Present: All the Justices
NORFOLK REDEVELOPMENT AND
HOUSING AUTHORITY
v. Record No. 051708 OPINION BY JUSTICE ELIZABETH B. LACY
June 8, 2006
C AND C REAL ESTATE, INC.
FROM THE CIRCUIT COURT OF THE CITY OF NORFOLK
John C. Morrison, Jr., Judge
This appeal pertains to the dismissal of a housing
authority's petition to acquire property by condemnation
pursuant to the authority's conservation plan.
Code § 36-49.1 authorizes localities to prepare, adopt,
and execute conservation plans to identify and rehabilitate
"slum, blighted, deteriorated or deteriorating areas" within
the locality. Pursuant to this authority, the Norfolk City
Council adopted a resolution in 1987 commissioning the Norfolk
Redevelopment and Housing Authority (the Authority) to examine
blighted and deteriorating land in the North Church Street
area of Norfolk to determine whether conservation was
possible. The following year, after a public hearing, the
City Council adopted the conservation plan (the Plan)
recommended by the Authority. See Code § 36-49.1(8).
The Plan allowed the Authority to acquire property
included in the conservation area by exercising the power of
eminent domain. The Property Acquisition section of the Plan
sets out the procedure for acquiring properties through
eminent domain and references a "Boundary and Land Acquisition
Map" that identifies properties to be acquired.
The Plan stated that there were "two large junk yards in
the area which add to the blighted condition of the district."
The Boundary and Land Acquisition Map identified those two
parcels as property "To Be Acquired" under the plan. C and C
Real Estate, Inc. (C&C) owns one of the parcels identified in
the Plan. C&C purchased this property (the Property) in 1997
and leased it to Downtown Used Auto Parts for use as an
automobile salvage yard. Downtown Used Auto Parts originally
leased the Property in 1992 from the former owner, who had
also operated a salvage yard on the Property.
In 1990, the Authority sent a notice to correct the
conditions considered as deficiencies to the owner of the
second junkyard identified in the Plan; however, it sent no
such notice to the owner of the Property now owned by C&C.
The Authority did notify C&C of its intent to acquire the
Property by letter dated December 1, 1999. During this time
period, the Mid-Atlantic Coca-Cola Bottling Company (Coca-
Cola) began discussions with the Authority about the
possibility of an expansion of its operations in the Mid-Town
area. Coca-Cola suggested that the City convert the Property
into a parking lot that could be used by Coca-Cola's
2
employees. No action was taken on Coca-Cola's suggestions at
that time.
By letter dated August 16, 2000, the Authority offered to
purchase the Property for $400,000. C&C did not reply to the
offer for over two years. During the interim, the owner of a
neighboring property successfully petitioned the City to close
a part of Armistead Avenue in an area adjacent to the
Property. C&C acquired part of the closed street from the
City during the first half of 2002 and, in November of that
year, rejected the Authority's purchase offer and asked that
the Authority "proceed to file the Petition in Condemnation."
The following year, on July 22, 2003, the Authority sent
another letter offering to buy the Property for $560,000. C&C
again refused the offer. On October 27, 2003, the Authority
passed a resolution authorizing the condemnation of the
Property. The petition for condemnation was filed in the
Circuit Court of the City of Norfolk on November 25, 2003.
Following an ore tenus hearing, the circuit court issued
a letter opinion concluding that the Authority's condemnation
petition should be dismissed because: (1) that part of the
Plan purporting to authorize condemnation of property solely
on a finding of blight or a blighting influence was invalid;
(2) C&C did not receive a one-year notice to correct
deficiencies to which it was entitled under the Plan; and (3)
3
the Authority's 15-year delay in filing the condemnation
proceeding raised due process concerns. The circuit court
also held that Code § 36-49.2 does not prevent the Authority
from using its condemnation power to acquire property
designated as blighted pursuant to a conservation plan even if
the property will be used for industrial purposes after
rehabilitation. Following further briefing and argument of
counsel, the circuit court entered a final order on May 12,
2005, incorporating its letter opinion and dismissing the
Authority's condemnation petition. The Authority timely filed
this appeal.
On appeal, the Authority raises eight assignments of
error. Four of these challenge the findings made by the
circuit court in conjunction with its conclusion that the
Authority's condemnation action violated C&C's due process
rights. Three assignments of error relate to the circuit
court's interpretation and application of the Plan. Finally,
the Authority challenges the admission of certain expert
testimony. Additionally, C&C assigns cross-error to the
circuit court's holding that Code § 36-49.2 did not prohibit
the Authority from using its eminent domain powers for
acquiring property that will be used for industrial purposes.
We will consider these issues in order.
THE AUTHORITY'S APPEAL
4
1. Due Process
The circuit court's conclusion that the Authority's
attempt to take C&C's Property violated due process was based
on the 15-year delay from the time the Authority made its
finding of blight until it attempted to correct the blighted
condition of the Property by filing the condemnation petition.1
This delay, according to the circuit court, "argues strongly
against" a finding that the elimination of blight was the
"real reason" the Authority sought to acquire the Property.
The circuit court further found that this delay gave rise to a
"reasonable expectation" that the Authority would not take the
Property and that the delay allowed C&C to expand its business
while the Authority was insulated from paying for the "value
of the ongoing business" in a condemnation proceeding. The
Authority challenges each ground relied upon by the circuit
court, arguing that the condemnation did not offend principles
of due process because the passage of 15 years did not alter
the reason for the taking, did not violate any limitations
period, and would not result in unfair compensation for the
Property to be taken. For the following reasons we agree with
the Authority.
1
Although the condemnation proceeding was not filed until
2003, C&C was aware of the Authority's interest in acquiring
the Property based on letters exchanged beginning in 1999,
some of which contained offers to purchase the Property.
5
The due process clauses of the Constitutions of the
United States and of the Commonwealth of Virginia prohibit the
government from taking private property unless such property
is taken for public use and the property owner receives just
compensation for the property taken. U.S. Const. amend. V;
Va. Const. art. 1, § 11; Kelo v. City of New London, ___ U.S.
___, ___ n.1, 125 S.Ct. 2655, 2658 n.1 (2005); State Highway &
Transp. Com. v. Linsly, 223 Va. 437, 443, 290 S.E.2d 834, 838
(1982).
Taking private property to stem blighting and
deteriorating conditions is a public purpose. Mumpower v.
Housing Authority, 176 Va. 426, 437, 11 S.E.2d 732, 735
(1940). A locality's determination pursuant to a conservation
plan that property is blighted and subject to acquisition is a
legislative act which, on review, is entitled to a strong
presumption of validity. Runnels v. Staunton Redevelopment &
Housing Authority, 207 Va. 407, 410, 149 S.E.2d 882, 884
(1966). The locality's determination may be set aside by a
circuit court only on a showing that the locality acted
arbitrarily. The burden is on the challenger to establish
that the decision was invalid by clear and convincing proof.
Id. In this case, C&C failed to carry that burden of proof.
As the circuit court noted, in 1988 the Authority
determined that the Property was a blight and exerted a
6
blighting influence on the area.2 The owner of the Property at
the time did not challenge that decision. The question before
us then is whether a challenge to that determination arising
many years later but before property has been acquired is
resolved by examining the condition of the property at the
time of the initial designation or at the time of acquisition.
This is an issue of first impression for this Court. We
conclude that while the original determination retains the
strong presumption of validity attached to such legislative
acts, the current status of the property must be considered
when determining whether the original purpose of the
acquisition remains viable at the time the condemnation
occurs. This standard is dictated by the statutes governing
conservation plans which allow the use of eminent domain only
2
The Authority made the following finding:
There are significant environmental
problems which are contributing to the
deterioration of the project area. Trash,
litter, and debris are found throughout
the area. Vacant lots are covered with
weeds and, in several cases, the partial
foundations of demolished buildings.
There are two large junk yards in the area
which add to the blighted condition of the
district. Derelict, abandoned motor
vehicles were identified throughout the
proposed project area prior to a concerted
effort to rid the area of this problem.
Although a number of vehicles have been
removed, the underlying conditions have
not changed and others will probably take
their place.
7
for the specific public purposes of eliminating deteriorating
properties or arresting the blighting influence. If a
property no longer meets that criteria, acquisition by
condemnation pursuant to a conservation plan would no longer
be authorized. See Code §§ 36-49.1, -50.1. Therefore, in
this case, to rebut the presumption of validity, C&C bore the
burden to show by clear and convincing evidence that the
Property no longer was a blight or no longer exerted a
blighting influence on the surrounding area.
The evidence relied upon by the circuit court to
show a change in acquisition purpose included the
Authority's discussions with Coca-Cola and improvements
to the Property, including adding water and sewer
service, cleaning up trash, painting and otherwise fixing
one building while demolishing another, and erecting a
fence limiting the visibility of the interior. The
evidence of discussions between Coca-Cola and the
Authority regarding use of the Property as a parking lot
does not address the condition of the Property and
therefore is not relevant rebuttal of the presumption
that the finding of blight remains valid. Furthermore,
the purpose of a conservation plan is to identify and
acquire blighted property so that the property may be
rehabilitated. Because properly designated and acquired
8
"blighted" property may eventually be made available to
and used by private enterprise, Code § 36-49.1, such
ultimate use does not alter the original acquisition
purpose of eliminating blight.
Although the evidence showed that improvements were made
to the condition of the Property, there is also evidence that
the Property remains a blight or has a blighting effect on
surrounding property. The Authority introduced pictures of
the Property from 1988 through the time of trial along with
the testimony of Karen Wilds, who qualified as an expert for
the Authority in the field of land planning. Wilds testified
that based on her observation of the current state of the
Property and the pictures of it, the Property remained
infeasible of rehabilitation and its condition was not
consistent with the objectives of the Plan.
This record does not contain clear and convincing
evidence sufficient to rebut the presumption that the
Authority's designation of the Property as blighted or
exerting a blighting influence remained valid. Accordingly,
the Authority did not acquire the Property for a non-public
purpose in violation of the federal and state due process
clauses.
In addition to limiting the government from taking
private property unless the taking is for a public use and the
9
landowner is justly compensated, constitutional procedural due
process mandates that the government provide a landowner
"notice and a reasonable opportunity to be heard" before
affecting that individual's property rights pursuant to a
binding court decree. Doe v. Brown, 203 Va. 508, 512, 125
S.E.2d 159, 163 (1962). However, our case law establishes
that the legislature may prescribe the manner in which that
notice will be provided, so long as its provisions afford the
individual a reasonable opportunity to be heard. Id.;
Williamson v. Hopewell Redevelopment & Housing Authority, 203
Va. 653, 655, 125 S.E.2d 849, 850-51 (1962).
In this case, the circuit court did not find, and C&C
does not assert, that the Authority failed to afford C&C
proper procedural due process under the notice provisions of
the eminent domain statutes. Code §§ 25.1-205 through –222;
see also Williamson, 203 Va. at 656, 125 S.E.2d at 851
(finding eminent domain hearing notice provisions under former
Code § 25-13 constitutional). To the extent the circuit court
and C&C maintain the Authority violated C&C's procedural due
process rights, they rely upon the 15-year delay between the
Authority's adoption of the Plan and filing the condemnation
proceeding. This delay, according to the circuit court, gave
C&C a "reasonable expectation that their property would not be
condemned . . . especially since the City of Norfolk conveyed
10
additional property to [C&C] in 2002 when part of Armistead
Avenue was closed" and allowed C&C to improve its business,
although the Authority would not be liable for "the value of
the ongoing business." We find, however, that these factors
do not implicate any procedural due process considerations in
the context of this case.
First, there is no limitations period defined by statute
for acquiring property under a conservation plan. Contra Code
§ 36-51(c)(five year limitation on acquiring property pursuant
to redevelopment plan commencing on date of plan approval).
Code § 36-51.1(7). Code § 36-51.1 allows an authority to
place such a limitation on conservation project activities,
but the Authority did not do so in this case. The Plan states
that "[i]t is the intent of the Authority to proceed
diligently to achieve completion of project activities" and
that "[t]he Project Area Committee has requested that the
project activities be completed by the end of 1997 and this
has been selected as the target date;" however, the Plan does
not preclude further acquisitions of properties within the
project area beyond 1997.
The absence of a limitations period for conservation
plans is reasonable because conservation projects are by
nature long-term undertakings. Nevertheless, when a delay in
pursuing condemnation proceedings becomes unreasonable, the
11
Authority is subject to Code § 36-27, which allows a court to
instruct the commissioners in such proceedings to allow
damages incurred by the landowner because of the delay.
Finally, neither the circuit court nor C&C have provided
any legal support for the proposition that a viable due
process claim in this case can be based on a "reasonable
expectation" that the Property will not be taken, regardless
of whether such expectation stems from the passage of time or
the acquisition of additional property prior to condemnation.
In the same vein, there is no basis for a constitutional
procedural due process challenge simply because the Authority
"is not required to pay for the value of the ongoing business"
in a condemnation proceeding. The measure of just
compensation for a governmental taking of property is the
"fair market value of the land as it stands today, in view of
all the purposes to which it is reasonably and naturally
adapted." Fonticello Mineral Springs Co. v. City of Richmond,
147 Va. 355, 361, 137 S.E. 458, 460 (1927). Paying for the
value of an ongoing business enterprise is not
constitutionally required. See id.
Accordingly, for these reasons, we conclude that the
circuit court erred in holding that the Authority's
condemnation proceeding violated principles of due process.
2. Interpretation and Application of the Plan
12
The Authority next challenges the circuit court's
determination that Paragraph 1 of the Acquisition section of
the Plan exceeded the authorization contained in Code § 36-
50.1(4), and that under the Plan, C&C was entitled to a notice
allowing it the opportunity to cure the blighted conditions
consistent with Code § 36-50.1(2). The pertinent language in
the Acquisition section of the Plan states:
The Boundary and Land Acquisition Map, Exhibit
One, identifies properties to be acquired
because they appear infeasible of
rehabilitation or their land use is
inconsistent with the purposes and objectives
of the Conservation Plan.
Properties within the Project Area will be
inspected to determine whether or not they
comply with the provisions of the Conservation
Plan Rehabilitation Standards . . . . The
owners of property which does not comply with
the Standards will be notified in writing of
observed deficiencies [and if] the property has
not been made to comply with the Standards
within one year after receiving a written
request for such compliance, then the Authority
may proceed to acquire the property by deed or
condemnation.
The relevant portions of Code § 36-50.1 are subsections
(2) and (4) which provide that in connection with a
conservation plan, an authority cannot exercise powers of
eminent domain except to acquire
(2) properties which are determined by the authority to
be in violation of the standards for design,
construction, maintenance and use of property set out in
the conservation plan . . . and which have not been made
to comply with such standards within one year after a
13
written request to rehabilitate to project standards is
given to the owner by the authority; or
. . .
(4) properties which are infeasible of rehabilitation or
. . . exert a blighting influence on adjacent properties
or prevent proper development of land so as to inhibit or
prevent accomplishment of the purposes of the
conservation plan.
The Authority argues that Paragraph 1 of the Acquisition
section complies with Subsection (4) of Code § 36-50.1 and
allows the Authority to acquire properties under that
paragraph without providing any notice to the landowner. A
comparison of the language in the Plan and in the statute,
however, demonstrates a difference in the conditions under
which property may be acquired. Subsection (4) of Code § 36-
50.1 allows acquisition without such notice if the properties
"are infeasible of rehabilitation . . . so as to inhibit or
prevent accomplishment of the purposes" of the plan.
(Emphasis added.) Paragraph 1 of the Acquisition section,
however, refers to properties that "appear infeasible of
rehabilitation or their land use is inconsistent with the
purposes and objectives of the Conservation Plan." (Emphasis
added.)
The Authority argues that despite this deviation in
language, the phrases used are synonymous; thus, it contends
that this portion of the Plan is not overbroad. The Authority
14
also argues that a reviewing court should not strictly
construe the terms of a conservation plan because as defined
by Code § 36-51.1, the conservation plan is merely "an outline
for the conservation, development or redevelopment of an
area," and need only be "sufficiently complete to indicate"
the conservation activities that will take place within the
project area. We disagree.
The Plan's phrase "appear infeasible" is more
encompassing than the Section's "are infeasible," as the
former would allow a taking of property that can "be taken
as," "look[s]," or "seem[s]" infeasible of rehabilitation,
Webster's Third New International Dictionary 103 (1993), while
the latter mandates that, to be taken, the property must be
infeasible of rehabilitation. Also, the definition of
"inconsistent" is "lacking consistency" or "incompatible,"
while the meaning of "inhibit" is to "prohibit from doing
something." Id. at 1144, 1163. A land use that lacks
consistency with the goals of a plan does not necessarily
prohibit an authority from achieving those goals. Thus, we
reject the Authority's argument that the language in Paragraph
1 of the Plan is synonymous with and no broader than that
language in Code § 36-50.1(4).
We also reject the Authority's argument that the Plan was
only an outline and any discrepancies were immaterial because
15
the statute would ultimately control. Although the statutes
authorize the creation and implementation of a conservation
plan, an authority's ability to undertake actions allowed by
statute arises by virtue of a duly adopted conservation plan.
The plan must be consistent with the grant of authority set
out in the statutes and, if the plan contains authorization
for acts beyond those delegated, such authorization is
invalid. City Council of Alexandria v. Lindsey Trusts, 258
Va. 424, 427, 520 S.E.2d 181, 182-83 (1999) (citing City of
Chesapeake v. Gardner Enterprises, Inc., 253 Va. 243, 246, 482
S.E.2d 812, 814 (1997)). Furthermore, distinguishing
properties to be acquired under Paragraph 1 or Paragraph 2 on
the Boundary and Land Acquisition Map does not cure the
infirmities in Paragraph 1 of the Plan. Thus, we hold that
the circuit court did not err in determining that the language
of Paragraph 1 is broader than that found in Code § 36-50.1(4)
and, therefore, cannot be utilized as a basis for the exercise
of eminent domain as authorized by that Code section.
We also conclude that the circuit court correctly
determined that, as written, the Acquisition section complies
with subsection (2) of Code § 36-50.1, which allows an
authority to identify properties not in compliance with its
standards and acquire them by eminent domain if a landowner
does not, within one year of written notice, remedy the
16
violations identified. The language of Paragraph 2 in the
Plan's Acquisition section is entirely consistent with Code
§ 36-50.1(2). The evidence is undisputed that C&C did not
receive the required notice to correct the deficiencies on the
Property from the Authority. Accordingly, the circuit court
did not err in holding that because the Authority failed to
provide such notice and because condemnation was not available
without notice pursuant to Paragraph 1 of the Plan, the
Authority could not maintain its condemnation petition against
C&C's Property in this case.
3. Expert Testimony
Finally, the Authority assigns error to the admission of
certain testimony of Timothy E. Barrow who qualified as an
expert in land planning. Much of Barrow's testimony involved
his interpretation and the Authority's application of the Plan
as they related to the Authority's determination of blight or
blighting influence and the operation of the Plan regarding
the need to provide a property owner with notice and an
opportunity to cure deficiencies. Because the issues in this
appeal can be and have been resolved without reference to
Barrow's testimony, we need not consider whether Barrow's
testimony was properly admitted.
C&C'S ASSIGNMENT OF CROSS-ERROR
17
We now turn to C&C's assignment of cross-error. C&C
asserts that Code § 36-49.2 bars the Authority from using its
power of eminent domain to acquire and redevelop properties in
the conservation project area for industrial use. The circuit
court held that Code § 36-49.2 "merely expands the means by
which property may be acquired by the housing authority."
Because the circuit court's interpretation of the statute is
correct, we will affirm the circuit court's judgment.
Code § 36-49.2 provides:
In addition to the other powers to acquire real
property by purchase or lease, an authority is
specifically empowered to purchase or lease real
property for immediate or future use, without the
exercise of the power of eminent domain, for
improvement and development for sale, lease, or
sublease as industrial sites, scientific research
laboratory sites, educational institution sites or
sites for housing persons displaced from other lands
of the authority.
The language of this statute does not specifically prohibit
the use of condemnation proceedings for acquisition of land
which will be used as an industrial site. The phrase upon
which C&C relies, "without the exercise of the power of
eminent domain," taken in context is consistent with a grant
of power to acquire property by lease or purchase for certain
uses, while restricting the use of eminent domain to those
circumstances in which a property satisfies one of the
criteria set out in Code § 36-50.1.
18
Adopting C&C's interpretation would create a conflict
with other statutory provisions that authorize an authority to
make land acquired pursuant to a conservation plan available
for use by private entities. See Code §§ 36-49.1, -51.1.
Such property may be acquired by purchase, lease, or eminent
domain, but if by eminent domain, compliance with Code § 36-
50.1 is required. As the circuit court concluded, the power
conferred by Code § 36-49.2 expands the means by which
property may be acquired and the purposes for which such
property may be used by the Authority. It does not prohibit
the use of condemnation by an authority for acquisition of
property that may subsequently be used for industrial sites or
purposes.3 Accordingly, we reject C&C's assignment of cross-
error.
CONCLUSION
In summary, although the circuit court erred in
concluding that the condemnation proceeding violated
principles of due process, the circuit court did not err in
3
On appeal, C&C also challenges this Plan in its entirety
on the ground that its purpose was "an industrial development
plan that takes property for industrial reuse," and it was
never designed to eradicate blight or address any other
condition enumerated in Code § 36-50.1. We reject this
argument for two reasons. First, C&C specifically waived this
challenge to the Plan at trial, Rule 5:25, and second, the
first stated objective of the Plan is "the arrest of
deterioration and the removal of blight, obsolescence and
incompatible land uses."
19
holding (1) that Code § 36-49.2 does not prohibit the use of
eminent domain for the acquisition of property which may be
used for industrial purposes pursuant to a conservation plan,
(2) that because the language of Paragraph 1 of the
Acquisition Section of the Plan was overbroad, it did not
allow acquisition of property as authorized by Code § 36-
50.1(4), and (3) that the Plan required the Authority to
provide C&C notice and an opportunity to correct deficiencies.
Because the Authority did not comply with the Plan by
providing C&C with the required notice, there was no error in
the dismissal of the condemnation proceeding.
Accordingly, for the reasons expressed in this opinion,
we will affirm the judgment of the circuit court.
Affirmed.
20