damages c l a u s e i s v a l i d because t h e damages a r e

by t h e n a t u r e of t h e c a s e extremely d i f f i c u l t o r impracticable t o

fix.     Deuninck v. West G a l l a t i n I r r i g a t i o n Company, 28 Mont. 255,

72 P. 618; C l i f t o n v. Willson, 47 Mont. 305, 132 P. 424.

          Big Sky met t h i s burden.             It presented evidence which i n d i c a t e d

t h e $500 per day f i g u r e was a r r i v e d a t by estimating l o s t r e n t a t

$120 per day; i n t e r e s t on money borrowed t o b u i l d t h e p r o j e c t a t
$440 per day; and $60 per day heating and light expense on the
units.    Big Sky also considered the harm to its sales effort if

the units were not completed in October as promised.     These

estimates were at best guesses, based on some prior experience

and knowledge of the project.    The total was rounded to $500 per

day as a reasonable conservative estimate of the loss Big Sky

would suffer if the project was late. Big Sky also offered evi-
dence which indicated that the total damage suffered by Big Sky

exceeded the $500 per day figure. Actual proof of the accuracy
and basis of these estimated figures is very nearly impossible.

As a result, construction contracts often provide for a fixed

sum as damages.    In 5 Corbin on Contracts, Damages, 31072, it is
stated:

         "In contracts for the construction and delivery of
         buildings or machinery, it is often provided that
         a fixed sum shall be paid for each day's delay in
         completion beyond a date agreed upon. Since the
         injury caused by such delay is nearly always diffi-
         cult to determine, the courts strongly incline to
         accept the estimate as reasonable and to enforce
         it. Jc * Jc"

         In 60 California Law Review 84, 122, Professor Justin Sweet,

discusses the California case law interpreting 951670, 1671,
California Civil Code, identical to fj&ct%dhs:13-884,13+805,R.C.~.

1947, and points out the reasons that such clauses are usually
upheld where there is an unexcused delay by the contractor:

         '* * * First, while the liquidation amounts may not
          I
         actually be bargained, the contractor can take this
         into account when he makes his bid. Second, most
         construction contractors are not so unsophisticated
         as to merit special protection by the courts. Third,
         courts enforce these clauses as a means of saving
         themselves from having to decide difficult fact questions
         relating to damages. Finally, these clauses are enforced
         because delays do cause losses, but the actual loss is
         often not provable under traditional damage rules, which
         require certainty, proof of causation, and forseeability."
Morgen & Oswood knew of the strict time limits and took them

into consideration when its bid was submitted. It submitted a

bid that was $15,000 less on the same project, if the time were
extended 46 days.   It is clear Big Sky suffered damages from the
delay in completion, but it is also true there would be difficulty
in showing the actual amount under the damages rules. The $500

per day deduction is the type of clause courts usually enforce and

one which meets all the requirements of section 13-805, R.C.M.

1947. The only serious impediment to finding that it is a valid

liquidated damages clause is that Big Sky, in its contract, referred
to the $500 per day deduction as a "penalty". This is not in
                              At
and of itself determinative. 15 Williston on Contracts, Third

Edition Section 784, p. 730, it is said:

      " ( ) The mere denomination of the sum to be paid
       '2
       as "liquidated damages," or as "a penalty," is
       not conclusive on the court as to its real character.
       Although designated as "liquidated damages" it may
       be construed as a penalty, and often when called a
       "penalty" it may be held to be liquidated damages,
       where the intention to the contrary is plain."'

The Oklahoma Supreme Court in Waggoner v.Johnston (Okla.1965),
408 P.2d 761, 769, when interpreting a contract in light of
statutory provisions identical to section 13-804 and section
13-805, R.C.M. 1947, said:

       "Whether the forfeiture provision imposed a penalty,
       or provided for liquidated damages, is to be determined
       from the language and subject matter of the contract,
       the evident intent of the parties and all the facts
       and circumstances under which the contract was made.
       The most important facts to be considered are whether
       the damages were difficult to ascertain, and whether
       the stipulated amount is a reasonable estimate of
       probable damages or is reasonably proportionate to the
       actual damage sustained at the time of the breach.''

Here the "most important facts" are in Big Sky's favor, the damages

were difficult to determine and they proved to be a reasonable
estimate of the damages actually suffered.
          The United S t a t e s Supreme Court faced a s i m i l a r problem

i n United S t a t e s v. Bethlehem S t e e l Co., 205 U.S.                    105, 27 S.Ct.

450, 51 L ed 731,737, t h e Court s a i d t h a t while t h e word "penalty"

was used and n o t t h e term " l i q u i d a t e d damages" t h a t :

          "*   **       I t was used simply t o provide t h a t t h e amount
          named might be deducted i f t h e r e were a delay i n
          d e l i v e r y . E i t h e r expression i s n o t always conclusive as
          t h e meaning of t h e p a r t i e s .      ***
          "*   **     I t would have been very               unusual t o allow t h e
          company t o o b t a i n t h e c o n t r a c t      f o r the construction
          of t h e s e . c a r r i a g e s , and y e t t o   place i t under no l i a -
          b i l i t y to. f u l f i l i t a s t o time       of d e l i v e r y , s p e c i a l l y
          agreed upon, o t h e r than t o pay                only those a c t u a l
          damages (not exceeding $35 per                     day) t h a t might be proved
          were n a t u r a l l y and proximately             caused by t h e f a i l u r e
          t o deliver."

Here, t h e same statement a p p l i e s .            The completion time was

p l a i n l y important and was t h e s u b j e c t of bidding.                 Morgen &

Oswood o f f e r e d a $15,000 decrease i n t h e c o n t r a c t p r i c e f o r an

i n c r e a s e of 46 days i n c o n t r a c t time which amounts t o over $300

per day.       This was refused by Big Sky.                     It i s obvious t h a t Morgen

& Oswood should n o t g e t t h e higher c o n t r a c t p r i c e and a t t h e

same time be a b l e t o avoid t h e time l i m i t which served a s t h e

c o n s i d e r a t i o n f o r t h e higher amount.         The use of t h e word "penalty1'

does n o t r e f l e c t c a r e f u l draftmanship b u t i t i s n o t a talisman

which prevents i n q u i r y i n t o t h e r e a l i t y of t h e i n t e n t of t h e

p a r t i e s and t h e f a c t s and circumstances surrounding t h e agreement.

The $500 per day deduction was an amount s t i p u l a t e d a s l i q u i d a t e d

damages and meets t h e requirements of s e c t i o n 13-805, R.C.M.                            1947.

I t i s a reasonable e s t i m a t e of damages which were impracticable

o r extremely d i f f i c u l t t o f i x .

          The remaining questions on appeal involve t h e determinations

by t h e d i s t r i c t c o u r t 1 ) January 3 , 1972 was t h e proper d a t e t o

end t h e deduction of t h e : l i q u i d a t e d damages; 2) Big Sky d i d n o t
c o n t r i b u t e s u b s t a n t i a l l y t o t h e delay i n completion; and 3)

t h e amount due was v a l i d l y tendered by Big Sky on February 25,

1972.      I t i s not a f u n c t i o n of t h i s Court t o make i t s own d e t e r -

mination a s t o t h e f a c t s and t h e law, r a t h e r i t reviews t h e

f i n d i n g s of t h e d i s t r i c t c o u r t ,   The Court i n Hellickson v.

B a r r e t t Mobile Home Transport, I n c . , 161 Mont. 455, 458, 507

P.2d 523, quoting from Hornung v. E s t a t e of Lagerquist, 155 Mont.

412, 420, 473 P.2d 541, pointed o u t :

         ".'Our duty i n reviewing f i n d i n g s of f a c t i n a c i v i l
           a c t i o n t r i e d by t h e d i s t r i c t c o u r t without a j u r y
           i s confined t o determining whether t h e r e i s s u b s t a n t i a l
          c r e d i b l e evidence t o support them. I I 1

The Court put i t another way i n Kamp v. F i r s t National Bank and

T r u s t Co., 161 Mont. 103, 106, 504 P.2d 987, quoting from Morrison

v. C i t y of B u t t e , 150 Mont. 106, 112, 431 P.2d 79:

           '"This c o u r t w i l l n o t overturn t h e holdings o r f i n d i n g s
           of a t r i a l c o u r t u n l e s s t h e r e i s a decided preponderance
           of t h e evidence a g a i n s t them, and, when t h e evidence
           f u r n i s h e s reasonable grounds f o r d i f f e r e n t conclusions,
           f i n d i n g s w i l l n o t be d i s t u r b e d .'"'

           Morgen & Oswood argues t h a t some of t h e seventeen b u i l d i n g s

were complete long before t h e d a t e upon which t h e a r c h i t e c t signed

t h e c e r t i f i c a t e of f i n a l completion.        I t a l s o p o i n t s out t h a t a

c e r t i f i c a t e of s u b s t a n t i a l completion was signed on December 11, 1971.

           W n o t e t h e c e r t i f i c a t e of s u b s t a n t i a l completion was
            e

accompanied by an extensive punch l i s t of unfinished work and

even t h e f i n a l completion c e r t i f i c a t e was accompanied by a punch

l i s t of unfinished i t e m s .            One important b i t of evidence which

supports t h e January completion d a t e , i s t h e f a c t t h a t Big Sky

had a s s t r o n g an i n t e r e s t i n g e t t i n g t h e c e r t i f i c a t e of f i n a l

completion a s d i d Morgen & Oswood.
       The "Unit Ownership Act", Chapter 23, Title 67, R.C.M.

1947, as it provided at the time of the contract, required a
statement by the architect or professional engineer who prepared

the floor plan, certifying the accuracy of the plans and the

date construction was completed. This statement accompanied

the recording of the declaration which had to be filed. This

meant that no sale could be closed and recorded until construction

was completed on the entire project.   Big Sky indicated there were
buyers who backed out when the completion was not on time and

those sales could have been made final, if the closings had been
on schedule. The architect testified there was considerable

pressure on him from Big Sky to certify completion. Testifying

about the certification that he signed he said:

       "* * *   I was very hesitant to sign anything until
       actually the last final check list item would be
       done. However, it could also be taken as substan-
       tial completion. And this was not clear to us at
       the time. Mr. Penwell was under pressure to close
       sales and the check list was not being completed.
       So we initiated this agreement in January that would
       essentially be the final completion still with the
       check list which was an unorthodox procedure just so
       I could sign them and say they were completed, I
       could sign them with a better conscience .'
                                                 I

Big Sky could not, and did not, close any sales until after all

of the buildings were certified as being complete.   It was reasonable
for the district court to use the January 3, 1972 date as the end

da tE for the liquidated damages.
       60 California Law Review 84, 123, points out:
       "The second interpretation problem courts frequently
       face is determining when a project is completed for
       liquidation purposes. The general answer is that
       actual, not substantial, completion is required. How-
       ever, courts will be hesitant to apply this rule where
       the stipulated damages are high and the project is
       available for use."
Here, t h e damages a r e high but t h e p r o j e c t was not ready f o r

t h e use Big Sky intended, t h e s a l e of t h e s e u n i t s .                 There i s

no showing t h a t t h e evidence preponderates a g a i n s t t h i s f i n d i n g

by t h e d i s t r i c t c o u r t and i t i s supported by s u b s t a n t i a l evidence.

           W f i n d no preponderance of evidence a g a i n s t t h e d i s t r i c t
            e

c o u r t ' s finding t h a t Morgen & Oswood f a i l e d t o prove a s u b s t a n t i a l

i n t e r f e r e n c e by Big Sky with t h e c o n t r a c t o r ' s work and t h a t

Morgen & Oswood f a i l e d t o make a p p l i c a t i o n i n compliance w i t h

t h e c o n t r a c t f o r extension of time.             Morgen & Oswood argue t h a t

Haggerty v. Selsco, 166 Mont. 492, 534 P.2d 874, which h e l d t h a t

delay caused by t h e owner c o n s t i t u t e s a waiver of l i q u i d a t e d

damages, a p p l i e s i n t h e i n s t a n t case.          W do n o t a g r e e , because
                                                               e

t h e r e i s no f i n d i n g t h a t Big Sky caused t h e delay here.                    It is

very d i f f i c u l t t o pinpoint with any c e r t a i n t y t h e reasons f o r

t h e delay, b u t t h e i n a b i l i t y t o g e t l a b o r , e s p e c i a l l y s k i l l e d

l a b o r , and t h e primative conditions a t t h e job s i t e were a p a r t

of t h e cause.        These m a t t e r s were t h e c o n t r a c t o r ' s r e s p o n s i b i l i t y

which had t o be taken i n t o account a t t h e t i m e t h e b i d s were

submitted.

           The d i s t r i c t c o u r t ' s finding t h e r e was a v a l i d tender i s

supported by s u b s t a n t i a l evidence on t h e record.                    Negotiations

between Big Sky and Morgen & Oswood broke down and Big Sky gave

a check t o Morgen & Oswood f o r t h e balance due on t h e c o n t r a c t ,

l e s s t h e l i q u i d a t e d damages.     This check was refused and returned.

The mechanic's l i e n was f i l e d and t h i s s u i t i n s t i t u t e d .             The n e t

amount due t o Morgen & Oswood was paid with no s t r i n g s a t t a c h e d .

Since t h e l i q u i d a t e d damages c l a u s e i s v a l i d and t h e check was

f o r t h e n e t amount due a f t e r t h e deduction of t h e l i q u i d a t e d

damages, t h e l i e n was improperly f i l e d .
          W have examined o t h e r i s s u e s r a i s e d and f i n d no m e r i t i n
           e

them.

          The d e c i s i o n of t h e d i s t r i c t c o u r t i s affirmed.




                                                     \   &4,5,&/+G,       &      ,   ?/
                                                                                     &
                                                                                     ,
                                             '   Justice              /




W Concur:
 e




Chief J u s t i c e




 Justices.                                       \




  C J&
   D&
Fly.
J-Go,d! Jack Shanstrom, D i s t r i c t
   dge, s i t t i n g f o r J u s t i c e