Amoco Production Co. v. Federal Energy Regulatory Commission

                        United States Court of Appeals


                     FOR THE DISTRICT OF COLUMBIA CIRCUIT


            Argued September 11, 1998   Decided October 23, 1998 


                                 No. 97-1607


                        Amoco Production Company and 

                      Amoco Energy Trading Corporation, 

                                 Petitioners


                                      v.


                    Federal Energy Regulatory Commission, 

                                  Respondent


                      City of Winfield, Kansas, et al., 

                                 Intervenors


On Petition for Review of Orders of the Federal 
Energy Regulatory Commission

     Katherine B. Edwards argued the cause for petitioners.  
With her on the briefs were Nancy J. Skancke, Frederick T. 
Kolb and Mickey J. Lawrence.



     Susan J. Court, Special Counsel, Federal Energy Regula-
tory Commission, argued the cause for respondent.  With her 
on the brief were Jay L. Witkin, Solicitor, John H. Conway, 
Deputy Solicitor, and Edward S. Geldermann, Attorney.

     Richard D. Avil, Jr. argued the cause for intervenor 
NorAm Gas Transmission Company.  With him on the brief 
were Martin V. Kirkwood, Jason F. Leif and Sherrie N. 
Rutherford.

     Before:  Silberman, Ginsburg, and Randolph, Circuit 
Judges.

             Opinion for the Court filed by Circuit Judge Silberman.

     Opinion concurring in part and dissenting in part filed by 
Circuit Judge Randolph.

     Silberman, Circuit Judge:  Petitioners, a group of natural 
gas shippers who are customers of Intervenor NorAm Gas 
Transmission Company's pipeline, seek review of an order 
issued by FERC approving proposed tariffs filed by NorAm.  
Those tariffs increase certain penalties on shippers and allow 
NorAm to retain the revenues resulting from the pipeline's 
assessment of these and other penalties.  We deny the peti-
tion with regard to increased penalty rates, but remand to the 
Commission for a more adequate explanation of its refusal to 
require penalty revenue to flow-through to the pipeline's 
customers.

                                      I.


     As we recently explained, in Pennsylvania Office of Con-
sumer Advocate (Pennsylvania) v. FERC, 131 F.3d 182, 184-
85 (D.C. Cir. 1997), modified on other grounds, 134 F.3d 422 
(D.C. Cir. 1998), the revolutionary Order 636, requiring pipe-
lines to unbundle their transportation and sales services, 
created certain operational problems for pipelines.  Under 
the new regime, shippers may contract with pipelines for 
transportation services;  a shipper typically contracts with a 
pipeline to reserve capacity for a maximum daily volume of 
gas that the shipper may tender to and remove from the 
system, and in turn, the pipeline agrees to ensure that it has 

the capacity to transport the agreed upon quantities.  In 
order to reduce the cost of reserving transportation capacity, 
however, shippers may set their maximum volume levels 
lower than anticipated, hoping that at peak times they can get 
transportation service on an interruptible basis.  In those 
situations, however, interruptible service may not be avail-
able, and shippers then might choose to take more gas from 
the system than the maximum volume allowed under their 
contracts.  Because the operational integrity of the pipeline 
can be threatened by imbalances between the volume of gas 
tendered to the pipeline and the volume taken by shippers, 
pipelines seek to deter shippers from abusing the system by 
issuing Operational Flow Orders (OFOs)--which direct ship-
pers to take specific actions to help keep the system in 
balance--and by imposing penalties.  When a shipper takes 
more gas from the system than the maximum volume allowed 
under the shipper's contract, the pipeline imposes an unau-
thorized overrun penalty.  Penalties are also imposed for 
violations of OFOs.

     In the winter previous to NorAm's filing when the spot 
market price for gas increased substantially, NorAm's ship-
pers on 250 occasions took overruns and thus incurred penal-
ties.  The cost of taking gas out of the pipeline, even with the 
penalties added, was apparently less than the shippers would 
have incurred from alternative sources.  Although NorAm, in 
the previous year, did not impose any penalties for shippers' 
failure to comply with OFOs, NorAm proposed in a section 4 
rate filing under the Natural Gas Act to increase penalties for 
both unauthorized overruns and failures to comply with 
OFOs.  The Commission, over the objection of petitioners, 
approved the filings as "just and reasonable."

                                     II.

     Although petitioners' objected below to the increase in both 
penalties, before us they challenge only the OFO increase and 
argue that it is unjustified.  The existing penalty level, it is 
claimed, was obviously adequate, since no penalties were 
incurred.  Their more fundamental challenge, however, is to 



the destination of any penalty revenue.  Petitioners argue 
that under cost of service pricing a pipeline is not entitled to 
pocket that money;  it must be passed on to its customers.

     We have little difficulty in rejecting petitioners' claim that 
the Commission acted unreasonably in permitting NorAm's 
increase in OFO penalties.  The Commission explained that 
NorAm's increase in OFO penalties merely brought NorAm 
into line with OFO penalties on nearby pipelines, such har-
monization being reasonable to ensure adequate deterrence of 
abuses on NorAm's line.  Moreover, there is an apparent 
functional relationship between OFO penalties and the unau-
thorized overrun penalty, since both penalties aim at deter-
ring shipper abuse.

     Much more troublesome, however, is petitioners' fundamen-
tal claim that the pipeline will enjoy a "windfall" if it is 
permitted to keep penalty revenue.  In Pennsylvania, we 
rejected a similar analytic challenge (in a section 5 proceed-
ing).1  But in that case, the penalty rate had been in existence 
for the previous year yet no penalties had been imposed.  We 
thus thought that the Commissioner was warranted in con-
cluding that "the mere possibility of revenue gains" did not 
"justif[y] a prospective requirement that the [penalty] reve-
nues be credited to customers."  Pennsylvania, 131 F.3d at 
187 (emphasis added).  The Commission, moreover, assured 
us that it was monitoring any revenues generated by the 
penalties and that it could revisit the issue in future rate 
filings if "significant" revenues were generated.2  Important-
ly, we did say that "[t]here appears to be no doubt that if [the 
pipeline] were to collect substantial penalties, those revenues 
would not be justified by the pipeline's cost of service."  Id.  
at 187.

__________
     1 Although this case involves a section 4 proceeding, the analysis 
regarding revenue retention is the same.  The difference is that the 
remedy in section 5 actions is prospective only.

     2 The Commission made the same pledge here;  however, as 
petitioners point out, NorAm is not obligated to make a section 4 
filing in the future, and as we explained, relief under section 5 is 
prospective only.


     In this case, NorAm, by contrast, has collected, in the year 
prior to the section 4 filing, 1.8 million dollars in overrun 
penalty revenues.  (Indeed, the Commission decision in this 
case was noted in Pennsylvania because NorAm's penalties--
at least to us--appeared significant.  See id. at 186.)  The 
Commission, nevertheless, predicted that future penalty reve-
nue would not be significant because the increase in penalty 
rates would deter shippers from taking unauthorized gas or 
violating OFOs.  The difficulty with FERC's logic is that it 
does not follow that NorAm's revenue will decrease merely 
because the penalties are raised.  Even if a lesser number of 
penalties are imposed, the increased penalty rate might result 
in a gross increase in penalty revenue.  Moreover--and this 
is the key imponderable--whether a shipper will be willing to 
incur the penalty depends on his cost in securing alternative 
supplies in a tight market.  Although we were willing to defer 
to FERC's predictive judgment in Pennsylvania because past 
experiences supported that judgment, its prediction here is so 
speculative that we cannot treat it, without more, as a suffi-
cient explanation.  In any event, the Commission never even 
explains how much revenue should be regarded as significant.

     The Commission forthrightly asserts that as a matter of 
policy it does not want to require pipelines to flow through 
penalty rates to their customers.  But FERC neither ade-
quately explains nor seeks to justify that policy in terms of 
the statute.  The Commission does not suggest that to pass 
the penalties through to all customers would undermine any 
deterrent effect.  (It could easily provide that the customers 
paying the penalty would be denied participation if that were 
thought to be a problem.)  Nor does the Commission claim 
(as does the intervenor) that to do so would be administra-
tively burdensome.  The Commission is content to assert, 
somewhat mechanically, that it does not expect the revenues 
to be "significant," so presumably we should think the prob-
lem is de minimis.

     Under these circumstances, we are obliged to remand to 
the Commission for a more adequate explanation for its 
order.




     Randolph, Circuit Judge, concurring in part and dissent-
ing in part:  In Pennsylvania Office of Consumer Advocate v. 
FERC, we faced the same question we face here regarding a 
pipeline's proposal to assess penalties on those customers 
whose actions threatened the pipeline's operational integri-
ty--namely, whether "as a policy matter, the mere possibility 
of revenue gains [from a natural gas pipeline's collection of 
penalties] justifies a prospective requirement that the reve-
nues be credited to customers."  131 F.3d 182, 187 (D.C. Cir. 
1997).  We there sustained the Commission's refusal to im-
pose such a requirement, in part because "the record failed to 
demonstrate that such revenue gains would occur."  The 
same is true here, as are the other reasons we gave for 
upholding the Commission.  Yes, NorAm collected $1.8 mil-
lion in overrun penalties (but nothing in penalties for viola-
tions of Operational Flow Orders) the year before its filing.  
If NorAm had proposed continuing the same level of penalties 
for the future, I would be with my colleagues.  But NorAm 
proposed, and the Commission approved, an increase in pen-
alties in order to prevent shippers from taking more gas from 
the system than they were entitled to take.  Given the 
increase in penalties, there is no evidence in the record that 
"revenue gains would occur" in the future;  past experience 
shows nothing of the sort.  In the Commission's expert 
judgment, based partly on the experience of other pipelines 
having the same level of penalties, little or no penalty revenue 
will be generated under the new penalty regime.  As in 
Pennsylvania Office of Consumer Advocate, the Commis-
sion's prediction may turn out to be right, or it may turn out 
to be wrong, but this "is an accepted feature of the rate-
setting regime."  Id. at 187.  The sort of certainty about the 
future my colleagues want from the Commission is unattaina-
ble, depending as it does on many unknowables, not the least 
of which is how cold the winters will be.

     Although I therefore dissent from the majority's opinion 
insofar as it orders the Commission to explain more fully its 
decision not to require penalty revenue crediting, I concur in 
the portion of the opinion upholding the increase in penalties.