IN THE COURT OF APPEALS OF TENNESSEE
AT KNOXVILLE
February 2, 2011 Session
DAVID BATES D/B/A DAVID BATES CONSTRUCTION CO. v.
CAROLINE BENEDETTI
Appeal from the Chancery Court for Knox County
No. 172212-2 Daryl R. Fansler, Chancellor
No. E2010-01379-COA-R3-CV Filed March 21, 2011
David Bates d/b/a David Bates Construction Co. (“Plaintiff”) sued Caroline Benedetti
(“Defendant”) for breach of a construction contract involving demolition of an existing
residential garage and construction of a new one. Defendant answered the complaint and
filed a counterclaim. After a bench trial, the Trial Court entered its order finding and
holding, inter alia, (1) that Plaintiff had not proven damages, (2) that Defendant had failed
to comply with Tenn. Code Ann. § 66-36-103 with regard to her counterclaim and, therefore,
pursuant to the statute her counterclaim should be abated, and (3) that Defendant also had
failed to give notice and an opportunity to cure pursuant to the common law and that her
counterclaim should be dismissed for that reason as well. Defendant appeals the abatement
and dismissal of her counterclaim. We find that Tenn. Code Ann. § 66-36-103 does not
apply to the case at hand, but that the Trial Court correctly dismissed Defendant’s
counterclaim. We, therefore, affirm the Trial Court’s order.
Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed;
Case Remanded
D. M ICHAEL S WINEY, J., delivered the opinion of the Court, in which C HARLES D. S USANO,
J R., and J OHN W. M CC LARTY, J.J., joined.
Michael S. Shipwash, Knoxville, Tennessee, for the appellant, Caroline Benedetti.
Bill W. Petty, Knoxville, Tennessee, for the appellee, David Bates d/b/a David Bates
Construction Co.
OPINION
Background
In February of 2006, Plaintiff and Defendant executed a written contract (“the
Contract”) which provided for Plaintiff to demolish an existing detached residential garage
and build a new garage with an upper story on Defendant’s real property for the contract
price of $40,770. Defendant became dissatisfied during construction with Plaintiff’s work.
She hired an attorney who wrote a letter to Plaintiff in July of 2006 asserting that Plaintiff
was in breach of the Contract. At that time, construction on the garage was approximately
50% complete. Defendant hired someone else to complete the garage.
In April of 2008, Plaintiff sued Defendant alleging, in part, that even though
Plaintiff had worked diligently to complete the job pursuant to the Contract, Defendant had
breached the Contract by having Plaintiff’s work permit suspended and/or revoked.
Defendant answered the complaint and filed a counterclaim alleging misrepresentation,
breach of contract, fraud, negligence, and violations of the Tennessee Consumer Protection
Act. The case was tried without a jury in May of 2010.
Plaintiff testified at trial about Defendant’s complaint that the garage was not
constructed to the size agreed on, which Defendant alleged was 20' x 20'. Plaintiff stated that
the first time Defendant raised any issue with regard to the 19' x 20' size of the garage as built
was after she hired an attorney. Plaintiff testified that a document that went to the city
showed that “the front was 20-foot wide with a dimension, arrows, and it shows the depth
was 19-feet deep, and that was on 6/15/06.” Plaintiff testified that both he and Defendant
signed that document. When asked if Defendant had raised any issue about the dimensions
of the garage before terminating Plaintiff from the job, Plaintiff stated:
Not - - no. As a matter of fact, when it was being excavated - - when
the excavator - - I wanted him to build a 20 by 20. I wanted him to put a footer
in for a 20 by 20. When he was excavating it, the pictures will show how
restricted that lot is. He said it was going to be almost impossible to get a 20
by 20 in there unless he cut further back in the bank. And [Defendant] was at
home that day. We got her out there and told her that it was going to work out
about 19 by 20, and she said that was no problem at all.
Plaintiff also testified about a crack in the foundation of the garage. When
asked what he did with regard to the foundation, Plaintiff testified:
We backfilled it with number 57 stone, is what I ordered, which is washed
-2-
stone, clean stone. We backfilled it up to almost the area where you’ll see the
waterproofing. We put two coats of waterproofing on it. We put drain tile,
four-inch slotted drain tile in there. And I took some photos of the drain tile
and showed that it was in there. We continued to backfill it with the stone
above the drain tile. And we couldn’t get any equipment in there to backfill
it, so my men had to backfill it with five-gallon buckets and shovels. I’ve got
a picture of that.
When asked how deep the gravel was, Plaintiff stated: “It would go from probably two-and-
a-half feet down to the front where the entrance of the garage is, to maybe eight inches.”
When asked how deep the soil was that was put on top of the gravel, he stated: “It was
probably anywhere from eight inches, maybe to 10, 12 inches. And that was topsoil that was
left on the job site to backfill that gravel with.” Plaintiff was asked if what he did is
consistent with the building code, and he stated:
The code doesn’t require that you use gravel. It’s a good building policy, but
the code will actually allow you to fill up, I believe it’s on an eight-inch block
foundation, they’ll allow you to fill up, backfill, about five feet unsupported
soil. Problem if you use a lot of soil, is you get hydraulic pressure, which you
don’t get with the rock. Because rock will drain the water out of there and not
establish hydraulic or hydrostatic pressure against the foundation walls.
Defendant testified at trial, and when asked to explain why she was not happy
with Plaintiff’s performance, she stated:
He was not building things. He didn’t, first of all, build a 20 by 20. It was
faulty work. He wasn’t showing up. He misrepresented himself saying he had
a good work record and said - - thought he was trustworthy. I go back and find
out that he’s with BB&B and the Tennessee Contractors. He did not represent
himself. I trusted him. And it was just not anything that I - -
Defendant also testified that when Plaintiff left the job, the crack in the foundation “had been
there for weeks.”
When asked if she has suffered damage because the structure is 19' x 20'
instead of 20' x 20', Defendant stated:
Yes. I’m not able to park my cars. There’s maybe a half an inch to even be
able to get them into the garage. I can’t store my items correctly. I had to
have storage built, the wall-to-wall storage, so that I could have - - I pull the
-3-
cars straight into the wall and the storage is around the car, so I can - - there
can be nothing in front of the car.
Timothy Scott Allen, the owner of Tim Allen Remodeling and Home
Improvement, was hired by Defendant to complete the garage. Mr. Allen is not a licensed
contractor. He testified that the finished garage measures 20 feet 1 ½ inches x 19 feet 1 ½
inches.
After trial, the Trial Court entered its order on May 27, 2010 finding and
holding, inter alia:
This is a suit involving a contract to construct a residential garage. The
original contract called for the construction of a garage 20ft x 20ft.
***
According to the Plaintiff, who is suing to collect the balance owed on
the original contract, they were unable to build a 20 x 20 garage without
additional excavating. According to him, he discussed with the Defendant and
she approved a 19 x 20 garage. He said he never heard a complaint about the
size of the garage until Defendant hired an attorney some time in July of 2006.
On July 13, 2006, Plaintiff says that he was told by Defendant’s
attorney to terminate work on the project and not return.
The Defendant has counter-sued alleging breach of contract and a
violation of the Tennessee Consumer Protection Act. A number of other
counts are contained in the counter-claim which seeks compensatory damages
in the amount of $100,000.
The Defendant had a number of complaints about [Plaintiff’s] progress
on the job. The primary complaints regarding the structure had to do with the
size of the garage, a crack in the block foundation, and what Defendant
deemed to be extraordinarily slow progress. A complete list of complaints was
set forth in a letter Defendant wrote to the Plaintiff on July 10, 2006, but which
Plaintiff denies having ever received. As can be seen from Exhibit No. 12,
Defendant had a number of complaints regarding the Plaintiff’s business
demeanor, his failure to communicate, and general dissatisfaction with the
progress of the work.
-4-
After July 13, 2006, Defendant obtained the services of Tim Allen, an
unlicensed contractor, to complete the work on the garage. She initially
claimed she paid $64,000 to Allen to complete the work. However, Allen was
unable to identify with any degree of certainty the amount of charges that were
actually attributable to the completion of the original contract between Plaintiff
and Defendant. Nevertheless, Counter/Plaintiff claims she should be entitled
to recover $14,340.37 as set forth in her Proposed Findings [of] Fact.
***
COUNTER-CLAIM
[Plaintiff] says [Defendant] failed to comply with Tenn. Code Ann. §
66-36-103, Procedures and requirements for notification and remedying
construction defects. That statute requires in actions brought against a
contractor related to an alleged construction defect, the claimant shall before
filing an action, serve written notice of claim on the contractor. The section
then goes on to set up a procedure whereby the contractor will be allowed to
inspect the alleged defect, propose a remedy, or in the alternative, deny
liability.
Tenn. Code Ann. § 66-36-102 states that if a claimant files an action
without first complying with these requirements, on motion by a party to the
action, the court shall abate the action. Blacks’ Law Dictionary defines an
abatement of an action as the entire overthrow or destruction of a suit so that
it is quashed and ended. Section 66-36-102 does provide that the abatement
of the action will be without prejudice. However, in this case the claimant has
completed all of the work and is in no position to ever give the contractor
notices required by the statute.
Counsel for [Defendant] and she both assert that notice was given.
They offered Exhibit Nos. 5 and 12 as evidence of said notice. However,
neither of these letters comply with the statute. Additionally, the plain
language of these letters indicate there was no anticipation that [Plaintiff]
would be allowed back on the job.
For example, in Exhibit No. 5, [the letter from Defendant’s attorney], he
makes demand on [Plaintiff] for $25,000. The letter says “This amount will
cover the payment for someone else to finish the job and to correct the
aforementioned deficiencies.” In Exhibit No. 12, which [Plaintiff] denies ever
-5-
receiving, [Defendant] says in her last sentence “I trust that your future
endeavors will be successful and that you are able to find out what works for
you.” Although not as straightforward as [her attorney’s] letter, the clear
inference to be drawn from the last line of Exhibit No. 12 is that [Defendant]
did not expect [Plaintiff] to return to the job.
Additionally, the unrefuted testimony of [Plaintiff] is that [Defendant’s
attorney] left a voice message at [Plaintiff’s] home on the evening of July 12
advising him not to return to the job site.
Aside from Tenn. Code Ann. § 66-36-101 et seq. the common law is
that one should give notice designed to allow the defaulting party to repair the
defective work, to reduce the damages, to avoid additional defective
performance and to promote settlements of disputes. McClain [v. Kimbrough
Constr. Co., Inc., 806 S.W.2d 194, 198 (Tenn. Ct. App. 1990)]. Thus,
[Defendant] was obligated to give the Plaintiff notice and an opportunity to
cure before terminating the contract for faulty performance. In this case, she
neither complied with the statute nor the common law requirement to allow the
contractor to cure. The failure to do so bars her right to recover in this case.
Defendant appeals the abatement and dismissal of her counterclaim.
Discussion
Although not stated exactly as such, Defendant raises one issue on appeal:
whether the Trial Court erred in abating and dismissing her counterclaim. Plaintiff raises no
additional issues.
Our review is de novo upon the record, accompanied by a presumption of
correctness of the findings of fact of the trial court, unless the preponderance of the evidence
is otherwise. Tenn. R. App. P. 13(d); Bogan v. Bogan, 60 S.W.3d 721, 727 (Tenn. 2001).
A trial court's conclusions of law are subject to a de novo review with no presumption of
correctness. S. Constructors, Inc. v. Loudon County Bd. of Educ., 58 S.W.3d 706, 710 (Tenn.
2001).
The case now before us on appeal involves the interpretation of a statute, and
as our Supreme Court has instructed:
[W]hen interpreting a statute, we “must first ascertain and then give full effect
to the General Assembly’s intent and purpose” in drafting those sections.
-6-
Waldschmidt v. Reassure Am. Life Ins. Co., 271 S.W.3d 173, 176 (Tenn.
2008). Our chief concern is to carry out the legislature’s intent without unduly
broadening or restricting the statute. Houghton v. Aramark Educ. Res., Inc.,
90 S.W.3d 676, 678 (Tenn. 2002) (quoting Owens v. State, 908 S.W.2d 923,
926 (Tenn. 1995)). We presume that every word in a statute has meaning and
purpose and should be given full effect if so doing does not violate the
legislature’s obvious intent. In re C.K.G., 173 S.W.3d 714, 722 (Tenn. 2005)
(quoting Marsh v. Henderson, 221 Tenn. 42, 424 S.W.2d 193, 196 (Tenn.
1968)). When the statutory language is clear and unambiguous, we simply
apply its plain meaning. Eastman Chem. Co. v. Johnson, 151 S.W.3d 503, 507
(Tenn. 2004). When a statute is ambiguous, however, we may refer to the
broader statutory scheme, the history of the legislation, or other sources to
discern its meaning. Colonial Pipeline Co. v. Morgan, 263 S.W.3d 827, 836
(Tenn. 2008).
Shelby County Health Care Corp. v. Nationwide Mut. Ins. Co., 325 S.W.3d 88, 92 (Tenn.
2010).
The Trial Court held that Defendant’s counterclaim should be abated pursuant
to Tenn. Code Ann. § 66-36-101 et seq. As pertinent to this appeal, Tenn. Code Ann. § 66-
36-102 provides:
66-36-102. Compliance with requirements. – If a claimant files an action
without first complying with the requirements of this chapter, on motion by a
party to the action, the tribunal having jurisdiction shall abate the action,
without prejudice, and the action may not proceed until the claimant has
complied with such requirements.
Tenn. Code Ann. 66-36-102 (2004). In pertinent part, Tenn. Code Ann. § 66-36-103
provides:
66-36-103. Procedures and requirements for notification and remedying
construction defects. – (a) In actions brought against a contractor,
subcontractor, supplier, or design professional related to an alleged
construction defect, the claimant shall, before filing an action, serve written
notice of claim on the contractor, subcontractor, supplier, or design
professional, as applicable. The claimant shall endeavor to serve the notice of
claim within fifteen (15) days after discovery of an alleged defect, but the
failure to serve notice of claim within fifteen (15) days does not bar the filing
of an action, subject to § 66-36-102.
-7-
(b) Within ten (10) business days after service of the notice of claim,
the contractor, subcontractor, supplier, or design professional may inspect the
structure to assess each alleged construction defect. The claimant shall
provide the contractor, subcontractor, supplier, or design professional and its
contractors or agents reasonable access to the structure during normal working
hours to inspect the structure, to determine the nature and cause of each
alleged construction defect and the nature and extent of any corrections,
repairs or replacements necessary to remedy each defect. The inspection may
include destructive testing.…
Tenn. Code Ann. § 66-36-103 (2004). The term ‘action’ as used in Tenn. Code Ann. § 66-
36-103 is defined in Tenn. Code Ann. § 66-36-101 as follows:
(1) “Action” means any civil action for damages or indemnity asserting a claim
for damage to or loss of commercial property caused by an alleged
construction defect, but does not include any civil action or arbitration
proceeding asserting a claim for alleged personal injuries arising out of an
alleged construction defect;
Tenn. Code Ann. § 66-36-101(1) (2004) (emphasis added). Commercial property is defined
as “all property which is not residential property. Residential property is property upon
which a dwelling or improvement is constructed or to be constructed consisting of one
dwelling unit intended as a residence of a person or family.” Tenn. Code Ann. § 66-36-
101(3) (2004).
The language of the statute is clear and unambiguous. It requires a claimant
to provide notice prior to filing an action “for damage to or loss of commercial property …,”
not residential property. Tenn. Code Ann. § 66-36-101(1) (2004) (emphasis added). As the
statute is clear and unambiguous, we apply its plain meaning. See Shelby County Health
Care Corp., 325 S.W.3d at 92.
In the case now before us on appeal, the Trial Court specifically found that the
Contract was for the construction of a residential garage. The evidence in the record does
not preponderate against this finding. As Defendant’s counterclaim is an action for damage
to or loss of residential property, not commercial property, Defendant was not required to
comply with Tenn. Code Ann. § 66-36-101 et seq. As such, Defendant’s claim was not
properly abated for failure to comply with Tenn. Code Ann. § 66-36-101 et seq.
We next consider whether the Trial Court correctly dismissed Defendant’s
counterclaim under the common law for failure to give Plaintiff notice and an opportunity
-8-
to cure. In its order, the Trial Court stated that the common law required that notice and an
opportunity to cure be given to the contractor, Plaintiff, prior to Defendant’s terminating the
contract for faulty performance. The Trial Court relied upon McClain v. Kimbrough Constr.
Co., Inc., 806 S.W.2d 194 (Tenn. Ct. App. 1990), for this proposition.
In McClain, this Court imposed upon a contractor a duty to give its
subcontractor notice and an opportunity to cure alleged defects prior to terminating a contract
for a commercial construction project. Id. at 198-99. In Carter v. Krueger, this Court
extended the rule to a case wherein a doctor and a contractor entered into a contract for the
construction of an addition to the doctor’s professional office building. Carter v. Krueger,
916 S.W.2d 932, 935-36 (Tenn. Ct. App. 1995). The Carter Court quoted McClain wherein
it was stated: “Requiring notice is a sound rule designed to allow the defaulting party to
repair the defective work, to reduce the damages, to avoid additional defective performance,
and to promote the informal settlement of disputes.” Carter, 916 S.W.2d at 935 (quoting
McClain, 806 S.W.2d at 198). The rule requiring giving notice and an opportunity to cure
has also been extended to cases involving residential construction. E.g., Greeter Const. Co.
v. Tice, 11 S.W.3d 907, 910-11 (Tenn. Ct. App. 1999); Lavy v. Carroll, No. M2006-00805-
COA-R3-CV, 2007 Tenn. App. LEXIS 809, at **9-10 (Tenn. Ct. App. Dec. 26, 2007), Rule
11 appl. perm. appeal denied May 27, 2008; and Custom Built Homes by Ed Harris v.
McNamara, No. M2004-02703-COA-R3-CV, 2006 Tenn. App. LEXIS 781, at **14-15
(Tenn. Ct. App. Dec. 11, 2006), no appl. perm. appeal filed.
In the case now before us on appeal, the Trial Court found that Defendant
failed to give Plaintiff notice of the alleged defects and an opportunity to cure. The Trial
Court found that Defendant sent Plaintiff a letter dated July 10, 2006, and that Defendant’s
attorney sent Plaintiff a letter dated July 12, 2006, but that “the plain language of these letters
indicate there was no anticipation that [Plaintiff] would be allowed back on the job,” in order
to cure the alleged defects. In addition, the evidence in the record shows that Plaintiff denied
ever receiving Defendant’s July 10, 2006 letter. Furthermore, the Trial Court found that “the
unrefuted testimony of [Plaintiff] is that [Defendant’s attorney] left a voice message at
[Plaintiff’s] home on the evening of July 12 advising him not to return to the job site.” This
evidence provides further support for the Trial Court’s finding that Plaintiff was not allowed
an opportunity to cure the alleged defects.
The evidence in the record on appeal does not preponderate against the Trial
Court’s findings that Defendant failed to give Plaintiff notice and an opportunity to cure the
alleged construction defects pursuant to the common law. As such, we hold that the Trial
Court correctly dismissed Defendant’s counterclaim. We, therefore, affirm the Trial Court’s
May 27, 2010 order.
-9-
Conclusion
The judgment of the Trial Court is affirmed, and this cause is remanded to the
Trial Court for collection of the costs below. The costs on appeal are assessed against the
appellant, Caroline Benedetti, and her surety.
_________________________________
D. MICHAEL SWINEY, JUDGE
-10-