Error: Bad annotation destination
United States Court of Appeals for the Federal Circuit
05-5162
PSEG NUCLEAR, L.L.C.,
and PUBLIC SERVICE ELECTRIC AND GAS COMPANY,
Plaintiffs-Appellants,
v.
UNITED STATES,
Defendant-Appellee.
Jay E. Silberg, Pillsbury Winthrop Shaw Pittman LLP, of Washington, DC, argued for
plaintiffs-appellants. With him on the brief were Alex D. Tomaszczuk, Daniel S. Herzfeld,
and Jack Y. Chu, of McLean, Virginia.
Harold D. Lester, Jr., Assistant Director, Commercial Litigation Branch, Civil Division,
United States Department of Justice, of Washington, DC, argued for defendant-appellee.
With him on the brief were Peter D. Keisler, Assistant Attorney General; David M. Cohen,
Director; Alan J. Lo Re, Senior Trial Counsel; and Heide L. Herrmann, Trial Attorney. Of
counsel was Jane K. Taylor, United States Department of Energy, of Washington, DC.
Jerry Stouck, Greenberg Traurig, LLP, of Washington, DC, for amici curiae. With him
on the brief was Robert L. Shapiro.
Appealed from: United States Court of Federal Claims
Senior Judge Bohdan A. Futey
United States Court of Appeals for the Federal Circuit
05-5162
PSEG NUCLEAR, L.L.C.,
and PUBLIC SERVICE ELECTRIC AND GAS COMPANY,
Plaintiffs-Appellants,
v.
UNITED STATES,
Defendant-Appellee.
__________________________
DECIDED: September 29, 2006
__________________________
Before LOURIE, RADER, and PROST, Circuit Judges.
PROST, Circuit Judge.
PSEG Nuclear, L.L.C. and Public Service Electric and Gas Company (collectively
“PSEG”) appeal the decision of the United States Court of Federal Claims holding that
the court lacked subject matter jurisdiction over PSEG’s breach of contract claims. Fla.
Power & Light Co. v. United States, 64 Fed. Cl. 37, 44 (2005) (“Florida Power I”).
Because we hold that the Court of Federal Claims possesses subject matter jurisdiction
over the claims under the Tucker Act, 28 U.S.C. § 1491(a)(1), we reverse.
BACKGROUND
I.
The breach of contract claims asserted in this case stem from contracts entered
into between PSEG and the Department of Energy (“DOE”) under the Nuclear Waste
Policy Act of 1982 (“NWPA” or “the Act”), 42 U.S.C. §§ 10101-10270. Congress
enacted the NWPA in January 1983 in order to provide for collection and storage of
radioactive waste and spent nuclear fuel (collectively “SNF”) by the DOE. Under its
scheme, section 302 of the Act authorized the DOE to enter into contracts with
companies who generate or hold SNF provided that the companies pay into a fund used
to pay for SNF collection and storage. 42 U.S.C. § 10222 (2000). The Act states in
pertinent part:
(a) Contracts
(1) In the performance of his functions under this chapter, the Secretary
[of Energy] is authorized to enter into contracts with any person who
generates or holds title to high-level radioactive waste, or spent nuclear
fuel, of domestic origin for the acceptance of title, subsequent
transportation, and disposal of such waste or spent fuel. Such contracts
shall provide for payment to the Secretary of fees pursuant to paragraphs
(2) and (3) sufficient to offset expenditures described in subsection
(d) . . . .
...
(5) Contracts entered into under this section shall provide that--
(A) following commencement of operation of a repository, the Secretary
shall take title to the high-level radioactive waste or spent nuclear fuel
involved as expeditiously as practicable upon the request of the generator
or owner of such waste or spent fuel; and
(B) in return for the payment of fees established by this section, the
Secretary, beginning not later than January 31, 1998, will dispose of the
high-level radioactive waste or spent nuclear fuel involved as provided in
this subchapter.
Id. (emphases added).
The DOE engaged in an administrative hearing process to create a single
contract with identical terms (“the Standard Contract”) for use with all parties contraction
under section 302. The contract included the terms required by the NWPA and also
05-5162 2
many additional terms. In general, the contract required companies with SNF to pay a
fee that the DOE would use to develop an SNF storage facility and to collect and
maintain the SNF at the facility.1 Beginning in 1983, utility companies with SNF entered
into contracts based on the Standard Contract and started paying into the fund while the
DOE, presumably, began preparations to start collecting and disposing of the
companies’ SNF.2
Once it became clear that the DOE would not be prepared to begin SNF
collection by the January 31, 1998 date in the Standard Contract, the contracting utility
companies, including PSEG, brought suit for breach of the Standard Contract. To date,
the government asserts that sixty-six such claims have been filed.
II.
One provision of the NWPA discusses judicial review of DOE actions taken
pursuant to the NWPA. This provision, section 119, states:
(a) Jurisdiction of United States courts of appeals
(1) Except for review in the Supreme Court of the United States, the
United States courts of appeals shall have original and exclusive
jurisdiction over any civil action--
(A) for review of any final decision or action of the Secretary, the
President, or the Commission under this part; . . . .
42 U.S.C. § 10139 (2000) (emphasis added).
1
The facility, still under development by the DOE, is commonly known as
Yucca Mountain.
2
PSEG entered into a contract based on the Standard Contract on June 13,
1983 and it alleges that it has paid at least $540 million into the SNF fund pursuant to its
obligations under the contract.
05-5162 3
In several cases, courts of appeals have asserted jurisdiction under section 119
over claims brought challenging DOE actions under the NWPA. The first of these cases
was General Electric Uranium v. United States Department of Energy, 764 F.2d 896,
901 (D.C. Cir. 1985). In that case, the plaintiff alleged that the DOE abused its
discretion when setting one-time fees under its authority under section 302(a)(3) of the
NWPA. Although section 302(a)(3) fell within Title III of the Act and section 119 was in
Title I and only conferred the courts of appeals with jurisdiction over agency actions
“under this part,” the D.C. Circuit held that it possessed jurisdiction over the case. The
court reasoned that DOE’s rule setting the one-time fee under section 302(a)(3) was
“well within the class of agency actions reviewable under section 119(a)(1)(A).” Id. The
court based this determination on three considerations: 1) the structure and language of
the NWPA evinced congressional intent to vest the courts of appeals with jurisdiction
over cases such as this one; 2) relevant legislative history did not compel a contrary
result; and 3) policy considerations supported the conclusion. Id. Subsequently, the
D.C. Circuit exercised original jurisdiction over several cases brought under the NWPA
challenging agency actions without any discussion of its jurisdictional limits under the
statute.3
3
See Commonwealth Edison v. U.S. Dep’t of Energy, 877 F.2d 1042, 1045
(D.C. Cir. 1989) (challenging the Treasury bill rate applied by DOE pursuant to the
section 302(a)(4) fee provision); Nat’l Ass’n of Regulatory Utility Comm’rs v. U.S. Dep’t
of Energy, 851 F.2d 1424 (D.C. Cir. 1988); Wisconsin Elec. Power v. Dep’t of Energy,
778 F.2d 1, 3 (D.C. Cir. 1985). In addition to the D.C. Circuit, other circuit courts have
also asserted jurisdiction over cases brought under NWPA Title III. See Ala. Power Co.
v. U.S. Dep’t of Energy, 307 F.3d 1300 (11th Cir. 2002); Natural Res. Def. Council, Inc.
v. Abraham, 244 F.3d 742 (9th Cir. 2001).
05-5162 4
Subsequently, the DOE began to see claims under the Standard Contract for its
failure to begin collecting SNF from the power companies by January 31, 1998. The
DOE initially issued a regulation which stated that it “does not have an unconditional
statutory or contractual obligation to accept nuclear waste beginning January 31, 1998
in the absence of a repository or interim storage facility constructed under the Act.” 60
Fed. Reg. 21,793 (1995) (“Final Interpretation of Nuclear Waste Acceptance Issues”).
However, in Indiana Michigan Power Co. v. Department of Energy, the D.C. Circuit held
that, contrary to DOE’s regulation, the agency was obliged to begin accepting SNF on
January 31, 1998, even in the absence of a repository. 88 F.3d 1272, 1277 (D.C. Cir.
1996).4 However, the court held that no remedy was available to the companies until
after the deadline had passed. The court’s jurisdiction over the case was not at issue.
The DOE proceeded by arguing that its failure to perform was an “unavoidable
delay” under the contract and was therefore not compensable. A group of power
companies sought a writ of mandamus from the D.C. Circuit requiring the DOE to
comply with Indiana Michigan and begin SNF collection by the contracted deadline. In
Northern States Power Co. v. United States Department of Energy, 128 F.3d 754 (D.C.
Cir. 1997), the court held that this mandamus request was not proper because the
companies had adequate remedies under the Standard Contract. However, so that the
companies would be able to enforce the terms of the contract to effectuate the DOE’s
duty, the court issued a writ of mandamus forbidding the DOE from claiming, in
proceedings under its contracts, that its failure to perform was “unavoidable” because a
repository was not available.
4
See also N. States Power Co. v. Dep’t of Energy, No. 94-1457, 1995 WL
05-5162 5
Soon after issuing the Northern States Power opinion just discussed, the D.C.
Circuit issued an unpublished opinion clarifying its jurisdictional position in the case. In
the opinion, the court sought to reiterate that the 1997 opinion merely “describes the
nature of the DOE’s obligation, which was created by the NWPA and undertaken by the
DOE under the Standard Contract. It does not place the question of contract remedies
in this court, nor set up this court as a source of remedies outside the Standard
Contract.” N. States Power Co. v. U.S. Dep’t of Energy, No. 97-1064, 1998 WL 276581,
at *2 (D.C. Cir. May 5, 1998). Shortly thereafter, several power companies with NWPA
Standard Contracts, including PSEG, filed claims for breach of contract and damages
for the DOE’s failure to meet the January 1, 1998 deadline in the Court of Federal
Claims.
Another company, Wisconsin Electric Power, however, continued to seek
remedies at the D.C. Circuit. Wis. Elec. Power v. U.S. Dep’t of Energy, 211 F.3d 646,
647 (D.C. Cir. 2000). Wisconsin Electric sought a writ of mandamus that the NWPA
required both monetary and non-monetary remedies for breach of the Standard
Contract. The company claimed the D.C. Circuit had jurisdiction under two bases: 1) its
authority to enforce its prior mandates, or 2) directly under section 119 of the NWPA.
The court held that it did not have jurisdiction under its authority to enforce prior
mandates because while “[t]hose mandates prohibit the DOE from interpreting the
NWPA and its contracts with utilities in a manner that would relieve the Department of
its unconditional obligation to begin disposing of SNF on January 31, 1998; [they]
expressed no opinion about the relief the DOE would have to provide for breach of that
479714, *1 (D.C. Cir. July 28, 1995) (dismissing the case for lack of final agency action).
05-5162 6
obligation.” Id. at 648. The court also refused to assert jurisdiction under section 119 of
the NWPA directly because while the statute “grants the court jurisdiction over cases
seeking review of: (1) final action taken by the agency pursuant to the NWPA, and (2)
the agency’s failure to take any action required by the NWPA[,] . . . a contract breach by
the DOE does not violate a statutory duty. The Court of Federal Claims, not this court,
is the proper forum for adjudicating contract disputes.” Id. (citations omitted).
III.
Several breach of contract cases seeking damages for the DOE’s failure to begin
SNF collection on January 1, 1998 have proceeded at the Court of Federal Claims and
at this court with no discussion of a lack of subject matter jurisdiction over the claims.
See Me. Yankee Atomic Power Co. v. United States, 225 F.3d 1336 (Fed. Cir. 2000);
N. States Power Co. v. United States, 224 F.3d 1361 (Fed. Cir. 2000). Then, in Boston
Edison Co. v. United States, the Court of Federal Claims considered the issue of
subject matter jurisdiction over the SNF cases and held that it did possess such
jurisdiction. 64 Fed. Cl. 167 (2005), The court held that the plain text of section 119
granted original and exclusive jurisdiction to the courts of appeals in six instances, none
of which relate to Title III of the Act. Id. at 179. Therefore, the court held that section
119 did not affect jurisdiction over actions taken under Title III, and accordingly did not
displace the Court of Federal Claims of its Tucker Act jurisdiction over an alleged
breach of contract. Id.
In 2005, a judge of the Court of Federal Claims sua sponte issued an order
requesting the government and four utility plaintiffs with SNF claims on her docket to
show cause why the claims should not be dismissed or transferred for lack of subject
05-5162 7
matter jurisdiction. See Florida Power I, 64 Fed. Cl. at 44-63. After briefing by the
parties, the court held that it lacked jurisdiction over the four breach of contract claims.
Id. at 44. The court first adopted the D.C. Circuit’s reasoning for its assertion of
jurisdiction in General Electric, agreeing that DOE actions under Title III fall under the
class of agency actions reviewable under section 119 of the NWPA. Id. at 40. It then
rejected the D.C. Circuit’s reasoning in Wisconsin Electric Power which held that section
119 did not vest the courts of appeals with jurisdiction over breach of contract cases
under the NWPA. Id. at 63. The court noted that the D.C. Circuit could not confer
jurisdiction on the Court of Federal Claims by disavowing jurisdiction contrary to statute.
Id. Since the court’s analysis of case law, legislative history, and the structure of the
statute led it to conclude that only the courts of appeals possessed jurisdiction over all
claims regarding the statutorily imposed deadline, she dismissed the case for lack of
jurisdiction. Id. at 40.
In Florida Power I, the Court of Federal Claims further held that this court had
identified “[t]wo circumstances in which statutory obligations in a contract [are] not
enforceable by actions for breach of contract.” 64 Fed. Cl. at 39 (citing City of Burbank
v. United States, 273 F.3d 1370, 1377 (Fed. Cir. 2001)). The circumstances were 1)
that the contract provisions were statutorily mandated, and 2) the existence of a
statutory provision that actions taken pursuant to the statute “shall” be filed in the courts
of appeals. The court found that here, the contract term was statutorily required and not
negotiated, the contract was the result of administrative hearings and rule-making, and
all evidence regarding the rule-making fall inside the administrative record. Id. at 40.
Therefore, the inclusion of the term was action taken pursuant to the statute and the first
05-5162 8
factor was present. Secondly, as in the statute at issue in City of Burbank, the court
held that the NWPA required challenges to agency actions pursuant to the statute to be
brought in the courts of appeals. It held that City of Burbank thus required that the
courts of appeals had exclusive jurisdiction over all actions relating to that contract term
and dismissed all four cases. Id. at 40.
Subsequently, the four SNF cases dismissed in Florida Power I were reassigned
to other judges at the Court of Federal Claims. The plaintiffs filed motions for
reconsideration in each of the four cases, arguing that the Court of Federal Claims did
possess jurisdiction to hear their breach of contract claims. In three of the cases, the
judges granted the motions for reconsideration and reversed the holding that the court
lacked jurisdiction. In one, the court held that the language of section 119 and structure
of the Act did not support courts of appeals jurisdiction over Title III cases through
section 119. Duke Power v. United States, No. 98-485C, slip op. (Fed. Cl. Mar. 3,
2005). In another, the Court of Federal Claims judge adopted the reasoning in Boston
Edison and Duke Power. Neb. Pub. Power Dist. v. United States, No. 01-116C, slip op.
at 2 (Fed. Cl. Mar. 30, 2005). And in the third case, the judge agreed with the reasoning
in the three opinions above in holding that it had subject matter jurisdiction over the
claims. Fla. Power & Light Co. v. United States, 66 Fed. Cl. 93 (2005).
In the fourth case dismissed by Florida Power I, the case before us, the Court of
Federal Claims denied the plaintiff’s motion for reconsideration on the basis that no new
evidence or law had been presented to justify reconsideration of the dismissal for lack of
jurisdiction. PSEG Nuclear, L.L.C. v. United States, No. 01-551C, slip op. (Fed. Cl. Apr.
05-5162 9
22, 2005). PSEG timely appealed the Court of Federal Claims’ decision to this court.
We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).
DISCUSSION
The sole question before this court is whether the Court of Federal Claims
possesses subject matter jurisdiction over PSEG’s claims arising out of breach of the
Standard Contract. “In a given case, whether Tucker Act jurisdiction exists is a question
of law that we review without deference to the decision of the trial court.” In re United
States, No. 06-M806, --F.3d--, 2006 WL 2597835, at *5 (Fed. Cir. Sept. 11, 2006)
(citing Core Concepts of Fla., Inc. v. United States, 327 F.3d 1331, 1334 (Fed. Cir.
2003); Clark v. United States, 322 F.3d 1358, 1362 (Fed. Cir. 2003)). We hold that the
NWPA did not strip the Court of Federal Claims of its Tucker Act jurisdiction over
PSEG’s claims.
Both parties agree on appeal that the Court of Federal Claims erred in finding no
jurisdiction, but propose different rationales as to why that court has jurisdiction. The
parties agree that section 119 of the NWPA encompasses judicial review of actions
taken under section 302, thereby conferring the courts of appeals with jurisdiction to
review those actions. The government urges that section 302 required only a single
DOE action, namely the inclusion of the January 1, 1998 deadline in the Standard
Contract. Because the term was included in the contract, the government argues, any
further claim regarding the deadline does not arise under section 302 of the NWPA, but
is a contract performance dispute that falls within the Court of Federal Claims’ Tucker
Act jurisdiction. Meanwhile, while PSEG agrees that section 119 does not strip the
Court of Federal Claims of jurisdiction over its breach of contract damages claim, it
05-5162 10
argues that the courts of appeals continue to have jurisdiction under section 119 over
agency actions under section 302. The difference in the parties’ positions amounts to
whether the courts of appeals continue to have jurisdiction to decide the propriety of
agency actions under section 302 once the government includes the required language
in the Standard Contract. Because this issue need not be resolved in this appeal, we
merely agree with the parties that the Court of Federal Claims is vested with jurisdiction
over PSEG’s breach of contract case and that the NWPA does not strip the court of its
Tucker Act jurisdiction.
The Tucker Act generally vests the Court of Federal Claims with jurisdiction to
render judgment in government contract disputes. See 28 U.S.C. § 1491(a) (2000).
This jurisdiction is supplanted only if, in a specific jurisdictional statute, Congress grants
exclusive jurisdiction over a contract dispute to another court. City of Burbank, 273 F.3d
at 1377. The NWPA did not strip the Court of Federal Claims of its jurisdiction over
PSEG’s claims because it did not vest that jurisdiction in another court.
The NWPA contains only one jurisdictional provision, section 119. Section 119
confers the courts of appeals with jurisdiction over, inter alia, “any final decision or
action of the Secretary, the President, or the Commission under this part; [or] (B)
alleging the failure of the Secretary, the President, or the Commission to make any
05-5162 11
decision, or take any action, required under this part . . . .”5 42 U.S.C. § 10139 (2000).
By its terms, section 119 only refers to agency actions required under Title I, Subtitle A
of the NWPA, entitled “Repositories for Disposal of High-Level Radioactive Waste and
Spent Nuclear Fuel.” Therefore, section 119 of the NWPA confers jurisdiction over
agency actions taken during development of a repository for SNF disposal.
The NWPA requires that contracts entered into between the DOE and persons
holding title to SNF “shall provide that” the disposal shall begin “not later than January
31, 1998” in section 302. This section is in Title III of the Act, entitled “Other Provisions
Relating to Radioactive Waste.” We agree with the parties, the Court of Federal Claims
in this case, and the D.C. Circuit that agency actions mandated under Title III which
5
NWPA section 119(a)(1) states in its entirety:
(a) Jurisdiction of United States courts of appeals
(1) Except for review in the Supreme Court of the United States, the
United States courts of appeals shall have original and exclusive
jurisdiction over any civil action--
(A) for review of any final decision or action of the Secretary, the
President, or the Commission under this part;
(B) alleging the failure of the Secretary, the President, or the Commission
to make any decision, or take any action, required under this part;
(C) challenging the constitutionality of any decision made, or action taken,
under any provision of this part;
(D) for review of any environmental impact statement prepared pursuant
to the National Environmental Policy Act of 1969 (42 U. S.C. 4321 et seq.)
with respect to any action under this part, or as required under section
10155(c)(1) of this title, or alleging a failure to prepare such statement with
respect to any such action;
(E) for review of any environmental assessment prepared under section
10132(b)(1) or 10155(c)(2) of this title; or
(F) for review of any research and development activity under subchapter
II of this chapter.
42 U.S.C. § 10139 (2000).
05-5162 12
relate to the creation of repositories for spent nuclear fuel fall within the class of actions
subject to review by the courts of appeals under section 119.
The remaining issue, therefore, is whether the breach of contract alleged by
PSEG is also an agency action subject to review by the courts of appeals. PSEG’s
claims are for breach of the Standard Contract’s provision requiring that the government
begin SNF collection by the statutorily mandated date. It does not challenge an agency
action taken under the agency’s statutory mandate.
In this regard, it is instructive to consider our decision in City of Burbank, a
breach of contract action against the Bonneville Power Administration (“BPA”). 273
F.3d 1370. There, we considered the scope of the judicial review provision contained in
the Pacific Northwest Electric Power Planning and Conservation Act of 1980, 16 U.S.C.
§§ 839-839h (“NPA”). The NPA permitted the BPA to enter into contracts which
included some statutorily mandated provisions and other provisions that were freely
negotiated between the parties. The judicial review provision of the NPA vested the
Ninth Circuit with exclusive jurisdiction over certain claims challenging the BPA’s
actions. This court held that “where disputed contract provisions are statutorily
mandated or are arrived at via an administrative hearing under the [Administrative
Procedures Act] in which the pertinent facts are reflected in an administrative record,
the Ninth Circuit possesses exclusive jurisdiction” under the NPA’s judicial review
provision. City of Burbank, 273 F.3d at 1380. However, we found that the provision did
not strip the Court of Federal Claims of its Tucker Act jurisdiction because 1) the
contract terms that the BPA had allegedly breached were not statutorily mandated, and
2) no pertinent facts relevant to the breach or the alleged damages were contained in
05-5162 13
an administrative record. The factors applicable in City of Burbank also illuminate our
analysis of PSEG’s claims.
The contract term at issue, the January 1, 1998 date for beginning SNF
collection, was clearly statutorily mandated. However, the key question is not whether
the breached contract provision was statutorily mandated, but whether the claims at
issue involve the agency’s authority under that statutory mandate. As both parties note,
section 302 of the NWPA only required that the DOE include certain obligations in its
contracts. Therefore, judicial review as to whether the DOE properly incorporated these
obligations within its contracts may fall within the jurisdiction conferred to the courts of
appeals in section 119. However, the performance of and any damages for failure to
meet those obligations were not provided for by statute. The claims at issue here
involve only issues of whether the DOE breached its contractual obligations, and if so,
to what damages, if any, PSEG is entitled for the breach. Because these are not within
the DOE’s statutory obligations under the NWPA, City of Burbank does not compel us to
conclude that section 119 of the NWPA strips the Claims Court of its Tucker Act
jurisdiction over PSEG’s claim merely because the claim involves a statutorily mandated
provision.
There is also no basis for concluding that PSEG’s claims can be resolved by
resort to the administrative record. The Court of Federal Claims in Florida Power I
seemed to reach this conclusion because the DOE published its proposed Standard
Contract in the Federal Register and used an administrative rulemaking to develop the
terms of the contract. However, the DOE was not statutorily required to use the
administrative rulemaking process or to even develop a Standard Contract. Rather, it
05-5162 14
did so because it preferred developing a contract with standard provisions that could be
used with multiple contractees to the extent practicable. See 48 Fed. Reg. 5458, 5459
(Feb. 4, 1983). DOE cannot unilaterally confer jurisdiction over contract claims to the
courts of appeals by its choice to develop a contract through administrative rulemaking.
In addition, any damages here will require extensive factual findings outside the
administrative record. For example, the Standard Contract contains many provisions
which were not statutorily mandated but will affect any measurement of damages.6 In
addition, any necessary calculation of damages for different contracting utilities will
require individual inquiries into when their SNF would have been collected and stored.
Where damages for breach are not within the administrative record, jurisdiction properly
lies with the Court of Federal Claims, which is equipped to hear evidence and determine
such damages. See General Electric, 764 F.2d at 903 (concluding that section 119 of
the NWPA should confer courts of appeals with exclusive jurisdiction over “judicial
review of administrative agency actions” considering “there are no factual findings to be
made” and “the court of appeals is fully able to consider” an administrative record). Any
issues related to the types of damages permitted under the contract, if any, and the
extent of those damages can be resolved by solely resolving the DOE’s contractual
obligations.
6
For example, the government cites the following sections in the Standard
Contract, among others, that are relevant to these claims but not statutorily mandated:
Article V regarding the procedure through which different nuclear utilities would receive
their SNF acceptance allocations; Article VI.B regarding the order in which SNF would
be accepted from nuclear utilities; Articles VI.A and Appendix E concerning the technical
requirements that SNF being accepted must satisfy to be accepted as part of the initial
acceptance queue. See 10 C.F.R. § 961.11.
05-5162 15
CONCLUSION
As in City of Burbank, there is no statutory provision conferring jurisdiction over
PSEG’s claims on another court. Further, these claims do not require the Court of
Federal Claims to inquire solely into the administrative record, but to resolve factual
issues regarding what damages are provided for by the parties in the contract.
Therefore, we hold that the Court of Federal Claims has jurisdiction under the Tucker
Act to hear PSEG’s breach of contract claims.
COSTS
No costs.
REVERSED
05-5162 16