United States Court of Appeals
For the First Circuit
Nos. 07-1482, 07-1483
COMMONWEALTH OF MASSACHUSETTS,
Petitioner,
v.
UNITED STATES; UNITED STATES NUCLEAR REGULATORY COMMISSION,
Respondents,
ENTERGY NUCLEAR OPERATIONS, INC.; ENTERGY NUCLEAR
VERMONT YANKEE LLC; ENTERGY NUCLEAR GENERATION COMPANY,
Intervenors.
ON PETITIONS FOR REVIEW OF ORDERS OF THE
U.S. NUCLEAR REGULATORY COMMISSION
Before
Torruella, Circuit Judge,
Stahl, Senior Circuit Judge,
and Lynch, Circuit Judge.
Matthew Brock, Assistant Attorney General, with whom Martha
Coakley, Attorney General, Diane Curran, and Harmon, Curran,
Spielberg & Eisenberg, L.L.P. were on brief for petitioner.
Steven C. Hamrick, Attorney, with whom Karen D. Cyr, General
Counsel, John F. Cordes, Jr., Solicitor, E. Leo Slaggie, Deputy
Solicitor, U.S. Nuclear Regulatory Commission, Ronald J. Tenpas,
Acting Assistant Attorney General, and Lane M. McFadden, Attorney,
U.S. Department of Justice, were on brief for respondents.
David R. Lewis with whom Paul A. Gaukler and Pillsbury
Winthrop Shaw Pittman LLP were on brief for intervenors.
April 8, 2008
LYNCH, Circuit Judge. The Commonwealth of Massachusetts
wishes to ensure that the United States Nuclear Regulatory
Commission ("NRC" or the "Commission") will take account of the
Commonwealth's safety concerns about treatment of spent fuel rods
before the NRC decides whether to renew the operating licenses of
two nuclear energy plants: the Pilgrim plant in Plymouth,
Massachusetts, and the Vermont Yankee plant in Vernon, Vermont,
which is within ten miles of the Massachusetts border. The
licenses were originally issued in 1972 and will expire in 2012;
the re-licensing proceedings have been initiated and are ongoing.
The Commonwealth says that old assumptions about safe
storage of spent fuel rods -- on which the NRC has relied since at
least the early 1970s -- no longer hold. The Commonwealth claims
that more recent studies and changed circumstances indicate an
increased risk that the plants' method of storing spent fuel rods
will lead to an environmental catastrophe. It also raises its
concern that the plants' method of storing spent fuel leaves the
plants vulnerable to terrorist attack.
Both sides agree that the safety issues raised are
deserving of careful consideration. Both sides also agree that the
Commonwealth is by law permitted to raise its various concerns by
some path and to obtain judicial review of any NRC decision that
adversely affects its interests in this matter. The question
presented here is whether the Commonwealth has, from the regulatory
-2-
maze, chosen the correct path for doing so. The Commonwealth
insists it has chosen the appropriate path, indeed, the only one
available to it. In short, the Commonwealth argues that it must be
allowed to participate directly in the re-licensing proceedings as
a party in order to get its safety-based contentions heard. In the
alternative, the Commonwealth argues that the NRC must ensure that
it resolves a separate rulemaking petition, initiated by the
Commonwealth and based on the same concerns about spent fuel
storage, before the Commission issues any renewal licenses so that
the results of the rulemaking will apply to the Pilgrim and Vermont
Yankee re-licensing proceedings.
The NRC says the Commonwealth has chosen the wrong path,
indeed, one precluded by its regulations. The agency also says
that another option is available, is the proper path to be
followed, and will adequately protect the state's interests.
According to the NRC, the Commonwealth must abandon its attempt to
attain formal "party" status in the licensing proceedings and
instead seek to participate in those proceedings as an "interested
governmental entity." The Commonwealth may, in that capacity,
petition the agency to delay issuance of the renewal licenses until
the Commonwealth's request for a rulemaking is resolved. Indeed,
the NRC has committed itself in this case to an interpretation of
its regulations in such a way as to provide this alternative path,
-3-
complete with opportunities for eventual judicial review, to the
Commonwealth.
We hold as a matter of law that the Commonwealth has
chosen the wrong path in seeking to raise the safety issues as a
party in the licensing proceedings and deny its petition. We also
bind the NRC to its litigation position, described in more detail
below. This leaves the Commonwealth free to follow the NRC's
preferred path if it so chooses. To the extent the Commonwealth
seeks an order from this court interfering with the NRC's ongoing
re-licensing proceedings by imposing decision-making timetables on
the agency, we issue a very brief stay but otherwise decline to
issue such relief.
I.
Regulatory Background
A description of the regulatory scheme governing the
process for renewing licenses to operate nuclear power plants is
helpful to understand this case. The Atomic Energy Act ("AEA")
contains the statutory basis for issuing and renewing such
licenses. See 42 U.S.C. §§ 2133, 2134(b). The AEA empowers the
NRC to make licensing decisions. Id. §§ 2133, 2134(b). The AEA
provides for initial operating licenses valid for up to forty years
and specifies that licenses "may be renewed." Id. § 2133(c).1 The
1
Sections 2133 and 2134(b) originally provided separate
bases for issuing atomic energy licenses. Unlike § 2133, § 2134(b)
does not explicitly impose a forty-year limit or provide for
-4-
AEA says nothing more about requirements for re-licensing, instead
delegating to the NRC authority to determine applicable rules and
regulations. Id. §§ 2133, 2134(b).
The NRC has codified two distinct sets of regulations
containing requirements for license renewal applications. The
first set of regulations focuses on technical issues such as
equipment aging. See, e.g., 10 C.F.R. § 54.4 (defining scope of
renewal requirements in 10 C.F.R. Part 54). Those provisions are
not at issue here.
The NRC promulgated the other set of regulations,
codified at 10 C.F.R. Part 51, primarily to fulfill the agency's
obligations under the National Environmental Policy Act ("NEPA").
See 10 C.F.R. § 51.10 (explaining purpose of Part 51 regulations).
NEPA requires federal agencies to document the environmental
impacts and possible alternatives to proposed "major Federal
actions significantly affecting the quality of the human
environment." 42 U.S.C. § 4332(C). In doing so, NEPA fulfills
dual purposes. First, it "places upon an agency the obligation to
consider every significant aspect of the environmental impact of a
license renewal. However, the agency has treated licenses issued
under either provision as subject to the same terms limiting the
initial license to no more than forty years and providing for
renewal following expiration of the initial license. See Nuclear
Power Plant License Renewal, 55 Fed. Reg. 29,043, 29,050 (proposed
July 17, 1990); see also 10 C.F.R. § 50.51. Agency regulations now
explicitly subject licenses for plants issued under both provisions
to the same requirements for renewal. See 10 C.F.R. § 54.1.
-5-
proposed action." Balt. Gas & Elec. Co. v. Nat'l Res. Def.
Council, Inc., 462 U.S. 87, 97 (1983) (quoting Vt. Yankee Nuclear
Power Corp. v. Nat'l Res. Def. Council, Inc., 435 U.S. 519, 553
(1978)) (internal quotation marks omitted). "Second, it ensures
that the agency will inform the public that it has indeed
considered environmental concerns in its decisionmaking process."
Id. (citing Weinberger v. Catholic Action of Haw. Peace Educ.
Project, 454 U.S. 139, 143 (1981)).
Issuance or renewal of a license to operate a nuclear
power plant is a "major Federal action" triggering NEPA's
requirement that the agency produce an Environmental Impact
Statement ("EIS") for such proceedings. 10 C.F.R. § 51.20.
Producing an EIS containing adequate discussion of all
the environmental issues relevant to licensing the operation of a
nuclear power plant poses a significant task for the NRC. In an
effort to streamline the license renewal process, the NRC in 1996
conducted a study to determine which NEPA-related issues could be
addressed generically (that is, applying to all plants) and which
need to be determined on a plant-by-plant basis. The agency
characterizes the first group of issues as Category 1, and the
second as Category 2, issues. See generally Office of Nuclear
Regulatory Research, U.S. Nuclear Regulatory Comm'n, NUREG-1437, 1
Generic Environmental Impact Statement for License Renewal of
Nuclear Plants (1996).
-6-
Category 1 issues are common to all nuclear power plants,
or to a sub-class of plants. As such, the NRC does not analyze
generic Category 1 issues afresh with each individual plant
operating license application. Instead, the agency conducted an
extensive survey and generated findings, contained within a Generic
Environmental Impact Statement ("GEIS"), that answer Category 1
issues as to all nuclear power plants. See id. at 1-3 to 1-6. The
GEIS findings have since been codified through a rulemaking. See
Environmental Review for Renewal of Nuclear Power Plant Operating
Licenses, 61 Fed. Reg. 28,467 (June 5, 1996) [hereinafter Final
Rule]; see also 10 C.F.R. pt. 51, subpt. A, app. B (listing "NEPA
issues for license renewal of nuclear power plants" and assigning
them to either Category 1 or 2). Category 2 issues, by contrast,
are those non-generic issues that require site-specific analysis
for each individual licensing proceeding. 10 C.F.R. pt. 51, subpt.
A, app. B, n.2.
These categories affect how the NRC handles the NEPA-
mandated EIS requirements. The process of creating the EIS for an
operating licensing (or re-licensing) proceeding begins with the
applicant, although producing the EIS is ultimately the NRC's
responsibility. Under the regulations, each applicant must submit
to the agency an environmental report that includes plant-specific
analysis of all Category 2 issues. Id. § 51.53(c)(3)(ii). The
regulations generally relieve applicants of having to discuss
-7-
Category 1 issues, instead allowing applicants to rest on the GEIS
findings. Id. § 51.53(c)(3)(i).
The regulation does require an applicant's report to
include "any new and significant information regarding the
environmental impacts of license renewal of which the applicant is
aware." Id. § 51.53(c)(3)(iv). The NRC concedes that this applies
even to "new and significant information" concerning Category 1
issues.
NRC staff then draw upon the applicant's environmental
report to produce a draft supplemental EIS ("SEIS") for the license
renewal. See id. § 51.95(c). This plant-specific SEIS addresses
Category 2 issues and complements the GEIS, which covers Category
1 issues. Id. § 51.71(d). When the GEIS and SEIS are combined,
they cover all issues that NEPA requires be addressed in an EIS for
a nuclear power plant license renewal proceeding.
Once the agency has prepared a draft SEIS, it must be
made available for comment both to the public and to other federal,
state, and local agencies. Id. §§ 51.73, 51.74. After receiving
comments, the NRC must then prepare a final SEIS. Id.
§ 51.95(c)(3) (referencing id. § 51.91).
Because Category 1 issues have already been addressed
globally by 10 C.F.R. pt. 51, subpt. A, app. B, they cannot be
litigated in individual adjudications, such as license renewal
proceedings for individual plants. See id. § 2.335; Fla. Power &
-8-
Light Co. (Turkey Point Nuclear Generating Plant), 54 N.R.C. 3, 12,
20-23 (2001). Instead, the agency has established other means for
challenging GEIS findings regarding Category 1 issues when
necessary, whether by the agency's own initiative or by petition
from an outside entity. This divergent treatment of generic and
site-specific issues is reasonable and consistent with the purpose
of promoting efficiency in handling license renewal decisions.
There are several methods of review of Category 1 issues.
First, the agency must review the GEIS findings every ten years.
See Final Rule, supra, 61 Fed. Reg. at 28,468. Second, the NRC
staff may make a request to the Commission that a rule be suspended
on a generic basis or that a particular adjudication be delayed
until the GEIS and accompanying rule are amended. Id. at 28,470.
This would be an appropriate course of action should public
comments on a draft SEIS (or information submitted by a license
renewal applicant) alert the agency to "new and significant
information" calling into question the validity of a GEIS finding.
Id.
Third, the NRC staff may request that a rule be suspended
with respect to a particular plant if comments to a draft SEIS
reveal site-specific information indicating that the rule would be
inapplicable to that particular plant. Id.
Fourth, "[a] party to an adjudicatory proceeding" may
petition for a waiver of an NRC rule or regulation with respect to
-9-
that proceeding. 10 C.F.R. § 2.335(b). "The sole ground for
petition of waiver or exception is that special circumstances with
respect to the subject matter of the particular proceeding are such
that the application of the rule or regulation . . . would not
serve the purposes for which [it] was adopted." Id.
Finally, any member of the public may petition the agency
for a rulemaking proceeding aimed at altering the GEIS and its
accompanying rule. Final Rule, supra, 61 Fed. Reg. at 28,470.
II.
Administrative Proceedings
Entergy,2 intervenor to these petitions, obtained
operating licenses for the Pilgrim and Vermont Yankee plants in
1972. Those licenses will expire in 2012, but they may be renewed
for an additional twenty-year period, which would last until 2032.
On January 25, 2006, Entergy submitted applications to begin the
license renewal process.3
Both the Pilgrim and the Vermont Yankee applications
included an environmental report specific to the respective plant.
Entergy's environmental reports did not contain in-depth discussion
2
We use "Entergy" to refer to three entities: Entergy
Nuclear Generation Company holds the Pilgrim plant possession and
use license; Entergy Nuclear Vermont Yankee LLC holds the Vermont
Yankee plant possession and use license; and Entergy Nuclear
Operations, Inc. holds the operating licenses for both facilities.
3
The Commission is currently scheduled to issue a decision
on the Plymouth application by July 27, 2008 and the Vermont Yankee
application by November 2008.
-10-
of any Category 1 issues and represented that "Entergy has not
identified any new and significant information concerning the
impacts addressed by these [GEIS] findings."
On May 26, 2006, the Commonwealth of Massachusetts
submitted parallel hearing requests in each of the two plant re-
licensing proceedings. Each request included only one contention
that the Commonwealth proposed to introduce into the proceedings:
that Entergy's environmental reports for each plant did not satisfy
NEPA "because [they do] not address the environmental impacts of
severe spent fuel pool accidents."
The storage of spent fuel on site at nuclear power plants
is a Category 1 issue for operating license renewal purposes.4 10
C.F.R. pt. 51, subpt. A, app. B. That subject is normally exempt
from discussion in a license renewal applicant's environmental
report, id. § 51.53(c)(3)(i), but may be raised elsewhere. The
Commonwealth contends that it may raise the issue in the re-
licensing proceeding and that Entergy's report violated NEPA and 10
C.F.R. § 51.53(c)(3)(iv) because it failed to address "new and
4
The regulation adopts the GEIS findings that "[t]he
expected increase in the volume of spent fuel from an additional 20
years of operation can be safely accommodated on site with small
environmental effects through dry or pool storage at all plants if
a permanent repository or monitored retrievable storage is not
available." 10 C.F.R. pt. 51, subpt. A, app. B. As such, the
license renewal regulations classify the environmental impacts of
on-site spent fuel storage as "small," i.e., "not detectable or .
. . so minor that they will neither destabilize nor noticeably
alter any important attribute of the resource." Id. at n.3.
-11-
significant information" regarding the risks of on-site spent fuel
storage.
Spent fuel rods are a radioactive waste product of
nuclear power plants. When the Pilgrim and Vermont Yankee plants
were originally licensed in 1972, it was common practice to arrange
spent fuel rods in low-density racks in water-filled storage pools
located at the plant that produced the waste. At the time, there
was a national policy of eventually disposing of spent fuel through
reprocessing. Long-term storage in a central geologic repository
posed another option for removing spent fuel from reactor sites.
However, the reprocessing strategy was abandoned in the mid-1970s,
and although the federal government has been planning to accept
spent fuel at a proposed repository at Yucca Mountain, Nevada, that
option will not be available until at least 2015, if at all. As a
result, spent fuel has accumulated at on-site storage facilities,
and power plant operators have replaced low-density racks with
high-density racks in storage pools in order to accommodate the
mounting volume of spent fuel rods. According to the Commonwealth,
use of high-density racks restricts the flow of cooling fluid
around spent fuel rods and raises the risk of fire under a number
of scenarios.
The Commonwealth contended in the re-licensing
proceedings that new and significant information about on-site
spent fuel storage at the Pilgrim and Vermont Yankee plants was
-12-
demonstrated by the switch to high-density storage racks, recent
scientific studies regarding the dangers of high-density storage
pool fires, and the increased likelihood of terrorist attack
following September 11, 2001. According to the Commonwealth,
[s]ignificant new information now firmly
establishes that (a) if the water level in a
fuel storage pool drops to the point where the
tops of the fuel assemblies are uncovered, the
fuel will burn, (b) the fuel will burn
regardless of its age, (c) the fire will
propagate to other assemblies in the pool, and
([d]) the fire may be catastrophic.
A spent fuel pool fire would be catastrophic in large part because
"[a] large, atmospheric release of radioactive material would
occur."
The Commonwealth appended four reports to its hearing
requests in support of its pool fire contention. The first two
resulted from studies commissioned by the Commonwealth to assess
the risks of and alternatives to on-site, high-density pool storage
at the Pilgrim and Vermont Yankee plants. The first of these was
written by Dr. Gordon R. Thompson of the Institute for Resource and
Security Studies in Cambridge, Massachusetts. The Thompson report
surveyed analyses by NRC staff and others and found that they
recognized that "a loss of water from . . . high-density, closed-
form storage racks would, over a range of scenarios, lead to self-
ignition" of a fire "that could propagate across the pool." The
report assessed the probability of a high-density storage pool fire
occurring at either Pilgrim or Vermont Yankee as at least one per
-13-
10,000 years. Dr. Thompson recommended replacing the high-density
storage racks at both facilities with low-density, open-frame
racks. This course would, according to Dr. Thompson, "return the
plant[s] to [their] original design configuration" and "achieve the
largest risk reduction[] during plant operation within a license
extension period." Dr. Thompson also surmised that re-equipping
the plants with the recommended racks would cost less than $110
million for each plant.
The second study commissioned by the Commonwealth was
authored by Dr. Jan Beyea, a nuclear physicist affiliated with
Consulting in the Public Interest, and focused on the consequences
of a hypothetical pool fire at the Pilgrim or Vermont Yankee
plants. Under a scenario in which ten percent of the radioactive
material in storage at the plants was released into the atmosphere
due to a pool fire, Dr. Beyea estimated economic costs of $105-171
billion for Pilgrim, and $87-165 billion for Vermont Yankee. If
one hundred percent of the radioactive material were released in
such a fire, the costs would rise to $342-488 billion at Pilgrim
and $364-518 billion at Vermont Yankee. Dr. Beyea estimated that
a one hundred percent release of radioactive material at either
plant could result in up to 8,000 cases of latent cancer. Dr.
Beyea's report further concluded that the results of recent
epidemiologic studies could significantly inflate his estimates of
the economic and health costs of a pool fire.
-14-
The third report submitted by the Commonwealth with its
hearing requests was authored by NRC staff to assess the risk of
spent fuel pool accidents at decommissioned nuclear power plants.
Published publicly in early 2001, the report acknowledged the
possibility that even a partial loss of cooling fluid in a storage
pool could result in a fire. The report also observed that because
"fuel assembly geometry and rack configuration are plant specific,"
the possibility of pool fires "cannot be precluded on a generic
basis." However, the report also concluded that "even though the
consequences from a zirconium fire could be serious," the risk of
such fires at decommissioning plants "is low and well within the
Commission's safety goals."
Finally, the Commonwealth submitted a report produced, at
the request of Congress, by the National Academy of Sciences to
examine the potential consequences of a terrorist attack on spent
fuel storage facilities sited at nuclear power plants. The report
concluded that while all plants should have on-site pools for
storage of spent fuel, there is some risk that a terrorist attack
could partially or fully drain such a pool, leading to a fire and
the release of radioactive material. The report also concluded
that "[t]he potential vulnerabilities of spent fuel pools to
terrorist attacks are plant-design specific. Therefore, specific
vulnerabilities can be understood only by examining the
characteristics of spent fuel storage at each plant."
-15-
The NRC convened two Atomic Safety and Licensing Boards
("ASLB" or "Board") to assess whether the various contentions
submitted by the Commonwealth and other entities were admissible in
the Pilgrim and Vermont Yankee license renewal proceedings. On
June 22, 2006, Entergy and the NRC staff filed oppositions to the
Commonwealth's hearing requests, arguing the Commonwealth had
chosen the wrong path to raise its contentions. They asserted the
Commonwealth had impermissibly challenged a generic Category 1
issue without requesting a waiver of the agency's rule within the
Pilgrim and Vermont Yankee proceedings. They also argued that the
information submitted by the Commonwealth did not constitute "new
and significant" information within the meaning of 10 C.F.R.
§ 51.53(c)(3)(iv). During oral arguments at pre-hearing
conferences in front of the ASLBs, the Commonwealth staked out its
position that the waiver provision was unavailable in any event; it
could not seek waiver in the individual proceedings because its
contention regarding pool fires was not specific to either of the
two plants, but was a safety issue common to all plants.
The Commonwealth also informed the ASLBs of its intention
to file a rulemaking petition aimed at modifying the GEIS findings
about on-site spent fuel storage. The parties agree that this
rulemaking path is and always has been open to the Commonwealth.
On August 25, 2006, following oral arguments in front of
the Pilgrim and Vermont Yankee ASLBs, the Commonwealth filed a
-16-
petition for rulemaking with the NRC based on the same pool fire
contention raised in its hearing requests in the individual
licensing proceedings.5 The petition requested that the NRC
(a) consider new and significant information
showing that the NRC's characterization of the
environmental impacts of spent fuel storage as
insignificant in the 1996 [GEIS] is incorrect,
(b) revoke the regulations which codify that
incorrect conclusion and excuse consideration
of spent fuel storage impacts in NEPA
decision-making documents, (c) issue a generic
determination that the environmental impacts
of high-density pool storage of spent fuel are
significant, and (d) order that any NRC
licensing decision that approves high-density
pool storage of spent fuel at a nuclear power
plant . . . must be accompanied by an [EIS]
that addresses (i) the environmental impacts
of high-density pool storage of spent fuel at
that nuclear plant and (ii) a reasonable array
of alternatives for avoiding or mitigating
those impacts.
The petition also urged the NRC to "withhold any decision to renew
the operating licenses for the Pilgrim and Vermont Yankee nuclear
power plants until the requested rulemaking has been completed" and
suspend consideration of the Commonwealth's contentions in the
individual proceedings. In support of its petition, the
Commonwealth appended the same four reports described above. To
date, there has been no decision on the rulemaking petition, and
5
The State of California has submitted a petition for
rulemaking raising similar concerns; the NRC is currently
considering both petitions. See State of California; Receipt of
Petition for Rulemaking, 72 Fed. Reg. 27,068 (proposed May 14,
2007); Mass. Attorney Gen.; Receipt of Petition for Rulemaking, 71
Fed. Reg. 64,169 (proposed Nov. 1, 2006).
-17-
the issue before us does not involve that petition, but rather the
Commonwealth's hearing requests in the individual plant re-
licensing proceedings.
The Vermont Yankee ASLB issued its decision on the
hearing requests in that proceeding on September 22, 2006. Entergy
Nuclear Vt. Yankee, LLC (Vt. Yankee Nuclear Power Station) (Vt.
Yankee I), 64 N.R.C. 131 (2006). As an initial matter, the ASLB
granted standing to the Commonwealth. Id. at 145. The Board went
on to reject the Commonwealth's contention, ruling that even if the
Commonwealth's contention presented "new and significant
information" about pool fires, "as a matter of law the contention
is not admissible because the Commission has already decided, in
Turkey Point, that licensing boards cannot admit an environmental
contention regarding a Category 1 issue." Id. at 155. The Board
stated the agency's position that under 10 C.F.R. § 51.53(c)(3), a
licensing applicant such as Entergy must provide analysis of new
and significant information regarding a NEPA issue, whether
Category 1 or 2, in its environmental report. Id. Further, the
Board observed that "if the information that the [Commonwealth]
presents is indeed new and significant, the Staff's SEIS needs to
address it." Id. at 156.
The Board's ruling did not purport to foreclose any
challenge by the Commonwealth to the agency's rule on on-site spent
fuel storage. Again citing Turkey Point, the Board pointed out
-18-
that the Commonwealth "has several options, including filing a
petition for rulemaking, providing the information to the NRC Staff
(which can then seek Commission approval to suspend the application
of the rules or delay the license renewal proceeding), or
petitioning the Commission to waive the application of the rule."
Id. at 159. The Board concluded its discussion of the
Commonwealth's contention by noting the Commonwealth's pending
rulemaking petition. "Thus we see," the Board stated, "that the
[Commonwealth] has already begun to pursue the alternative remedies
specified in Turkey Point." Id. at 161.
On October 16, 2006, the Pilgrim ASLB issued a ruling
rejecting the Commonwealth's pool fire contention on substantially
the same grounds as had the Vermont Yankee ASLB. Entergy Nuclear
Generation Co. (Pilgrim Nuclear Power Station), 64 N.R.C. 257, 294-
300 (2006).
The Commonwealth appealed the ASLB decisions to the NRC.
The Commission affirmed the Pilgrim and Vermont Yankee ASLB
decisions on January 22, 2007. Entergy Nuclear Vt. Yankee, LLC
(Vt. Yankee Nuclear Power Station) (Vt. Yankee II), 65 N.R.C. 13
(2007). The NRC agreed with the ASLBs that the Commonwealth "chose
the appropriate way to challenge the GEIS when [it] filed [its]
rulemaking petition." Id. at 20. The Commission explained that
"[i]t makes more sense for the NRC to study whether, as a technical
matter, the agency should modify its requirements relating to spent
-19-
fuel storage for all plants across the board than to litigate in
particular adjudications whether generic findings in the GEIS are
impeached by . . . claims of new information." Id. at 20-21.
Otherwise, plant-by-plant litigation of Category 1 issues "would
defeat the purpose of resolving generic issues in a GEIS." Id. at
21.
The Commission's decision also described how the pending
rulemaking could affect the Pilgrim and Vermont Yankee licensing
proceedings. The Commission rejected the Commonwealth's request
that it suspend the licensing proceedings. It would be "premature"
to delay a final decision on licensing, the Commission reasoned,
where "final decisions in those proceedings are not expected for
another year or more" and "involve many issues unrelated to the
[Commonwealth's] rulemaking petition." Id. at 22 n.37. However,
"depending on the timing and outcome" of the rulemaking, the
Commission recognized the possibility that NRC staff could request
that the Commission suspend the generic rule and include plant-
specific analysis of pool storage in the Pilgrim and Vermont Yankee
SEISs. Id. at 22. We are told that to date, that has not
happened.
The Commission also outlined a route by which the
Commonwealth itself could influence the timing of the licensing
decisions:
NRC regulations provide that a petitioner who
has filed a petition for rulemaking "may
-20-
request the Commission to suspend all or any
part of any licensing proceeding to which the
petitioner is a party pending disposition of
the petition for rulemaking." 10 C.F.R.
§ 2.802(d). An interested governmental entity
participating under 10 C.F.R. § 2.315 could
also make this request.
Id. at 22 n.37. Because alternatives were available, "admitting
the [Commonwealth's] contention for an adjudicatory hearing is not
necessary to ensure that the claim receives a full and fair
airing." Id. at 22.
The Commonwealth filed a motion for reconsideration and
clarification on February 1, 2007. The Commonwealth requested that
the Commission
establish that: (a) [Vt. Yankee II] is not a
final decision with respect to the
[Commonwealth's] rights of participation in
the Pilgrim and Vermont Yankee license renewal
proceedings, (b) the Commission will treat the
[Commonwealth] as a party if the
[Commonwealth] later decides to seek to
suspend the license renewal decisions for [the
plants] under 10 C.F.R. § 2.802, and (c) as a
party, the [Commonwealth] would be permitted
to seek judicial review of any decision by the
NRC that fails to make timely application of
the results of the proceeding on the
[Commonwealth's] petition for rulemaking to
the individual license renewal decisions for
Pilgrim and Vermont Yankee.
The Commission denied the motion on March 15, 2007.
Entergy Nuclear Vt. Yankee, LLC (Vt. Yankee Nuclear Power Station)
(Vt. Yankee III), 65 N.R.C. 211 (2007). The Commission found that
the motion failed to demonstrate "compelling circumstances"
-21-
justifying reconsideration. Id. at 214. The Commission clarified
that its previous decision constituted a final decision with
regards to the NRC's rejection of the Commonwealth's contentions in
the licensing proceedings. The Commission also pointed out that
the Commonwealth, after the NRC's decision of the rulemaking
petition, could eventually also obtain judicial review of that
decision. Id. at 214 & n.13. Finally, the Commission made clear
that the Commonwealth "could seek [interested governmental entity]
status even now," a maneuver that would allow the Commonwealth to
request a stay of the licensing proceedings under 10 C.F.R.
§ 2.802(d). Id. at 214-15 & n.16.
The Commonwealth petitioned this court for review of the
Commission's decisions.
III.
The Commonwealth's principal argument in these petitions
is that by refusing to take into account its alleged new and
significant information regarding pool fires in the Pilgrim and
Vermont Yankee license renewal proceedings, whether by admitting
the Commonwealth as a party to the licensing proceedings or by
promising to apply the results of the rulemaking to those
proceedings, the NRC violated NEPA and the Administrative Procedure
Act ("APA").
The NRC and Entergy respond that the Commonwealth's NEPA
and APA claims are not properly before this court. Both of these
-22-
parties assert that the agency's ruling in Vt. Yankee II that it
had not suspended the licensing proceedings is not yet ripe for
judicial review because there has been no final agency action on
either the rulemaking petition or the license renewal applications.
Entergy further argues that we may not review the NEPA and APA
claims because the Commonwealth failed to exhaust available
administrative remedies.
A. NRC Decisions
The Administrative Procedure Act authorizes this court to
displace the Commission's decisions only to the extent that they
are "arbitrary, capricious, an abuse of discretion, or otherwise
not in accordance with law." 5 U.S.C. § 706(2)(A); Massachusetts
v. U.S. Nuclear Regulatory Comm'n, 878 F.2d 1516, 1522 (1st Cir.
1989). This general posture of deference toward agency decision-
making is particularly marked with regards to NRC actions because
"[t]he [AEA] is hallmarked by the amount of discretion granted the
Commission in working to achieve the statute's ends."
Massachusetts, 878 F.2d at 1523 (quoting Pub. Serv. Co. of N.H. v.
U.S. Nuclear Regulatory Comm'n, 582 F.2d 77, 82 (1st Cir. 1978)).
This principle is applicable in the context of licensing decisions,
where statutory directives are scant and the AEA explicitly
delegates broad authority to the agency to promulgate rules and
regulations. See, e.g., 42 U.S.C. §§ 2133, 2134(b).
-23-
This court must also be mindful of the substantial
deference required when an agency adopts reasonable interpretations
of regulations of its own creation. Fed. Express Corp. v.
Holowecki, 128 S. Ct. 1147, 1155 (2008); Auer v. Robbins, 519 U.S.
452, 461 (1997). We must accept the agency's position unless it is
"plainly erroneous or inconsistent with the regulation." Auer, 519
U.S. at 461 (quoting Robertson v. Methow Valley Citizens Council,
490 U.S. 332, 359 (1989)) (internal quotation marks omitted).
The Commission's decision to deny party status to the
Commonwealth in the Pilgrim and Vermont Yankee license renewal
proceedings is reasonable in context, and consistent with agency
rules. As the Commonwealth has conceded, the pool fire contention
it raised in its hearing requests does not apply solely to the
Pilgrim or Vermont Yankee plants and instead challenges a Category
1 GEIS finding.
Where environmental impacts of an NRC action are not
plant-specific, the Supreme Court has endorsed "[t]he generic
method . . . [as] clearly an appropriate method of conducting the
hard look required by NEPA." Balt. Gas & Elec. Co., 462 U.S. at
101 (citing Vt. Yankee, 435 U.S. at 535 n.13). "Administrative
efficiency and consistency of decision are both furthered by a
generic determination of these effects without needless repetition
of the litigation in individual proceedings, which are subject to
review by the Commission in any event." Id.
-24-
The NRC's procedural rules are clear: generic Category 1
issues cannot be litigated in individual licensing adjudications
without a waiver. 10 C.F.R. § 2.335; see also Dominion Nuclear
Conn., Inc. (Millstone Nuclear Power Station), 54 N.R.C. 349, 364
(2001); Turkey Point, 54 N.R.C. at 12; Duke Energy Corp. (Oconee
Nuclear Station), 49 N.R.C. 328, 343 (1999). If the Commonwealth
or any citizen wishes to attack the agency's rule on such an issue,
it must petition for a generic rulemaking. Turkey Point, 54 N.R.C.
at 12.
NEPA does impose a requirement that the NRC consider any
new and significant information regarding environmental impacts
before renewing a nuclear power plant's operating license.
However, "NEPA does not require agencies to adopt any particular
internal decisionmaking structure." Balt. Gas & Elec. Co., 462
U.S. at 100. Here, the NRC procedures anticipate a situation, such
as that alleged here by the Commonwealth, in which a generic
finding adopted by agency rule may have become obsolete. In such
a situation, the regulations provide channels through which the
agency's expert staff may receive new and significant information,
namely from a license renewal applicant's environmental report or
from public comments on a draft SEIS, and the NRC staff may seek
modification of a generic Category 1 finding.
The Commonwealth has already chosen the available option
of a rulemaking petition. But the rulemaking petition may not move
-25-
quickly enough to address the Commonwealth's safety concerns before
the Commission renders re-licensing decisions regarding the Pilgrim
and Vermont Yankee plants.
The Commonwealth argues that the NRC acted arbitrarily
and capriciously when it channeled the Commonwealth's pool fire
concerns into a generic rulemaking without any assurances that the
result of the rulemaking would apply to the individual licensing
proceedings for the Pilgrim and Vermont Yankee plants. Central to
the Commonwealth's argument is its assumption that "[u]nder the
NRC's present process, the Commonwealth does not even have a right
to request the agency to exercise its discretion to stay the
individual proceedings so that the results of the rulemaking may be
applied to Pilgrim and Vermont Yankee." Pet'r Br. 35.
The Commonwealth's concern is apparently based on a
misreading of the NRC's position. Both in its decisions in the
administrative proceedings and before this court, the NRC has
outlined at least one path by which the Commonwealth may establish
a connection between the rulemaking and the licensing proceedings.
That path consists of two stages. First, the Commonwealth may
participate in the licensing proceedings not as a party with its
own contentions, but as an interested governmental body under 10
C.F.R. § 2.315(c).6 Second, in the rulemaking proceedings, the
6
That regulation states that the officer presiding over a
licensing proceeding
-26-
Commonwealth may invoke 10 C.F.R. § 2.802(d), which provides that
a rulemaking petitioner "may request the Commission to suspend all
or any part of any licensing proceeding to which the petitioner is
a party pending disposition of the petition for rulemaking." This
stay procedure would, the agency argues, allow the Commonwealth an
opportunity to influence the order and timing of the agency's final
decisions in the rulemaking and licensing proceedings. But, since
the Commonwealth has as yet done neither of those things, there is
no final order and those issues are premature.
will afford an interested State, local
governmental body . . . and affected,
Federally-recognized Indian Tribe, which has
not been admitted as a party under [10 C.F.R.]
§ 2.309, a reasonable opportunity to
participate in a hearing. Each State [and]
local governmental body . . . shall, in its
request to participate in a hearing, each
designate a single representative for the
hearing. The representative shall be
permitted to introduce evidence, interrogate
witnesses where cross-examination by the
parties is permitted, advise the Commission
without requiring the representative to take a
position with respect to the issue, file
proposed findings in those proceedings where
findings are permitted, and petition for
review by the Commission under § 2.341 with
respect to the admitted contentions. The
representative shall identify those
contentions on which it will participate in
advance of any hearing held.
10 C.F.R. § 2.315(c). The regulation echoes a provision of the AEA
that requires the NRC to "afford reasonable opportunity" for state
representatives to participate in licensing proceedings. 42 U.S.C.
§ 2021(l).
-27-
The Commonwealth asserts the agency is changing positions
before this court regarding the availability of the § 2.802(d)
mechanism. Again, we think this is based on a misunderstanding.
The Commonwealth quotes a passage from the NRC's denial of the
motion for reconsideration: "[U]nder NRC regulations, the
[Commonwealth] currently has no right to request that the final
decisions in the Pilgrim and Vermont Yankee license renewal
proceedings be stayed until the rulemaking is resolved." Pet'r Br.
36 (quoting Vt. Yankee III, 65 N.R.C. at 214) (internal quotation
marks omitted). The Commission's decision goes on to explain,
however, that the Commonwealth could not "currently" request a stay
under § 2.802(d) because at the time of the NRC's decision, the
Commonwealth had neither been admitted as a "party" to the
licensing proceedings nor asserted interested governmental entity
status under § 2.315.7 Vt. Yankee III, 65 N.R.C. at 214-15. The
Commission further represented that the Commonwealth could attain
7
Agency procedure precludes a state from participating in
a single proceeding as both a party with an admitted contention and
an interested governmental entity. 10 C.F.R. § 2.315(c); La.
Energy Servs., L.P. (Nat'l Enrichment Facility), 60 N.R.C. 619,
626-27 (2004). The Commonwealth could thus not participate under
§ 2.315(c) until the NRC disposed of the Commonwealth's hearing
requests. Because the NRC has refused the Commonwealth party
status in a decision that is "final" as to those hearing requests,
and we deny the Commonwealth's petition, the path has been cleared
for the Commonwealth to seek interested governmental entity status,
if it so chooses. See Vt. Yankee III, 65 N.R.C. at 214-15 & n.16.
-28-
interested governmental entity status "even now." Id. at 215
n.16.8
The Commonwealth seizes upon a textual mismatch in the
regulations to argue that an "interested State" participating in a
licensing proceeding under § 2.315(c) is distinct from a "party,"
and therefore could not invoke the § 2.802(d) procedure. Compare
10 C.F.R. § 2.315(c) (making participant status available to a
governmental body "which has not been admitted as a party") with
id. § 2.802(d) (allowing petitioner in pending rulemaking to
request suspension of a licensing proceeding "to which the
petitioner is a party").
While we recognize what may be tension between the
wording of these two regulations, we decline to adopt the
Commonwealth's preclusive reading of the term "party" in the face
of a contrary and reasonable reading by the agency. Dispositive
here is the agency's own reasonable reading of the term, which
treats an interested governmental entity as the equivalent of a
"party" for purposes of § 2.802(d). "Party" can both be defined in
one context as a term of art, e.g., as one who has demonstrated
standing and whose contention has been admitted for hearing in a
8
The NRC has represented to this court that even though
the Pilgrim and Vermont Yankee proceedings have continued since the
Commission's decision dated March 15, 2007, the Commonwealth may
still attain interested governmental entity status and avail itself
of the § 2.802(d) stay procedure. We consider the NRC to be bound
by this representation.
-29-
licensing adjudication, see 10 C.F.R. § 2.309(a), and deployed in
its more general sense of one who participates in a proceeding or
transaction, see Webster's Third New International Dictionary 1648
(1993) (defining "party" to include one who "takes part with others
in an action or affair" or an individual "involved in the case at
hand"). The NRC has not defined the term "party" uniformly
throughout its regulations. See, e.g., 10 C.F.R. § 2.4 (containing
regulatory "Definitions," but not including one for "party"). We
must pay deference to this agency's interpretation of its own
regulations. Auer, 519 U.S. at 461.
The Commonwealth charges that the NRC has adopted this
interpretation for the first time before this court "[i]n an effort
to avoid judicial review." Pet'r Supplemental Reply Br. 5. This
is not a mere litigation position. The Commission explicitly
stated in its January 22, 2007 affirmance of the ASLB rulings that
an interested governmental entity participating under § 2.315(c)
could request a suspension under § 2.802(d). Vt. Yankee II, 65
N.R.C. at 22 n.37. We thus take the NRC's proffered reading of how
§ 2.315(c) and § 2.802(d) interact to be consistent with the
agency's practice generally, as well as its litigation position in
this court.
In sum, the NRC acted reasonably when it invoked a well-
established agency rule to reject the Commonwealth's requests to
participate as a party in individual re-licensing proceedings to
-30-
raise generic safety concerns and required that the Commonwealth
present its concerns in a rulemaking petition. The agency is also
within the bounds of its authority to interpret its regulations to
afford the Commonwealth an opportunity to participate in the
Pilgrim and Vermont Yankee licensing proceedings under § 2.315(c)
and thereby qualify to request a suspension of those proceedings
under § 2.802(d). We note, however, that these conclusions rely on
our deference to the agency's interpretations of its own
regulations. By staking its position regarding procedural avenues
available to the Commonwealth in this case, both in its
administrative decisions and in its representations before this
court, the agency has, in our view, bound itself to honor those
interpretations. See New Hampshire v. Maine, 532 U.S. 742, 749-51
(2001). Further, if the agency were to act contrary to these
representations in this matter, a reviewing court would most likely
consider such actions to be arbitrary and capricious.
Timing is a factor in this case. Section 2.315(c)
affords interested states an opportunity to participate in
licensing hearings, but the agency has not stayed the Pilgrim and
Vermont Yankee proceedings pending the outcome of this court's
decision, and the hearing schedule in at least the Pilgrim
proceedings may be coming rapidly to a close. We therefore stay
the close of hearings in both plant license renewal proceedings for
-31-
fourteen days from the date of issuance of mandate in this case9 in
order to afford the Commonwealth an opportunity to request
participant status under 10 C.F.R. § 2.315(c), should it desire to
do so.
What remains is the Commonwealth's objection that
accepting the NRC's recommended procedural vehicle subjects the
Commonwealth's rights under NEPA to "the NRC's unfettered
discretion to grant or withhold" a stay of the licensing
proceedings. Pet'r Br. 36. Again, although NEPA does impose an
obligation on the NRC to consider environmental impacts of the
Pilgrim and Vermont Yankee license renewal before issuing a final
decision, the statute does not mandate how the agency must fulfill
that obligation. See 42 U.S.C. § 4332; Balt. Gas & Elec. Co., 462
U.S. at 100-01; Vt. Yankee, 435 U.S. at 548. Beyond "the statutory
minima" imposed by NEPA, Vt. Yankee, 435 U.S. at 548, the
implementing procedures are committed to the agency's judgment. In
theory, what fetters the agency's decision-making process and
ensures ultimate compliance with NEPA is judicial review. The NRC
does not take the position that the Commonwealth is not entitled to
judicial review in the future. We turn next to the question of
9
Action by this court was held in abeyance from December
6, 2007 to February 14, 2008 in order to afford the parties an
opportunity to settle. A settlement was not reached, but the
Commonwealth's opportunity to avail itself of the NRC's procedural
mechanisms to participate in the Pilgrim and Vermont Yankee
proceedings should not be prejudiced by the delay in securing a
decision from this court.
-32-
whether a meaningful opportunity to seek judicial review would be
available to the Commonwealth should it pursue the procedural
course advanced by the agency.
B. Availability of Judicial Review
The NRC and Entergy point out two routes by which the
Commonwealth can obtain judicial review of the agency's ultimate
treatment of its concerns involving spent fuel pool fires. The
first is direct review of the results of the now-pending rulemaking
petition; the second is review of a hypothetical Commission denial
of a § 2.802(d) stay request, should the Commonwealth pursue that
route.10
The question of the availability of judicial review upon
the occurrence of contingent hypothetical events is not before us
and we do not give advisory opinions. It suffices to say that the
Commonwealth's argument is not proven that this proceeding must not
be dismissed because it is the Commonwealth's one and only path for
review of the agency's ultimate resolution of the Commonwealth's
pool fire concerns. We doubt the Commonwealth will wish to push
10
The NRC also suggests that in the event that the agency
issues the Pilgrim and/or Vermont Yankee renewal licenses before
concluding the pending rulemaking, the Commonwealth could petition
this court for a writ of mandamus under 28 U.S.C. § 1651 to compel
a final decision from the agency. Because more conventional
avenues to judicial review exist, we do not consider here whether
and under what circumstances this "extraordinary remedy" would be
available to the Commonwealth. Telecomms. Research & Action Ctr.
v. FCC, 750 F.2d 70, 78 (1984); accord In re City of Fall River,
470 F.3d 30, 32 (1st Cir. 2006).
-33-
this argument in the future, and we see no reason why it cannot
change its position. We do offer a few comments to explain our
conclusion.
The Hobbs Act provides the jurisdictional basis for
federal court review of NRC actions. See 28 U.S.C. §§ 2342(4),
2344. Section 2344 provides that "[a]ny party aggrieved by the
final order may, within 60 days after its entry, file a petition to
review the order in the court of appeals wherein venue lies." Id.
§ 2344. The statute embodies two threshold requirements for a
court to assert jurisdiction to review an NRC action. A petitioner
must first qualify as a "party aggrieved" under the statute in
order to have standing to appeal. Clark & Reid Co. v. United
States, 804 F.2d 3, 5 (1st Cir. 1986). There must also be a "final
order" for the court to review. 28 U.S.C. §§ 2342(2), 2344; see
generally Bennett v. Spear, 520 U.S. 154, 177-78 (1997);
Massachusetts, 878 F.2d at 1519-20.
This court applies a functional test to determine whether
one is a "party aggrieved" for Hobbs Act purposes. That test asks
whether the would-be petitioner "directly and actually participated
in the administrative proceedings." Clark & Reid Co., 804 F.2d at
5. Because "we do not equate the regulatory definition of a
'party' in an [agency] proceeding with the participatory party
status required for judicial review," id. at 6, it matters not here
-34-
whether NRC regulations label the Commonwealth as a "party" or an
"interested governmental entity."
C. Commonwealth's NEPA and APA Claims
The Commonwealth makes a claim for immediate injunctive
relief from claimed statutory violations by the NRC.11 The NRC and
Entergy are correct that the Commonwealth's claims that the agency
violated the NEPA and the APA by failing to consider the pool fire
contention, regardless of the path followed, is not reviewable at
this time.
The Commonwealth's claim that the agency committed
statutory violations by rejecting its hearing request fails because
it does not meet the basic prerequisite that a petitioner for
judicial review of an agency action first exhaust administrative
remedies. P.R. Assoc. of Physical Med. & Rehab., Inc. v. United
States, ___ F.3d ___, 2008 WL 787972, at *2 (1st Cir. Mar. 26,
2008) (citing Myers v. Bethlehem Shipbuilding Corp., 303 U.S. 41,
11
Specifically, the Commonwealth requests that this court
direct the agency to
withhold any final decision in the individual
license renewal proceedings for Pilgrim and
Vermont Yankee unless and until the Commission
considers and rules upon the Commonwealth's
new and significant information in accordance
with NEPA and the AEA and any further rulings
by the Court, and the Commission applies those
considerations and rulings to the individual
Pilgrim and Vermont Yankee relicensing
proceedings.
Pet'r Br. 43.
-35-
50-51 (1938)); see also 33 Wright & Koch, Federal Practice &
Procedure: Judicial Review § 8398, at 397 (2006). The
administrative exhaustion requirement gives agencies "a fair and
full opportunity" to adjudicate claims presented to them by
requiring that litigants use "all steps that the agency holds out,
and do[] so properly (so that the agency addresses the issues on
the merits)." Woodford v. Ngo, 126 S. Ct. 2378, 2385 (2006)
(quoting Pozo v. McCaughtry, 286 F.3d 1022, 1024 (7th Cir. 2002))
(internal quotation mark omitted). Otherwise, court review might
interrupt the administrative process, impinge on the discretionary
authority granted to the agency by the legislature, and squander
judicial resources where continued administrative proceedings might
resolve the dispute in the petitioner's favor. McKart v. United
States, 395 U.S. 185, 193-95 (1969). Those concerns are involved
here.
The Commonwealth argues that when the NRC dismissed it
from the license renewal proceedings without addressing the NEPA
claims, the NRC "conclusively established the Commonwealth's rights
and . . . eliminate[d] the Commonwealth's right to challenge the
agency's compliance with NEPA . . . ." Pet'r Reply Br. 6. The
availability of interested state status under § 2.315(c) and the
request for suspension mechanism in § 2.802(d) undermine that
position. There has not yet been such a conclusive order. We
cannot at this point in the administrative proceedings predict how
-36-
the agency would respond on the merits to a § 2.802(d) request from
the Commonwealth, let alone evaluate the agency's ultimate
compliance with NEPA should the Commonwealth follow that procedure.
The Commonwealth argues separately that the NRC violated
NEPA and acted arbitrarily and capriciously when it refused to
ensure that the results of the rulemaking would apply to the
Pilgrim and Vermont Yankee licensing proceedings. This argument
merely repackages the Commonwealth's claims regarding its dismissal
from the licensing proceedings and recasts them in the context of
its rulemaking petition. We cannot review the NRC's treatment of
that petition, however, because the agency has not issued a final
order regarding the rulemaking petition.
The NRC decision which the Commonwealth attempts to
construe as a "final" refusal to tie the results of the rulemaking
back into the individual proceedings was no such thing; it was a
"final order" only insofar as it affirmed the agency's dismissal of
the Commonwealth's hearing requests in the re-licensing
proceedings. See Vt. Yankee III, 65 N.R.C. at 214. Further, by
their express language, the Commission's decisions did not purport
to rule out a possible future order suspending the Pilgrim and
Vermont Yankee proceedings. The Commission merely observed that it
would be "premature to consider" such action at a time when there
were other, unrelated issues involved in the licensing proceedings
that would require significant time to resolve. Vt. Yankee II, 65
-37-
N.R.C. at 22 n.37. The NRC's statements about the rulemaking
within its decisions to dismiss the Commonwealth's hearing requests
are "merely tentative" and do not determine any legal rights or
consequences. See Bennett, 520 U.S. at 177-78.
The petitions for review are denied. No costs are
awarded.
-38-