No. 81-265
IN THE SUPREME COURT OF THE STATE OF MONTANA
SHELDON CHANDLER and MARILYN
CHANDLER, husband and wife,
Plaintiffs land Respondents,
ROBERT H. MADSEN,
Defendant and Appellant.
Appeal from: District Court of the Thirteenth Judicial District,
In and for the County of Yellowstone
Honorable Robert Wilson, Judge presiding.
Counsel of Record:
For Appellant:
Hibbs, Sweeney, Colberg, Jensen and Koessler,
Billings, Montana
Maurice Colberg argued, Billings, Montana
For Respondents:
Crowley, Haughey, Hanson, Toole & Dietrich, Billings,
Montana
Bruce Toole argued, Billings, Montana
Submitted: December 4, 1981
Decided: nRp1 5 @tl
MAR
Filed. 15 7982
Mr. J u s t i c e J o h n Conway H a r r i s o n d e l i v e r e d the Opinion of
the Court.
'This a p p e a l arises from a complaint by Sheldon and
Marilyn Chandler, husband and w i f e , a g a i n s t R o b e r t Yladsen,
s e e k i n g damages f o r n e g l i g e n c e , b r e a c h of implied warranty
of h a b i t a b i l i t y and s t r i c t l i a b i l i t y i n t o r t .
In April 1977, respondents, the Chandlers, entered
into a buy-sell agreement with the appellant, Madsen, to
purchase a house, built by him, at 3203 S i l v e r w o o d S t r e e t
near Billings, Montana. The agreed purchase price was
$90,280, which was p a i d when t h e b u i l d i n g was t r a n s f e r r e d .
At the t i m e of this agreement, t h e framework on t h e h o u s e
was i n p l a c e , b u t t h e b u i l d i n g was n o t c o m p l e t e d .
Madsen, a civil engineer working for the United
S t a t e s Government, had c o n s t r u c t e d a number of b u i l d i n g s f o r
s a l e on h i s own, i n c l u d i n g s i n g l e f a m i l y r e s i d e n c e s .
In the summer and f a l l of 1977, t h e Chandlers com-
pleted the final. landscaping of the lot and installed a
swimming p o o l and s p r i n k l i n g s y s t e m .
I n J u n e 1 9 7 7 , t h e C h a n d l e r s moved i n t o t h e h o u s e and
immediately experienced problems with doors and windows
sticking and locks failing to operate. The Chandlers
n o t i c e d c r a c k s i n t h e bedroom w a l l s and a hump i n t h e l i v i n g
room floor which was above a supporting partition in the
basement. Through h i s e m p l o y e e s , Madsen made a d j u s t m e n t s t o
the doors, but they continued t o s t i c k .
By May 1978, additional settling had caused severe
cracks i n most rooms o f t h e house, bending and b u l g i n g o f
the floors, broken windows, inoperative doors and door
locks, bowed d e c o r a t i v e room d i v i d e r s , b e n t plumbing, badly
c r a c k e d basement w a l l s and f l o o r s , s e p a r a t i o n between f i r e -
place masonry and the house structure, cracked bathroom
tiles, separation between bathtubs and walls, uneven
b a s e m e n t f l o o r s and g e n e r a l u n s i g h t l y i n t e r i o r o f t h e h o u s e .
The s e t t l e m e n t d e v e l o p e d s o t h a t p a r t s of t h e f o u n d a t i o n on
t h e w e s t s i d e o f t h e h o u s e were a s much a s 3 . 6 i n c h e s l o w e r
t h a n t h e f o u n d a t i o n on t h e e a s t s i d e .
A depression extends along t h e n o r t h end o f t h e l o t
in question in an east-west direction. The depression
c o l l e c t s water periodically and h a s done so since before
t h e C h a n d l e r s took p o s s e s s i o n of t h e house. Former next-
door n e i g h b o r s of t h e Chandler house t e s t i f i e d v i a deposi-
tion that t h e y had t o r e f r a i n from w a t e r i n g t h e i r lawn t o
prevent "ponding" i n t h e depression both during and after
c o n s t r u c t i o n of t h e C h a n d l e r h o u s e and t h a t w a t e r c o l l e c t e d
periodically i n t h e depression before any l a n d s c a p i n g was
done. According to the landscaper, Jim Sturn, the only
c h a n g e i n g r a d e h e made n e a r t h e n o r t h end o f t h e l o t was
t h e removal of some e a r t h n e a r t h e deck, which would h a v e
t e n d e d t o improve d r a i n a g e o u t o f t h e d e p r e s s i o n .
Piadsen testified he created a depression extending
e a s t and west t o c o l l e c t w a t e r and c o n s t r u c t e d a s w a l e on
t h e e a s t s i d e of t h e h o u s e t o d r a i n t h e a r e a . The d e p r e s -
s i o n Madsen c r e a t e d was s u c h t h a t i t would be d i f f i c u l t t o
observe with the naked eye. He did not use any survey
i n s t r u m e n t o r t r a n s i t t o d e t e r m i n e i f i n f a c t t h e a r e a would
drain, nor d i d h e i n f o r m t h e C h a n d l e r s t h e y s h o u l d p r o c e e d
t o create drainage.
The house is located on moisture-sensitive soil
which, when wet, becomes compressible. The p r e s e n c e of
w a t e r i n t h e s o i l c a u s e d s e t t l i n g of the footings, founda-
t i o n s , and o t h e r p a r t s o f t h e h o u s e which i n t u r n c a u s e d t h e
e x t e n s i v e damage t o t h e s t r u c t u r e .
T e s t i m o n y showed a n e s t i m a t e d c o s t o f repairing the
h o u s e was $ 6 5 , 0 0 0 . T h i s e s t i m a t e was c a l c u l a t e d on a c o s t
plus overhead basis with a 12% contingency allowance for
c e r t a i n p o r t i o n s of t h e work. Further testimony revealed,
however, that a firm price contract for the repair would
c o s t 50% more t h a n t h e e s t i m a t e , o r $ 9 7 , 5 0 0 , considering the
c o n t i n g e n c i e s of t h e work. The r e p a i r s would require the
Chandlers to move out of their home for three to four
months.
The case was heard by the District Court sitting
without a jury. On J a n u a r y 15, 1981, t h e D i s t r i c t Court
issued findings of fact and conclusions of law holding
Madsen liable to t h e Chandlers on the t h e o r i e s of implied
w a r r a n t y and n e g l i g e n c e and a w a r d i n g damages of $ 1 0 7 , 4 6 2 . 5 1 .
Following p o s t - t r i a l m o t i o n s t h e D i s t r i c t C o u r t amended i t s
o r d e r on F e b r u a r y 2 6 , 1981, d e l e t i n g t h e f i n d i n g of negli-
gence and reducing the damage award to $99,975.00. The
reduction deleted $4,000 previously awarded for temporary
rental and $3,487.51 previously awarded for moving and
storage. From t h i s o r d e r , b o t h p a r t i e s a p p e a l .
The i s s u e s b e f o r e t h i s C o u r t a r e :
1. Whether appellant, as a builder-vendor of a
r e s i d e n c e which he s o l d t o r e s p o n d e n t s , may be h e l d l i a b l e
to respondents under the doctrine of implied warranty of
habitability?
2. Whether t h e D i s t r i c t C o u r t e r r e d i n n o t a l l o w i n g
a p p e l l a n t t o r e c o v e r t h e amount c l a i m e d on h i s c o u n t e r c l a i m ?
3. Whether t h e D i s t r i c t C o u r t e r r e d i n d e l e t i n g i t s
finding that the appellant's negligence was the proximate
cause of respondents' damages?
4. Whether appellant is liable unJer the doctrine of
strict liability in tort?
5. Whether the District Court erred in the award of
damages?
IMPLIED WARRANTY OF HABITABILITY
The question of the liability of a builder-vendor of
a new residence to the first purchaser under an implied
warranty of habitability is one of first impression before
this Court.
Caveat emptor, which traditionally has applied to
sal.es of real estate, developed at a time when a buyer and
seller were in equal bargaining positions. They were of
comparable skill and knowledge and eacn could protect
himself in a transaction.
In the modern marketplace that equality of position
no longer necessarily exists, and a growing number of juris-
dictions have abandoned caveat emptor in favor of implied
warranties where a builder-vendor sells a new residence.
Yepsen v. Burgess (1974), 269 Or. 635, 525 P.2d 1019;
Pollard v. Saxe & Yoll- Development Co.
=. (1974), 115
Cal.Rptr. 648, 12 Cal.3d 374, 525 P.2d 88; Hanavan v. Dye
(1972), 4 Ill.App.3d 576, 281 N.E.2d 398; Bethlahmy v.
Bechtel (1966), 91 Idaho 55, 415 P.2d 698; Carpenter v.
Donohoe (1964), 154 Colo. 78, 388 P.2d 399.
We agree with the Oregon Supreme Court which stated
in Yepsen that the essence of the transaction between a
builder-vendor and a buyer is an implicit agreement that the
seller w i l l transfer a h o u s e which is s u i t a b l e f o r h a b i t a -
tion. The b u y e r i s n o t i n an e q u a l b a r g a i n i n g p o s i t i o n and
is e s s e n t i a l l y forced to rely on the seller's skill and
knowledge regarding the habitability of the house. In
a d d i t i o n , t h e b u i l d e r i s i n a b e t t e r p o s i t i o n t o e x a m i n e and
discover defects. Yepsen v . B u r g e s s , 525 P.2d a t 1 0 2 2 .
The doctrine of c a v e a t emptor no longer serves the
r e a l i t i e s of the marketplace. Therefore, we h o l d t h a t t h e
builder-vendor of a new home impliedly warrants that the
residence is constructed in a workmanlike manner and is
suitable for habitation.
Madsen a r g u e s t h a t even if the implied warranty of
habitability is adopted, it should not apply i n t h i s c a s e
because the defect which caused the damage here is not
s t r u c t u r a l b u t r a t h e r is i n h e r e n t i n t h e l a n d .
I n t h i s c l a i m , Madsen r e l i e s p r i m a r i l y on B e r i , Inc.
v. Salishan Properties, Inc. ( 1 9 7 8 ) , 282 Or. 569, 580 P.2d
173, where the plaintiffs leased buildings constructed by
the d e f e n d a n t on oceanfront lots which s u b s e q u e n t l y began
eroding. The Oregon c o u r t found a n i m p l i e d w a r r a n t y d i d n o t
apply because the defect--susceptibility to erosion--had
s o l e l y t o do w i t h t h e i n h e r e n t n a t u r e of t h e land and was
n o t a p r o d u c t of t h e b u i l d e r ' s work on t h e l a n d .
In Beri, supra, the land in question was on the
o c e a n f r o n t where t h e p r o s p e c t o f e r o s i o n s h o u l d have been,
if not certain, at least equally as apparent to buyer-
lessees as to seller-lessors. In addition, the Beri opinion
gives no indication that the erosion was furthered by
a n y t h i n g o t h e r t h a n t h e n a t u r a l a c t i o n of t h e ocean.
That is not so in the present case. Here, the
District Court found the cause of settling damage to the
Chandler h o u s e was the presence of water in the moisture-
s e n s i t i v e s o i l upon which t h e h o u s e was b u i l t . The f a c t o f
the moisture-sensitive s o i l was n o t the sole defect. The
" p o o l i n g " of wa t e r a t t h e n o r t h end o f t h e h o u s e was also
part of the defective condition. The D i s t r i c t Court a l s o
found that, if water collected at the north end of the
house, it d i d s o b e f o r e any l a n d s c a p i n g by t h e C h a n d l e r s and
was n o t c a u s e d by t h e C h a n d l e r s .
A basic concern i n applying t h e implied warranty is
whether the defect r e l a t e s e s s e n t i a l l y t o u s e f u l occupancy
of t h e house. Mazurek v . N i e l s e n ( 1 9 7 9 ) , 42 Colo.App. 386,
599 P . 2 d 269; Yepsen, supra. Sometimes a d e f e c t i s e s s e n -
tial to occupancy but is not strictly structural. See:
Yepsen, supra (defect involved improper construction of
septic tank and drainfield); Tavares v. Horstman (Wyo.
1 9 7 5 ) , 542 P.2d 1275 ( s e p t i c d r a i n f i e l d installed i n gumbo
c l a y s o i t would n o t d r a i n ) ; F o r b e s v . Mercado ( 1 9 7 8 ) , 283
Or. 291, 583 P.2d 552 ( w e l l water u n u s a b l e because of h i g h
iron content).
Madsen a r g u e s h e had no r e a s o n t o s u s p e c t t h e r e was a
moisture-sensitive s o i l which would c a u s e s e t t l i n g . But t h a t
is not the issue. The c o n c e p t h e r e i s n o t o n e o f f a u l t or
wrong-doing but, rather, where o n e of two i n n o c e n t p a r t i e s
w i l l s u f f e r , which was i n t h e b e t t e r p o s i t i o n t o p r e v e n t t h e
harm?
Whether o r n o t t h e r e was r e a s o n f o r Madsen t o s u s p e c t
the problem, as the builder-vendor he c l e a r l y was in the
better position to prevent the problem. We, therefore,
a f f i r m t h e D i s t r i c t Court r e g a r d i n g Madsen's l i a b i l i t y under
t h e implied warranty.
COUNTERCLAIM
Madsen counterclaimed for $637 which the Chandlers
agree remained unpaid for specific "extras" completed by
Madsen. 'The D i s t r i c t Court concluded t h a t Madsen was n o t
entitled to the counterclaim because of failure of
consideration. Madsen a r g u e s t h i s c o n c l u s i o n was i n c o r r e c t
because the defense of failure of consideration was not
a l l e g e d by t h e C h a n d l e r s a s an a f f i r m a t i v e d e f e n s e o r r a i s e d
in their pretrial order and because there i s no e v i d e n c e
t h a t Madsen d i d n o t p e r f o r m t h e work f o r t h o s e e x t r a s .
Failure of consideration is an affirmative defense
which m u s t be p l e a a affirmatively. Rule 8 ( c ) , M.R.Civ.P.
If an affirmative defense is not plead, it is g e n e r a l l y
waived. C a m a l i e r & Buckley-Madison, I n c . v . Madison H o t e l ,
Inc. (D.C. Cir. 1 9 7 5 ) , 5 1 3 F.2d 407. The key t o d e t e r m i n i n g
t h e s u f f i c i e n c y of t h e p l e a d i n g of an a f f i r m a t i v e d e f e n s e i s
w h e t h e r i t g i v e s f a i r n o t i c e of t h e d e f e n s e . Wyshak v . C i t y
N a t i o n a l Bank ( 9 t h C i r . 1 9 7 9 ) , 607 F.2d 824.
H e r e , t h e C h a n d l e r s d i d n o t s p e c i f y t h e i r r e l i a n c e on
f a i l u r e of c o n s i d e r a t i o n a s a d e f e n s e t o Madsen's counter-
claim e i t h e r i n t h e p l e a d i n g s o r t h e i r p r e t r i a l memorandum.
Sheldon Chandler testified at trial that among the items
purchased f o r t h e house i n a d d i t i o n t o t h o s e included i n t h e
purchase price were "extras" from Madsen. Chandler also
testified that he had paid Madsen $1,500 and s t i l l owed
$637. The evidence does not specify what "extras" were
i n v o l v e d nor d o e s i t e s t a b l i s h t h a t t h o s e " e x t r a s " w e r e n o t
supplied.
We find the Chandlers' failure to plead failure of
consideration here was fatal to that defense, and the
D i s t r i c t C o u r t ' s c o n c l u s i o n i s u n s u p p o r t e d by t h e e v i d e n c e .
NEGLIGENCE
I n i t s o r i g i n a l f i n d i n g s of f a c t and c o n c l u s i o n s o f
law the District Court found that Madsen had a responsi-
bility of providing drainage around the house to prevent
damage t o t h e h o u s e and t h a t Madsen n e g l i g e n t l y f a i l e d t o d o
so. Further, t h e D i s t r i c t Court found Pladsen's negligence
caused or contributed to cause the water to enter the
s u b s o i l and t h e h o u s e t o s e t t l e .
The amended findings and conclusions stated the
Chandlers failed to carry their burden of proof that
Madsen's n e g l i g e n c e was t h e p r o x i m a t e c a u s e of t h e damage.
The C h a n d l e r s a r g u e t h a t g i v e n t h e D i s t r i c t C o u r t ' s f i n d i n g
t h a t t h e m o s t p r o b a b l e c a u s e o f t h e damage t o t h e h o u s e was
water under the footings, t h e o n l y e x p l a n a t i o n i s Pladsen's
conduct.
On r e v i e w , t h e s t a n d a r d w e m u s t a p p l y is whether the
District Court's conclusion is supported by substantial
c r e d i b l e e v i d e n c e and t h e l a w . If s o , t h i s Court w i l l n o t
d i s t u r b it. Woodahl v . Matthews ( 1 9 8 2 ) , - Mont. -, -
P . 2d , 39 S t . R e p . 238; L a u t e r j u n g v . J o h n s o n ( 1 9 7 7 ) , 1 7 5
Mont. 74, 572 P.2d 511.
Although our weighing of the facts might have
resulted in a different conclusion, we find the District
Court ' s findings and conclusions regarding negligence are
s u p p o r t e d by s u b s t a n t i a l e v i d e n c e t h a t t h e C h a n d l e r s f a i l e d
t o prove Madsen's n e g l i g e n c e .
STRICT L I A B I L I T Y
S i n c e w e h a v e d e t e r m i n e d l i a b i l i t y h e r e on t h e t h e o r y
of implied warranty, we f i n d i t u n n e c e s s a r y t o d i s c u s s t h e
s t r i c t l i a b i l i t y doctrine.
DANAGES
Macisen claims the District Court's finding of the
cost of repairs at $97,500 is punitive, speculative and
u n s u p p o r t e d by t h e e v i d e n c e . H e r e l i e s heavily i n h i s claim
on Spackman v . R a l p h M. P a r s o n s Co. ( 1 9 6 6 ) , 147 Mont. 500,
414 P.2d 918, in which the plaintiff sought damages
resulting from sewage flooding to personal and real
property. Madsen a r g u e s t h a t Spackman f o r g e s a s t r i c t r u l e
of law i n Montana t h a t t h e m e a s u r e o f damages is t h e c o s t o f
repair if t h e c o s t i s less t h a n t h e d i m i n u t i o n i n v a l u e of
property but i n no c a s e w i l l t h e r e c o v e r y e x c e e d t h e v a l u e
of t h e p r o p e r t y b e f o r e i n j u r y .
Spackman d o e s n o t s e t t h i s p r i n c i p l e o u t , h o w e v e r , a s
a hard-and-fast rule but, rather, as a guide to common
sense:
"Where damage t o p r o p e r t y i s c o n c e r n e d , t h e
p u r p o s e of a w a r d i n g damages i s t o r e t u r n t h e
p a r t y i n j u r e d t o t h e same, o r a s n e a r l y a s
p o s s i b l e t h e same, c o n d i t i o n a s he e n j o y e d
before the injury t o h i s property ...
" I n g e n i o u s men h a v e p r o p o u n d e d i n g e n i o u s
m e t h o d s , s y s t e m s and f o r m u l a s f o r d e t e r m i n i n g
i n monetary t e r m s t h e v a l u e of p r o p e r t y p a r -
t i a l l y damaged o r d e s t r o y e d . h h i l e such
methods s e r v e a s u s e f u l g u i d e s , t h e f i n a l
answer must r e s t i n good s e n s e r a t h e r t h a n
mechanical a p p l i c a t i o n of such formulas."
Spackman, 1 4 7 M o n t . a t 5 0 6 , 414 P.2d a t
921-922.
I n Bos v . D o l a j a k ( 1 9 7 5 ) , 1 6 7 Mont. 1 , 534 P . 2 d 1 2 5 8 ,
t h i s Court recognized t h a t t h e Spackman r u l e c a n n o t a l w a y s
c l e a r l y be a p p l i e d . In - t h e defendants contracted with
Bos
p l a i n t i f f s t o e r e c t f o r $ 6 , 5 0 0 a g r a i n s i l o which p l a i n t i f f s
had p u r c h a s e d s e c o n d h a n d b u t which was t h e e q u i v a l e n t o f a
new silo. Defendants secured the raised s i l o with fewer
jacks t h a n r e q u i r e d by t h e c o n s t r u c t i o n manual and a l l o w e d
the silo to twist so it could not readily be lowered.
During the process, a windstorm threw the silo off its
f o u n d a t i o n and v i r t u a l l y d e s t r o y e d i t .
A t trial plaintiffs presented damages totaling
$25,274.61: $15,342.61 was t h e c o s t o f replacing the s i l o
and $9,932 cost from loss of use. The jury awarded
$17,626.75.
T h i s C o u r t a p p r o v e d t h e d e t e r m i n a t i o n o f damages and
n o t e d t h a t t h e Spackman r u l e d e a l t w i t h r e a d i l y r e p l a c e a b l e
i t e m s w i t h an e s t a b l i s h e d m a r k e t v a l u e . vJhere a n i t e m was
not readily replaceable, d i d n o t h a v e an e s t a b l i s h e d m a r k e t
value, and was i n t e g r a l t o a larger o p e r a t i o n such a s t h e
plaintiffs' dairy farm, this Court held that other
c o n s i d e r a t i o n s were appropriate including compensation for
l o s s of u s e .
In the case before us, Claude Gerbase, a Billings
contractor, testified that repair of the Chandler house
would require drying out the subsoil, cutting the house
l o o s e from i t s f o u n d a t i o n and b r i n g i n g i t t o a l e v e l g r a d e .
Once the house was made level and secure, additional
c o s m e t i c and s t r u c t u r a l r e p a i r s would be r e q u i r e d i n c l u d i n g
replacement of s h e e t r o c k .
Gerbase t e s t i f i e d h i s estimated c o s t of r e p a i r of t h e
h o u s e was $ 6 5 , 0 0 0 , which included a 12 percent contingency
factor. He further testified that because of the
c o m p l i c a t e d and u n c e r t a i n n a t u r e o f t h e j o b he would c h a r g e
$91,500 to enter into a fixed price contract for the
repairs. The D i s t r i c t C o u r t awarded damages o f $ 9 7 , 5 0 0 .
Madsen a r g u e s t h e f i n d i n g i s p u n i t i v e and c o n t r a r y t o
law i n p a r t b e c a u s e t h e h o u s e was o r i g i n a l l y s o l d f o r less
t h a n t h e damage a w a r d . W disagree.
e
Madsen also claims that if he is liable for any
damages the proper amount is $65,000 which was Gerbase's
repair estimate. Madsen a r g u e s t h e $ 9 7 , 5 0 0 i s s p e c u l a t i v e
i n t h a t i t was q u o t e d by G e r b a s e a s h i s f i x e d c o n t r a c t p r i c e
o n l y t o g u a r a n t e e h e would l o s e no money on t h e job. We
disagree.
An estimate, by its very nature, is speculative,
particularly where, as here, the job is complicated and
subject to revision as it progresses. It would be of
q u e s t i o n a b l e v a l u e t o t h e C h a n d l e r s t o r e c e i v e $65,000 for
r e p a i r s only t o discover, once into the project, the cost
would be s i g n i f i c a n t l y more. G i v e n t h e n a t u r e of t h e damage
t o t h e C h a n d l e r home and t h e r e p a i r s r e q u i r e d , w e a f f i r m t h e
D i s t r i c t C o u r t ' s award f o r r e p a i r s .
The Chandlers argue that the District Court erred
when i t d e l e t e d t h e c o s t s o f t e m p o r a r y r e n t a l and moving and
s t o r a g e from t h e damage a w a r d .
The initial question in resolving this issue is
whether a breach of an implied warranty arises out of a
c o n t r a c t obligation or some o t h e r obligation. That d e t e r -
mination will establish what damages are available as a
r e s u l t of b re a c h . S e c t i o n s 27-1-311 and 27-1-317, MCA.
I n F e r g u s o n v . Town Pump, I n c . ( 1 9 7 8 ) , 177 Mont. 122,
580 P.2d 915, this Court found an oral contract for
c o n s t r u c t i o n o f g a s o l i n e s t a t i o n t o c a r r y w i t h i t an i m p l i e d
term that the work would be performed in a reasonably
skillful and workmanlike manner. It also found that a
negligent f a i l u r e t o perform according t o t h e implied term
resulted i n a breach of contract a s w e l l as a tort. 177
Mont. a t 1 3 1 , 580 P.2d a t 920.
A l t h o u g h h e r e w e do n o t h a v e t h e n e g l i g e n c e component
which sustained the tort theory i n Ferguson, w e do h a v e a
b r e a c h of an i m p l i e d term of t h e c o n t r a c t . Madsen's breach
of i m p l i e d w a r r a n t y is a b r e a c h of c o n t r a c t and s u b j e c t t o
the provisions of section 27-1-311, IJICA. That provision
sets the measure of damages for breach of an obligation
a r i s i n g f r o m a c o n t r a c t a s " t h e amount which w i l l c o m p e n s a t e
t h e p a r t y a g g r i e v e d f o r a l l t h e d e t r i m e n t which was p r o x i -
mately caused thereby or i n t h e o r d i n a r y c o u r s e of things
would be l i k e l y t o r e s u l t t h e r e f r o m . "
It i s a p p a r e n t t h a t t h e n e c e s s i t y o f moving from a
residence undergoing irlassive repairs and of renting a
t e m p o r a r y r e s i d e n c e i s l i k e l y t o r e s u l t from major damage t o
a structure. We, therefore, f i n d t h a t c o s t s f o r moving and
s t o r a g e and temporary rental were improperly deleted from
t h e damage award.
M a r i l y n C h a n d l e r t e s t i f i e d s h e had o b t a i n e d e s t i m a t e s
from a B i l l i n g s r e a l e s t a t e o f f i c e t h a t a s u i t a b l e t e m p o r a r y
r e n t a l f o r t h e C h a n d l e r s would c o s t b e t w e e n $600 and $ 1 , 0 0 0
per month. She testified that she also had obtained an
e s t i m a t e of $3,487.51 f o r moving the Chandlers' furniture.
In addition, Gerbase testified the Chandlers would be
r e q u i r e d t o move from t h e i r h o u s e f o r t h r e e t o f o u r months
during repairs.
Since the testimony establishes a $400-per-month
disparity in rental figures, an award of t h e middle f i g u r e
appears appropriate. Therefore, we award the Chandlers
$3,200 ( $ 8 0 0 p e r month f o r f o u r m o n t h s ) f o r t e m p o r a r y r e n t a l
and r e i n s t a t e t h e award o f $ 3 , 4 8 7 . 5 1 f o r moving and s t o r a g e .
The C h a n d l e r s a l s o a r g u e t h e D i s t r i c t C o u r t e r r e d i n
f a i l i n g t o g r a n t damages f o r e m o t i o n a l d i s t r e s s . Since we
have found no l i a b i l i t y f o r n e g l i g e n c e o r s t r i c t 1 - i a b i l i t y ,
s u c h damages need n o t be c o n s i d e r e d h e r e .
SURPRISE
Madsen requests that a new t r i a l be g r a n t e d on t h e
damage issue on the grounds he has been surprised under
s e c t i o n s 25-11-102(3) and 25-11-103, MCA. This request is
based on the affidavit of Madsen's attorney, which states
that an extensive discussion with Claude Gerbase, had in
l i e u of d e p o s i t i o n on December 6 , 1 9 8 0 , i n d i c a t e d G e r b a s e ' s
e s t i m a t e f o r c o s t of r e p a i r would be $ 6 5 , 0 0 0 . On December
9, 1980, a t t h e r e q u e s t of Madsen's a t t o r n e y , Gerbase sub-
m i t t e d a d e t a i l e d breakdown of t h e e s t i m a t e . Subsequently,
according to the a£f i d a v i t , Madsen's attorney contacted
another c o n t r a c t o r who examined t h e d o c u m e n t a r y and v i d e o -
taped evidence and concluded his estimate would not be
s i g n i f i c a n t l y l e s s t h a n $65,000.
The Chandlers argue the claim of surprise is
unfounded. In support of their position, the Chandlers
refer t o a l e t t e r of October 29, 1.980, from t h e i r attorney
t o Madsen's a t t o r n e y which stated: "Another item t o take
i n t o account i s t h a t t h e Gerbase e s t i m a t e is only t h a t . It
is n o t an agreement t o r e s t o r e t h e house. The C h a n d l e r s a r e
e n t i t l e d t o have their house restored and if a contractor
r e q u i r e s an a d d i t i o n a l sum of money f o r c o n t i n g e n c i e s , s u c h
a s h e would regularly charge in the course of his trade,
t h e n we w i l l want t o add t h a t o n . "
In addition, Claude Gerbase, by affidavit, stated
t h a t a c c o r d i n g t o h i s r e c o l l e c t i o n o f t h e December 6 , 1 9 8 0 ,
meeting with the attorneys for both parties, he told all
t h o s e p r e s e n t t h a t he would n o t e n t e r into a firm contract
f o r t h e amount o f h i s e s t i m a t e .
S u r p r i s e h a s o n l y o n c e been a c c e p t e d a s t h e b a s i s f o r
granting a new trial in Montana. Porter v. Industrial
P r i n t i n g Co. ( 1 9 0 1 ) , 26 Mont. 1 7 0 , 66 P . 839, m o d i f i e d , 67
P. 67. The C o u r t found s u c h s u r p r i s e where t h e t r i a l c o u r t
had granted default against the plaintiff for failure to
reply t o the defendant's counterclaim. At trial t h e defen-
d a n t p r e s e n t e d no p r o o f i n s u p p o r t o f i t s c o u n t e r c l a i m . The
C o u r t l a t e r d e c l a r e d o n l y t h r e e of t h e c o u n t e r c l a i m s s t a t e d
causes of action and entered judgment for the plaintiff.
T h i s C o u r t found s u r p r i s e which " o r d i n a r y p r u d e n c e c o u l d n o t
have guarded a g a i n s t . " P o r t e r , 26 Mont. 1 8 2 , 66 P. a t 8 4 1 .
W e do n o t have s u c h a s i t u a t i o n h e r e . iv"e f i n d t h e r e
was s u f f i c i e n t r e f e r e n c e t o t h e f a c t a f i x e d - p r i c e contract
would be d i f f e r e n t t h a n t h e e s t i m a t e and would be r e l i e d o n
by t h e C h a n d l e r s t o p r e c l u d e s u r p r i s e .
This case is remanded to the District Court with
i n s t r u c t i o n s t o amend i t s judgment i n accordance with t h i s
opinion.
W concur:
e
Chief J u s t i c e
Mr. J u s t i c e John C. Sheehy, c o n c u r r i n g s p e c i a l l y :
I agree with t h e r e s u l t here. I a f f i r m t h e damages
award o f $97,500 f o r r e p a i r o f t h e h o u s e b e c a u s e w e a r e bound
by t h e a p p e l l a t e r u l e t h a t t h e f i n d i n g s o f a d i s t r i c t c o u r t
may n o t b e s e t a s i d e u n l e s s c l e a r l y e r r o n e o u s . Rule 5 2 ( a ) ,
M.R.Civ.P. A f i n d i n g i s " c l e a r l y e r r o n e o u s " when, although
t h e r e i s e v i d e n c e t o s u p p o r t i t , t h e r e v i e w i n g c o u r t on t h e
e n t i r e e v i d e n c e i s l e f t w i t h t h e d e f i n i t e and f i r m c o n v i c t i o n
t h a t a m i s t a k e h a s b e e n committed. U n i t e d S t a t e s v . Gypsum
Co. ( 1 9 4 8 ) , 333 U.S. 364, 394-395, 68 S.Ct. 525, 92 L.Ed. 746.
I am p u r s u a d e d on t h i s p o i n t by t h e e v i d e n c e o f t h e c o n t r a c t o r
t h a t h e would n o t e n t e r i n t o a f i r m c o n t r a c t f o r r e p a i r a t t h e
f i g u r e o f $67,500. The b u r d e n o f p r o o f o n t h e p l a i n t i f f s was
by a p r e p o n d e r a n c e o f t h e e v i d e n c e . The G e r b a s e e v i d e n c e ,
b e i n g c r e d i b l e , i s s u b s t a n t i a l and t h e r e f o r e i t overcomes t h e
"clearly erroneous" rule. S e e W e s t e r n C o t t o n o i l Co. v. Hodges
(5th C i r . 1 9 5 4 ) , 218 F.2d 1 5 8 .
4J u s t,,L?hkiL7
; ice