Present: Keenan, Koontz, Kinser, Lemons, and Millette, JJ.,
and Carrico and Lacy, S.JJ.
THE PIEDMONT ENVIRONMENTAL COUNCIL, ET AL.
OPINION BY
v. Record Nos. 090249, 090253, JUSTICE LAWRENCE L. KOONTZ, JR.
090258, 090278, November 5, 2009
& 090284
VIRGINIA ELECTRIC AND POWER COMPANY,
D/B/A DOMINION VIRGINIA POWER, ET AL.
FROM THE STATE CORPORATION COMMISSION
These five consolidated appeals of right arise from an
order of the State Corporation Commission dated October 7,
2008 granting certificates of public convenience and necessity
to two electric utilities, Virginia Electric and Power Company
(“VEPCO”) and Trans-Allegheny Interstate Line Company
(“TrAILCo”), for the construction and operation of two
Virginia segments of a proposed 500 kilovolt (500kv)
interstate electric transmission line. 1 The interstate
transmission line is to be operated by a regional transmission
1
The appellants in the respective appeals are Fauquier
County Board of Supervisors (Record No. 090249), Piedmont
Environmental Council (Record No. 090253), Prince William
County Board of Supervisors (Record No. 090258), Power-Line
Landowners Alliance (Record No. 090278), and Culpeper County
Board of Supervisors (Record No. 090284). An appeal brought
by Virginia’s Commitment, Inc. (Record No. 090272), also
originally consolidated with these five appeals, was dismissed
upon motion of the appellant. Following consolidation of the
appeals, the Piedmont Environmental Council assumed the role
of lead appellant, and for convenience we will refer to the
appellants collectively as “Piedmont.”
entity which is subject to federal regulation. VEPCO and
TrAILCo are members of that regional transmission entity. As
will be addressed subsequently in some detail in this opinion,
the focus of the issues raised by the appellants in their
challenge to the decision of the Commission involves the
interplay of the requirements placed on the Commission by Code
§§ 56-46.1 and 56-265.2 and certain federal regulations
pertaining to the reliability of a regional electric
transmission grid such as the one involved in the present
case.
BACKGROUND
On April 19, 2007, VEPCO and TrAILCo, pursuant to the
requirement of Code § 56-265.2, filed applications with the
Commission for approval of two Virginia segments of a 500kv
interstate electric transmission line project. 2 The project
was intended to address an anticipated need for increased
2
In pertinent part, Code § 56-265.2 provides:
A. It shall be unlawful for any public utility to
construct, enlarge or acquire, by lease or
otherwise, any facilities for use in public utility
service, except ordinary extensions or improvements
in the usual course of business, without first
having obtained a certificate from the Commission
that the public convenience and necessity require
the exercise of such right or privilege . . . . The
certificate for overhead electrical transmission
lines of 150 kilovolts or more shall be issued by
the Commission only after compliance with the
provisions of § 56-46.1.
2
reliability in the transmission of electricity for
distribution to the Virginia suburban communities of the
Washington, D.C. metropolitan area along a transmission line
originating at generation sources in central Pennsylvania and
extending through West Virginia and the Shenandoah Valley to
northern Virginia. 3 VEPCO’s application, filed jointly with
TrAILCo which would hold a 50% stake in ownership of VEPCO’s
segment of the line, sought authority to build a transmission
line from a point in Warren County on the west side of the
Appalachian Trail near the boundary of Warren and Fauquier
Counties to VEPCO’s existing Loudoun Substation in Loudoun
County. TrAILCo’s separate application was for its wholly-
owned segment of the transmission line that would enter the
Commonwealth at the Virginia/West Virginia state line, run
through the existing Meadow Brook Substation in Warren County,
and continue from there a short distance to connect with
3
The terms generation, transmission, and distribution
have specific meanings within the electric utility industry,
and the definitions of these terms have been adopted within
the statutes and regulations that govern that industry. See,
e.g., Code § 56-576. Generation is the production of electric
power, usually on a large scale for wholesale delivery;
transmission is the transfer of electric energy from its
sources of generation across high voltage lines to either a
local distributor or a large-scale industrial consumer;
distribution is the transfer of electric energy through a
retail delivery system to industrial, commercial, and
residential consumers.
3
VEPCO’s line. Each application proposed preferred and
alternate routes for each line.
Prior to the filing of the applications for approval of
the proposed segments of the transmission line by the
Commission, the determination of the need for the construction
of the entire 500kv interstate electric transmission line was
subject to a federal regulatory process. That process
involved the interaction of three administrative entities:
the Federal Energy Regulatory Commission (“FERC”), a federal
agency whose jurisdiction includes regulation of interstate
electricity sales and wholesale electric rates as well as the
authority to impose mandatory reliability standards on bulk
electric transmission systems, commonly referred to as
“grids;” the North American Electric Reliability Corporation
(“NERC”), a non-profit corporation overseen by FERC and its
Canadian regulatory counterpart that is responsible for
developing standards for transmission grid operation,
monitoring and enforcing compliance with those standards, and
assessing the reliability of interconnected regional grids;
and PJM Interconnection, LLC (“PJM”), a regional transmission
entity 4 (“RTE”) regulated by FERC and monitored by NERC that
4
Also referred to in the record as a “regional
transmission organization,” or RTO, the term used in federal
legislation and regulations; “regional transmission entity” is
the term used in the applicable Virginia statutes, see, e.g.,
4
coordinates wholesale electricity transmission in 13 states
and the District of Columbia, including most of Virginia.
The federal determination of need for the new interstate
transmission line was the result of a mandatory regional
transmission expansion planning (“RTEP”) process in which PJM
attempts to identify future transmission system additions and
improvements needed within PJM’s operating area necessary to
maintain transmission reliability standards established by
NERC. During its 2006 RTEP process, PJM determined that
additional transmission capacity would be needed to supply
electricity to northern Virginia based on data that showed
that an existing transmission line, the “Mt. Storm – Doubs
line,” was expected to begin experiencing intermittent
overloads in 2011 with increasing severity thereafter,
resulting in violations of NERC reliability standards on that
line and elsewhere within PJM’s operational area. VEPCO and
TrAILCo used PJM’s data showing the projected NERC violations,
which supported the federal regulatory finding of need for the
interstate transmission line, in their applications to the
Commission to support the assertion that the Virginia segments
of the line were a necessary improvement as required by Code
§§ 56-265.2 and 56-46.1(B).
Code § 56-579, and, accordingly, we will adopt that term for
use in this opinion.
5
On June 1, 2007, the Commission issued an order directing
publication of public notice of VEPCO’s and TrAILCo’s
applications. The order also established a schedule for
reviewing the applications and set hearing dates to receive
public comment and evidence. The Commission appointed
Alexander F. Skirpan, Jr., as a Hearing Examiner, to conduct
further proceedings on the applications for approval of the
segments of the transmission line. On July 28, 2008, Skirpan
entered a 223-page report that detailed the extensive
proceedings which he conducted, summarized the voluminous
record, analyzed the evidence and issues, and made certain
findings and recommendations to the Commission for favorable
resolution of the applications.
As reflected in his report to the Commission, between
July 2007 and July 2008, Skirpan conducted 23 days of public
hearings in Richmond, as well as in Bristow, Front Royal,
Warrenton, and Winchester, communities located on or near the
proposed routes of the transmission lines. Skirpan identified
over 30 government entities, public interest organizations and
individuals, including the five appellants, who had directly
participated in these proceedings. In addition, the
Commission received over 1,300 written and electronic
communications during the course of the proceedings.
6
Among the evidence and supporting documents received by
Skirpan was the post-hearing memorandum of the Commission
staff discussing the issues that the Commission would be
required to address and giving recommendations as to their
resolution. As relevant to the issues raised in these
appeals, the staff’s analysis of the utilities’ assertion of
need for the lines was based principally upon a report made by
Bates White, LLC (“Bates White”), a consulting firm retained
by the Commission “to conduct a review and independent
verification of the Applicants’ load flow modeling,
contingency analyses and reliability needs assessment as
introduced in the applications to justify the proposed
transmission line.” Bates White reviewed the reliability data
originally used by PJM in the federal regulatory process that
established the need for the new line in order to satisfy NERC
standards, as well as updates to that data provided by the
utilities at the request of the Commission. Bates White also
reviewed evidence from the record to determine whether there
were alternative methods to meet the anticipated future
transmission reliability requirements including increasing the
transmission infrastructure in other ways, introducing new
sources of power generation on the existing transmission
infrastructure, and through demand side management strategies
7
for increased conservation to reduce the need for increased
transmission and/or generation infrastructure.
On October 7, 2008, the Commission issued a final order
approving both applications. As relevant to the issues raised
in these appeals, the Commission found that the evidence
established that the transmission line was needed to ensure
future NERC reliability requirements within PJM’s region of
operation and specifically with respect to VEPCO’s
distribution of electricity to consumers in northern Virginia
in 2011. The Commission further found that reasonably
reliable estimates of new generation capacity within VEPCO’s
service area alone would not be sufficient to meet the future
needs of the northern Virginia area, and that conservation
through demand side management, alone or in combination with
other transmission upgrades and/or additional generation
capacity, would not be sufficient to avoid violations of NERC
reliability requirements.
The Commission addressed the environmental impact of the
proposed routes for the line segments and the review process
conducted under the auspices of the Department of
Environmental Quality in that regard. In giving final
approval to the applications, the Commission conditioned its
issuance of the certificates of public convenience and
necessity to the utilities on the approval of the remaining
8
segments of the line by the respective state commissions of
West Virginia and Pennsylvania. The Commission further
addressed the basis for the selection of the approved routes
for the line segments from among the options given in the
applications and placed additional restrictions and
requirements on the utilities that are not germane to the
issues raised in these appeals.
In a separate concurrence to the order approving the
applications, Commissioner Preston C. Shannon 5 noted his
concern, echoing the position of some of the opponents to the
approval of the applications, that changes in the process for
regulating the electric utility industry in Virginia, which
had resulted in the mandatory transfer of control over
transmission infrastructure within Virginia to an RTE, Code
§ 56-579, “places a myriad of restrictions on Virginia’s
sovereign authority over its public utilities – including
effectively placing the responsibility for transmission
planning, as well as [VEPCO’s] ability to interconnect its new
generating facilities to its transmission facilities, under
the control of the federally-regulated PJM.” In Commissioner
Shannon’s view, the legislature’s decision to place Virginia’s
electric transmission infrastructure under the supervision of
5
Commissioner Shannon, who retired from the Commission in
1996, sat on this case by designation.
9
federally-regulated RTEs “has not served Virginia well” and
“could prevent critical generation, needed in Virginia, from
being implemented on a timely basis.” Nonetheless, he agreed
with the majority view of the Commission that approval of the
applications at issue here was in accord with “the current
laws that this Commission must follow in conjunction with the
facts presented.”
Following entry of the Commission’s order granting the
applications, the five appellants each noted appeals as a
matter of right pursuant to Code § 12.1-39. By orders dated
April 2, 2009, we consolidated the appeals for briefing and
oral argument.
STANDARD OF REVIEW
Under the Constitution of Virginia and in statutes
enacted by the General Assembly, the Commission is given broad
authority over the control and regulation of public service
corporations. Board of Supervisors of Campbell County v.
Appalachian Power Co., 216 Va. 93, 105, 215 S.E.2d 918, 927
(1975). In exercising this authority, “[t]he Commission is
charged with the responsibility of finding the facts and
making a judgment. This court is neither at liberty to
substitute its judgment in matters within the province of the
Commission nor to overrule the Commission’s finding of fact
unless we can say its determination is contrary to the
10
evidence or without evidence to support it.” Id.; see also
Appalachian Voices v. State Corp. Comm’n, 277 Va. 509, 516,
675 S.E.2d 458, 461 (2009).
Accordingly, our review of the Commission’s order in the
present cases is guided by the well established principle that
“[o]n appeal, the findings of the Commission are presumed to
be just, reasonable, and correct. The decisions rendered by
the Commission must be ascribed the respect due to the
judgments of a tribunal appointed by law and informed by
experience. Accordingly, a presumption of correctness
attaches to actions of the Commission, and its orders will not
be disturbed when they are based upon the application of
correct principles of law.” Swiss Re Life Co. Am. v. Gross,
253 Va. 139, 144, 479 S.E.2d 857, 860 (1997)(citations and
internal quotation marks omitted); accord Northern Virginia
Electric Coop. v. Virginia Electric and Power Co., 265 Va.
363, 368, 576 S.E.2d 741, 743 (2003). Moreover, although
questions of law are reviewed de novo, the practical
construction given by the Commission to a statute it is
charged with enforcing “‘is entitled to great weight by the
courts and in doubtful cases will be regarded as decisive.’”
Appalachian Voices, 277 Va. at 516, 675 S.E.2d at 461 (quoting
Commonwealth v. Appalachian Elec. Power Co., 193 Va. 37, 45,
68 S.E.2d 122, 127 (1951)).
11
DISCUSSION
While Piedmont makes eleven assignments of error, which
are distilled into eight interrelated questions presented, the
arguments asserted in their opening brief and during oral
argument of these appeals may be fairly narrowed to the
following substantive issues:
(1) Whether the Commission erroneously interpreted
federal law and regulations governing RTEs as
requiring the Commission to limit the scope of its
inquiry as to the necessity for the Virginia
segments of the interstate transmission line to a
review of PJM’s determination that the new
transmission line was needed in accord with federal
regulations.
(2) Whether the Commission failed to conduct an
independent analysis of the applications for the
Virginia segments of the interstate transmission
line by failing to properly consider additional
generation and conservation alternatives in
determining whether the transmission line was
needed.
(3) Whether the Commission erred in approving the
applications because of the “inherent bias” of the
evidence relied upon by the Commission.
Federal and State Regulation of Electric Utilities
Because the Commission does not operate in a vacuum at
any given time, it will be beneficial initially to summarize
the changes that have occurred over the past several decades
in the regulation of the generation, transmission, and
distribution of electricity in the United States. Generation,
transmission, and distribution of electricity historically
were provided by a single utility that had exclusive rights
12
over a limited geographic area within a state. The utility
was permitted to maintain this monopoly because its operations
were regulated by the state, which controlled the construction
of new generation and transmission infrastructure and the
rates the utility could charge for distribution of electricity
to consumers. However, over time as a result of efficiencies
of scale favoring the construction of larger generation
facilities that could supply electricity to wider geographic
areas, a division arose between generation and distribution,
with the owners of the generation infrastructure typically
also owning the transmission lines. Inevitably, this resulted
in electricity generated in one state being sent over
transmission lines to be sold by a distributor in another
state.
In Public Utilities Commission v. Attleboro Steam &
Electric Co., 273 U.S. 83, 90 (1927), the United States
Supreme Court, holding that the negative impact of the
Commerce Clause prohibits state regulation that would directly
burden interstate commerce, determined that the interstate
transmission of electrical power was subject to regulation
only “by the exercise of the power vested in Congress.” 273
U.S. 83, 90 (1927). Congress exercised this power eight years
after the Attleboro Steam decision by enacting the Federal
Power Act of 1935, now codified as amended at 16 U.S.C. § 824
13
et seq. (2006 & Supp. I 2007), which created the Federal Power
Commission (“FPC”), the predecessor of FERC, “to provide
effective federal regulation of the expanding business of
transmitting and selling electric power in interstate
commerce.” Gulf States Utils. Co. v. FPC, 411 U.S. 747, 758
(1973). Specifically, Congress recognized the FPC’s
jurisdiction as including “the transmission of electric energy
in interstate commerce” and “the sale of electric energy at
wholesale in interstate commerce.” 16 U.S.C. § 824(b).
Following passage of the Federal Power Act of 1935, the
generation and transmission of electric power has increasingly
become a matter of interstate commerce, and correspondingly
the federal role in the regulation of the electric industry
has also grown. With the passage in 1978 of the Public
Utility Regulatory Policy Act (“PURPA”), 16 U.S.C. § 2601 et
seq. (2006 & Supp. I 2007), the federal government required
utilities to allow the transmission of power from other
generators across their transmission and distribution lines,
even within the borders of a state. This was deemed necessary
because established producers of electric power continued to
control the majority of the transmission capacity and were
reluctant to purchase power from “nontraditional facilities”
or allow such competitors to have access to the existing
transmission infrastructure. PURPA directed FERC to
14
promulgate rules requiring utilities to purchase electricity
from “qualifying cogeneration and small power production
facilities” and allow transmission of power produced by other
generators on their lines. FERC v. Mississippi, 456 U.S. 742,
751 (1982); see also 16 U.S.C. § 824a. Overseen by FERC, this
“open access” mandate for wholesale interstate transmission of
electricity would prove to be the first step toward market
competition through the creation of regional distribution
systems on a nationwide structure of interconnected
transmission grids.
Subsequent federal legislation further expanded FERC’s
authority to order individual utilities to provide
transmission services to unaffiliated wholesale generators on
a case-by-case basis. See 16 U.S.C. § 824j and § 824k. In
addition, FERC was also authorized to override any state law
or regulation that “prohibits or prevents the voluntary
coordination of electric utilities.” 16 U.S.C. § 824a-1(a).
Applying this authority, FERC promulgated the so-called “Open
Access Rules” though its Orders 888 and 889. FERC’s Order No.
888 “remove[d] impediments to competition in the wholesale
bulk power marketplace and [brought] more efficient, lower
cost power to the Nation's electricity consumers” by requiring
any public utility that owns, operates or controls interstate
transmission facilities to provide service to any power
15
supplier needing to transport electricity across the utility’s
lines. Promoting Wholesale Competition Through Open Access
Non-Discriminatory Transmission Services by Public Utilities,
61 Fed. Reg. 21,450 (May 10, 1996)(codified at 18 C.F.R. pts.
35 & 385). FERC’s Order No. 889 required that there be a
functional separation of control by utilities that owned both
transmission and generation infrastructure. Open Access
Same-Time Information System & Standards of Conduct, 61 Fed.
Reg. 21,737 (May 10, 1996)(codified at 18 C.F.R. pt. 37).
These “Open Access Rules have been described as ‘the legal,
functional, and regulatory prerequisite to the implementation
of nationwide deregulation of the electric utility
business.’ ” State ex rel. Sandel v. New Mexico Pub. Util.
Comm'n, 980 P.2d 55, 59 (N.M. 1999) (quoting Michael Evan
Stern & Margaret M. Mlynczak Stern, A Critical Overview of the
Economic and Environmental Consequences of the Deregulation of
the U.S. Electric Power Industry, 4 Envtl. Law. 79, 95
(1997)).
Concurrent with the expanding role of the federal
government in regulating the interstate transmission of
electricity, members of the electric utilities industry
recognized the need to assure that the expanding interstate
transmission infrastructure would be sufficient to meet the
rapid increase in demand for electricity in growing urban
16
markets. Compacts between electric utilities, originally
known as “power pools” and now more commonly referred to as
“interconnections,” date to the early twentieth century.
Following the “Great Blackout” of November 9, 1965, which
resulted from a catastrophic failure of the interconnected
electric transmission grids in the northeastern United States
and Ontario, Canada, the FPC, at the direction of President
Lyndon Johnson, recommended the formation of a council on
power to assist in resolving interregional coordination of
transmission reliability. See, e.g., Steven Ferrey, Power
Future, 15 Duke Envtl. L. & Pol'y F. 261, 276 n.55 (2005);
Scott V. Heck, Lights Out For New Jersey: The August 2003
Blackout and the End of Electricity Regulation in New Jersey,
29 Seton Hall Legis. J. 279, 280-81 (2004).
The resulting entity, the National Electric Reliability
Council, the predecessor of NERC, was formed in 1968 and
originally served only in an advisory capacity with no
official regulatory function. See, e.g., Garkane Power Ass’n
v. Public Serv. Comm'n, 681 P.2d 1196, 1201 (Utah 1984). The
Federal Power Act of 2005, however, directed FERC to designate
a national Electric Reliability Organization charged with
establishing and enforcing reliability standards for the
interstate transmission of electricity. 16 U.S.C.
§ 824o(a)(2). Not surprisingly, NERC was the sole applicant
17
which sought to be designated as the national Electric
Reliability Organization and was subsequently designated by
FERC to fulfill that role. See Alcoa Inc. v. FERC, 564 F.3d
1342, 1345 (D.C. Cir. 2009). Following the designation of
NERC as the national Electric Reliability Organization, FERC
adopted through a rulemaking process the majority of NERC’s
formerly voluntary transmission reliability standards, making
them mandatory and subject to penalty by fines against RTEs
and independent utilities that fail to adhere to those
standards. 6 Id. at 1344 (citing Mandatory Reliability
Standards for the Bulk-Power System, 72 Fed. Reg. 16,416 (Apr.
4, 2007) (codified at 18 C.F.R. pt. 40) (FERC’s final rule
adopting NERC standards)).
In apparent response to increased federal regulation and
industry emphasis on assuring the reliability of the
interstate transmission grids, a number of states began to
revise their regulatory schemes governing the operation of
electric utilities within their borders. State restructuring
of regulations governing the operation of electric utilities
was driven principally by the worthy belief that increased
competition in the generation and transmission of electricity
6
NERC has already sought, and FERC has approved,
imposition of fines in many cases. See, e.g., Scott Grover,
FERC Guidance Order Shows Inter-Agency Tension, 23 Nat.
Resources & Env’t 61, 61-62 (2009).
18
would lead to reduced costs for all consumers, but especially
for large industrial users, who became strong advocates of
deregulation. See, e.g., David B. Spence, The Politics of
Electricity Restructuring: Theory vs. Practice, 40 Wake Forest
L. Rev. 417, 446-47 (2005).
As part of Virginia’s restructuring of regulation of the
operation of electric utilities, in 1999 the General Assembly
enacted the Virginia Electric Utility Restructuring Act, now
known as the Virginia Electric Utility Regulation Act, Code
§ 56-576 et seq. As relevant to the issues raised in these
appeals, the Act required electric utilities within the
Commonwealth that own, operate, or otherwise have control over
transmission infrastructure to “join or establish a regional
transmission entity” and “transfer the management and control
of its transmission system” to the RTE. Code § 56-577(A)(1).
The Act further provided that “the Commission shall continue
to regulate . . . to the extent not prohibited by federal law,
the transmission of electric energy in the Commonwealth.”
Code § 56-580(A). Moreover, the Act expressly provided that
the Commission would retain “authority over transmission line
or facility construction, enlargement or acquisition within
this Commonwealth.” Code § 56-579(D)(1).
In 2004, the Commission approved the applications of
VEPCO and Allegheny Power, the parent affiliate of TrAILCo, to
19
transfer operational control of their transmission
infrastructure within Virginia to PJM. 2004 S.C.C. Ann. Rept.
294 (VEPCO); 2004 S.C.C. Ann. Rept. 300 (Allegheny Power).
Thus, the transmission infrastructure of these utilities
became part of the regional transmission grid administered by
PJM and was thereafter included in its ongoing RTEP process
for evaluating the reliability of its members’ transmission
infrastructure in order to respond to projected reliability
violations of NERC standards.
With this background in mind, we now address the issues
raised by Piedmont in these appeals.
Reliance on PJM’s Application of NERC Reliability Standards
Piedmont contends that the Commission erred, as a matter
of law, when it “conclud[ed] that it was obligated under Va.
Code §§ 56-46.1 and 56-265.2 to grant the Applications if a
clear reliability need had been shown and the transmission
line at issue is an ‘acceptable’ option to meet that need.”
Piedmont reasons that the Commission must have “erroneously
concluded that it was prevented by federal regulation or
policy from conducting the investigation and analysis that is
prescribed by state statutes” to make an independent
determination of the need for the transmission line.
The Commission responds that the record does not support
Piedmont’s contention that the Commission premised its
20
decision on a presumption that it was preempted by federal
regulation or policy from conducting a full and independent
review of the applications to determine that the construction
of the transmission line was necessary and otherwise comported
with the requirements of Code § 56-46.1. Rather, in the
Commission’s view, Piedmont’s contentions are based on a
mischaracterization of the Commission’s recognition that the
federal regulations were mandatory as applied to the
utilities, and that the Commission could take this factor into
account in its review process. We agree with the Commission.
In his hearing examiner’s report, Skirpan noted that Code
§ 56-46.1(B) directs the Commission to verify “the
applicant[s’] load flow modeling, contingency analyses, and
reliability needs presented to justify the new line.” Skirpan
further noted that “[t]he determination of need begins with a
review of NERC transmission planning reliability standards,
and the procedures and tests employed by PJM and [VEPCO]” to
comply with those standards. While acknowledging that
Piedmont and other opponents to approval of the applications
“questioned whether the PJM tests are appropriate” for
determining whether the line was specifically needed for the
benefit of Virginia consumers, Skirpan concluded that “the
NERC transmission planning standards are mandatory and that
21
the tests employed by PJM and [VEPCO] properly apply the NERC
standards.”
The Commission agreed with Skirpan’s conclusions,
expressly adopting his findings that:
(i) “[t]he PJM generation deliverability and load
deliverability tests and the [VEPCO] test properly
apply mandatory NERC transmission reliability
planning standards;” (ii) “[t]he Applicants’ load
forecasts are based on reasonable assumptions for
transmission planning purposes, including
assumptions that project future savings from [demand
side management programs] to remain at current
levels;” (iii) “[t]he Applicants’ assumptions
regarding future generation are consistent with the
federally-mandated functional separation of
transmission and generation, and PJM’s general lack
of authority to cause generation to be constructed;”
and (iv) “[t]he Applicants’ projected load-flow
results for 2011 and 2012 support the need for
additional transmission to address violations of
NERC transmission reliability planning standards.”
Piedmont contends that these statements show that the
Commission incorrectly presumed it could not base its decision
to grant or deny the applications on factors other than
verification of the utilities’ own data showing the
anticipated violation of NERC reliability standards. As a
result, Piedmont asserts the Commission assumed “that because
PJM was obligated to find a solution to a violation of the
NERC criteria, the Commission was bound to accept PJM’s
solution and ignore the requirements of Va. Code §§ 56-46.1
and 56-265.2.”
22
Our review of a decision by the Commission requires that
we undertake an examination and study of the entire record.
Rappahannock League for Environmental Protection, Inc. v.
Virginia Electric & Power Co., 216 Va. 774, 783, 222 S.E.2d
802, 808 (1976). When so viewed, we find no support for the
assertion that the Commission presumed it was required by the
federal regulatory process to limit its consideration of the
applications to a review of PJM’s determination that the
proposed transmission line was an “acceptable” solution to the
anticipated NERC reliability violations or that the Commission
actually limited its consideration of the applications in that
way. By focusing on isolated statements in the hearing
examiner’s report and the Commission’s order to support its
contention that the Commission somehow viewed federal
regulations as preempting the Commission from conducting the
independent review of the applications required by Virginia
law, Piedmont has discounted the overwhelming weight of
evidence in the record that is plainly contrary to Piedmont’s
assertion.
Skirpan correctly noted that as part of the Commission’s
responsibility under Code § 56-46.1 to determine that the line
is needed “the Commission shall verify the applicant’s load
flow modeling, contingency analyses, and reliability needs
presented to justify the new line.” (Emphasis added.) A
23
plain reading of the statute does not support the conclusion,
apparently urged by Piedmont, that to accomplish this
verification the Commission is required to obtain new data
from an independent source, rather than giving any weight to
the data provided by the applicant.
Moreover, the record amply demonstrates that the
Commission, through its staff, fulfilled its statutory
obligation to verify the applicants’ assertion of need for the
transmission line by having Bates White analyze the
reliability data originally used by PJM and VEPCO that showed
the projected violations of NERC standards. Bates White
independently reviewed the assumptions on which this data was
based, finding that these assumptions were reasonable. While
the Commission’s ultimate decision to accept Skirpan’s
recommendation to use PJM’s data in determining the need for
the new transmission line was obviously contrary to the
desires of Piedmont and the other opponents to approval of the
applications, the record simply does not support the
conclusion that the Commission determined that it was
compelled to accept this data because it also had been used in
the federal regulatory process approving the need for the line
by NERC. Rather, the record more readily supports the
conclusion that the Commission, aided by its staff and the
employment of a skilled, independent consultant, properly
24
verified the utilities’ load flow modeling, contingency
analyses, and reliability needs presented to justify the new
line. Accordingly, we hold that the Commission did not err in
using PJM’s NERC data to determine the need for the proposed
transmission line as required by Code § 56-46.1.
Consideration of Generation and Conservation Alternatives
Piedmont contends that the Commission also erred, as a
matter of law, in that it failed to independently review
alternative solutions for addressing the anticipated deficit
in transmission reliability on the Mt. Storm - Doubs line.
According to Piedmont, rather than conduct its own analysis,
the Commission effectively “delegated its statutory
responsibility to PJM” by accepting PJM’s assertion that there
were no alternatives that could successfully address the
increased demand for electricity in northern Virginia by 2011,
which the new line was intended to resolve.
The Commission responds that the record shows it reviewed
options for developing new generation capacity within VEPCO’s
service area, the use of conservation through demand side
management, and the availability of alternative transmission
infrastructure upgrades, but concluded that none of these
alternatives, alone or in combination, were sufficient to
assure that PJM’s transmission capability to avoid violations
of NERC reliability standards would not be adversely affected
25
by the anticipated increase in demand for electricity in
northern Virginia in 2011 and beyond. In doing so, the
Commission acknowledged that the assumptions regarding future
generation and conservation through demand side management
were in part based upon data developed though the federal
regulatory process overseen by NERC, and that these
assumptions favor increased transmission capacity as the
principal method for assuring compliance with mandatory
reliability standards. Nonetheless, the Commission maintains
that its decision was reached through an independent
examination of the data as required by Virginia law. Again,
we agree with the Commission.
The record reflects that Bates White “studied five
additional transmission solutions to overloads on the Mt.
Storm - Doubs line,” finding only one alternative to the
proposed new transmission line that could sufficiently reduce
the chance for reliability violations in the short term. The
utilities contended that this alternative would not provide a
long-term solution, while Bates White concluded that the
utilities’ projections for long-term reliability problems were
speculative. Similarly, Skirpan concluded that “PJM’s
generation assumptions produce less and less reliable power-
flow model results as the forecasts project farther into the
future.”
26
The record also shows, however, that the Commission
concluded that the interpretations of the data for
transmission alternatives that were presented by opponents to
approval of the applications were equally speculative. Thus,
the Commission ultimately adopted Skirpan’s view that “the
focus of the needs analysis should be on results for 2011 and
2012,” and that the Commission should accept PJM’s data as
being the most accurate for verifying that the new
transmission line was the only viable option for assuring that
NERC reliability standards would be timely met.
Similarly, the record reflects that consideration was
also given to the data analysis presented by the utilities and
the opponents on generation and conservation alternatives. In
his report to the Commission, Skirpan extensively detailed
these alternatives, including the environmental impact of the
proposed line and the alternative solutions. Based on the
independent analysis by Bates White and the recommendations of
the staff and the hearing examiner, the Commission found that
it was not “reasonable to assume that a sufficient amount of
additional new generation necessarily will be available . . .
to obviate the reliability need,” and concluded that “the
generation assumptions used in the PJM and [VEPCO] tests . . .
are reasonable.” Ultimately, the Commission adopted the
conclusions drawn by Bates White, the staff, and Skirpan that
27
none of the alternative scenarios, whether applied
individually or in combination, “is a reasonable proposal to
meet the need satisfied by the [new] transmission line.”
We agree with the Commission that the record as a whole
demonstrates that the Commission fulfilled its statutory
obligation to consider alternative solutions to the need for
the proposed transmission line. We hold that the Commission
acted within its authority to evaluate the evidence presented
by the utilities on this issue and determine whether that
evidence, when considered against evidence presented by other
participants in the process, was reliable and could serve as
the basis for the Commission’s determination that no other
alternative was available that would obviate the demonstrated
need for the line.
It is understandable that the opponents would have
preferred that the Commission not rely on the utilities’ data
and analysis concerning alternatives to the transmission line.
Nonetheless, the record simply will not support a conclusion
that the Commission’s decision to do so was arbitrary or
capricious so as to amount to a “delegation” of its
responsibility to PJM or any other entity. Rather, it is
clear that the Commission reached its conclusion through a
deliberative consideration of all the evidence consistent with
28
the authority given to it by the Constitution and the General
Assembly.
Approval of the Applications
Piedmont asserts that the Commission erred in approving
the applications because the Commission failed to consider the
“inherent bias” of VEPCO, TrAILCo, and PJM in reviewing the
data submitted by them. Citing Virginia Electric and Power
Company v. Citizens for Safe Power, 222 Va. 866, 869, 284
S.E.2d 613, 614 (1981), Piedmont contends that the Commission
erred because it “deferred” to the utilities and the RTE by
accepting their data instead of exercising its statutory
authority to “obtain all relevant . . . information reasonably
necessary for it to make a considered judgment.” In
Piedmont’s view, because federal law prohibits direct
cooperation between the entities that control generation and
transmission infrastructure, PJM’s assumptions of future NERC
violations are arbitrary in that they consider only the effect
of future demands on the transmission grid without regard to
the effect of additional generation capacity or conservation
efforts. Piedmont contends that “[a]ny arbitrariness in PJM’s
assumptions, then, [is] imputed to the Commission” and, thus,
to its decision to approve the applications. Piedmont asserts
that the Commission should have used its authority to order
the utilities to undertake an integrated resource planning
29
(“IRP”) process, Code § 56-597 et seq., or otherwise exercised
its general investigative powers to challenge PJM’s
assumptions concerning the lack of sufficient generation or
conservation alternatives. Piedmont also asserts that the
Commission erred in not exercising its authority under Code
§ 56-235.1 “to consider generation and conservation
alternatives to the proposed transmission line, [and] to
require [VEPCO] to implement them.”
In its order approving the applications, the Commission
noted that Piedmont and other opponents to approval of the
applications contended that because the assumptions used by
VEPCO and TrAILCo were, in their view, inherently suspect, the
Commission should initiate an IRP “to mesh the myriad of
transmission, generation and conservation (including [demand
side management]) options into a comprehensive plan that could
be presented as a better alternative than building the
proposed transmission line.” While indicating that it was
“sympathetic to the opponents’ position that planning for
transmission, generation and conservation should be done in an
integrated and holistic process, in order to arrive at the
most rational and cost-effective plan to meet Virginia’s
future load growth and transmission reliability needs,” the
Commission concluded that “the law and facts applicable to
this matter do not enable us to use a transmission line case
30
brought under Va. Code §§ 56-265.2 and 56-46.1 to conduct an
IRP exercise . . . and then use the result of that exercise as
a legal basis to deny the application[s] when a clear
reliability need has been shown and the proposed transmission
line is an acceptable option under Virginia statutes to meet
that need.”
The Commission went on to observe that
[a]s a matter of policy, transmission planning and
control of transmission assets are now conducted on
a regional, multi-state basis by a regional
transmission entity (“RTE”), which in this case is
PJM. This is a direct result of [Code § 56-579]
that requires Virginia’s utilities to join an RTE
. . . . It is also undisputed from the record of
this case that under federal policy PJM itself
cannot order a generating plant to be built to solve
a clear reliability problem on a transmission line
. . . that clearly tilts the field towards PJM
recommending more and more new transmission lines
when other options might be a more efficient use of
capital and much less intrusive on the landscape.
Since PJM is regulated by FERC, whether these
federal rules represent sensible policy is
ultimately for the United States Congress to decide.
The Commission further noted that even if it were to find that
future additions to the transmission and generation
infrastructure could obviate the need for the proposed
transmission line if it ordered VEPCO to accelerate the
timetable for building that infrastructure, it did not have
the authority to independently order the inclusion of that
infrastructure into PJM’s federally-regulated, interstate
operations.
31
Like the Commission, we are not unmindful of the tensions
that have been created as the result of the significant
changes in the manner in which electric utilities are
regulated. The IRP process, enacted by the General Assembly
in 2008, is clearly intended as a response by the legislature
to reassert some modicum of state control over future
development of new transmission and generation infrastructure.
However, we agree with the Commission that the IRP process is
a separate and independent provision of the law, and nothing
within Code § 56-265.2 would permit the Commission to delay
action on or deny approval of an otherwise proper application
for a new transmission line under that statute by asserting
the need for a completed IRP. 7 Similarly, even if Piedmont
were correct that by ordering VEPCO to accelerate the building
of new generation infrastructure the need for the proposed
line could be obviated, the Commission is correct that its
authority does not extend to requiring that PJM introduce this
new generation infrastructure into its interstate transmission
grid on an accelerated schedule.
7
Code § 56-599 required electric utilities subject to
regulation by the Commission to file their initial biennial
IRPs by September 2009. Thus, while the Commission will have
access to current IRPs in considering future applications for
additional transmission and generation infrastructure, we
express no view in this opinion as to the role that IRPs
should or will play in the evaluation of such applications.
32
It is undeniable that the evidence in the record
submitted to the Commission by VEPCO and TrAILCo was
influenced by the nature of the federal regulatory process
that preceded it. And, as the Commission observed, as
presently constituted, it is equally undeniable that this
process is “tilted” toward favoring improvements in
transmission infrastructure over increased generation and
improved conservation. However, the resulting “inherent bias”
of PJM and the transmission divisions of its member utilities
in seeking approval of new transmission lines does not render
their evidence concerning the need for such improvements
necessarily unreliable. Moreover, it would be an
irresponsible approach for the Commission to resolve the issue
of the need for a new transmission line by ordering the
utilities to build additional generation capacity but waiting
until that additional generation was connected to the
interstate transmission grid before ascertaining whether the
identified need had been met, as Piedmont seems to suggest in
these appeals.
The record in this case amply demonstrates that the
Commission understood the federal regulations or policies
which influenced the evidence presented to it by VEPCO and
TrAILCo, but based upon its independent review of that
evidence, found that the data presented by them was reliable
33
and established that the proposed interstate transmission line
was both needed and, in consideration of all other factors, an
acceptable solution to resolve the anticipated need for
reliability in the delivery of electricity to the affected
areas of northern Virginia.
In short, while Piedmont may question the efficacy of the
collaborative governance between the federal and state
governments that has resulted from the restructuring of
electric utility regulation, the Commission was required to
make its decision to approve the applications at issue in
these appeals based on the record before it and under the
current state of the applicable law. We hold that the
Commission’s decision to approve the applications is supported
by the evidence in the record and proper interpretations of
the law.
CONCLUSION
In summary, we hold that the record manifestly
demonstrates that the Commission conducted its review of the
applications for a new transmission line in accord with the
requirements of Code §§ 56-46.1 and 56-265.2, and that the
Commission’s decision to grant the applications is supported
by the evidence. For these reasons, the order of the
Commission approving VEPCO’s and TrAILCo’s applications to
34
construct their respective segments of the 500kv transmission
line, as conditioned, will be affirmed.
Affirmed.
35