National Housing Building Corp. v. Acordia of Virginia Insurance Agency, Inc.

PRESENT: Hassell, C.J., Lacy, Keenan, Kinser, Lemons, and Agee,
JJ., and Carrico, S.J.

NATIONAL HOUSING BUILDING CORPORATION
                                            OPINION BY
v.   Record No. 030269                JUSTICE G. STEVEN AGEE
                                         JANUARY 16, 2004
ACORDIA OF VIRGINIA INSURANCE
AGENCY, INC., T/A ACORDIA OF VIRGINIA


       FROM THE CIRCUIT COURT OF THE CITY OF VIRGINIA BEACH
                   H. Thomas Padrick, Jr., Judge

      National Housing Building Corporation ("NHBC") brought suit

against Acordia of Virginia Insurance Agency, Inc. ("Acordia"),

for negligence and breach of an oral contract by failing to

include NHBC as a named insured on a policy of builders risk

insurance.   The trial court granted Acordia's motion to strike

NHBC's evidence for failure to prove "a covered cause of loss,"

even though it found that Acordia was negligent in failing to

list NHBC as a named insured on the policy.

      On appeal, NHBC asserts ten assignments of error, all of

which revolve around the trial court's refusal to allow recovery

for expenses incurred in "mitigating" defects in the

construction covered by the policy.

      For the reasons that follow, we will affirm the judgment of

the trial court.

                                I.

      Madison Ridge, L.P. ("Madison Ridge") hired NHBC as a

general contractor to build the Madison Ridge apartment complex

in Harrisonburg, Virginia, (the "Project").   National Housing
Corporation ("NHC"), as agent for NHBC, negotiated with Acordia

to procure a builders risk insurance policy covering NHBC and

other entities for work on several construction projects,

including the Project.   Acordia obtained a builders risk

insurance policy from Security Insurance of Hartford

("Security") and intended that NHBC be an insured under that

policy ("the Policy").   Acordia admitted, however, that it never

asked Security to list NHBC as a named insured and, in fact,

NHBC was not a named insured under the Policy.

     The Project was built on a steep slope that required the

construction of multiple retaining walls.    The retaining walls

constrained the earth behind them which, in turn, supported

apartment buildings further up the slope from the walls.     NHBC

does not dispute that it defectively designed and built the

retaining walls because its specifications failed to properly

consider the steep incline of the Project.

     In the early months of 1998 NHBC requested that a civil

engineer examine one of the retaining walls (Wall 1-2) that had

moved forward approximately eight feet so that it was no longer

straight.   This condition concerned NHBC and its engineer

because the soils retained by Wall 1-2 supported the other walls

and the foundations of the apartment buildings uphill.   Due to

his concern about the structural collapse of Wall 1-2, the

engineer recommended taking remedial measures to ensure the

stability of the foundations for the uphill apartment buildings.
                                2
NHBC instituted the suggested remedial measures and eventually

replaced Wall 1-2 with one designed to properly accommodate the

topography of the project.   Although the other walls had not

failed and the apartment buildings suffered no physical damage,

NHBC adopted the engineer's suggested remedial measures to

underpin the foundations of those structures so as to prevent

any loss or damage.   No loss or damage occurred to the apartment

buildings.

     NHBC notified Acordia of its claimed loss for the remedial

measures, and on May 5, 1998, NHBC formally requested that

Acordia submit a claim under the Policy to Security.   On several

occasions executives at Acordia notified NHBC of its duty to

mitigate any loss, but did not affirm a coverage determination

had been made.   Security initially denied NHBC's claim based on

an exclusion in the Policy for loss "caused by or resulting from

any of the following: . . . . error, omission or deficiency in

designs, plans or specifications," due to the defective wall

design.   Subsequent to its first denial of NHBC's claim and the

filing of a suit by NHBC to recover insurance proceeds, Security

notified NHBC that it "was not and never had been a named

insured under the policy claimed and sued upon."

     NHBC then filed a motion for judgment claiming breach of

contract and negligence by Acordia for the failure to include

NHBC as a named insured under the Policy.   NHBC claimed damages

from Acordia "for engineering, repairing, and stabilizing the
                                3
affected walls, and underpinning buildings whose structural

integrity and safety had been compromised" (the "remediation

expenses").   NHBC alleged these "losses would have been covered

by the policy if it had been a named insured thereunder."

     At trial, Acordia questioned whether NHBC was the proper

party to bring suit since Madison Ridge paid the remediation

expenses.   Acordia asserted that NHBC was not obligated to cover

the remediation expenses because Madison Ridge incurred the

expenses and failed to "purchase or maintain" all-risk insurance

covering NHBC as required by the contract between NHBC and

Madison Ridge.

     At the conclusion of all the evidence, Acordia renewed a

motion to strike NHBC's evidence.     The trial court found that

NHBC had sustained damages in the amount of $518,690.25 for the

remediation expenses and that Acordia was negligent as a matter

of law in failing to include NHBC as a named insured on the

Policy.

     The trial court then determined that NHBC could not recover

against Acordia because even if NHBC had been a named insured

under the Policy, its "loss" was not covered by the Policy.

Since NHBC could not have recovered under the Policy, then it

could not recover against Acordia.    The trial court then granted

Acordia's motion to strike because NHBC failed "to prove a

covered cause of loss."   We granted NHBC this appeal.

                                II.
                                 4
     [A] court must adhere to the terms of a contract
     of insurance as written, if they are plain and
     clear and not in violation of law or inconsistent
     with public policy. It is not our function to
     "make a new contract for the parties different
     from that plainly intended and thus create a
     liability not assumed by the insurer."

Blue Cross & Blue Shield v. Keller, 248 Va. 618, 626, 450 S.E.2d

136, 140 (1994) (quoting Pilot Life Ins. Co. v. Crosswhite, 206

Va. 558, 561, 145 S.E.2d 143, 145 (1965)).

     NHBC's claim against Acordia rests on the premise that had

Acordia properly fulfilled its duty as an insurance broker and

caused NHBC to be listed on the Policy, then NHBC would have

recovered from the insurer the remediation expenses caused by

the defective wall.   In other words, if NHBC could have

recovered under the Policy, it could recover against Acordia.

     In sustaining Acordia's motion to strike, the trial court

opined from the bench.

     I don't want to substitute my judgment for the
     jury, but the Court is making a legal finding
     that it doesn't fall within the policy, and that
     if the jury did come back and award $518,690.25,
     quite frankly I would have to take it away. . . .
     But the facts are what the facts are. It's true
     that Acordia screwed up. They didn't list [NHBC]
     as a named insured. If they had listed them as a
     named insured then the result would have been the
     same.

     We agree with the trial court.

     The Policy provides coverage "for 'loss' to Covered

Property from any of the Covered Causes of Loss."   The term

"Covered Causes of Loss" is then defined as "Risks of Direct

                                 5
Physical 'Loss' to Covered Property except those causes of

'loss' listed in the exclusions." (Emphasis added).

     The Exclusions provision of the Policy then plainly

provides:

            2.   We will not pay for a "loss" caused by
                 or resulting from any of the following:

                                . . . .

            e.   Defective materials or poor
                 workmanship; error, omission or
                 deficiency in designs, plans or
                 specifications.

                 This exclusion does not apply to
                 resultant "loss" to other Covered
                 Property.


     There is no dispute about, and NHBC does not assign error

to, the trial court's finding that Wall 1-2 was defectively

designed and the activities NHBC undertook in anticipation of

the prospect that Wall 1-2 would fail are the basis of the

remediation expenses.    Despite the Policy's plain language

excluding loss caused by defective design from coverage under

the Policy, NHBC nonetheless claims its remediation expenses are

compensable under the "Duties in the Event of Loss" section of

the Policy, which provides in pertinent part:

                   C.   DUTIES IN THE EVENT OF LOSS

     You must see that the following are done in the
     event of "loss" to Covered Property:

                                . . . .


                                   6
     4.   Take all reasonable steps to protect the
     Covered Property from further damage and keep a
     record of your expenses necessary to protect the
     Covered Property, for consideration in the
     settlement of the claim. This will not increase
     the Limit of Insurance. However, we will not pay
     for the subsequent "loss" resulting from a cause
     of loss that is not a Covered Cause of Loss.

     Essentially, NHBC claims it would have been under a

contractual duty, had it been listed as a named insured, to have

undertaken the mitigation resulting in the remediation expenses

in order to prevent loss to the uphill apartment buildings,

which are "Covered Property" under the Policy.   That duty, if it

existed, does not afford a right to compensation to NHBC under

the facts of this case.

     No damage occurred to the apartment buildings or other

Covered Property.   Therefore, as the trial court noted, there

was no "loss" to Covered Property.   Such loss is a condition

precedent to any compensation under the "Duties in the Event of

Loss" section.   A " 'loss' to Covered Property", the Policy's

predicate to mandatory mitigation, did not occur, and therefore

no obligation to compensate NHBC arose under the Policy.

     Moreover, subparagraph 4 of the "Duties in the Event of

Loss" section further limits any obligation of the insurer

because the contractor's expenses to protect Covered Property

are to be considered "in the settlement of the claim."   The

claim, under the facts of this case and policy, would be



                                 7
"resulting from a cause of loss that is not a Covered Cause of

Loss" and therefore not compensible.

     In effect, NHBC attempts to bootstrap its remediation

expenses into a covered claim through the "Duties in the Event

of Loss" provision, despite the clear exclusion from coverage

for loss caused by NHBC's defective design.      We agree with the

trial court that the Policy's plain language does not permit

NHBC to circumvent the exclusion from coverage in this manner

and recoup its remediation expenses.       See Southern Cal. Edison

Co. v. Harbor Ins. Co., 83 Cal. App. 3d 747, 759-60 (1978) ("The

duty of an insured to prevent and mitigate insurable loss and

the obligation of the insurer to reimburse for expenses so

incurred are separate questions.       The fulfillment of the duty to

mitigate does not necessarily give rise to the obligation of

reimbursement . . . .").

     Even if the Policy does not permit NHBC to recover its

remediation expenses, NHBC claims that its common law duty to

mitigate damages allows recovery of the remediation expenses

from Acordia.   Usually, the failure to mitigate damages is an

affirmative defense and, therefore, on that point the breaching

party, not the injured party, has the burden to produce

evidence.   Marefield Meadows, Inc. v. Lorenz, 245 Va. 255, 266,

427 S.E.2d 363, 369 (1993).   However, this case does not involve

a failure to mitigate damages.


                                   8
     In a case such as this, where the injured party asserts as

part of his recovery the expense of taking corrective measures

to mitigate the potential liability of the defendant, the cost

of mitigation is simply another element of his damages.   It is

axiomatic that where “there is no liability, . . . there can be

no recovery.”    Southern Railway Co. v. Lewis, 113 Va. 117, 120,

73 S.E. 469, 470 (1912).   NHBC's theory of liability is that but

for Acordia's negligence, its damages, including the cost of

mitigation, would have been recoverable under the insurance

contract.   As we have demonstrated, however, those losses were

not a liability covered by the policy and, thus, Acordia's

negligence was not a proximate cause of NHBC's losses.

Regardless of whether NHBC premises its theory of recovery on

contract law or common law, it cannot recover damages where

there is no liability.

                                III.

     For the reasons stated above, we find that even if NHBC had

been a named insured on the Policy, the Policy did not provide

coverage for the remediation expenses it now seeks against

Acordia.    Consequently, NHBC has no cognizable claim against

Acordia either in contract or tort.    The trial court did not err




                                  9
in granting Acordia's motion to strike NHBC's evidence.

Therefore, the judgment of the trial court will be affirmed. *

                                                          Affirmed.




     *
       Having resolved NHBC's assignments of error in favor of
Acordia, we do not address any of Acordia's assignments of
cross-error.
                                10